sap pp sample

Upload: sunny-sapsd

Post on 02-Jun-2018

352 views

Category:

Documents


10 download

TRANSCRIPT

  • 8/11/2019 Sap Pp Sample

    1/17

    SAP Multiple Choice Question with Answers

    For

    SAP Certified Application AssociateProduction Planning &

    Manufacturing with SAP ERP 6.0 EHP5 (SAP Course Code:

    C_TSCM42_65)

  • 8/11/2019 Sap Pp Sample

    2/17

    Tables of Contents:

    Question1: Usage of planned independent requirement as a planning strategy

    Question2: Using Consumption Based Planning

    Question3: Detailed planning in MRP

    Question4: Make-to-stock production strategy

    Question5: Feature of make-to-stock production

    Question6: Consumption mode

    Question7: Features of make-to-order production strategy

    Question8: Special form of make-to-order production

    Question9: Planning strategy used in planned independent requirement

    Question10: Customization setting for requirement planning

    Question11: Availability check

    Question12: Features of multilevel requirement planning

    Question13: Prerequisite for planning for a material

    Question14: Processing key used in MRP planning run

    Question15: Planning run with processing key

    Question16: Firming type and its features

    Question17: Stock exclusion during MRP planning run

    Question18: Features of partially available safety stock for planning

    Question19: Net requirement calculation

    Question20: Grouping of requirements

    Question21: Procurement key in Material Master

    Question22: BOM explosion during planning run

  • 8/11/2019 Sap Pp Sample

    3/17

    Question23: BOM selection

    Question24: MRP List

    Question25: Features of discrete manufacturing

    Question26: Exception messages

    Question27: Restriction while customizing Exception messages

    Question28: MRP elements used in evaluation of order report

    Question29: Pegged requirements

    Question30: Features of MPS in planning of material

    Question31: Stock transfer using one step procedure

    Question32: stock transfer using two step procedure

    Question33: Stock transfer order without delivery

    Question34: Stock transfer order with delivery using tow step procedure

    Question35: Material Requirement Planning

    Question36: Planning with MRP areas

    Question37: prerequisites to use MRP with MRP areas

    Question38: Material planned in MRP area using special procurement type

    Question39: Types of MRP areas

    Question40: Planning strategy for make-to-stock production

    Question41: Function of Material requirement planning

    Question42: Master data for MRP components

    Question43: Quota rating

    Question44: Net requirement calculation in planning run

    Question45: Net requirement calculation in reorder point planning

    Question46: Procedures in lot-sizing calculation

    Question47: Optimum lot sizing procedure

  • 8/11/2019 Sap Pp Sample

    4/17

    Question48: Bill of Material status

    Question49: Lot-sizing procedure

    Question50: Types of lot-sizing procedure

    Question51: Types of production

    Question52: Functional process integrated with production order management

    Question53: Master data for production order

    Question54: Activities in production order

    Question55: Effects of good receipt in reference to production order

    Question56: Material staging

    Question57: Features of confirmations

    Question58: Use of Order-related Cost object controlling

    Question59: Use of Product-relate Cost object controlling

    Question60: Features of Process order

    Question61: GMP-compliant production using process order

    Question62: Restriction applicable in batch derivation

    Question63: Master data for Process-Order-Controlled production

    Question64: Master data for Repetitive Manufacturing

    Question65: Reporting point backflush in repetitive manufacturing

    Question66: Integration of repetitive manufacturing with controlling

    Question67: KANBAN procedure

    Question68: Object to organize the material flow in the KANBAN procedure

    Question69: Source of supply for material in KANBAN procedure

    Question70: Difference between plan-controlled production and KANBAN

    Question71: Basic data for Project-oriented production

    Question72: Stock maintenance in project-oriented production

  • 8/11/2019 Sap Pp Sample

    5/17

    Question73: Step in project-oriented production process

    Question74: Use of Production/resource tools (PRT) in the manufacturing process

    Question75: Features of lead time scheduling

    Question76: Time elements of an operation

    Question77: Follow on activity when a production order is saved

    Question78: Setting for routing selection

    Question79: Setting for BOM selection based on lot size

    Question80: Feature of production order item category

    Question81: Operation sequence in production order

    Question82: Conversion of planned order to production order

    Question83: Steps in sequence for MRP

    Question84: Features of planned order

    Question85: Planning procedure using SAP SCM (APO)

