g.275/wssr-611920/2019-20 work study to review the …
TRANSCRIPT
G.275/WSSR-611920/2019-20
WORK STUDY TO REVIEW
THE STAFF STRENGTH AT
SSE/SIGNAL/PLNI-
MDU - DIVISION.
SOUTHERN RAILWAY
PLANNING BRANCH
G.275 / WSSR-611920 / 2019-20
STUDIED BY
WORK STUDY TEAM
OF
PLANNING BRANCH
DECEMBER - 2019
WORK STUDY TO REVIEW
THE STAFF STRENGTH AT
SSE/SIGNAL/PLNI - MDU DIVISION
I N D E X
CHAPTER NUMBER
CONTENTS PAGE
NUMBER
(i) ACKNOWLEDGEMENT
1 (ii) AUTHORITY
(iii) TERMS OF REFERENCE
(iv) METHODOLOGY
(v) SUMMARY OF RECOMMENDATIONS 2
CHAPTERS
I INTRODUCTION 3 - 4
II PRESENT SCENARIO 5 - 39
III CRITICAL ANALYSIS 40 - 43
IV PLANNING BRANCH’S REMARKS ON CO-ORDINATING OFFICER’S VIEWS
44
V FINANCIAL SAVINGS 45
ANNEXURES
I S.A.V.E. STATEMENT 46
II DESU STATEMENT – SSE/SIG/PLNI 47
1
(i) ACKNOWLEDGEMENT
Southern Railway, Headquarters, Planning Branch Work Study team
sincerely acknowledges the valuable guidelines and co-operation rendered by the
DRM/MDU, ADRM/MDU, Sr.DSTE/MDU, ADSTE/MDU Co-ordinating
Officer, SSE/SIG/DG Co-ordinating Supervisor, SSE/SIG/PLNI and other
Supervisors and Staff of SSE/SIG/PLNI Unit for their immense help to conduct
this Work Study with excellence.
(ii) AUTHORITY
Annual Programme of work studies for the year 2019-20.
(iii) TERMS OF REFERENCE
To review the staff strength at SSE/SIGNAL/PLNI
(iv) METHODOLOGY
The following methodology has been adapted while conducting this Work
study:-
1) Collection of data.
2) Field Study to observe the present working system.
3) Discussion with Division Officers and Supervisors
4) Application of yardstick/bench mark
5) Arrived man power on need basis if required
2
(iv)
SUMMARY OF RECOMMENDATIONS
Recommendation:
3 posts of Technician Gr.I/Signal Maintainer in Level – 5 (GP Rs.2800) and 2
posts of Technician Gr.III/Signal Maintainer in Level – 2 (GP Rs.1900) are found
surplus to the requirement, the same may be surrendered and credited to the
Vacancy Bank.
(Total – 5 Posts)
3
CHAPTER – I
1.0 INTRODUCTION
1.1 Indian Railways is amongst the various possessions owned by our country
that makes India and people of India proud all over the Globe and it is in
news as a fast profit making Organization.
1.2 The great Indian Railways routed its path to the length and breadth of our
country.
1.3 The part of Staff cost in Total expenditure is about 33.5% and it is steadily
growing 12-15% in every year. To achieve the target Operation Ratio, the
Planning Branch/HQ Work study wing continuously strives to identify the
optimum Man Power to all the units of our Zone.
1.4 Madurai division is one of the state-of-art modern Railway station in
Southern Railway. Madurai is bounded on the North by the districts of
Dindigul and Tiruchchirappalli, Sivagangai on the east, Virudhunagar on
the south and Theni on the west. Madurai lies on the flat and fertile plains
of the river Vaigai. The city built around the famous Meenakshi Amman
Temple is also referred as Koodal in olden days which mean an assembly
of scholarly people, referring to the three Tamil Sangams held at Madurai.
1.5 Signaling system is essential for the safe and speedy movement of trains.
In Indian Railways, this system has made tremendous progress from old
Semaphore type to electrical signaling with Multiple Aspect Color Light
Signals (MACLS).
1.6 Some of the mile stones reached in Signaling system is as follows:
➢ MACLS – Better visibility, quick operation and less maintenance.
➢ BPAC – enhancement in the safety of train by proving the complete
arrival of train, elimination of the delay in granting line clear.
➢ Track circuiting – Detection of the presence of a train on the track
in order to prevent the arrival of the train on occupied line.
➢ AFTC – Replacement of conventional DC track circuit in the
electrified sections, avoidance of failures due to block joint shorting.
4
➢ TPWS – Information to the driver to regulate the speed of the train,
automatic actuation of the brakes without the intervention of the
driver.
➢ Datalogger – Detection of cases in respect to passing the signal at
danger by the driver and all other operations connected with signals,
points, track circuits etc with time and clues in case of accidents.
This can avoid manipulations and help to arrive at correct
conclusions.
➢ IPS - Continuous availability of power supply for modern electrical
signaling systems by enhancing the reliability of working of the
signaling system
➢ LED signals for CLS – Enhancement of life by reducing the
incidences of signal lamp fusing and consumption of less power.
The list is only indicative and not exhaustive.
1.7 An attempt has been made to study the present system of working at
SSE/Sig/PLNI unit of MDU division based from Benchmarking norms. With
the enhanced DESUs/manpower and further scope of growing technology
in terms of less maintenance involving financial implications, the workload
vs. requirement of the manpower is critically examined in the subsequent
chapters.
1.8 The salient features of most of the advanced technologies/equipments
involving less/free maintenance and the investments made in the
procurement of new assets etc. have been taken into account while
conducting the study.
This Study is confined to Signal & Telecom Department of MDU
Division/Southern Railway.
1.9 The Signal Department is controlled by CSE in Zonal level and Sr. DSTE in
Division level under the overall head of PCSTE who is the Principal HOD.
1.10 This Work study is circumscribed to assess the optimum Man Power
requirement of SSE/Signal/PLNI Unit.
5
CHAPTER – II
2.0 PRESENT SCENARIO:
2.1 Organization: The Signal Unit SSE/Signal/PLNI is headed by Sr.DSTE/MDU
and under the direct control of DSTE and ADSTE/MDU. There are 2
Supervisors and 16 staff working against the sanctioned strength of 25 and net
vacant is 7. The SAVE statement is given by Sr.DPO/MDU on 16.07.19 vide
Annexure-I. Palani town is having the pilgrimage temple of Palani Andavar
Murugan Temple which is known as one of the Arupadaiveedu Temple.
2.2 Organisational Structure:
The hierarchy is as:-
2.3 This SSE/Signal/PLNI office is located at PLNI station and responsible to
maintain signal assets from excluding DG Junction to GMGM and excluding
POY station. The above three sections jurisdiction and details are given
below:
