generation dispatch in a smart grid environment · smart distribution grids. smart substation....

33
Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung 1 1 Generation Dispatch in a Smart Grid Environment Kwok W. Cheung, Xing Wang, But-Chung Chiu, Ying Xiao, Ricardo Rios-Zalapa AREVA T&D Inc. IEEE Innovative Smart Grid Technologies Conference Jan 19-21, 2010 Washington, DC

Upload: hanhan

Post on 27-Aug-2018

218 views

Category:

Documents


3 download

TRANSCRIPT

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung1 1

Generation Dispatch in a Smart Grid Environment

Kwok W. Cheung, Xing Wang, But-Chung Chiu, Ying Xiao, Ricardo Rios-Zalapa

AREVA T&D Inc.

IEEE Innovative Smart Grid Technologies ConferenceJan 19-21, 2010

Washington, DC

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung2 2

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung3 3

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung4 4

AREVA T&D Automation Activities

EMS

/ DM

S / M

MSMarket

ManagementSystems

(MMS)

Energy & Distribution Management

Systems (EMS / DMS)

Dat

aC

om

Dedicatedtelecommunication network

Subs

tatio

nAu

tom

atio

n

Substation Substation Substation

Protection Measurement Substation Control

Support Integrated refurbishment, system upgrade, system monitoring, system life-cycle management, system reliability, expert training

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung5 5

North America RTO/ISO’s

US electricity markets have been converging towards to a model of multi-settlement using locationalmarginal pricing for congestion management.

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung6 6

Optimization-based Integrated Approach

SystemOperator

MarketOperator

NetworkModel and

Constraints

LoadForecast

BalancedDispatch

Points

Bid Data MarketPrices

RTO/ISO

DualSolutionsof SCED

Consistent dispatch signals and price signals Security constrained economic dispatch (SCED)

Locational Marginal Pricing (LMP)

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung7 7

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung8 8

Smart Grid Market Drivers

Society’s growing dependency on electricity Looming risks of major system disturbances Focus on reliable demand-supply balance & grid security

Global energy & environmental movement Increasing presence of DER - Distributed Energy Resources (e.g. wind, DR,

etc) Operational challenges: DER performance uncertainties

Experiences from deregulated system operations Established foundation for integrating demand-supply balance with grid

security constraints (e.g. LMP). Identified emerging deficiencies in Dispatch Instructions

Unrelenting complexity in business & technical decision process Smart

devices/resources with distributed intelligence

Coordinated decision making

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung9 9

Smart Grid from Vision to Product

Smart Dispatch Smart Transmission Grids Smart Distribution Grids Smart Substation

Smart Grid

Generation PortfolioManagement including

renewable

Full Integration of pricing and

demand/supply principles to manage

the grid

On-line Asset Management

On-Line StabilityAnalysis &

Defense Plans

Automatic Meter Management System

Integrated Distributed Management Systems

Dynamic balancing with centralized and distributed resource

Substation Protection & Control

Architectures

Self-adaptive Defense Plans

Renewable and load management integration

Secondary Distribution Smart Grid Box

Smart Power Electronic Controls (HVDC, FACTS, SVC…)

Visualization, Situation Awareness and Decision Support Tools

System Architecture including Common Information Model

Secure, deterministic and reliable data communication

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung10 10

Evolution of Generation Dispatch

Classical Dispatch Unit Commitment Scheduling, Economic Dispatch, AGC Grid security, scheduling, dispatch are Independent tasks

Market-Based Dispatch UC/ED with explicit transmission security constraints Formal Day-Ahead and Real-time tasks Pricing - Dual of the MW signal Transparency & consistency Large-scale system dispatch

Smart Dispatch Dispatch with explicit forward vision Dispatch with intelligence (e.g. parameter adaptation) Improve system resiliency against uncertainties (e.g. DER, RE, DR) Mitigate root-causes for dispatch deficiencies Process re-engineering for business/economic analysis

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung11 11

Smart Grid Challenges

A lot of emphasis of renewables, distributed energy resources (DER) and demand response (DR), PHEVs etc.

