Functional & Sustainable Design for
IBS, Also Translate Into Cost Saving
1/23
IBS
Functional Features Stable
Sustainable System Savings= +
2/23
Setia Precast Sdn Bhd was established in 1996.
Specializes in utilizing Setia IBS for Affordable Apartments.
From 1996 until now, we have built more than 21,000 units
Setia Precast Sdn Bhd - Setup
3/23
20
16
CID
B M
CIE
A I
BS
AW
AR
D
SE
RI J
AT
I A
PA
RTM
EN
T
20
17
CID
B M
CIE
A I
BS
AW
AR
D
SE
RI K
AS
TU
RI A
PA
RTM
EN
T
20
05
MC
IEA
MA
JO
R S
CLA
E P
RO
JEC
T
(B
UILD
IN
G) P
UTR
AJA
YA
P8
68
4 U
NITS
2
BLK
16
STO
REY
20
11
MC
IEA
IB
S A
WA
RD
PA
RC
EL
15
-12
B P
UT
RA
JA
YA
2013 M
CIE
A
IBS
AW
AR
D
AC
CH
KL
CERTIFICATES & AWARDS
4/23
PUSAT BANDAR PUCHONG
BANDAR SETIA ALAM
PUTRAJAYA ECOHILL SEMENYIH
UNIT
PROJECTS
CONSTRUCTION OF APARTMENT UNITS USING SETIA IBS BY SETIA PRECAST SDN BHD
400
PUSAT BANDAR PUCHONG
BUKIT INDAH AMPANG
800 1200 1600 2000 2400 2800 3200 3600 4000 4400 4800 5200 5600 6000 6400 6800 7200 7600 8000 8400
AIMST UNIVERSITY
PUTRAJAYA
BANDAR SETIA ALAM
ECOHILL SEMENYIH
3,006 UNITS
998 UNITS
576 UNITS
7,436 UNITS
6,550 UNITS
1,905 UNITS
COMPLETED PROJECTS : 20,471 UNITS
7,174 UNITS
2,555 UNITS
8000 8400
ON-GOING PROJECTS : 1,274 UNITS
TOTAL : 21,745 UNITS
Functional Features
Smart Collaboration
• Whole System Thinking - BuildabilityProductivity
“D f M A” Safety
• Front Loaded Planning - Production, Transportation
“Do It Right the First Time” Installation
• Teamwork - ClientConsultants
“Partnership” Pre-Caster
5/23
Functional Features
Smart Design
14 23
Conceptialize the layout that able to harness the utilization :-
- Availability & Suitability of Plant & Machineries
- Increase repetition for both horizontal & vertical plane
- Floor to floor height to facilitate logistic limitation
6/23
Functional Features
Smart Repetition
DE CENDANA RUMAH SELANGORKU
3 Blocks, 650 Units, 14 Storeys
Affordable RSKu at RM100,000, 750 Sq.Ft.De Cendana : 650 UnitsDe Cemara : 422 UnitsDe Cempaka : 422 UnitsTotal : 1,494 Units
A functional efficient unit layout collaboratedfrom a union of 3 Architects and Client.
Freedom to design and relocate staircases, liftlobby and external facade treatment by eachArchitect.
7/23
Functional Features
Smart Repetition
2 Blocks, 442 Units, 15 Storeys
8/23
Functional Features
Smart Repetition
2 Blocks, 442 Units, 15 Storeys
9/23
Functional Features
Smart Repetition
Precast Bathroom Unit for 1534 repetitions.
10/23
11/23
Functional Features
Private Affordable Apartment, 950 Sq.Ft., RM242,000 Public RSKU Apartment, 800 Sq.Ft., RM170,000
Public RSKU Apartment, 810 Sq.Ft., RM100,000
Design Fit-for-Purpose
12/23
Functional Features
Wall Design
Cost Efficient :-
Dual-Sharing vs Non-Sharing Walls
Straight vs Curve/Slanting Walls
Increase moulds usage
No
n-S
harin
g
Du
al-
Sh
arin
g
Unit Unit
13/23
Functional Features
Wall Design
Structural Framing :-
Distribution of Shear Walls & Beams
14/23
Functional Features
Facade Features – Cost effective for Precast
15/23
Functional Features
Facade Features – Cost effective for Precast
16/23
Functional Features
Facade Features – Cost effective for Precast
17/23
Sustainable System
Economic Sustainability
Casting Yard : Locate at Developer’s Township Development
US
J P
recast
Pla
nt
15
00
UN
ITS
/Y
EA
R
BS
A P
recast
Pla
nt
2
00
0 U
NITS
/Y
EA
R
Eco
hill
Precast
Pla
nt
30
00
UN
ITS
/Y
EA
R18/23
Sustainable System
Economic SustainabilitySetia IBS Open System : Able to out-source to other Pre-Casters
BUBBLE DECK : BUBBLE DECK SLAB FOR
ROOF OF COMMUNITY HALL
SETIA PRECAST : PRECAST WALL
PRECAST HALF SLABPRECAST STAIRCASEPRECAST BATHROOM SLABPREFABRICATED BATROOM UNIT
SETIA WOOD : PREFABRICATED ROOF TRUSS
BRICK DOTCOM:GREENEDGE MODULAR PANEL
LYSAGHT :BONDEK FOR WATER TANK FLOOR SLAB
19/23
Sustainable System
Economic Sustainability
IBS SCORE : 93.95
IBS Score :
Part 1 Structure = 44.05
Part 2 Wall = 19.90
Part 3 = 30.00Other SimplifiedSolutions
Total IBS Score = 93.95
20/23
KKM Quarters, 1 Blocks, 24 Units, 15 Storeys
Sustainable System
Environmental Sustainability
Less Wet Works : Cleaner Site
Less Material Wastage : Steel Moulds at Production
Flat Slab at Site
21/23
Social Sustainability
Sustainable System
0
10
20
30
40
50
60
70
80
90
100
110
M A M J J A S O N D M A M J J S O N DJ F0
10
20
30
40
A
2014 2015
CO
NC
RE
TE
VO
LU
ME
M
3 / D
AY
AV
ER
AG
E W
OR
KF
OR
CE
/ D
AY
0
100
200
300
400
500
600
700
M A M J J A S O N D M A M J J S O N DJ F0
A
2014 2015
ER
EC
TE
D A
PT
. U
NIT
S / M
ON
TH
AV
ER
AG
E W
OR
KF
OR
CE
/ M
ON
TH
50
100
150
200
13u
63u
116u
194u
262u
352u
423u
480u
530u
592u
676u
WORKFORCE AT CASTING YARD
WORKFORCE AT CONSTRUCTION SITE
60 workers able to complete 4 units/day : 720m2/day (7750sqft) 1 worker able to complete : 12m2/day (129sqft)
Maximum Workforce : 225 WorkersMonthly Units/Floors Completion : 67 Units/4 Floors
Less Foreign Workforce : Reduce Social Problems
Production : 12m2/day/worker
Site : Max. 250 workers at peak
22/23