API ODC CHPT PLNI PPTR MVRD UDT & GMGM
ADSTE/MDU
SSE/SIG/PLNI
Technician/ Sig. Maintainers
MNM
DSTE/MDU
Sr. DSTE/MDU
Helpers
6
2.4 The Stations in the jurisdiction of SSE/Signal/PLNI
Station No. of Lines
No. of Routes
Located at km Class Standard of Interlocking
API 3 30 10.698 B STD II R - RRI
ODC 3 30 32.840 B STD II R – RRI
CHPT 3 30 42.790 B STD II R – RRI
PLNI 4 58 58.262 B STD II R – RRI
PPTR 3 30 71.814 B STD II R - RRI
MVRD 3 30 82.582 B STD II R - RRI
UDT 3 30 91.986 B STD II R - RRI
GMGM 3 30 105.54 B STD II R - RRI
2.5 Details of Inter locked LC Gates / Block
Sl.No. Name of LC
Gates KM Class Block Instrument/
Method of working
1 LC No.8 17/600-700 B FM Diado
2 LC No.11 9/600-700 C FM Diado
3 LC No.12 12/500-600 C Push Button
4 LC No.18 17/600-700 C Push Button
5 LC No.24 27/00-100 C Push Button
6 LC No.30 30/700-800 C Push Button
7 LC No.37 35/700-800 Special Push Button
8 LC No.38 36/100-200 C Push Button
9 LC No.40 37/200-300 C Push Button
10 LC No.44 41/500-600 C Push Button
11 LC No.49 45/900-46/00 Special Push Button
12 LC No.56 52/500-600 Special Push Button
13 LC No.58 53/500-600 C Push Button
14 LC No.59 53/800-900 C Push Button
15 LC No.64 60/400-500 A FM Diado
16 LC No.65 63/600-700 C FM Diado
17 LC No.68 67/700-800 A FM Diado
18 LC No.77 76/00-100 B FM Diado
19 LC No.80 79/400-500 B FM Diado
7
20 LC No.90 89/500-600 C FM Diado
21 LC No.91 90/100-200 C FM Diado
2.6 Signal Details
Station Type of Signal
Total No. of
Signals 4 aspect 3 Aspect 2 Aspect
Type of Route
Remarks
API MACLS 12 - 6 2 Junction LED
ODC MACLS 12 - 6 6 Junction LED
CHPT MACLS 12 - 6 6 Junction LED
PLNI MACLS 13 - 5 8 Junction LED
PPTR MACLS 12 - 6 6 Junction LED
MVRD MACLS 12 - 6 6 Junction LED
UDT MACLS 12 - 6 6 Junction LED
GMGM MACLS 12 - 6 6 Junction LED
2.7 SSE / S&T /PLNI of Lever Statements / Units for 2018-19.
Sl. No. Station / LC No. Lever Units
1 LC 8 130
2 API 795
3 LC 18 79
4 LC 24 79
5 ODC 866
6 LC 37,38 & 40 185
7 CHPT 762
8 LC 49 79
9 LC 56 79
10 LC 58 & 59 150
11 PLNI 1080
12 LC 65 79
13 LC 68 79
14 LC 77 79
15 PPTR 707
8
16 LC 80 79
17 MVRD 743
18 UDT 797
19 GMGM 744
20 POY 3
Total 7594
2.8 TYPES OF SIGNALLING AND SYSTEM OF WORKING:
i. Absolute Block System
ii. Multiple Aspects Color Light Signaling (MACLS)
2.9 MAXIMUM PERMISSIBLE SPEED OF THE SECTION:
➢ DG-PLNI section: 75 Kmph for EY Goods & 60 Kmph for CC+6/8+2t
➢ PLNI-POY section: 70 Kmph for Goods and 60 Kmph for Goods loaded
CC+6/8+2 t.
2.10 LINE CAPACITY UTILIZATION:
✓ DG-PLNI section: 32 %
✓ PLNI-POY section: 28 %
2.11 Signaling Staff & Signal installations and their Functions:-
Strength and charges of SSE, JE, Technicians, section gangs and the strength
of the office staff shall be fixed by the Principle Chief Signal &
Telecommunication Engineer with consideration of nature of installation
density of work, size of installation & general importance of work.
2.12 STAFF DISTRIBUTION: The Book of sanction of the Unit SSE/Signal/PLNI is 25 and the actual is 17
and the net vacancy is 8. The Sanction, Actual, Vacant, Excess Statement is
furnished as Annexure -I
The actual staff strength of this Unit is 2 Supervisors, 8 Technicians and 7
Helpers together makes 17. The distribution is as below:
9
Sl. No.
Category Level Sanction Actual Vacancy
1 SSE/Signal 7 2 1 1
2 JE/Signal 6 1 1 0
3 Sr.Tech/Sig. Mtr. 6 2 2 0
4 Tech.Gr.I/Sig. Mtr. 5 9 2 7
5 Tech.Gr.II/Sig. Mtr. 4 1 1 0
6 Tech.Gr.III/Sig. Mtr. 2 5 3 2*
7 Helper/Signal 1 5 7 +2
Total 25 17 8
* One Re-engaged staff in Tech.Gr.III/Sig. Mtr.
2.13 Terminologies in installations and functions:-
In Indian Railways, this system has made tremendous progress from old
Semaphore type to electrical signaling with Multiple Aspect Color Light Signals
(MACLS). Mile stones reached in Signaling system are as follows:
➢ MACLS – Better visibility, quick operation and less maintenance.
➢ BPAC – enhancement in the safety of train by proving the complete
arrival of train, elimination of the delay in granting line clear.
➢ Track circuiting – Detection of the presence of a train on the track in order
to prevent the arrival of the train on occupied line.
➢ AFTC – Replacement of conventional DC track circuit in the electrified
sections, avoidance of failures due to block joint shorting.
➢ TPWS – Information to the driver to regulate the speed of the train,
automatic actuation of the brakes without the intervention of the driver.
➢ Data-logger – Detection of cases in respect to passing the signal at
danger by the driver and all other operations connected with signals,
points, track circuits etc. with time and clues in case of accidents. This
can avoid manipulations and help to arrive at correct conclusions.
➢ IPS:- Continuous availability of power supply for modern electrical
signaling systems by enhancing the reliability of working of signals.
➢ LED Signal Unit: – Enhancement of life with reduction in incidences of
signal lamp fusing maintenance cost is reduced, as they don't need
frequent replacement except occasional cleaning.
10
➢ Electronic Interlocking(EI) like Solid State Interlocking(SSI)
➢ Route Relay Interlocking (RRI) & Panel Interlocking(PI)
➢ Point Machines, Battery Charger, DG Sets, Inverters. LED lamps.
➢ SPD - Surge Protection Device, SSDAC-Single Section Digital Axle
Counter,
➢ ABS–Automatic Block Signaling, IBS-Intermediate Block Signaling
➢ PC–Personal Computer
➢ Auto Exchanges(AX), Trunk & Manual Exchanges(TX), Line Plant(LP)
➢ Telegraphy(TY), Traffic Train Control(TC), Sound Distribution
System(PA)
➢ Electric Clocks(E/C), , Yard Communication System(YARD)
➢ High Frequency Radio Communication System(HF)
➢ Line of Sight Systems(UHF/VHF/Microwave)(MW), Power Plant
System(PP)
➢ Carrier Communication(CC), Cable (CABLE), Optical Fiber Cable(OFC)
➢ Repeater Station Cable(RSQ), Cable Hut(CHQ), Computers(COMP)
➢ Token-less Block Instruments, Integrated surveillance system, Data
loggers, LED lamps, train display Boards, etc.
2.14 All enhances safety enhancement of safety levels in train operations on IR,
with vast improvement in signaling system, safety, & security of train
operations, and better customer interface in Railways.
2.15 Interlocking can be defined as an arrangement between points, signals and
other appliances interconnected electrically/mechanically/both to ensure
objectives viz.;
a) It shall not be possible to take ‘off’ signals for a route unless all the points
are correctly set and the facing points are locked for that route,
b) Once the signals are cleared, it shall not be possible to alter the points on the route unless the signals are put back to ‘on’,
11
c) Even though the signals are put back to ‘on’, it shall not be possible to alter the points unless the intended movement over such points is completed,
d) It shall not be possible to operate signals leading to conflicting
movements,
e) The points and signals can be operated only in a sequence to ensure safety, and
f) Where signals are connected to any devices, the signal shall not obey
until the conditions for working such devices are fulfilled.
2.16 The above objectives can be summarized as four essentials of interlocking:- i)
setting of route, ii) locking, iii) holding, iv) prevention of conflicting movements.
2.17 Standards of interlocking:- Depending upon the standards of safety devices
provided at the stations, in conformity to the speed factor, there are four
standards of interlocking, namely Std.I(R), Std.II(R), Std.III(R) and Std.IV(R).
The signal equipment, the manner of locking facing points and operation of
points and signals differ in the different standards of interlocking.
2.17.1 Panel interlocking is a modern signaling system provided at the stations
wherein both points and signals are operated from a centrally located panel by
means of push buttons or knobs. This system essentially provides for relay
interlocking and has augmented safety features with consolidating interlocking.
2.17.2 The status of the points, signals and the reception lines is readily available on
hand to the Station Master, which makes for smoother operation.
2.18 Track circuits:-
Track Relays: - Shelf type track relays shall normally be overhauled every 10 years subject to a maximum of 12 years. Plug in type track relays have to be replaced on completion of 12 years or earlier if warranted by the actual condition of the relay and / or its usage. The ballast used on track in the vicinity of glued joints shall be cleaned to ensure efficient packing and drainage. The clearance from the underside of rail below a glued joint must not be less than 50mm.
12
2.19 Track Circuits - Periodicity of testing
- The operating characteristics of the track relay should be checked once every two years.
- Track Relays of shelf type must be overhauled at intervals not exceeding 10 years. Plug-in type track relays are to be replaced after 12 years (or earlier if warranted).
- Main cable should be tested once a year, tail cables once in 6 months.
- Train shunt test must be taken every time a track circuit is adjusted. It should be taken at parallel portions of the track also with minimum 0.5 ohm resistance.
2.20 Electric Point Machine:-
• Testing of Electric Point Machine for the individual integrity of contacts of point machines and corresponding detection relay in the relay room.
• Once in three months check & clean the carbon brushes and commutator with chamois leather until carbon deposits are disappeared. Track locking should be tested for tightness and friction free.