Increase amount of uncertainties: Generations and Demand Response Demand forecast Transmission constraints Resource characteristics

Modeling of uncertainties Confidence Interval Scenario-based

Volumes and distributiveness of DERs and DRs Aggregation model

Smart Dispatch Holistic forward-looking view of system conditions More robust solution

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung12 12

Expanded Dimensions in Smart Dispatch

Time

Scen

ario

s

Classical Dispatch

Smart Dispatch

(Vision)(ForensicAnalysis)

(Rob

ustn

ess)

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung13 13

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung14 14

Vision of a Smart Dispatch System

Comprehensive Operating Plan (COP)

SKED 1t=30,60,90,120,180...720..

SKED 2t=15,30,45,60...

SKED 3 t=5,10,15...

5 min

Quarter Hourly

Hourly

Outages

Demand Forecast

Adaptive Model Management

5 min to Hourly

On Demand

Asynchronous

Explicit Real-time Dispatch

Implicit/Indirect Dispatch After-the-Fact Forensic Analysis

Perfect Dispatch

5 min On Demand

5 min On Demand

Physical System Operation Archived System

Operation History

5 min

5 min On Demand

On Demand

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung15 15

SKED 1, 2 & 3

Multi-stage resource scheduling Functions (SKED1, 2 & 3): security constrained unit commitment and economic dispatch sequences with different look-ahead periods (e.g. 6 hours, 2 hours and 20 minutes)

The results of each stage form progressively refined regions that guide the dispatching decision space of the subsequent stages.

Various SKED cycles are coordinated through the Comprehensive Operating Plan (COP).

Comprehensive Operating Plan (COP)

SKED 1t=30,60,90,120,180...720..

SKED 2t=15,30,45,60...

SKED 3 t=5,10,15...

5 min

Quarter Hourly

Hourly

Outages

Demand Forecast

Adaptive Model Management

5 min to Hourly

On Demand

Asynchronous

Explicit Real-time Dispatch

Implicit/Indirect Dispatch After-the-Fact Forensic Analysis

Perfect Dispatch

5 min On Demand

5 min On Demand

Physical System Operation Archived System

Operation History

5 min

5 min On Demand

On Demand

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung16 16

After-the-Fact Analysis

After-the-Fact Analysis (AFA) Systematic analysis of past

events and practices

Quantitative assessments of how do specific events and practices affect system performance

Use-case comparative approach

Perfect Dispatch A class of use cases of AFA

that focus on “Day-After” analysis of the performance of actual system dispatch results, including the impacts of specific events.

Comprehensive Operating Plan (COP)

SKED 1t=30,60,90,120,180...720..

SKED 2t=15,30,45,60...

SKED 3 t=5,10,15...

5 min

Quarter Hourly

Hourly

Outages

Demand Forecast

Adaptive Model Management

5 min to Hourly

On Demand

Asynchronous

Explicit Real-time Dispatch

Implicit/Indirect Dispatch After-the-Fact Forensic Analysis

Perfect Dispatch

5 min On Demand

5 min On Demand

Physical System Operation Archived System

Operation History

5 min

5 min On Demand

On Demand

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung17 17

Demand Forecast

Demand forecast takes DR, DER, and Wind generation into account.

Need to integrate various forecast engines to achieve performance.

Easy manipulation of forecast profile (similar day, transformation etc.)

Comprehensive Operating Plan (COP)

SKED 1t=30,60,90,120,180...720..

SKED 2t=15,30,45,60...

SKED 3 t=5,10,15...

