1 First wall mods status NCSX SIT Meeting July 1, 2002 •Points at 0, 30, 60 degrees from Art •Points x 1.025 in cross sections •RF launchers bigger issue than trim coils

Upload: sara-glenn

Post on 30-Dec-2015

23 views

Category:

Documents


0 download

DESCRIPTION

First wall mods status. Points at 0, 30, 60 degrees from Art Points x 1.025 in cross sections RF launchers bigger issue than trim coils. NCSX SIT Meeting July 1, 2002. Model. Vessel with insulation. RF launcher locations, typ 6 places. FW panels, 360 deg shown. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: First wall mods status

1

First wall mods status

NCSX SIT Meeting

July 1, 2002

•Points at 0, 30, 60 degrees from Art

•Points x 1.025 in cross sections

•RF launchers bigger issue than trim coils

Page 2: First wall mods status

2

Model

RF launcher locations, typ 6 places

FW panels, 360 deg shown

Modular coil partial assembly

Vessel with insulation

Page 3: First wall mods status

3

Plan cross section

10 deg

0 deg

20 deg

30 deg

40 deg

50 deg60 deg

RF launcher locations

Trim coils

Page 4: First wall mods status

4

Cross section at 0 degrees

Trim coils intersect this section

Almost all points are inside first wall

Page 5: First wall mods status

5

Cross section at 10, 20 degrees Points not available yet Trim coils intersect 10 deg section

20 deg

10 deg

Page 6: First wall mods status

6

Cross section at 30 degrees

Trim coils do not intersect this section

Closest approach to first wall

Page 7: First wall mods status

7

Cross section at 40, 50 degrees Points not available yet RF launchers intersect these sections

40 deg

50 deg

Co-ax

Faraday shield

Page 8: First wall mods status

8

Cross section at 60 degrees

Field joint and limiters are around this section

RF launchers on either side

Almost all points are inside first wall

Page 9: First wall mods status

9

Cross section at 60 degrees

Cross section changes abruptly

Limiter visible in this view

RF launchers on either side of this section mostly hidden by limiter

limiter

Page 10: First wall mods status

10

RF launcher options

Reduce number of launchers to 4 instead of 6 per section Less power?, unless strap lengths can be increased

Reduce coax to 4 inches instead of 6, maybe smaller

Move feeds farther out by running strap through “tunnels” to get straight-in shot at feed, but need more than 3 cm behind FW in these areas.

Page 11: First wall mods status

11

PFC panel / rib detail

Details for one concept for panel attachment developed with BFG Aerospace

Plasma

Vacuum vessel

Heated / Cooled RibThermally insulated connection to vessel

Panel installed

Panel ass’y retracted