    Question86: Horizon in planning functions

    Question87: Features of APO production orders

    Question88: Implementation of floats in SAP APO production order

    Question89: Material availability check

    Question90: Availability checks using multipart check instructions

    Question91: Printing of Production order documents

    Question92: Time tickets of an operations

    Question93: Generation of confirmation slips of an operation

    Question94: BOM controls

    Question95: Material staging procedures

    Question96: Splitting of production order

    Question97: Functionality of process integration

  • 8/11/2019 Sap Pp Sample

    6/17

    Question98: Elements and functions of work instructions

    Question99: Message types for production orders

    Question100: Process integration of production orders

    Question101: Confirmation of production order

    Question102: Capacity requirement of a production order

    Question103: Features of good receipt in production order

    Question104: Good receipt posting

    Question105: Product-related costs object controlling

    Question106: Deletion of Production order in SAP APO

    Question 107: Evaluation of production order

    Question108: setting for posting of good issue automatically

    Question109: Good Receipt posting

    Question110: Features of collective order

    Question111: Tasks required for rework order

    Question112: Integration of sales & operational planning and capacity planning

    Question113: Capacity leveling for planned order

    Question114: Covering available capacity

    Question115: Prerequisite for finite scheduling

    Question116: Midpoint scheduling

    Question117: Coverage for disruptions during an operation or production

    Question118: Rescheduling/Deallocation in capacity planning

    Question119: Factors influencing planning strategies in capacity planning

    Question120: Setting to check the operation dates and order floats

    Question121: Factors effecting mass dispatching

    Question122: Capacity assignments in Production planning

  • 8/11/2019 Sap Pp Sample

    7/17

    Question123: Split types used in resource planning

    Question124: Parameters during capacity evaluation

    Question125: Prerequisite to configure the charts with material stock curves on capacity planning

    table

    Question126: Functionality of routings in production planning

    Question127: Setting for automatically creation of material master for each storage location

    Question128: Views in material master used by Production planning module

    Question129: Tales where MRP and forecast data are stored

    Question130: Creation of Views in material master

    Question131: Use of material type while creation of material master

    Question132: Units of measurement

    Question133: Class type used for batch management

    Question134: Activation of batch management in material master

    Question135: Where-used list in Production planning module

    Question136: Report to determine the effect of component changes in BOM

    Question137: Reports to overview all the necessary parts and materials

    Question138: Reports to view the difference between the BOMs with their change statuses

    Question139: Task type list used in repetitive manufacturing

    Question140: Prerequisite for creating a routing

    Question141: Material assignment in routings

    Question142: Suboperations supported in routing

    Question143: User defined fields used in the routings

    Question144: Use of replace function in mass changing of objects

    Question145: Prerequisite for component allocation

    Question146: Making changes in routings

    Question147: Manufacturing of co-products, by-products, waste products

  • 8/11/2019 Sap Pp Sample

    8/17

  • 8/11/2019 Sap Pp Sample

    9/17

    Question173: Use of Work Center

    Question174: Availability check customization

    Question175: Alternative sequence in routing

    Question176: Customization of Material Master

    Question177: Validity of Bill of Material

    Question178: Bill of Material status

    Question179: Item category in Bill of material

    Question180: Routing status

    Question181: Task list profiles in routing

    Question182: Screen sequence and attributes of material master

    Question183: Pre-requisite for BOM creation

    Question184: User-specific settings in BOM

    Question185: Make-to stock production

    Question186: MRP processing key

    Question187: Control parameters in long-term planning strategy

    Question188: Planning time fence

    Question189: Forecast-based planning

    Question190: Formulas for work center

    Question191: Material master configuration

    Question192: Control Key in a work center

    Question193: Changing material type

    Question194: BOM comparison

    Question195: Usages of routing

    Question196: Work center integration with costing

    Question197: Integration of routing

  • 8/11/2019 Sap Pp Sample

    10/17

    Question198: Material assignment in routing

    Question199: Mass changes of objects

    Question200: Pre-requisite for component allocation

  • 8/11/2019 Sap Pp Sample

    11/17

    1)

    Your Organization is using Planned independent requirement as a planning strategy. Which of

    following statement are correct?

    Note: There are more than one correct answers to this question.

    a)

    It is used generally with make-to-order production

    b)

    The stock requirements can be derived from a forecast of future demands

    c)

    It is used when a specific sales orders are received

    d)

    It is used to spread the burden evenly as possible across your production resources

    Answer: b, d

    Explanation:

    Planned independent requirements are stock requirements that can be derived from a forecast

    of future demand. It is generally used in made-to-stock production, where we want to start

    procurement of the affected materials without waiting for specific sales orders. On the one

    hand this kind of procedure allows us to reduce delivery times, while on the other hand, we can

    use forecast planning to spread the burden as evenly as possible across our production

    resources.