• Obstruction test should be carried out fortnightly by Signal Technician, monthly by Sectional JE(Sig.) & Quarterly by SSE(Sig.) in-charge.
• Insulation tests on the point machine to be conducted Half-yearly by Sectional JE (Sig.) & yearly by SSE (Sig.) In-charge.
The Meggering should be carried out at initial stages, before and after cable
laying with periodical maintenance.
Electric Point Machine:– Maintenance of Electric point machine, Maintenance schedules are as laid down in SEM part II strictly.
Parameters of Electric Point Machine
Description Siemens
Point Machine IRS
Point Machine IRS Point Machine
(Clamp type)
GRS 5 E Point Machine
Inspection
Schedule
Maintainer – fortnightly, JE (Sig.)-monthly & SSE(Sig.) [in-Charge]
Quarterly
13
2.21 Axle Counters:-
Applications of Digital Axle counters:
• Digital Axle counters both Single section and Multi section have a variety of following applications:
• Berthing tracks in station areas and yards.
• Point zones in station areas and yard.
• Automatic Signaling sections.
• Block working thro’ axle counters.
• Level Crossing warning system using axle counter.
• Intermediate Block Signaling (IBS) in Double line sections.
2.22 Digital axle counter is the advanced form of track circuit which has its own
advantages and additional safety features. Failure of axle counters in a station
or block section paralyses the movement of trains thereby affecting their
punctuality.
FRAUSCHER ACS2000- Multi Section Digital Axle Counter
Track circuits play a vital role in train operation by detecting the presence of train vehicle, thereby ensuring safety in train operation.
As these cards are technically sophisticated, on getting the Cards Repaired at the LAB concerned it shall be put in the system again.
2.23 Periodic Overhauling of Block Instruments:
Periodical overhauling interval shall not exceed ten years for Single Line Token Block Instruments and seven years for Double Line Block Instruments and Handle type Single Line Token less Block Instruments. Push Button Token less Block Instruments do not require overhauling. The associated polarized relay shall also be overhauled along with the Block Instrument.
14
2.24 Maintenance of SGE Double Line Block Instrument :
➢ Needle indicators must be properly maintained so that they operate fully and
return to the normal position, when the commutator is brought to Line Closed
position.
➢ It should be ensured that the commutator movement is smooth while turning it
from one position to another position.
➢ It should be ensured that commutator gets locked, when it is turned from Line
Clear to Train On Line position, before Train On Line indication contacts are
made.
➢ See that all terminals screws, nuts, lock nuts and locking screws are tight and
all split pins are open.
➢ Inspect the contact surfaces on the butterfly assembly. If pitted, clean them
with chamois leather.
➢ Check the resistance of indicator coil, lock coil and their working currents, if :
➢ Considerable difference is noted between subsequent readings, locate the
fault and rectify the same.
➢ Check the full lock notch and half lock notch on the locking drum, for their
correct shape & squareness. Correct them if necessary.
➢ Check that no loose wires get trapped in the moving parts.
➢ Check that only correct springs make when commutator is in “Line Clear” &
“Train On Line” positions.
➢ Check that the desired springs make when bell plunger is pressed and that
bell beats are registered properly when bell plunger is pressed by the adjacent
station.
➢ Check the coil resistance of bell relay, bell coil and their working currents
during inspections. If considerable difference is noticed between subsequent
readings, locate the fault and rectify it.
➢ Check the telephone battery, replace if necessary.
➢ All batteries must be kept clean. Terminals must be free from dirt and
corrosion.
➢ Ensure that wire connections at the terminals are firm.
➢ Check and ensure that earth and earth connections are effective and in good
condition.
➢ Ensure that common earth is not used for indication circuit because in case of
leakage or breakage of one earth, both the instruments will come in series.
➢ In case of “Train on Line” position +ve will on line & -ve on earth from the line
battery.
15
➢ At that time for another line clear the -ve will be on line & +ve on earth, during
this period if earth breaks PR (Polarized relay) may attract to Train On Line
position & a PD (potential drop) is created. If the value of PD is more than 5
volts, PR will attract to line closed position when a train is in the section. This
enables the Last stop signal to be off for 2nd train which is unsafe hence
common earth should not be provided.
2.25 Single line Handle type Token less block instrument (FM coded)
Maintenance:-
▪ Always keep each part clean to ensure its proper working.
▪ Keep Terminals, bolts and plugs of Transmitter and Receiver always well
tightened to prevent any looseness of fixtures and consequent poor contact.
▪ All Contacts in. Block Handle, PB1, PB2 buttons S1, S2 switches are clean
and free from grease or dirt.
▪ All springs are in good condition and kept properly adjusted.
▪ Contact and switches are under appropriate pressure. The Contacting
Portion should be maintained smooth as they wear out at the time of sliding.
▪ All mechanical moving parts inside the tokenless Instrument work freely and
are well lubricated. Special Care to be taken during rainy weather to prevent
rusting and sticking of parts.
▪ Locking piece and locking segments inside the token-less instrument shall
be cleaned regularly specially during rainy weather.
▪ No oil or grease should be applied in the locking piece and locking segment.
▪ At respective handle stops, there shall not be more than 0.5 mm clearance
between locking piece and the projection of locking segment.
▪ Between locking piece and the upper edge of the locking segment when the
former is in locked condition and between the Locking piece and the lower
edge of locking segment when the former is in unlocked condition there shall
be a slight clearance and there shall be no possibility of the locking piece
being lifted up.
▪ The lock armature works freely and the locking portion is properly forced
down for each locking portion.
▪ There is no undue tendency for the Lock Magnet to be held when
electrically de-energized.
▪ The magnet coil does not retain any Magnetism.
▪ Switches S1 and S2 should be checked regularly. Number of counter
operates serially;
▪ Number in every case is clear and visible.
▪ Connecting rod with shunt key and Block Handle assembly shall be
checked frequently.
16
▪ The minimum line battery voltage should be maintained at 21.5V.D C.
▪ The minimum line battery voltage should be maintained and ensure
operating voltage at the other instrument at 21.5 V D.C.
▪ The output voltage of receiver for operating CR1 or CR2 shall be 19.2V min.
▪ Transmitter - Source voltage - 24 V.DC Output
▪ Receiver-Source voltage-24 V.DC, Input voltage-0.2 V to 1.0 V(with VTVM).
▪ TOLK armature should be checked for its placement in the center channel
putting the fingertip at the edge of the armature on both sides lightly to check
easy play and full operation of parabolic indicator.
▪ When the input voltage is in the range of 0.2 V to 1.0 V (by VTVM) the
output terminal voltage should be 19.2 volt min.
2.26 Push button token-less Block instrument (PTJ make)-Guidelines for
installation & maintenance :
▪ Line Circuit with EARTH RETURN shall not be used.
▪ Local Battery voltage at the Instrument terminals on load should not be
below 24 Volts.
▪ Secondary cells of sufficient capacity may be used, as the maximum
working current per Instrument is about 1.2 Amps.
▪ The Local battery voltage on load should not exceed a maximum of 29 V as
it may affect the zener diode working.
▪ The difference between the local battery voltages of the interconnected
instruments on load should be kept to a maximum of 4 volts i.e. between 24 V
& 29 V.
▪ The line battery shall be capable of supplying a minimum current of 60 mA
on line but not more than 70 mA.
▪ The Line current shall be measured both at the transmitting and receiving
ends. There shall not be appreciable variations.
▪ Separate line battery should be provided for each instrument. Whenever
the line battery is changed the line current should be checked.
▪ Wherever dual bank batteries are used for line circuit, the current should be
measured before and after every change over. This is to assess the level of
charging required for the discharged battery bank.
▪ While installing these instruments, care shall be taken to ensure that the
Relay plug boards and the Relay contact springs are not damaged. (Keep the
Relays parallel while plugging/removing the Relays).
▪ Maintain correct polarity while connecting HOOTER leads.
17
▪ HMT cord should be connected to the respective terminals to ensure that no
current is drawn from the telephone battery when the HMT button is not
pressed.
▪ Whenever the instrument fails, interchanging of Relays and units shall not
be resorted to, without ascertaining the actual cause and this change may be
effected only if it is warranted.
▪ Relays and timer units shall not be left without the Relay retaining clip.
▪ Whenever the resistance or condensers are replaced in the units correct
values have to be selected and soldered properly.
▪ Oiling of TLB switch contacts shall be avoided.
▪ During periodical maintenance/Inspection, the charger shall be switched
‘OFF’ and the working of the Relays has to be observed for few operations.
The terminal voltage should also be monitored during the working in order to
ensure the condition of the battery.
▪ All Instruments should be paired with similar type only.
▪ The entire latch Relays(QL1 Relays) should be in de-latched condition while
commissioning the equipment.
