final report for summer training - naif aljuhani

38
KING ABDULAZIZ UNIVERSITY MECHANICAL ENGINEERING DEPARTMENT DEPARTMENT THERMAL ENGINEERING AND DESALINATION TECHNOLOGY PROGRAM MEP 390 SUMMER TRAINING SUMMER TRAINING FINAL REPORT STUDENT NAME: NAIF MOHAMMED ALJUHANI COMPUTER NOUMBER: 1207841 EVALUATOR: DR. MAJED ALHAZMI SUPERVISOR: DR. MANSOOR SIDDIQUE FALL 2017

Upload: naif-mohammed

Post on 25-Jan-2017

19 views

Category:

Documents


10 download

TRANSCRIPT

Page 1: Final Report For Summer Training - Naif AlJuhani

KING ABDULAZIZ UNIVERSITY

MECHANICAL ENGINEERING DEPARTMENT

DEPARTMENT THERMAL ENGINEERING AND

DESALINATION TECHNOLOGY PROGRAM

MEP 390 – SUMMER TRAINING

SUMMER TRAINING FINAL REPORT

STUDENT NAME: NAIF MOHAMMED ALJUHANI

COMPUTER NOUMBER: 1207841

EVALUATOR: DR. MAJED ALHAZMI

SUPERVISOR: DR. MANSOOR SIDDIQUE

FALL 2017

Page 2: Final Report For Summer Training - Naif AlJuhani

i

ABSTRACT:

This report presents the training program from the period of 8 weeks from 22/5/2016

until 22/7/2016. The training was in Saudi Electricity Company at Jeddah Power Plant

3. This report describes the main activates which done during my training. The training

program covers many application in thermal mechanical engineering as Gas Turbine,

Pumps and heat exchangers. The training gave me a real experience of trouble shooting.

Page 3: Final Report For Summer Training - Naif AlJuhani

ii

TABLE OF CONTENTS

ABSTRACT i

LIST OF TABLES iv

LIST OF FIGURES v

1. INTRODUCTION: 1

1.1 The student’s mission statement for the training activity 1

1.2 Expected Training Learning Outcomes. 1

2 THE COMPANY: 2

2.1 Historical Background 2

2.2 Organizational Structure 4

2.3 Products 5

2.4 Customers 5

2.5 Engineering Units 5

2.6 Industrial Process 5

2.7 Environmental and Social Impact 17

2.8 Quality System 17

3 THE TRAINING ENVIRONMENT: 18

3.1 Work environment 18

3.2 Regulations and standards 18

3.3 Training Timeline 19

4 ASSIGNED TASK AND PROJECT: 20

4.1 Problem definition 21

4.2 Literature review and data collection 22

4.3 Knowledge integration with course work 24

4.4 Safety and environmental issues 24

4.5 Work plan 27

4.6 Economic Factors 28

4.7 Implementation 28

4.8 Impact analysis 28

4.9 Evaluation 29

Page 4: Final Report For Summer Training - Naif AlJuhani

iii

5 CONCLUSIONS AND RECOMMENDATIONS: 30

5.1 Achievement of expected learning outcomes 30

5.2 Recommendations to enhance future training in this

company 30

5.3 Recommendations to enhance future training of KAU

engineering students 30

REFERENCES 31

APPINDIX A 32

Page 5: Final Report For Summer Training - Naif AlJuhani

iv

LIST OF FIGURES

Fig(1): Power plant No.3 3

Fig(2): Jeddah power plant 3 organizational structure 4

Fig(3): Gas turbine components 6

Fig(4): Air inlet from outside of unit 7

Fig(5): Air filters 7

Fig(6): The compressor with 17 stages 8

Fig(7): The combustion chambers in GE unit 8

Fig(8): The ten combustion chambers in GE 9

Fig(9): The combustion chamber in APP unit 9

Fig(10): Liner in combustion chamber 10

Fig(11): Transition pieces in combustion chamber 10

Fig(12): Turbine stages in BBC unit 11

Fig(13): Rotor and stator of electrical generator 11

Fig(14): The Casing of gas turbine 12

Fig(15): Welding machine 13

Fig(16): Electric rod 14

Fig(17): Welding process 14

Fig(18): Turning machine 15

Fig(19): Grinding machine 15

Fig(20): Drilling machine 16

Fig(21): Electrical power generating stations 17

Fig(22): The training timeline 19

Fig(23): Gas turbine from GE ( 7001EA ) 21

Fig(24): Brayton cycle 22

Fig(25): The Helmet 26

Fig(26): Ear plugs 26

Fig(27): Ear muffs 26

Fig(28): Overall 27

Fig(29): The gloves 27

Fig(30): Safety glasses 28

Fig(31): Safety shoes 28

Fig(32): Electricity cost in Saudi Arabia 29

Page 6: Final Report For Summer Training - Naif AlJuhani

v

LIST OF TABLES

Table (1): Stages of plant build up 4

Table(2): Common problems in pumps workshop 16

Table(3): Specification of Frame 7001EA 20

Table(4): Work plan 27

Page 7: Final Report For Summer Training - Naif AlJuhani

1

1 INTODUCTION

1.1 The student’s mission statement for the training activity

In this report I will show and describe the main activates which done during my

training. I will mention what I learned during this program. It was the first time to me