    2)

    When do we use Consumption-based planning when we are planning for a material?

    Note: There are more than one correct answers to this question.

    a)

    We are planning for high value materials

    b)

    It is based on the current and future sales as a reference point for planning the material

    c)

    One of the requirement is efficient and up-to-date inventory management

    d)

    We are planning for low value materials

    Answer: c, d

  • 8/11/2019 Sap Pp Sample

    12/17

    Explanation:

    Consumption-based planning is based on historical consumption values and uses forecast or

    statistical procedures to determine future requirements. Consumption-based planning is

    characterized by its simplicity and is mainly used for B and C parts with a low value. One

    prerequisite of consumption-based planning is efficient-and constantly up-to-date inventorymanagement.

    In contrast to consumption-based planning, material requirements planning take current and

    future sales as a reference point and are executed for the whole BOM structure. The planned

    requirement quantities trigger the MRP calculation. It produces better planning results than

    consumption-based planning.

    3)

    How does the system do the detailed planning in MRP?

    Note: There are more than one correct answers to this question.

    a)

    The procurement dates and quantities for the required assemblies and components are

    determined based on the requirements dates and quantities for the finished product

    b)

    Scheduling of procurement for in-house products is carried out using the BOM

    c)

    The assemblies required for production is determined using the routing

    d)

    Bill of material and routing must be available for the material planned

    Answer: a, d

    Explanation:

  • 8/11/2019 Sap Pp Sample

    13/17

  • 8/11/2019 Sap Pp Sample

    14/17

    Make-to-stock strategies are aimed at planning the procurement of components (procurement

    or purchasing) by planning the finished product. If it is easier to plan at component level, we can

    use planning at assembly level. We choose make-to-order production strategy if

    The materials do not have to be stored separately or are assigned to a specific sales

    order; The costs have to be visible at material level, in other words not at sales order level.

    We use make-to-stock production when we produce stock independently of an order, because

    we want to supply our customers with goods from this stock later. We may want to produce

    goods without a sales order if we expect a demand for them in future. Make-to-stock strategies

    thus support very close customer-supplier relationships, since their purpose is to supply the

    customer with goods from stock as quickly as possible.

    5)

    You have been asked to explain the feature of make-to-stock production with net

    requirement planning according to strategy 10. Which of the following features are correct?

    Please choose the correct answer.

    a)

    Sales order are relevant for MRP

    b)

    Sales order are fulfilled from stock

    c)

    Goods withdrawals against sales order reduce the respective planned independent

    requirements

    d)

    The planned independent requirement is reduced in accordance with the LIFO principle

    using the requirement date

    Answer: b

    Explanation:

  • 8/11/2019 Sap Pp Sample

    15/17

    In pure make-to-stock production (net requirements planning according to strategy 10), the

    demand program is determined without reference to sales order

    Sales orders are not relevant for MRP, but we can display them for information purposes. Sales

    orders are fulfilled from stock. No consumption with planned independent requirements occurs.

    We can carry out the availability check with ATP logic in Sales and Distribution. Goodswithdrawals against a sales order reduce the respective sales order.

    Reduction of the demand program, that is, of the planned independent requirements, is carried

    out at goods issue. The oldest planned independent requirement is reduced first, in according

    with the FIFO (first in first out) principle using the requirement date. Future planned

    independent requirements are also reduced by goods issues, provided this is allowed by the

    forward consumption period in the material master.

  • 8/11/2019 Sap Pp Sample

    16/17

    6)

    Your organization is using forward/backward consumption mode to determine the direction

    on the time axis in which incoming sales orders are to consume planned independent

    requirement. So which consumption you would choose to support this type of consumption

    mode?

    Please choose the correct answer.

    a)

    Consumption mode 1

    b)

    Consumption mode 2

    c)

    Consumption mode 3

    d)

    Consumption mode 4

    Answer: d

    Explanation:

    We can use consumption mode to determine the direction on the time axis in which incoming

    sales orders are to consume planned independent requirements.

    In backward consumption (consumption mode 1), the sales order consumes planned

    independent requirements from before the customer requirement.

    In forward consumption (consumption mode 3), the sales order consumes planned independent

    requirements from after the customer requirement.

    We can combine backward and forward consumption provided that we take the consumption

    periods into account (consumption mode 2 or 4).

  • 8/11/2019 Sap Pp Sample

    17/17

    We can define the consumption mode and the consumption periods either in the material

    master or for each plant and MRP group. If no values have been entered, the system uses the

    default setting with the backward consumption for 999 days.