5 min

Quarter Hourly

Hourly

Outages

Demand Forecast

Adaptive Model Management

5 min to Hourly

On Demand

Asynchronous

Explicit Real-time Dispatch

Implicit/Indirect Dispatch After-the-Fact Forensic Analysis

Perfect Dispatch

5 min On Demand

5 min On Demand

Physical System Operation Archived System

Operation History

5 min

5 min On Demand

On Demand

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung18 18

Adaptive Model Management

Adaptive Constraint Modeling (ACM) ACM uses intelligent methods to

preprocess transmission constraints based on historical and current network conditions, load forecasts, and other key parameters. It shall have ability to achieve smoother transmission constraint binding.

Adaptive Generator Modeling (AGM) AGM will provide other GCA

components information related to specific generator operational characteristics and performances. The resource “profiles” may contain parameters such as ramp rate, operating bands, predicted response per MW of requested change, Max & Min limits, etc.

Comprehensive Operating Plan (COP)

SKED 1t=30,60,90,120,180...720..

SKED 2t=15,30,45,60...

SKED 3 t=5,10,15...

5 min

Quarter Hourly

Hourly

Outages

Demand Forecast

Adaptive Model Management

5 min to Hourly

On Demand

Asynchronous

Explicit Real-time Dispatch

Implicit/Indirect Dispatch After-the-Fact Forensic Analysis

Perfect Dispatch

5 min On Demand

5 min On Demand

Physical System Operation Archived System

Operation History

5 min

5 min On Demand

On Demand

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung19 19

Comprehensive Operating Plan (COP)

COP has the repository of all operating plans in a multi-stage decision process.

Each stage in the decision process generates a set of schedules that are reflected in its corresponding COP (COPi)

The aggregated results from the multi-stage decision process are captured in the total COP (COPt), which is the merged outcome of the individual COPi’s.

A COP contains quantities (e.g. MW generation level) being scheduled over different Operating Intervals.

Operator interaction is typically with COPt

Current Operating Plan (COP) – COP_1

Input Configurator

Current Operating Plan (COP) – COP_2

Current Operating Plan (COP) – COP_3

Consolidated Current Operating Plan (COP) – COP_total

Plan Consolidation

SKED 1Output Plan-

Update

Input Configurator SKED 2

Output Plan-

Update

Input Configurator SKED 3

Output Plan-

Update

Consolidated COP with Operator Over-rides

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung20 20

Benefits of COP

Holistic forward-looking view of operating plan

Modular SKED Multiple SKEDi’s are coordinated using subordinate COPi’s

which are synchronized into the overall COPt.

This removes the need for individual SKED applications to communicate with each other directly.

Flexible design with high availability: SKED’s may be added, removed and/or modified with minimal

impact on the other SKEDs and COPs.

Ensures high availability for the mission critical real-time GCA SKED functions. Failure of any one or more SKED components will cause smooth degradation of, instead of abrupt service interruptions to, real-time dispatch instructions.

Intrinsic flexibility enables low-risk, cost-effective business process evolution.

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung21 21

Practical Applications of COP: An Example

NCG (North China Grid) applies the concept of COP to build a unified scheduling framework.

Scheduling processes range from annual planning to real-time dispatch.

NCG generation scheduling processes:Rolling forward scheduling monthly contract generation

based on annual contracts.Rolling forward scheduling daily contract generation

based on monthly contracts.Day-ahead quarter-hourly generation scheduleRolling forward intra-day GCA SKEDs.

COP streamlines the business processes.

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung22 22

North China Grid Generation Scheduling Coordination

Day-Ahead Scheduling

(e.g. April 11, 2008)

23:45 23:30 23:15 .. .. .. .. .. 01:00 00:45 00.30 00:15 4/10/2008::D

Daily Contract Generation from latest Month-to-day scheduling results

Month-to-Day Scheduling

(e.g. April 2008)

30 29 28 .. .. .. .. .. .. 3 2 1 3/16/2008::M

Monthly Contract Generation – from latest Annual-to-Month Scheduling results

30 29 11 10 9 8 2 1 4/10/2008::M

Annual-To-Month Scheduling

(e.g. year 2008)

D N O S A J J M A M F J 12/15/2007::A

Annual Contract Generation

D N O S A J J M A M F J 3/15/2008::A

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung23 23

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung24 24

Generation Control Applications (GCA)

Optimization engine for security-constrained multi-period, time coupled commitment and dispatch. Mixed Integer Programming (MIP) / Linear Programming (LP) based

Support both price- and cost-based modeling and analysis, for energy, ancillary services, demand response, energy conservation, and emission reduction.