working at a company. I felt the different between the studying and the working life. In

this training, I visited many sections which is helpful for me in many aspects. This

training improved my communication skills. This is coming from my communication

with our supervisor, the engineers and all staff in the plant. It's learned me how to deal

with the equipment and how to use safety tools. Also, I have learned a lot about the gas

turbine and its main component and its function.

1.2 Expected Training Learning Outcomes

- Team work skills

- How to work under supervisor

- Know the different between academic life and the field.

- An ability to use the engineering skills and tools for engineering practice.

Page 8: Final Report For Summer Training - Naif AlJuhani

2

2 THE COMPANY

2.1 Historical Background

On 05/04/2000, Saudi Electricity Company was established as a Saudi joint stock

company with a paid-up capital of (41,665,938,150) Saudi Riyal (Forty-one billion six

hundred and sixty-five million nine hundred and thirty-eight thousand one hundred and

fifty Saudi Riyals). This amount was divided into (4,166,593,815) shares (four billion

one hundred and sixty-six million five hundred and ninety three thousand, eight hundred

and fifteen shares). This was achieved by virtue of the Council of Ministers Order (No.

169) Dated 11/08/1419H which stipulated the merger of all Saudi electricity companies

in the Central, Eastern, Western, and Southern Regions in addition to the ten small

companies operating north of the Kingdom as well as the other electricity operations

managed by General Electricity Corporation, into a single joint stock company which is

now known as Saudi Electricity Company.

After the completion of the merger process in the year 2000, we followed a gradual and

systematic method in restructuring the company's business lines for the purpose of

assuring continuity of the electrical power services while maintaining the credibility of

the reliability of the electrical system and quality of services to our customers. We also

prepared our human resources to adapt to the required changes to realize our strategic

objectives and mutual vision.

In the beginning of 2002, the Board of Directors approved the new transitional

organizational structure which was designed based on functional business lines for

specialized activities. Strategic business functions emerged, i.e. Generation,

Transmission and Distribution, and Customer Services; including shared businesses and

support services to enable us to reinforce our performance at the level of all business

lines to draw our future directions for the anticipated holistic change.

In the beginning of 2003, the transitional organizational structure was activated, and the

second stage of the new organizational structure had been applied. In this concern, the

sectors and affiliate departments were defined directly for each and every specialized

business line. The job descriptions were prepared as well as the completion of the job

descriptions of all the other organizational sectors.

In the beginning of 2012, the National Grid SA, a limited liability company wholly

owned by the Saudi Electricity Company was established and launched. Its tasks and

Page 9: Final Report For Summer Training - Naif AlJuhani

3

responsibilities include electricity transmission in the Kingdom of Saudi Arabia and the

operation, control, and maintenance of the electrical grid. During that year, two more

business lines were introduced: Engineering and Projects Management, and Supply

Chain business lines.

In March 2014, the Board of Directors approved the organizational structure of the

Energy Trading & New Ventures business line which will supervise the trade relations

organized for the Saudi Electricity Company with electric power producers and major

consumers. Its new organizational structure will commence work before the end of the

year as per agreement with the Electricity and Cogeneration Regulatory Authority

(ECRA).

Currently, extensive work is in progress to complete the restructuring project in

compliance with the directions of the Board of Directors for bringing in strategic

partners of world-class service experiences in the field of electric power production and

distribution.(1)

Training location:

Power plant NO.3 Fig(1) is located in south of Jeddah in the first Industrial Area.

Fig(1): Power plant No.3

Stages of build up the plant:

In the third power plant, there is 35 gas turbine established in five stages since

1975 up to 2005 Distributed as follows in table 1:

Page 10: Final Report For Summer Training - Naif AlJuhani

4

Table (1): Stages of plant build up

2.2 Organizational Structure

Fig(2): Jeddah power plant 3 organizational structure

Number of

units

The

kind Model

Date

created Factory

Productivity

(MW)

Type of

fuel

1-4

Gas

turbine

7001B

1396 H

GE

44.6 for unit

Diesel

11-5

Gas

turbine

7001B

1399 H

GE

44.6 for unit

Diesel

12-17

Gas

turbine

11D5

1400 H

ABB

51.7 for unit

Crude

18-27

Gas

turbine

11D5

1402 H

ABB

51.7 for unit

Crude

28-35

Gas

turbine

7001EA

1425 H

GE

60 for unit

Diesel &

Crude

Page 11: Final Report For Summer Training - Naif AlJuhani

5

2.3 Products

PP3 product is an electricity. It's product about 1618 megawatts. It's the third largest

electric power production plant for the Western Region. Where the productivity percent

in this plant is 18% from the total energy produced for the Western Region.