▪ Ensure all the removable connectors are locked perfectly in the plug board. 2.27 Electric Lifting Barrier:- Periodicity of Replacement of parts :
1) The spring loaded Carbon Brushes are meant for permanent usage. However the contacts made by the carbon brushes need to be closely watched so that the circuit controller operation is not affected. This should be watched every three months.
2) Check Gear Box for any leakage of oil every three months. Oil has to be replaced after 1 Lac operation or One year whichever is earlier.
3) For rest of the item periodic maintenance of 6 months is sufficient Quarterly maintenance-
Check clutch slippage torque. Adjust if required.
Check Timing Belt tension for both barriers & Hand Generator. Adjust if
required.
Check contacts of copper ring with carbon bushes of all circuit
controllers.
Annual maintenance:-
• Replace the oil in the barrier gear unit. Old oil is removed from the
bottom of the gear unit by opening the bottom plug. New oil is filled from the
top of the gear unit, by opening the top plug provided.
18
• Replace Timing Belts if worn out.
• Oil the clutch slippage bush.
Perform System changeover schedule in a hot standby EI system once in a month.
2.28 Electric Lifting Barrier :
▪ Fortnightly/Monthly maintenance
▪ Check for smooth operation of Barrier and auto stop of barrier in the fully open
and closed position. Adjust limit switches if required.
▪ Clean the inside and outside of mechanism.
▪ Tighten all fixing nuts and bolts of the mechanism base, gear box, motor,
boom and counterbalance channels.
▪ Operating current measurement.
▪ Quarterly maintenance
▪ Check clutch slippage torque. Adjust if required.
▪ Check Timing Belt tension, Adjust if required.
▪ Check and replace limit switches if contacts worn out.
▪ Check contact of Boom Lock Proving switch. Replace if required.
▪ Annual maintenance
▪ Replace the oil in the barrier and Hand Generator gear unit. Use gear oil
SAE 90 or equivalent.
▪ Replace Timing Belts if worn out.
▪ Replace Clutch plate if required.
▪ Oil the clutch slippage bush.
2.29 Effective or Maintenance-free earthing:-
This type of earthing is provided with earth electrode of a highly conductive,
corrosion-resistant material with low soil resistivity earth enhancement
compound around it. This arrangement eliminates the drawbacks of
conventional earthing such as corrosion of electrode and high and fluctuating
earth resistance.
Maintenance free earthing is provided for signaling and telecomm equipments
with solid state components requiring low earth resistance of the order of 1
Ohm such as Integrated Power Supply, Digital Axle Counter, Data Logger,
Electronic Interlocking etc. Earthing of signaling cables and equipments is
done to ensure reliable and safe operation of the equipments by limiting or
eliminating the induced voltages in signal and Block circuits.
19
2.30 Block Earths – Periodicity of testing:- Block earths and their connect ions
must be examined at intervals not exceeding one month and should be tested
for resistance once a year. Where the resistance exceeds 10 ohms, action
should be taken to reduce the resistance.
2.31 Loose wires for maintenance purposes:- The desired cable route should
be shown clearly on cable route plan showing the actual alignment of track,
giving offsets from permanent way or permanent structures.
2.32 Equipment – Disconnection Notice:- Before attending to the defect
involving interference with the interlocking gears, procedure laid down for
Disconnection Notice. While undertaking the items of work, it is essential that
the Station Master concerned be kept informed by the official of S&T
department undertaking the work so that Station Master on duty is aware that
the S&T staff is working on signaling gears at his station. Notice in the form
S&T (T/351) (Annexure – B of para1416 of Signal Engineering Manual) and his
permission obtained before the work is started.
1. The situations are grouped under three sets and the details under each group
are;
Group (A) – Situations not requiring the consent of on duty Station Master
Group (B) – Situations definitely requiring the consent of on duty SM.
Group(C) – Situations demand issue of Disconnection Notice is definitely.
2. Attending to signal and point failures:- As soon as the Station Master on duty
becomes aware of any failure of signaling equipment at his station governing
the movements of trains, he should immediately report such failures in writing
personally or through control phone to the MSM/ESM as the case may be and
to the Signal Inspector apart from advising all other officials in accordance
with S.R.3.68.3.
ESM/MSM who attends such failures shall record the failure in the proforma
as given on the reverse side of Annexure A of 1414 of SEM. These reports
shall be forwarded weekly to the Signal Inspector for further scrutiny. It is
reiterated that the Signal Maintainer must not permit any other artisan or
Group D staff to do any adjustment for cleaning or repairs of signal equipment
except under his personal supervision. After the failure is set right, the person-
20
in-charge shall test and certify in writing the rectification of the defect and if
necessary demonstrate to the traffic staff about the normal working.
2.33 Testing and Overhauling of Electrical Locking:- Power interlocking frames,
provided with electrical locking must be tested at least once a year and
overhauled at least once in 3 years.
2.34 Testing of locking:- Approach locking, indication locking, track locking, time
release, cross protection, route locking and back locking should be tested
once in three years.
2.35 Inspection & Maintenance of Surge arrestors:- In lightning arrestors of
Class B, aging phenomena may occur in rare cases, adversely affecting the
protective function of the devices, because of frequent overloading/lightning. It
is therefore advisable to check the arrestors every two to four years, and after
direct lightning strikes. Surge arrestors of Class C contain varistors having an
indicator, which shows whether the device is faulty. The indicators of these
should be checked, especially after a period of thunderstorms. If the indicator
changes from green to red, the device must be replaced, since it no longer
gives protection.
2.36 Integrated Power Supply system:- The function of Integrated Power Supply
system is to provide a stable and reliable AC and DC power supply to the
Railway signaling installations against all AC mains variations or even
interruptions. This is very essential for proper movement of trains. As the
name indicates, it is designed and developed with a view to provide complete
power solutions from single system to all signaling circuits. The IPS for
Railway Signaling circuits shall be manufactured as per Latest RDSO
specification No.RDSO/SPN/165/2012 Version3.0.
2.37 SMPS BASED INTEGRATED POWER SUPPLY:- For a robust Signaling
system installation, stable and reliable power supply system is vital. Power
supply arrangement is the heart of signaling system. For a reliable signaling
system installation, reliable power supply system is most important.
• Revised specification RDSO/SPN/165/2012 with reliability improvement feature
has been issued.
• To improve the reliability, auditing and modification of IPS is carried out.
21
1. IPS is covered under warranty and AMC to be arranged after warranty expires.
2. However, periodical maintenance & inspection is required to check the health
of system by recording voltage and current of sub systems.
3. Batteries shall be checked individually, top up electrolyte if require, white
petroleum jelly to be applied on the terminals and cell retentively test also to
be done time to time.
4. Potential contact shall be suitable proved in data logger for continuous
monitoring.
5. Once in a month, switch OFF main Converter in IPS and observe if the stand-
by is taking the load.
6. Once in a month, switch OFF Stand-by Converter in IPS and observe if the
main is taking the load. Cleaning of dust collected inside the IPS panels
(SMPS, DCDP & ACDP) should be done with the help of blower once in a
month.
7. Check the healthiness of SPD periodically and whenever you feel surge is
occurred.
8. Once in a month, check for Auto changeover operation between Inverters and
Bypass CVT as described in instruction manual.
2.37.1 Advantage of IPS using switch mode technology over thruster based
system:-
o Integration of various power supply equipments i.e. Battery charger,
Transformer, DC-DC Converter, Inverter and Voltage Regulator in one
equipment.
o Based on high efficiency 90% SMPS based latest technology with phase
correction. Hence power factor (PF) achieved is better than 0.9.
o Modular in design with modules working in n+1 hot standby mode to provide
redundancy and future expansion at any time later on even in working
installation by adding more modules.
o Provision of continuous battery health monitoring with indication and alarms on
Status monitoring panel with Station Master.
o Remote monitoring of failures of modules is possible through Data logger as
potential free contacts for such failures are provided in the equipment.
22
o Standard configurations adopted for small and medium size stations to
increase reliability, availability and maintainability.
o Reduce maintenance efforts due to centralized maintenance.
o Higher reliability due to in-built redundancy and integrated factory wiring.
2.37.2 Integrated Power Supply (IPS)
Power Supply (IPS) Is having
various chargers and batteries for
different supply. This has improved
efficiency because it is based on
SMPS technology with improved
reliability due to in-built redundancy
of modules. Comprehensive
guidelines for improving reliability of
IPS have been issued to Railways
vide Lr. No. STS/E/IPS Genl. dt.
21.11.2013.
