Framework FundingStatus of ’07-’09 Projects
Report to OGIC3/18/2009
![Page 2: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/2.jpg)
2
‘07-’09 Framework Funding
OGIC endorsed projects on 1/25/09 7 projects $451,000 Projects expire and deliverables due
6/30/09
![Page 3: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/3.jpg)
3
‘07-’09 Framework Funding
Hydro Development WRD, BLM Cadastral Data Sharing LCOG, Deschutes Co, DOR Wetlands OWEB Geologic Data DOGAMI Road Centerline ODOT Soils OSU Fish Habitat Distribution ODFW
![Page 4: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/4.jpg)
4
Hydro Development
WRD, BLM Funded for $50,000 Work performed to date:
Incorporated State of Oregon identified edits into NHD Technical support to the Hydro LiDAR pilot project
Project Status: On budget, on schedule
![Page 5: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/5.jpg)
5
Cadastral Data Sharing
LCOG, Deschutes Co., DOR Funded for $36,000 Work performed to date:
License agreement developed by work group Agreement distributed to County Assessors DAS, DOR monitoring adoption
Project Status: Making progress
![Page 6: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/6.jpg)
6
Wetlands
OWEB Funded for $48,000 Work performed to date:
Scan and digitize 240 NWI quads Attribute resulting product Conduct QA
Project Status: FIT funded portion complete
![Page 7: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/7.jpg)
7
Geologic Data
DOGAMI Funded for $150,000 Work performed to date:
Scan and digitize W and NW project areas Attribute resulting product
Project Status: Several tasks complete Delivery of completed project database and metadata by May, 2009
(ahead of contract target)
![Page 8: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/8.jpg)
8
Road Centerline
ODOT Funded for $75,000 Work performed to date:
Received updated road centerline data from 32 of the 36 county road authorities
Feature Manipulation Engine (FME) workbenches have been developed for all of the county road authorities
QA/QC work to begin on the newly updated data soon and continue through June
Project Status: Contract issues have delayed project
![Page 9: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/9.jpg)
9
Soils
OSU Funded for $75,000 Work performed to date:
Significant progress on best-available data layer for soils Significant progress on consistent Statewide soils data layer
Project Status: On budget, on schedule
![Page 10: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/10.jpg)
10
Fish Habitat Distribution
ODFW Funded for $17,000 Work performed to date:
Migrate anadromous salmonid data to the 1:24k Framework hydro from previously existing 1:100k lines and 1:24k points
Additional significant updates to several species and basins
Project Status: Complete, Statewide data available
![Page 11: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/11.jpg)
11
Funding Status
$451,000 Original amount $195,631 Invoiced to date $255,369 Remaining
Final report prior to September Meeting
![Page 12: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/12.jpg)
12
![Page 13: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/13.jpg)
FGDC CAP Grants
Report to OGIC3/18/2009
![Page 14: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/14.jpg)
14
FGDC CAP Grants
Category 7:“Demonstration of Geospatial Data Partnerships across Local, State and Federal Government”
Category 3:“Develop and implement statewide strategic and business plan”
![Page 15: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/15.jpg)
15
Facilitated Meetings
Discuss and collaborate on the navigatOR strategy
Outline the navigatOR initiative Initiate dialogue as to how navigatOR can
be improved or modified to better meet the needs of the participants
![Page 16: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/16.jpg)
16
Meeting Locations
![Page 17: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/17.jpg)
17
Meeting Follow-up
Summary of meeting outcomes Identify common outcomes from multiple
meetings Communicate summaries to all
participants from every meeting
![Page 18: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/18.jpg)
18
Meeting Follow-up
It is expected that there will be some commonalities in the discussion at the various meetings and seeing those commonalities will begin to create a more cohesive sense of community and shared direction among the members of the GIS and government business communities
![Page 19: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/19.jpg)
19
Tracking Mechanism
Track accrual of navigatOR benefit Work with URISA and NSGIC Research and identify examples
![Page 20: Framework Funding Status of ’07-’09 Projects](https://reader035.vdocuments.us/reader035/viewer/2022081519/56814588550346895db26d79/html5/thumbnails/20.jpg)
20
Final Steps
Compile Review Revise Produce Share