fuse customer perspectives webinar: project compliance
DESCRIPTION
A webinar featuring panelists from DCMA, LA Metro, GAO and Austal and how they are currently using Acumen Fuse® to ensure compliance with government and industry standards.TRANSCRIPT
// Fuse Customer Perspectives Series
Ensuring Project Compliance
// Using your control panel GotoWebinar
To minimize the
window, click the
red arrow.
Raise your hand
to speak to all
attendees.
To ask a
question, simply
type it in the chat
window.
Does Fuse integrate with P6?
// Overview & Objectives
◦ High Fuse adoption rate since product inception ◦ Proven value in:
◦ Analysis time savings ◦ Best practices and standards implementation ◦ General insight & best practice maturity improvement
◦ Webinar highlights four specific use cases ◦ Firsthand customer perspective!
◦ Four user stories ◦ Fuse 3.1 briefing ◦ Q&A (submit Q’s through Questions box)
// Acumen
◦ Project management software company
◦ Insight into challenges & use of analytics to overcome them
◦ Core Concepts: 1. Project success requires a sound plan
2. Forecast accuracy requires risk consideration
Proven Project Analytics
Product Offerings
Risk Workshops
Acumen Fuse®
Software Training
Realistic Scheduling
Critiqued
The Base
Risk-Adjusted
Optimized
Team-Aligned // S5
// S4
// S3
// S2
// S1
// Acumen Fuse Platform
◦ Fuse: analytics platform
◦ Improves schedule quality
◦ Insight into performance
◦ Fuse 360: goal-based acceleration ◦ Schedule Acceleration
◦ Decision-support
Enterprise Project Analysis
Metric Analyzer
Logic Analyzer
Forensic Analyzer
Schedule Cleanser
Schedule Accelerator
// Anthony Presley, DCMA Earned Value Management Specialist
Daniel Goldsmith, DCMA Electronics Engineer
// Government Review
◦ Defense Contract Management Agency
◦ 5 – 6 months of schedules to analyze at all times
◦ Before, used Excel macros and built-in tools
DCMA
// Beyond the 14-Point Assessment
◦ Custom metric library ◦ 100+ hand-picked metrics to determine health
and quality of the schedule
◦ Use tripwires to identify areas of concern
◦ Results are documented and sent to supplier ◦ Each area or metric of concern
DCMA
// Metric Customization
◦ Customized both schedule quality and cost metrics
◦ For example, “Overstated Performance to Status Date” ◦ Sum(if(((ProjectTimeNow-ActualStart)-ActualDuration)<0,1,0))
◦ Moving into cost and schedule integration
DCMA
// Julie Owen, LA Metro Senior Project Controls Manager
// Infrastructure Construction
◦ Required review of contractor baseline and monthly updates
◦ Projects > 1M submitted in P6 ◦ Projects >10M are cost loaded
◦ Construction claims can be common
LA Metro
// Forensics
◦ Pre-Fuse ◦ Built-in tools ◦ 1-to-1 comparison ◦ Claims consultants
◦ Use for monthly reviews on schedules ◦ In claims of delay, can determine causes
of delay
LA Metro
// Future Applications
◦ Rolling out between now and July 1
◦ Automatic generation of contractor review letters
◦ Standardized schedule quality metrics
◦ Calendar Forensics
LA Metro
// Bruce Jones, Austal Scheduling Manager
// Government Contractor
◦ Two programs, 10 vessels per program in progress
◦ Implemented Earned Value for the past three years
◦ Use several tools to schedule, rate and report
Austal
// In-depth Analysis
◦ Adopted Fuse to streamline schedule review
◦ Replaced using complex filters in
scheduling tool to assess schedule health ◦ standardized slice-and-dice
◦ Quick comparisons to baseline
Austal
// Complete Customization
◦ In the standard EV library, labor hours were only calculated based on cost
◦ Based on feature request, can now be
calculated in labor hours
◦ Moving forward: using dashboard views for reporting to management
Austal
// Karen Richey, GAO Assistant Director – Applied Research and Methods Team
// Congressional Investigation
◦ GAO is a non-partisan agency that works for Congress
◦ GAO investigates how the federal government spends taxpayer dollars
◦ Internal consultants on cost, schedule and EVM
GAO
// Schedule Assessment
◦ Established 9 Scheduling Best Practices ◦ Created custom metric library with Acumen
◦ Adding an additional guideline focused on baselines
◦ 5 members on the team assessing approximately 30 programs at any given time ◦ Currently using Excel macros ◦ Copy-paste accuracy concerns
GAO
// Fuse Benefits
◦ Non-Fuse users still benefitting ◦ Use Fuse as a fast fact check for assessments ◦ Good validation and controls
◦ Fuse analysis shows every detail – establishing complete transparency
◦ Opens up the conversation, opportunities for “Get Well” planning
GAO
// Acumen Fuse® 3.1 Briefing
◦ Schedule Quality Index: the true standard of standards!
◦ Acumen Cloud™: benchmarking
◦ Schedule Cleanser™: intelligent schedule improvement
◦ Calendar forensics: interrogation of calendar definition
◦ Enhanced P6 integration: XML & inter-project data
// Q & A
// Upcoming Events
◦ Acumen Fuse Customer Perspectives Series: Oil & Gas
◦ May 24, 10:30 a.m. to 12:00 p.m.
◦ To register, www.projectacumen.com/events/seminars
4/20/12 // Slide: 24
// Acumen Annual Summit
Hotel ZaZa // Houston, TX ◦ Fuse hands-on workshops
◦ Metric Development ◦ Custom Reporting ◦ API
◦ Presentation sessions ◦ Schedule and risk management best
practices ◦ Fuse user stories
◦ Networking events ◦ Opening poolside reception ◦ Networking party at The Houston Zoo
September 17 – 19, 2012
4/20/12 // Slide: 25
//
More Information: White papers: www.projectacumen.com Software Trial: www.projectacumen.com/trial Twitter: @projectacumen E-mail: [email protected]