In Southern Railway during Feb’2011 the reliability improvement works by
providing IPS, maintenance free earths, lightning dischargers and replacement
of batteries and improved maintenance of DG sets.
23
MAINTENANCE:
Weekly (by maintainer)
a) Check voltage (12v&24v DC) at IPS and MLK Rack
b) Check all fuses
Weekly by Signal Engineer
a) Back up schedule : User data log. Event log & error log back to be taken in
hand disk as well as floppy disk for remote storage
Monthly by Signal Engineer:
a) System Changeover. System changeover from A to B/B to a to be carried out
monthly
b) Measuring of earth readings
Annually
a) Replace the lithium battery
b) Check the converter cum isolator
c) Perform the inspection activities mentioned in section 8.3 of 6800C manual.
Five Years by Signal Engineer:
Inspect surge protection devices, replace if required.
24
2.38 LED Signal Maintenance
▪ Input Voltage range available to Signal Aspect on load at site >82.5V to <137.5
V AC.
▪ Ensure that terminations on CR and fuse terminal block are proper and tight.
▪ Ensure that interconnecting cable between CR and LED/Signal lighting Unit is
properly connected and tight.
▪ Ensure that mounting screws of LED Signal Lighting Unit, CR and fuse terminal
block are properly fixed.
▪ Ensure that protective Caps are placed on the supply terminals of CR.
▪ Tighten all terminals in CT rack, junction Box, LED Signal Lighting Unit, Current
Regulator, HMU, Route Signals, Shunt Signals and Calling-On Signal
periodically or as per instructions given by the railways.
▪ Ensure that mounting bolts/screws have been tightened for LED signal lighting
unit, current regulator and Health monitoring unit once in a six month or as
instructed by railways.
▪ Clean the LED signal lighting units, all terminals and current regulator
periodically with soft cloth.
▪ Ensure that LED signal does not vibrate during the running of trains.
▪ Ensure that the all LEDs of LED signal lighting unit are properly lit.
▪ LED signal lighting unit should be stored in suitable cover provided with
thermocol packing on the inner side surface.
▪ Ensure that the protection cover is provided on the current regulator terminals to
avoid external interference.
▪ The connections in the location boxes should be cleaned for removing
oxidation, rusting etc. regularly.
▪ After any check opening/refitting CRC spray should be provided.
▪ The LED signal lighting unit clear lens should be cleaned once in a six month to
remove the dust with anti-static soft cloth or as per instruction given by the
railways.
▪ Ensure that the AC supply used for lightening the LED Signal Lighting units is
pure sine wave (i.e.50Hz ± 2 Hz).
▪ Ensure that correct polarity is connected while connecting power supply in case
of DC lit signals.
▪ Check periodically and ensure that signal housing door is kept shut and locked
properly.
▪ Safety validation test as per the pre-commissioning check list may be conducted
once in a year.
25
2.39 (i) Preventive Maintenance
The following checks should be performed at least on an annual basis
▪ Clean the outside of the card file/enclosure using a soft clean cloth.
▪ Inspect the card file/enclosure for dents and scratches and internal damage.
▪ Ensure that the all card file modules are properly mounted and securely fastened.
▪ Remove all printed circuit boards from the card file. Inspect the card file back-
plane for loose or damaged connectors. Also, thoroughly inspect each printed
circuit board for physical damage, discolored or damaged components and
wiring insulation, cracked or broken component leads and copper traces.
Questionable circuit boards should be replaced from the spares inventory.
▪ If necessary, vacuum-clean the interior of the card file without disturbing any wiring.
▪ Use a non-metallic, insulated vacuum head.
▪ Re-install the circuit boards into the card file. Tighten the board retaining screws finger tight.
▪ Check all power input and signal supply leads for frayed or discolored insulation and loose connections. Also check all lightning arrestor/voltage suppressor devices for any signs of physical degradation.
▪ Visually examine all wire and cable harnesses for proper bundling and slack.
▪ Remove the VCOR relay from the installation and inspect it.
▪ Caution
(ii) Corrective maintenance
▪ Corrective maintenance on the MICROLOK II system is limited to the correction of basic wiring and hardware problems and the replacement of modular system components.
▪ If a component has been determined faulty, return it to M/s Ansaldo STS Transportation Systems Pvt. Ltd for repair or replacement.
2.40 SMR Maintenance:- SMRs are fully alarmed and operate in an active loop
sharing arrangement. However, some regular checks can be early warning of
problems waiting to happen. Check for failure signal by switching off one SMR
at a time one in a month.
2.41 Battery Maintenance:- The manufacturer’s maintenance manual and instructions
of Zonal Railways are to be followed and important points are;
26
2.42 VRLA battery:-
• Cleaning of all cells near its terminals.
• Reading of all cell’s voltage with Charger switched ON.
• Reading of all cell’s voltage with Charger switched OFF.
• Boosting of Sick cell using Sick cell Charger.
• Replacement of the faulty cell with new cell.
2.43 Low Maintenance Battery:-
• Cleaning of all cells around top cover and terminals periodically.
• Applying petroleum jelly over the terminals.
• Periodically recording of all cell voltages and their specific gravity.
• Periodically checking of electrolytic level of cells.
• Periodically recording of all cell voltages with Battery Charger switched OFF.
• Boosting of Sick cell using Sick cell Charger.
• Replacement of non-reparable cell in a bank by fresh charged cell.
2.44 Cleanliness:- Apart from these instructions regular cleaning of IPS and battery
room should be done Cleaning of dust collected inside the IPS panels (SMPS,
DCDP & ACDP) should be done through blower once in a month.
2.45 Checking of earth resistance:- Check earth resistance every 3 month with
earth resistance meter. It should be less than 3 Ohm.
2.46 Electronic Interlocking [MICROLOK II Electronic Interlocking system
Maintenance]:-
Weekly Maintenance:-
(a) Measuring Voltages, Fuse Checking, Back up Schedules–Performed by Signal Maintainers.
(b) Backup Schedules - Performed by Signal Engineer
[User Data Log, Event Log and Error Log backups are to be taken in Hard Disk
as well as Floppy Disk for remote storage.]
2.47 Monthly Maintenance:-
(a) System Changeover, Measuring Earth Resistance Value and Annual Maintenance Performed by Signal Engineer
27
[During Changeover, SGE block instrument must be kept in TOL condition.
Ensure Synchronization Microlock II clock time with Maintenance PC time after
changeover.]
(b) Replace the Lithium Battery, Check the Converter cum isolator, Remove the
VCOR relay from the installation and inspect it and perform the inspection
activities as Preventive Maintenance.
2.48 Five years Maintenance:- - Performed by Signal Engineer
▪ Inspect Surge Protection Devices(SPDs)
▪ Replace if found deteriorated.
▪ And System Failure Register to be maintained.
2.49 IPS Maintenance:-
Check Points for DC-DC Converters:-
Sl. No.
Check Point
Action required Frequency
1. Converter
O/P Voltage Check if the O/P Voltage are set as per
requirement. If not, correct them. Once in 15
days.
2.
Paralleling of
Converters
Switch OFF main Converter and observe if the stand-by is taking the load.
Once in a month.
Switch OFF Stand-by Converter and observe if the stand-by is taking the load.
Once in a month.
3. Converter
Mechanical Alignment
Check if all the converters are inserted properly.
Once in 3 months.
4. Converter Cleaning
Remove one by one and clean the converter using soft cloth. Gently blow some air from
top or Bottom to remove the dust inside.
Once in 3 months.
5. Converter
failure. Check for failure Signal.
Once in 3 months.
Check Points for ACDP:-
Sl.No. Check Point Action required Frequency
1. O/P Voltage of inverters, AVRs, Step-Down Transformers as per requirement.
Check if the O/P voltages are set as per requirement. If not, check for fuses contactors.
Once in 15 days.
2. O/P Voltage of inverters, AVRs, Step-Down Transformers
Check if the O/P voltages are set as per requirement. If not, check for fuses contactors.
Once in 15 days.
3. Inverter O/P current Check if the DPM is showing the signal current as per original settings.
Once in 15 days.
28
4. Auto changeover between inverters and Bypass CVT
Check for this changeover operation as described.
Once in a month.
5. Connector mechanical Alignment
Check if all the connectors of various sub systems are inserted properly.
Once in a month.
6. Sub-system Cleaning Remove one by one and clean them using a soft cloth. Gently blow some air to remove the dust inside.
Once in 3 months.
2.50 Railway Board Lr.No.2014/Sig/SF/Summer Precautions Dt.15-04-2015;
prescribes Summer and Pre-Monsoon Precautions apart from local
requirements, shall be taken to minimize effect of high temperatures on
Signaling systems in Track Circuits, Points, Signals, Power Supply and DG
sets, Relay Rooms, Electronic Signaling systems in general, Cable/Block and
Lightning and Surge protection.
