I T Broadband Connectivity Infrastructure Projects Projects Status

Upload: briana-lewis

Post on 24-Dec-2015

224 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: IT Broadband Connectivity Infrastructure Projects Projects Status

IT

Broadband Connectivity Infrastructure Projects

Projects Status

Page 2: IT Broadband Connectivity Infrastructure Projects Projects Status

IT

• Step 1: Enabling Environment already in place that allows investment in sector: Policies, Institutions, Regulatory Environment

• Step 2: Infrastructure Challenge being addressed– See next Diagram (NBB, KMN, WiBro, Rwandatel and MTN fiber Networks and Several ISP Wimax Solutions now exist)

• Step 3: Developing IT driven Service Sector [Ongoing, needs accelerated development]– Efficient Banking Systems, Tourism and Public Service Delivery– Financing of Development

• Step 4: Needs concerted efforts in building a critical mass of highly skilled workforce— We have chosen Software Development as a key driver of our transformation process

2

Rwanda Vision For Science & Technology – Focus on ICT

Page 3: IT Broadband Connectivity Infrastructure Projects Projects Status

IT

2001-2005 2006-2010 2010-2015 2015-2020

Policie

s

In

frastr

uctu

re

B

usin

ess

Page 4: IT Broadband Connectivity Infrastructure Projects Projects Status

IT

4

NATIONAL BACKBONE

ARTEL(Satellite

Com)

KMN

Kigali Metropolitan Network

Network Operations

Center

Local IEXInternational

Gateway

National Data

Center

WiBro

Enabling Environment: Investment ICT in Infrastructure

Page 5: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

The Projects

1. NBB: National Backbone Fibre-Optic Network

2. KMN: Kigali Metropolitan Network

3. WiBro: Wireless Broadband Network

Page 6: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

National Backbone Network

• A high-speed 2,300 Km fiber-optic network that will interconnect all the districts and border posts of the Country

• This network shall also provide converged IP/MPLS services to 226 identified located in the districts

• Sites to be connected: district headquarters, schools, universities, hospitals, health centers, social security fund offices, RRA & Customs offices, police offices, immigration offices, utilities, army camps/barracks, BNR branches, Judiciary Offices, ORTPN sites, etc…

• Border post connectivity for regional and international traffic

About the Project

Page 7: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

National Backbone Network

Page 8: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

National Backbone Network

Civil Works: Kigali - Gatuna

Page 9: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

The Projects

1. NBB: National Backbone Fibre-Optic Network

2. KMN: Kigali Metropolitan Network

3. WiBro: Wireless Broadband Network

Page 10: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

Kigali Metropolitan Network

• Construction of a high-speed Fiber-optic network in the Kigali metropolitan area;

• Deployment of Network Equipments (MPLS) to provide IP data, voice and video services to all government agencies in Kigali City;

• Construction of a Network Operations Control Center (NOC) for central network management and operation;

• Network capacity: 10Gbps ring (STM-64), max1Gbps network equipment for each government site

• Interconnection with the National Backbone Network (all the 30 districts and border posts)

About the Project

Page 11: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

Kigali Metropolitan Network

• Phase 1:– Installation of underground fibre-optic cables (57 Km, 54

government buildings, 63 agencies) – Deployment of IP/MPLS Network Equipments to (46

Routers, 105 Switches, 53 Optical Fiber Distribution Frame (ODF), 72 Network racks, 73 UPS) Installation and configuration completed for 46 government agencies

– Construction of Network Operation Center (NOC) at Telecom House

– 3040 VoIP phones delivered (1725 phones configured)– Configuration of VoIP System & Data Connectivity– Network Migration: 10th of December 2009

Completed Activities

Page 12: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

Kigali Metropolitan NetworkNetwork Operation Center (NOC) at Telecom House

for Real-time Network Control & Monitoring

Page 13: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

The Projects

1. NBB: National Backbone Fibre-Optic Network

2. KMN: Kigali Metropolitan Network

3. WiBro: Wireless Broadband Network

Page 14: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

WiBro Network

• WIBRO stands for Wireless Broadband; it is a Korean Mobile WiMax Technology which provide superior broadband services for data, voice , video

• The network consists of a core fibre-optic transmission network , wibro radio equipments, antennas and masts installed at various locations in the city

• Project implementation started in June 2008. First trial-run succesfully conducted in Dec 2009

• The project is divided into 2 phases.

– The first phase is coverage of Kigali City

– Second phase is coverage of 5 towns: Rwamagana, Huye, Rusizi, Ruhengeri and Gisenyi.

About the Project

Page 15: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

WiBro Network

Page 16: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

WiBro Network

Topology

ACR-Telecom House

BCDICentenary

HouseCity Plaza

APEX

Nyarugenge

RWT Switch

KabugaKinamba

Okapi Hotel

MininfraKimihurura 1RITA

Kacyiru 1

Kacyiru 2

GisoziSamantha

House

Mburabuturo

KIST 3KIST 2

Gorilla Hotel

Kimihurura 2

Gicondo 1Gicondo 2

Giporoso

Giporoso

StadiumKanombe

Kimironko 2

Kissementi

Minijust

Nyarutamara

Biryogo

Covibar

Golf Club

Kibagabana

KL House

Inind HouseKicukiro

Gitega

Nyakabanda

Nyamirambo

Internet Backbone

AAA

AAA

Page 17: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

WiBro Network

Civil works for fibre-optic cables installation – 95% completed Site acquisition – 100% completed Power Installation – 80% completed Telecommunication Tower construction – 90% completed Equipment installation(Antennas, Base station, repeaters...) –

95 % completed – Total of 40 Sites (Towers & Rooftop) WIBRO Network Operating Center – 90% completed

Project Status

Kigali WiBro Network scheduled to go live on December 10th, 2009– Trial Run Phase (Dec 2009 to February)– Commercial Services requires a company set-up (Regulatory Requirement) WiBro network should be owned and managed by a Commercial Entity

Page 18: IT Broadband Connectivity Infrastructure Projects Projects Status

IT Broadband Connectivity Infrastructure Projects

WiBro Network

Tower Construction & Installation

RDB-IT has constructed 40 Sites (Towers and Rooftop types) in Kigali City