15
TEST FLEXIBLE PLANNING 1. Create info structure ( MC21 ): CHOOSE CHARACTER TAB Click on the required field catalog on right column Now select the required characteristics by double clicking on them in the left column

Upload: debraj-bhaduri

Post on 06-Dec-2014

275 views

Category:

Education


14 download

DESCRIPTION

sap flexible planning procedure for the beginers

TRANSCRIPT

Page 1: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

1. Create info structure ( MC21 ):

CHOOSE CHARACTER TAB

Click on the required field catalog on right column

Now select the required characteristics by double clicking on them in the left column

Page 2: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

CLICK ON ‘COPY+CLOSE’

NOW CLICK ON ‘COPY’

NOW CLICK ON ‘CHOOSE KEY FIGURE’

Page 3: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Click on the required field catalog on right column

Now select the required characteristics by double clicking on the Field catalog fields in the left column.

SAVE

Page 4: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

2.Activate the info structure ( MC22 ):

Click on red colour ‘generate ‘ tab

Page 5: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Go back & Save

3.Assigning the planning parameters to the info structure ( MC7F ):

Click on details

Save

Page 6: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

4.Creation of Planning Hierarchy ( MC61 ):

Save

Page 7: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

5.Creation planning type and Macros ( MC8A ):

Add the key figures on by one by clicking +Structure button

Page 8: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Save

6.Calculate Proportional Factors ( MC9B ):

Execute

7.Planning in the planning table ( MC93 ):

Page 9: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Now enter the sales plan and copy them to production

Page 10: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Click on keyfigure

Save

Page 11: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

8.Copy planning version ( MC8V ):

9.Transfer planning data to demand management ( MC90 ):

Transfer now

Page 12: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Page 13: Flexible planning in sap pp

TEST FLEXIBLE PLANNING

Now check in the MD04 for the planned independent requirements for the respective materials

Page 14: Flexible planning in sap pp

TEST FLEXIBLE PLANNING