2.51 Railway Bd. Lr.No.2015/Sig/SF/Monsoon Precautions Dt.18-05-2015;
Stipulates holding of a Joint Inspection by ADEN, ADSTE, AOM, ADEE and
ADMO with their supervisors of Signal and Engineering Departments in
accordance with JPO and for attending deficiencies before the onset of
monsoon.
2.52 Inspect and check Track Circuits, Points, Signals, Relay Rooms, Cabins and
Equipment Room, Power Supply arrangement, S&T Cables, locations Boxes,
Earthing & Lightning protection devices, operating cum indication panel, level
crossing gate, Electronic interlocking, general signal equipments like SSDAC,
MSDAC, EI, IPS, Data Logger, UFSBI, AFTC, DAC, emergency lights,
torches, petromax, all measuring instruments and readiness of transport
facilities etc.
2.53 PREVENTIVE MAINTENANCE
A) Daily
• Batteries voltage and charger output voltage.
• AC supply voltage and charger output voltage.
• Cleaning of equipment rooms with vacuum cleaner and wiping of the
floor for all rooms.
• Failure list of the subscribers.
• Testing of all the trunks (STD, OTD and other) circuits.
• Working of Lights, Air conditioners.
• System status listing
29
• Failure history list
• Alarm checking
• Room temperature recording
B) Weekly
• Specific gravity, voltage and load test of the batteries, sulphation of terminals.
C) Monthly:
• Wiring and connecting terminals of power supply arrangement.
• The different modes of operation of FCBC, the internal checking and cleaning of FCBC.
• Earthing connections of all equipment and earth electrodes.
• All cabinets of equipment, Man machine interaction, terminal printer, attendant consoles to be cleaned.
• Cable termination MDF and IDF to be cleaned and checked.
• Cable runs-inter rack, rack to IDF, MDF and Attendant consoles to be checked.
• Transmission loss test of all trunk circuits
• Office Data Back up to be updated.
• Checking of GD tubes
• Functional Testing of Attendant console
• Tone testing of MW circuits & realignments
• Traffic data listing & analysis
D) Quarterly:
• Contact points of Attendant console to be cleaned with contact cleaner.
• Testing of All Service features from the Test Telephones.
• Cleaning of terminations in CT boxes, Location boxes.
• Adjustment of SMPS modules
E) Yearly:
• Earth resistance value measurement
• Line loop resistance and insulation testing
• Checking of wiring of subscribers premises, CT boxes and location boxes.
• Testing of spare cards.
• Analysis of load distribution among operators console.
• System programme backup.
2.54 INTERLOCKED GATES:- At interlocked gates, interlocking and communication
equipment are provided and maintained by S&T department. Interlocking shall be
provided as per para7.82 of SEM, Part I.
30
2.55 The following points shall be followed during Maintenance & testing of Electric
Signal lamp:-
a) Lamps shall be operated in the vertical position cap up.
b) Lamps shall be tested for 6 hours.
c) Testing shall be under ON-OFF condition for one minute each continuously.
d) Testing voltage should be 10.5 V on lamp terminal
e) Separate signal transformer should be used for each lamp.
f) Single filament and double filament lamp shall be tested separately.
2.56 MAINTENANCE OF CABLE:- Signaling cable must be tested for continuity and
insulation. The tests should be carried out before and after cable lying. For
maintenance purposes these tests shall be performed after every one year for main
cable and after every six month for tail cable.
2.57 Replacement Schedule for Single/double Filament Lamp at 80/30days or as per
CSTE’s instruction. Maintenance schedule for SSDAC:-
2.58 Train Management System (TMS) /Centralized Train Control (CTC)
Train Management System (TMS) /Centralized Train Control (CTC) covers following
two categories of functions:
➢ Centralized operation of signaling systems for a large section encompassing
multiple interlocked stations
31
➢ Centralized real time monitoring of train traffic for enabling efficient decision
making for traffic control of large section.
The features like software
based interlocking logic,
less wiring, easy
alterations, self-diagnostic,
in-built data logger etc.
make it maintainer friendly.
2.59 LED Signals: - This signal provides better visibility over the conventional
incandescent lamp signals. LED signals also have longer life, consume less energy
and require low maintenance efforts. So far, more than 2,50,000 aspects have been
installed over Indian Railways. Integrated LED Signal Lamps have been developed
which have better reliability.
Poly Carbonate cover of LED Signal Lighting Unit may be cleaned with soft and
antistatic cloth periodically.
Check installation once a year by disconnecting the interconnecting Cable between
CR & LED Signal Lighting Unit of Main Signal to check audio-visual alarm and
correspondence of ECR.
Check health monitoring device on each visit.
32
33
2.60 Lithium Batteries:- WESTRACE Network Communications Module (NCDM) has
Lithium batteries installed. Replace Lithium batteries of WESTRACE NCDM module
every 5years. MICROLOK II CPU also consists of Lithium batteries. Replace these
once in a year.
2.61 Vital Cut -Off Relay (VCOR):- Each card file will have one Vital Cut-off relay (VCOR)
to ensure the healthiness of the system. Once in a year, remove the VCOR relay
from the installation and inspect it.
2.62 WESTRACE VLM6 EI:- Moviola works as the maintenance terminal and data logger
for the WESTRACE. It helps in easy identification of fault s and diagnosis of any
failure in WESTRACE. It also helps in monitoring the interlocking.
2.63 CENTRAL MONITORING UNIT OF DATA LOGGER: A remote centralized system for
monitoring the status of signaling gears and systems through data loggers located at
wayside stations.
A typical Electronic Interlocking installation shall consist of VDU Control Terminal
and/or CCIP, Central Processing Unit, Object Controller and/or relay driver circuit,
Maintenance Terminal & Data logger, etc.
Maintenance terminal(MT) with display, keyboard, printer and event logging facility for
minimum 10,00,000 events or one month data (whichever is larger) of its own.
2.64 Joint Inspection of Points and Crossings by the Divisional officials of Engineering
and S&T Department vide Joint Circular No.SG.85/1 dt.7.1.1986 and 27.10.1988, on
aspects that are Essential for ensuring correct and smooth operation of the points.
This would mainly focus on the portion between SRJ and the HEEL of the Switch.
The tolerances specified are only for working of connected signalling gear.
2.65 FREQUENCY and level of Inspection:- Every interlocked point in a yard shall be
jointly inspected by the PWI-in-charge and the S.I. in Grade I or above, once in six
months by rotation according to a pre-determined schedule. Where, an official of
Grade-I is not available, an official in next lower grade may be associated.
2.66 RECORDING of observations:- A bound register of Joint Inspection of Points and
Crossings be maintained at each Station.
34
2.67 Annual Maintenance Contract(AMC) with Original Equipment Manufacturers (OEMs),
give rise to follow up failures, etc. The installation of data loggers with proper
networking resulting in proving of relays, in maintenance and upkeep. Provision of
Block Proving by Axle Counter(BPAC) reduces dependence on human element in
train operation through a system of automatic counting of axles of a moving train over
a section and enhances safety.
2.68 Analysis of signal failures:- There is a significant correlation between safety and
reliability of assets. As reliability of asset improves, dependence on human judgment
decreases and safety is enhanced.
2.69 Single Section Digital Axle Counters (SSDACs) were used for train detection in yards
as well as block section. However, from 2005-06 and onwards, Multi Section Digital
Axle Counters (MSDAC) is increasingly used in the yards for train detection
purposes. The use of LED signals provided great respite to the signaling
maintenance management from the pre-mature fusing of conventional lamps and
frequent replacing of signal lamps. A specific example shows that 70 – 80% of block
and track circuit incidents are due to equipment failures pertaining to electronics
based digital axle counters.
2.70 CLASS `C' STATIONS or BLOCK HUTS: Where permission to approach may not be
given for a train, unless the whole of the last proceeding train has passed complete at
least 400 Mts. beyond the Home Signal (IBS/IBH) and is continuing its journey. This
will also include an Intermediate Block Post.
35
2.71 Data Logger:- Data logger stores status of relays in chronological order. This is useful
in analysis of failures and unusual events. It is also used for “predictive
maintenance”. The networking of data loggers provides remote monitoring of events.
2.72
Universal Fail Safe Block Interface (UFSBI) has been developed to interface conventional block instruments with OFC. With the help of this, conventional block instrument can be operated on OFC channel. Development completed in 2006. This equipment will be used in Block Proving by Axle Counters (BPAC) applications using block panel in lieu of conventional block instruments. Improvements in functioning of UFSBI are being carried out by introduction of media diversity auto switch & efficient power supply will also reduce operating time from 16s to 4s by eliminating DC pulse transmission.
