Industrial Engineering
For
Mechanical Engineering
By
wwwthegateacademy com
http://www.thegateacademy.com/http://www.thegateacademy.com/http://www.thegateacademy.com/http://www.thegateacademy.com/http://www.thegateacademy.com/http://www.thegateacademy.com/http://www.thegateacademy.com/ -
8/10/2019 GATE Industrial Engineering Book
3/12
Syllabus Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
080 65700750 i f @th t d C i ht d W b th t d
Syllabus for Industrial Engineering
Production Planning and Control: Forecasting models, aggregate production planning,
scheduling, materials requirement planning.
Inventory Control: Deterministic and probabilistic models; safety stock inventory
control systems.
Operations Research: Linear programming, simplex and duplex method, transportation,
assignment, network flow models, simple queuing models, PERT and CPM.
Analysis of GATE Papers
(Industrial Engineering)
Year Percentage of marks Overall Percentage
2013 6.00
7.85
2012 5.00
2011 0.00
2010 12.00
2009 11.00
2008 9.33
2007 5.33
2006 10.67
2005 11.33
-
8/10/2019 GATE Industrial Engineering Book
4/12
Contents Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
080 65700750 i f @th t d C i ht d W b th t d P i
C O N T E N T S
Chapter Page No.
#1. Production, Planning and Control 1 23
Forecasting 1 3
Statistical Forecasting 4 5
Production Planning and Control 5 7
Solved Examples 7 14
Assignment 1 15 16
Assignment 2 17 18
Answer Keys 19
Explanation 19
23
2. Inventory Control 24 48
Inventory 24 25
Inventory Models 25 37
Solved Examples 37 41
Assignment 1 42 43
Assignment 2 43 44
Answer Keys 45
Explanations 45 48
3.Operations Research 49 119 Introduction 49
Linear Programing 49 52
Characteristics of Corner Points 52 56
Simplex Method 56 62
Transportation Problem 62 82
Assignment Problems 82 84
Algorithms to Solve Assignment Model 84 85
Optimality Test of Total Opportunity Cost Matrix 86 89
Queuing Models 89 97
CPM and PERT 97
Methodology of CPM 98 Terminology used in CPM/PERT 98 99
Rules of Constructing Network Diagram 100
Difference Between CPM and PERT 100 101
Solved Examples 102 109
Assignment 1 110 111
Assignment 2 112 114
Answer Keys 115
Explanations 115 119
-
8/10/2019 GATE Industrial Engineering Book
5/12
Contents Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, Keshava Krupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
080 65700750 i f @th t d C i ht d W b th t d P ii
Module Test 120 130
Test Questions 120
125 Answer Keys 126
Explanations 126 130
Reference Books 131
-
8/10/2019 GATE Industrial Engineering Book
6/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 1
CHAPTER 1
Production, Planning and Control
Forecasting
The main purpose of forecasting is to estimate the occurrence, timing or magnitude of future
events. Once, the reliable forecast for the demand is available, a good planning of activities is
needed to meet the future demand. Forecasting thus provides the input to the planning and
scheduling process.
Types of Forecasting
Long range forecast
Long range forecast consists of time period of more than 5 years. The long range forecasting
is useful in following areas
Capital planning
Plant location
Plant layout or expansion
New product planning
Medium range forecast
Medium range forecast is generally from 1 to 5 years. The medium range forecasting is
useful in the following areas
Sales planning
Production planning
Capital and cash planning
Inventory planning
Short range forecast
The short range forecast is generally for less than 1 year
Purchasing
Overtime decision
Job scheduling
Machine maintenance
Inventory planning
-
8/10/2019 GATE Industrial Engineering Book
7/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 2
Quantitative Methods of Forecasting
1. Extrapolation
Extrapolation is one of the easiest ways to forecast. In this method, based on the past fewvalues of production capacity, next value may be extrapolated on a graph paper.
2.
Simple moving average
In this method, mean of only a specified number of consecutive data which are most recentvalues in the series is calculated. Forecast for ( t+1)thperiod is given by
Where,Di= Actual demand for ithperiod & n= Number is periods included in each average
3.
Weighted moving average
In this method, more weightage of given to the relatively newer data. The forecast is theweighted average of data.
Where, Wi= Relative weight of data for i thperiod and
It may be noted that when more weight is given to the recent values, the forecast is nearerto likely trend. Weighted moving average is advantageous as compared to simple movingaverage as it is able to give more importance to recent data.
Example
The value of moving average base n lies between
A.
0 & 1
B. 2 & 10
C. -1 & 1D. None of the above
[Ans: A]
4. Exponential smoothing
In the exponential smoothing method of forecasting, the weightage of data diminishesexponentially as the data become older. In this method all past data is considered. The
weightage of every previous data decreases by (1-), where is called as exponentialsmoothing constant.
( ) ( ) ( ) Where,
Di= One period ahead forecast made at time t
Dt= Actual demand for tthperiod
Smoothing constant (0 )Comments regarding Smoothing constant Smaller is the value of , more is the smoothing effect in forecast.
