foph hira1
TRANSCRIPT
-
7/29/2019 Foph HIRA1
1/6
LC(Y-Yes,N-NO)
IPC(Y-Yes,N-NO)
1 Excavation
NFalling of person or
vehicle into the
excavated area
Minor/Major injury N Y
Vehicle accident may
cause major/fatal
Y Y
Fall down cause minor
injury
N N
Collision vehicle to
vehicle or to structure
cause major/ fatal
Y Y
1.Fall of tools and
structure parts from
height.
Major injury / fatal
Y Y
2.Rolling of Plate. Major injury / fatal
3.Lifting of plate from
grond.Major injury / fatal
4.1
Electrical construction
power distribution:-
1.PSS Installation N
Above ground cable open
termination,loose
connection, improper
earthing ,ingress protection
overload.
Y Y
2
N
3
LANCO BABANDH POWER LTD
HAZARDS I
Doc No: LBPL/Ele/ HIRA/SWYD/01 Issue No: 1
SlNO
Activities
Condition
(N/AB/E)
Hazards Identification Risk Identification
Department: Electrical
OH & S Participation: Mukesh Behera
Material Handling and
Transportation
Vehicle movement at site
for shifting of material.
Structure(Shell) erection N
-
7/29/2019 Foph HIRA1
2/6
4.2 2.Cable Laying N
Above ground cable open
termination,over load,loose
termination,improper
clipping,cable damage.
Y Y
4.33.Installation of
Distribution boardN
Improper earthing,loose
termination,ingress
protection,improper
clipping,improper housing
of electrical equipment.
Y Y
4.45.Power Supply to the
equipment
N Improper switching. 1.Electrocution,
2.Damage of materials
3.Job hamper.
Y Y
4.5 Testing of equipment-
5
Area Lighting N
Improper of lack of
lighting Injury to person,
vehicle accident Y Y
-
7/29/2019 Foph HIRA1
3/6
BC(Y-Yes,N-NO)
E(Y-Yes,N-NO)
Ref of Legal
requirementS L
RiskLevel
Riskcontrol
Plan
ExistingControl
RefOCP
Anyadditional
controlproposed
Y N NO 4 3 E CP2 Barricading the
excavated area
LBPL
Y Y NO 3 4 M CP2 LBPL
N N NO 2 4 L CP1 LBPL
Y Y NO 4 4 E CP2 Vehicle moving to other
site location are not
allowed to enter into work
area for taking any
short cut way. Continuous
supervision.
LBPL
Y Y 3 3 H LBPL
Y Y
ENTIFICATION AND RISK ASSESMENT (HIRA)
Date- 31.10.12 Rev. No: 0/ Date- 31.10.12
Area : FOPH AREA
Proper approach road need
to be made using stone or
stone dust , short cut
approach not to be allowed ,
rain boot must be used during
walk
1.All armoured power cable
tobe undergrounded,
unarmourpower cable to be
over headed or
undergrounded in movement
area Damaged cable should
be removed from the work
Barricading the protected
area where height work is
going on, proper tieing of
tools , use of PPE as
mandatory.
-
7/29/2019 Foph HIRA1
4/6
Y Y
Y Y
Y Y 4 3 E CP3 LBPL
Y Y 3 4 M CP2
Proper planning of night work
and be it informed well
before evening, Use of
fluorescent dress
at night. LBPL
area. 2.Earthing should
be provided to the elecrical
DB and equipment. RCCB and
earth pit to be tested at
regular interval. 3.
Sufficient no of standard
measuring electrical tools to
be used.
4.IP 55 protection of the
equipment should be
provided.
5.Proper cable termination
with proper tightness of the
joint.
6.Bare wire connection
should be prohibited and
proper plug top should be
provided.
-