2.72.1 The essential duties of SSE/SE/JE covers execution of all works involving
alterations to the existing installations, and installations of new equipment, its
adjustment and connections and Carrying out periodical tests on line wires
independently as well as jointly with the officials of the Posts & Telegraphs
department.
2.73 DUTIES OF SIGNALING SUPERVISORS & SIGNAL MAINTAINERS:-
GENERAL DUTIES:-
Knowledge of rules and instructions
❖ A Maintainer shall be conversant with rules, regulations and instructions
concerning his work contained in the following books of reference as well as other
instructions issued from time to time.
❖ General & subsidiary rules, Signal Engineering Manual[SEM]; Safety First Book
36
❖ A Maintainer shall not permit any artisan or Class IV staff to do any adjustment to
the gear in use except under his personal supervision and he shall ensure that the
staff under him clearly understands this rule.
2.74 Maintenance of muster sheets etc.
• A Maintainer shall mark his own attendance and that of his staff on the muster
sheets received from the SSE/JE (Signal) before starting his work. Erasing and
over-writing is not permitted. Loss of muster sheet shall be brought to the notice of
the SSE/JE(Signal) at the earliest. A Maintainer shall work to the duty rosters
provided and see that the staff under him also works according to the roster.
2.75 MATERIALS AND TOOLS AND PLANT
❖ A Maintainer shall, where necessary, get his requirements of materials for
maintenance and repair work from the SSE/JE (Signal), giving full particulars of
station, location and the gears to be replaced.
❖ Released materials shall be returned to the SSE/JE (Signal) immediately. There shall
absolutely be no wastage of any material.
❖ A Maintainer shall always take his tools with him when on duty. All tools shall be kept
in a condition fit for immediate use.
2.76 Co-operation between Electrical and Mechanical signal maintainers:
❖ Electrical and Mechanical Signal Maintainers shall co-operate in testing all signals
operated mechanically and controlled electrically.
❖ Electrical and Mechanical Signal Maintainers shall extend full co-operation to each
other in their day to day work.
2.77 TECHNICAL DUTIES OF SIGNAL MAINTAINERS
❖ Efficient maintenance and testing of all equipment under his charge such as
Mechanical Signaling equipment, Electrical and Electronic Signaling equipment,
Telecommunication equipment, etc.., so as to keep them properly adjusted and in
good working condition, in accordance with instructions contained in the Manual and
such Circulars or Instructions, as may be issued from time to time.
❖ The term electrical signaling equipment includes Block Instruments.
37
❖ Carrying out works and alterations to the existing installations under the instructions
of the SSE/SE/JE (Signal).
❖ Bringing to the notice of the SSE/JE (Signal) any emergency and situation that may
be beyond his competence or control by a message on control phone or by a
telegram or by a messenger or personally.
❖ Ensuring that the safety appliances like Safety Belts, lifting tackles and staging, etc..,
are in good condition and are always made use of in order to ensure his safety and
the safety of staff working under him.
2.78 Duties of Technicians:-
• Periodical maintenance of signals, block instruments, interlocking gears, panels,
RRIs, track circuits-both preventive and repairs attendance.
• Replacement of Spare parts, Equipments etc.
• Attendance of failures
• Restoration works during accidents, unusual occurrences
• Cleaning, Lubricating, Testing etc. of equipments.
• Assisting Engineering& Electrical staff wherever S&T items are involved
• Disconnection works
• Maintenance of records
• Collection of stores tools and plants etc.
2.79 Duties of Signal Maintainers during Signal Failures:-
A Maintainer shall attend to all failures in his section promptly proceeding by the first
available means on receipt of information. Before taking up work, he shall first obtain
failure report/message from SM/ASM in writing in accordance with provision of
G.R.3.68. He shall make every endeavor to rectify the failures expeditiously and take
all possible steps to prevent recurrence. If a gear has failed on the unsafe side and
the ASM has been unable to put the relevant signal to 'ON', the Signal Maintainer
shall take steps to disconnect/disable the relevant signal and bring it to 'ON'. Failures
beyond his competence or control must be brought to the notice of the SSE/SE/JE.
2.80 Duties of Signal Maintainers during accidents:- On receipt of advice about any
accident in his jurisdiction, the Maintainer shall proceed to the site of accident by first
available means. He shall not interfere with any equipment on his own but shall act
upon the orders given by the senior most officials at the site of accident.
38
2.81 Signal Sighting Committee:- All new signals/modified signals and warning boards
etc. shall be inspected and passed by “Signal Sighting Committee” consisting of
(i)SSE/SE/JE(Signal) (ii) Loco Inspector & (iii) Traffic Inspector as per standard
proforma. For existing signals the above inspection should be carried out quarterly.
Foot-plate Inspection:- In order to check visibility of signals from Driver`s view, Signal
Staff have to travel by Locomotive. This is known as Foot -plate
Inspection. All SSE/SE/JE(S) shall carry out Foot-Plate Inspection of all signals by
day and by night in both Up and Down directions once in a month or once in 3
months as applicable over their entire jurisdiction and submit record of observations
in the prescribed format. During the inspection they shall take special notice of the
following.
a) Signals should be correctly focused and should be burning brightly
b) All cabins should be provided with sufficient lighting arrangements
c) No fixed light should be interfering with the sighting of signals
d) The speed of the train should not exceed the maximum permissible speed
e) Examine the visibility of signals from the driver side. If a signal is seen
obstructed by tree branches or other obstructions the detail should be noted
for remedial action.
f) Note down the signals found drooping or improperly taken off or incorrectly
g) All signals should have adequate visibility as specified preferably from the
driver side of the foot -plate.
h) Anything that may endanger safety or may interfere with signaling gears shall
be brought to the notice of the concerned department. If immediate action is
necessary, the train may be stopped at the next stat ion for giving necessary
information to the SM.
i) All warning boards should be in proper fettle. Signal that are to be replaced to
“ON” by the passage of t rains are being so replaced.
j) Fireman/ Asst. Driver should be calling out signals clearly and loudly Speed
Restrictions & Caution Orders should be observed precisely by the crew.
k) Day Foot-Plate Inspect ion should be done during broad day light hours
preferably at noon and night foot-plate Inspection should be done between
odd hours(midnight ) to 0400 Hrs. (4AM).
39
2.82 General Safety Precautions to be taken during Maintenance:-
Do not touch the electric / electronic equipment unless sure that there is no
leakage current in the body of the equipment.
While working on the electrical/electronic equipment always use rubber shoes,
rubber mattress, rubber gloves or dry wooden platform to maintain the separation
from the earth.
Before switching on the equipment always ensure that the circuit is properly
connected and no person is working on the circuit.
Before doing any experiment always have full knowledge of experiment and all
required tools, equipment and circuits with you.
Before starting any maintenance, repair, always disconnect equipment from
mains. Never pull the plug from the socket by holding the lead wire of mains.
Whenever working on the mains your hands should be dry. Never touch the
mains, electrical equipment with wet hands.
If there is any high voltage capacitor in the circuit, always touch or disconnect the
capacitor after discharging it.
@@@
40
CHAPTER – III
3.0 CRITICAL ANALYSIS
3.1 The prime task of the work study is to right size the man power in the general
interest of productivity of the Indian Railways. Right sizing of Man power is a
continuous and comprehensive measure referring with the current work load
and the present processes methods. Also RITES recommended the concept
of zero based budgeting in man power planning on regular basis as in such to
justify the presence of every employee.
There are lot of tools available to measure the Man power requirement,
normally the activities are split up into small groups and analyzed into micro
level to arrive the required Man power. In Indian Railways, the work study
conducted to the unit basis level, hence Macro level study is only possible and
it is being carried out with the help of
i. Bench Mark
ii. Need basis
3.2 Calculation of DESU of MDU Division:
Divisional Equated Signal Units otherwise known as DESU is a derived unit
from Signal Assets after the addition of many other factors and constants like
Annual Train Kilometers, Route Km etc. The DESU of the whole of the MDU
division for the year 2018-19 is as follows;
A1 Total No of signal units - 77823.000
F Annual Train Kms (H+J+K+L) - 7776.788
H Passenger & proportion of mixed trains - 7375.042
J Goods & proportion of mixed trains - 363.052
K Department trains - 38.694
L EMU trains - 0.000
Calculation of A2
G = Total Route Kms - 1294.000
F/G-7.3 - -1.290
A2 = A1 x (F/G-7.3) x 3.42/100 - -3433.708
41
Calculation of A3
Signal units/Route Kms (A1/G) - 60.141
Value of Y - 0.000
A3 = A1 x Y/100 - 0.000
Calculation of A4
Z=F/G - 6.01
A4 = A1 x Z x 0.94/100 - 4396.532
Calculation of A5
A5 = 1.67 x G - 2160.980
DESU= A1+A2+A3+A4+A5 - 80946.804
DESU of MDU Division = 80947
3.3 DESU Calculation of Signal/PLNI:
Total Signal Units of MDU division - 77823
DESU value of MDU division - 80947
Conversion factor (80947/77823) - 1.04
DESU value given by the Division and PLNI section are tabulated below:
Sl. No.