Coordinate multiple scheduling time horizons (Intra-day, near real-time, real-time) with Comprehensive Operating Plan (COP).

Scenario-based robust scheduling and dispatch

Typical Configuration: SKED-DA: day-ahead resource commitment (hourly interval for a

look-ahead window of a day or two)

SKED 1: intra-day incremental resource commitment (15 min to hourly intervals for a look-ahead window of 6-8 hours)

SKED 2: Fast-start resource commitment (15 min intervals for a look-ahead of 2-4 hours)

SKED 3: Real-time dispatch of generating resources every 5 min

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung25 25

GCA - Dynamic Dispatch

0

100

200

300

400

500

t0 t1 t2 t3 t4

time

MW

Alta D Parkcity D Sundance D Brighton DAlta S Parkcity S Sundance S Brighton S

Dynamic dispatchBrighton ($10)backs down to

allow pre-ramping

Dynamic dispatch

Alta ($11) and Parkcity ($15)

pre-ramp

Dynamic dispatchSundance ($95)

can produce less

Sequential Dynamic

Cost t1 t2 t3 t4 totalDynamic dispatch 9570 10670 20845 15570 56655Sequential dispatch 9420 10495 23220 20070 63205

SKED3 sequential vs. dynamic dispatch

Value of pre-ramping

PriceE MaxRampUp MaxRampDn PgSE

Alta 11 5 100 20Parkcity 15 5 100 10Solitude 30 10 100 0

Sundance 95 100 100 50Brighton 10 10 100 420

t0 t1 t2 t3 t4Alta 20 20 20 20

Parkcity 10 10 10 10Solitude 0 0 0 0

Sundance 50 50 50 50Brighton 350 350 350 350

Pgmin

t0 t1 t2 t3 t4Alta 150 150 150 150

Parkcity 150 150 150 150Solitude 0 0 0 0

Sundance 400 400 400 400Brighton 500 500 500 500

Pgmax

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung26 26

t0 t1 t2 t3 tn t1(sc2)

SKED-2 (M)

Low

SE time stamp

Pgmin(tn)

....

SE

Pgmax(tn)

High

Medium

t2(sc2) t3(sc2)

COP Coordination - Reachability

Envelope of reachability

Coupling between SKED2 and SKED3 to ensure that SKED3 solution gets into the envelope of SKED2.

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung27 27

GCACOP – Resource Status Override

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung28 28

GCASKED Overview

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung29 29

GCACOP Overview

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung30 30

Dimension Coverage in Smart Dispatch/GCA Applications

Time

Scen

ario

s

SKED 3

SKED

-DASK

ED 1

SKED

2

(Rob

ustn

ess)

(ForensicAnalysis)

(Vision)

ClassicalDispatch

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung31 31

Outline

Introduction Smart Grid Challenges Smart Dispatch Framework Generation Control Applications (GCA) Conclusions

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung32 32

Conclusions

Discussed the vision and the challenges of Smart Dispatch in the context of control center’s operations for the evolving smart grid environment.

Presented the framework of Smart Dispatch Proposed a new dispatch system (GCA)Cope with the increasing amount of uncertaintiesProvide a better holistic and forward-looking view of system

conditions and generation patterns and help system operators to make better decisions.

An example to apply COP is given. GCA is deemed critical for the success of efficient power

system operations in the near future.

Copyright © 2009 AREVA T&D Inc. All Rights Reserved. Kwok Cheung33 33

Q & A