Higher value of gives more robust forecast and response more quickly to changesHigher value of gives more weightage to past data as compared to smaller value
-
8/10/2019 GATE Industrial Engineering Book
8/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 3
Example
The limitation in moving average method for forecasting cans
A.
Demand pattern is stationaryB. Demand pattern is varyingC. Demand pattern has a constant mean value
D. Both A & C
[Ans: D]
Example
ind relationship between exponential smoothing coeff () and N, so that responses are sameSolution
Average life of data S = 0 (N )
or, average life of data =()
S =
()()
(N )
= ( N ) . . . . (i)
Average life of data for exponential smoothing
S 0* * ( ) * ( )
+ . . . . . . . . + (N )( )
+ . . . .. = ( ) ( ) ( )+ . . . . . . . . [( ) ( ) ( ) ] . . . . (ii)
Now; multiplying (ii) by (1 ) and subtracting from (ii) we get [( ) ( ) ( ) ( ) ]
( )S [( ) ( ) ( ) ]S[ ( )] [( ) ( ) ( ) ( ) ]
, () ( ) ()
,
()From (i) & (iii)
2 N , Or, N
Or, (N) , Or,
-
8/10/2019 GATE Industrial Engineering Book
9/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 4
Statistical Forecasting
Statistical forecasting is based on the past data. We evaluate the expected error for the statistical
technique of forecasting. Some common regression functions are as follows
Let
Ft= Forecast for time period t
dt= Actual demand for time period t
t= time period
1. Linear Forecaster
Ft= a+bt
Where a and b are parameters
2.
Cyclic Forecaster
Ft= a+ uCos (2/N)t + vSin (2/N)t
Where a, u and v are parameters and N is periodicity
3. Cyclic Forecaster with Growth
Ft= a+ bt+ uCos (2
/N)t + vSin(2
/N)t
Where a, b, u and v are parameters and N is periodicity
4.
Quadratic Forecaster
Ft=a +bt+ct2
Where a, b and c are parameters
Accuracy of Forecast
Many factors affect the trend in data therefore it is impossible to obtain an exact right forecast.Below are the tools that are used to determine the error in the forecasted value.
1. Mean Absolute Deviation MAD)
This is calculated as the average of absolute value of difference between actual and
forecasted value.
MAD = ||
Where,
Ft= Actual demand for period t
Dt= Forecasted demand for period t
n= number of periods considered for calculating the error
-
8/10/2019 GATE Industrial Engineering Book
10/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 5
2.
Mean Sum of Square Error MSE)
The average of squares of all errors in the forecast is termed as MSE. Its interpretation is
same as MAD.
( )
3.
BIAS
BIAS is calculated as the average of the difference between actual and forcast value. A
positive value means under estimation and negative value means over estimation.
( )
Production Planning and Control
Production planning and control is one of the most important areas of industrial management.
This aims at achieving the efficient utilization of resources in any organization through planning,coordination and control of production activities.
Phases of PPC
Preplanning
Product development and design
Process design
Work station design
Factory layout and location
Planning Different Resources
Material
Method
Machine
Men
Control
Inspection
Expedition
Evaluation
Dispatching
Production Planning and Control Steps
-
8/10/2019 GATE Industrial Engineering Book
11/12
Chapter 1 Industrial Engineering
THE GATE ACADEMY PVT.LTD. H.O.: #74, KeshavaKrupa (third Floor), 30th
Cross, 10th
Main, Jayanagar 4th
Block, Bangalore-11
: 080 65700750 info@thegateacademy com Copyright reserved Web: www thegateacademy com Page 6
1.
Routing
Routing is the process of deciding sequence of operations (route) to be performed during
production process. The main objective of routing is the selection of best and cheapest wayto perform a job. Procedure for routing is as follows
Conduct an analysis of the product to determine the part/ component/ sub-assemblies
required to be produced.
Conduct the analysis to determine the material needed for the product.
Determine the required manufacturing operations and their sequence.
Determine the lot size.
Determine the scrap.
Estimate product cost.
Prepare different forms of production control.
2.
Scheduling
Scheduling involves fixing the priorities for different jobs and deciding the starting andfinishing time of each job. Main purpose of scheduling is to prepare a time-table indicatingthe time and rate of production, as indicated by starting and finishing time of each activity.
Scheduling will be discussed in detail in next section.
3.
Dispatching
Dispatching is the selection and sequencing of available jobs to be run at the individualworkstations and assignments of those jobs to workers. Functions of dispatching are asunder.
Collecting and issuing work centre
Ensuring right material, tools, parts, jigs and fixtures are available.
Issues authorization to start work at the pre-determined date and time.
Distribute machine loading and schedule charts
4.
Expediting
This is the final stage of production planning and control. It is used for ensuring that thework is carried out as per plans and due dates are met. The main objective is to arrest
deviations from the plan. Another objective is to integrate different production activities tomeet the production target. The following activities are done in expediting phase
Watching the progress of the production process.
Identification of delays, disruptions or discrepancies.
Physical control of work-in-progress through checking
Expediting corrective measures.
Coordinating with other departments.
Report any production related problems.
-