Description DESU value at
Division DESU value at SSE/SIG/PLNI
1 LC 8 130 81
2 API 795 918 (Incl. of LC 11 & 12)
3 LC 18 79 81
4 LC 24 79 81
5 ODC 866 855
6 LC 37,38,40 185 212
7 CHPT 762 762
8 LC 49 79 81
9 LC 56 79 196
10 LC 58,59 150
11 PLNI 1,080 1,080
12 LC 65 79 81
13 LC 68 79 81
14 LC 77 79 81
42
15 PPTR 707 707
16 LC 80 79 91
17 MVRD 743 743
18 UDT 797 802
19 GMGM 744 853 (incl. of POY Block)
20 POY 3 0
21 LC 30 0 86
22 LC 64 0 86
23 LC 90, 91 0 125
Total 7,594 8,083
From the above, the man power calculation is based on the DESU value given
by the SSE/Sig/PLNI.
Total signal units of SSE/Sig/PLNI - 8083
DESU value of SSE/Sig/PLNI (1.04 x 8083) = 8406
3.4 MAN POWER REQUIREMENT AS PER BENCH MARKING:
Bench marking is a very important tool in IR for rightsizing man Power, Man
Power calculation is also calculated based on the current Bench marking. In
the Report of Efficiency and Research Directorate of Railway Board ED(E&R)
D.O No. 2004/E&R /2800/Rly/Imp/I Dt. 14.02.2005.
3.5 Calculation:
As per the current benchmark issued by RB in the Month of September 2019,
(Placed as Annexure – II), MDU division falls under the classification
‘Divisions less than 120 DISTUs ’. The best performing signal unit with less
than 120 DISTUs is SA division in Southern Railway which has the manpower
of 2.22 per 1000 DESUs.
If this bench mark is adopted, the man power required for SSE/Signal/PLNI
would be 18.66 Say 19 staff (8406/1000 x 2.22) leaving a surplus of 6 staff
from sanctioned strength of 25. Out of six posts one post is allotted for
Office/Store maintenance.
43
3.6 Actual requirement of Supervisor staff:
In view of the technical skill required for the inspection/maintenance of modern
equipments, 3 sanctioned posts of SSE/JE may allowed to continue for smooth
operation. Therefore, the 5 Technician vacant posts viz., 3 posts of Technician
Gr.I/Sig.Mtr. in Level 5 (GP Rs.2800) and 2 posts of Technician Gr.III/Sig.Mtr.
in level 2 (GP Rs.1900) are found surplus only.
Sanction Vs Requirement:
Sl. No.
Category San Act Requirement Surplus
1 SSE/Signal 2 1 2 0
2 JE/Signal 1 1 1 0
3 Sr.Tech/Sig. Mtr. 2 2 2 0
4 Tech.Gr.I/Sig. Mtr. 9 2 6 3
5 Tech.Gr.II/Sig. Mtr. 1 1 1 0
6 Tech.Gr.III/Sig. Mtr. 5 3 3 2
7 Helper/Signal 5 7 5 0
Total 25 17 20 5
* One Re-engaged staff in Tech.Gr.III/Sig. Mtr.
Recommendation:
3 posts of Technician Gr.I/Signal Maintainer in Level – 5 (GP Rs. 2800) and 2
posts of Technician Gr.III/Signal Maintainer in Level - 2 (GP Rs.1900) are
found surplus to the requirement, the same may be surrendered and credited
to the Vacancy Bank.
(Total – 5 Posts)
*****
44
CHAPTER - IV
4.0 PLANNING BRANCH’S REMARKS ON CO-ORDINATING OFFICER’S
VIEWS:
45
CHAPTER –V
5.0 FINANCIAL SAVINGS
If the recommendations made in the study report are implemented, the annual
recurring financial savings will be as under:
Sl. No.
Category Level / Grade
pay (Rs.)
No. of post
Mean Pay (Rs.)
Annual savings (Rs.)
1 Technician Gr.I/ Signal Maintainer
Level – 5 (2800)
3 68040 2449440
2 Technician Gr.III/ Signal Maintainer
Level – 2 (1900)
2 46536 1116864
Total 5 114576 3566304
46
G.275/WSSR-121718/2017-18
WORK STUDY TO REVIEW THE STAFF
STRENGTH AT SSE/SIGNAL/MNM-
MDU - DIVISION.
G.275/WSSR-121718/2017-18
WORK STUDY TO REVIEW THE STAFF
STRENGTH AT SSE/SIGNAL/MNM
MDU - DIVISION.
G.275/WSSR-121718/201-18
WORK STUDY TO REVIEW THE STAFF
STRENGTH AT SSE/SIGNAL/MNM-
MDU - DIVISION.
47
Since such a drastic reduction in the sanctioned strength would affect the
present working of the unit and therefore the same is not adopted for the study.
Madurai division’s Man Power Ratio is 3.87/1000 DESUs, but this peak value
is 1.7 times greater than the current bench mark value of 2.22 in Salem
division. If this bench mark could be adopted, the manpower required for
SSE/Signal/PLNI would be 0.72 times greater than the sanctioned strength.
Therefore, the study team has considered the average bench mark value of all
divisions (except MAS) in Southern Railway. The bench mark value of each
division is given and taken the average bench mark value as below.
MDU division = 3.87
TPJ division = 3.08
PGT division = 2.37
TVC division = 2.86
SA division = 2.22
Total = 14.4/5 = 2.88 say 3
Hence, the Southern railway average bench mark is taken as 3. Since the
current IR average is closely near to this bench mark it would be more
appropriate to adopt the average bench mark of southern railway for
SSE/Sig/PLNI as well. By applying this bench mark, the manpower required at
SSE/Sig/PLNI would be 23.7 say 24 (7898/1000x3) leaving a surplus of 1 post.
However, taking a lenient view and since the Sothern Railway average is more
than the current bench mark, and hence it is most suitable and adopted.
This is the most liberal calculation amongst the above current and current IR
average bench marks calculations and which is also very close to the present
utilization.
At present there is no ministerial staff in this unit, the unit operated a suitable
Group – D staff for office uses on need basis to cater to the works of
establishment and stores of this unit. The work study team recommend to
division may create one ministerial post for this unit.
48
3.6 Out sourced details:
Sl.No Description of work Amount in Rs
Name of the contractor (Shri)
1 Signaling arrangement at pamban viaduct Bridge No.346(44 Spans)
45,59,486 Mohamed Ekram Madurai
2
Proposed provision of series track circuit on D-Route in DG-MDU, TEN-TCN, VPT-TSI, MDU-MNM, TPJ-MNM, MNM-RMM
49,41,177 Meltronics Systemtech Pvt Ltd Bangalore
3 Proposed signaling reliability improvement works in VPT-MNM
31,31,598 Meltronics Systemtech Pvt Ltd Bangalore
Total 1,26,32,261
From the above table shown that the contract works amount Rs. 1,26,32,261/-
is raised in MDU division. Out of which MNM section is having the contract
value Rs. 76,91,084/- only. Generally, in any work study to take 35% of the
value in total amount of contract works and to convert manpower in terms of
daily labour cost or mean pay of the monthly Tech-III (Skilled) salary in which
most beneficiary of the division is to be taken as the manpower calculation.
Therefore, the total contract value Rs. 76,91,084/- is taken for manpower
calculation in MNM section as below;
35% of the total value of Rs. 76,91,084/- - Rs. 26,91,879/-
Mean pay of Tech.III/month - Rs. 43,628/-
Salary of Tech.III/year - Rs. 5,23,536
Required manpower calculation is - Rs. 26,91,879/Rs. 5,23,536
Manpower arrived as = 5.14 say 5 Staff
LR/RG = 1 staff
Total staff to reduced on contract account = 6 staff
As per work study Vs contract works, 6 staff must be reduced from
sanctioned account. But the work study team has decided for future
improvement works like Railway Electrification, doubling etc. it is
suggested that not taking any reduction on outsourcing/contract works.