garrison project update to focus group presentation (novemeber 6, 2014)

9
GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014 Garrison Elementary School Focus Group Meeting Thursday, November 6, 2014

Upload: dc-department-of-general-services

Post on 19-Jun-2015

182 views

Category:

News & Politics


0 download

DESCRIPTION

About the Department of General Services: The mission of the Department of General Services (DGS) is to elevate the quality of life for the District with superior construction, first-rate maintenance and expert real estate management. By building and maintaining safe and green state-of-the-art facilities which foster economic growth and elevate educational environments, our trusted and skillful employees create modern and vibrant communities across all of the District of Columbia. ### Follow DGS on Twitter, Facebook, and Visit Our Website! Follow DGS on Twitter at @DCDGS - Facebook at facebook.com/dcdgs Visit DGS at dgs.dc.gov

TRANSCRIPT

Page 1: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

Garrison Elementary School

Focus Group Meeting

Thursday, November 6, 2014

Page 2: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

AGENDA

•  Introductions •  Rules of the Road •  Meeting Goals •  Site Aerial •  Project Budget •  What has been Considered •  Project Status •  Next Steps

Page 3: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

FOCUS GROUP MEETING GOALS

•  Introduce Garrison Project Team

•  Introduce Focus Group Members & Their Role

•  Provide Project Status

•  Hear concerns of the community

•  Next Steps

Page 4: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

N

Aerial View of Current School Site

Page 5: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

CURRENT PROJECT BUDGET

• FY15 = $18m Million

• FY16 = $22 Million

• Total Budget - $40 Million

Page 6: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

WHAT WE HAVE CONSIDERED

•  Achieving a World Class Elementary School

•  New Building or Major Renovations to Existing

•  Pick-up and Drop-off •  Traffic •  Parking

Page 7: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

PROJECT SCHEDULE •  11-03-14 Site Survey

•  12-15-14 Conceptual Design Drawings

•  04-15-15 Design Development Drawings (75%)

•  05-04-15 General Contractor prepares Guarantied Maximum Price (GMP)

•  06-01-15 Permit applications submitted to DCRA

•  06-15-15 Construction Start - Site Work

•  08-25-16 Substantial Completion of Project for first day of classes

•  05-01-17 TBD - Demolition of existing school & completion of site work

Page 8: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014

Questions & Answers

Page 9: Garrison Project Update to Focus Group Presentation (Novemeber 6, 2014)

GARRISON ELEMENTARY SCHOOL – NOV. 6, 2014