2.4 Customers

The electricity from plant gathered to the network. Where the National Grid is

responsible for electricity distribution across the country.

2.5 Engineering Units

- Mechanical Engineering

This section comprises the design, analysis and of heat and mechanical power for the

operation of machines and mechanical systems.

- Electrical Engineering

Electrical engineering comprises the study and application of electricity, electronics,

and electromagnetism.

2.6 Industrial Process

2.6.1 Development of Gas Turbine

Gas turbine is an effective way to generate electric power . It is a turbine driven by

expanding hot gases produced by burning fuel. The production of gas turbine is between

1 MW and 250 MW .It Commonly used in rush hours.

Advantage of gas turbine

Quick startup (Compared with steam turbine)

Low cost (Compared with steam turbine)

Easy to maintenance

Quick shutdown (Compared with steam turbine)

Disadvantage of gas turbine

Low production (Compared with steam turbine)

High fuel consumption (Compared with steam turbine)

Low life cycle

Page 12: Final Report For Summer Training - Naif AlJuhani

6

Components of gas turbine

Generally, Gas turbine has five main components Fig(3) which are:

1. Air inlet

2. Compressor

3. Combustion chamber

4. Turbine

5. Electrical generator

Fig(3): Gas turbine components

In field, each component need process and protection to work perfectly. We will start to

talk about each component separately.

1. Air inlet

Where this point is the entrance of air, we have about 700 air filter to make sure is no

any sands or dirty things. The air enters to compressor with pressure equal to 1 bar (

Atm ). 30 % of inlet air will be for combustion chamber and the other 70 % for cooling

inside the unit. Fig(4) shows the air inlet from outside of unit. In Fig(5) we see two

types of filters. One of them is cylindrical and the other is conical.

Page 13: Final Report For Summer Training - Naif AlJuhani

7

Fig(4): Air inlet from outside of unit

Fig(5): Air filters

2. Compressor

The compressor is a machine used to increase the pressure of gases. The air enter to

compressor with pressure equal to 1 bar and leave with 8 bar. Where the change of the

pressure is very high So, we need a compressor with multiple stages. The compressor

contains 17 stages Fig(6).

Page 14: Final Report For Summer Training - Naif AlJuhani

8

Fig(6): The compressor with 17 stages

3. Combustion chamber

As we mention in Ch1, In Jeddah Power plant No. 3, it has two types of units one of

them from GE and the other from ABB. The units from GE contain 10 combustion

chambers surrounding the compressor Fig(7) and Fig(8). The units from ABB contain

only one combustion chamber Fig(9).

Fig(7): The combustion chambers in GE unit

Page 15: Final Report For Summer Training - Naif AlJuhani

9

Fig(8): The ten combustion chambers in GE

Fig(9): The combustion chamber in ABB unit

Components of combustion chamber in GE:

1. Fuel nozzle

2. Liner. Fig(10)

3. Transition pieces. Fig(11)

4. Spark plugs

5. Flame detectors

Page 16: Final Report For Summer Training - Naif AlJuhani

10

Fig(10): Liner in combustion chamber

Fig(11): Transition pieces in combustion chamber

4. Turbine

Is a machines having a rotor, usually with vanes or blades, driven by the pressure,

momentum, or reactive thrust of a moving fluid, as steam, water, hot gases, or air, either

occurring in the form of free jets or as a fluid passing through and entirely filling a

housing around the rotor. In GE units, the turbine has 3 stages where the BBC units

contains 5 stages Fig(12).

Page 17: Final Report For Summer Training - Naif AlJuhani

11

Fig(12): Turbine stages in BBC unit

5. Electrical Generator

Is a machine to convert mechanical energy to electrical energy. It contains two

components: Rotor and stator Fig(13).

Fig(13): Rotor and stator of electrical generator

How the gas turbine works?

1. Air enters to the compressor due to suction process inside the compressor up to

given pressure ratio.

2. The compressor increase the pressure and temperature of air .

Page 18: Final Report For Summer Training - Naif AlJuhani

12

3. The air with high pressure goes to combustion chambers, the fuel nozzle will

start to spray the fuel with air inside each chambers. Then the spark plugs will

start the combustion.

4. Inside the combustion chambers, the hot burnt gases are produced and they go to

the turbine and exert pressure on the turbine blades.

5. The turbine starts rotation and producing mechanical power.

6. In the generator, the rotor will rotate with the high velocity that generate a

magnetic field then the electrical power will produce.

Casing:

Gas turbines have a casing Fig(14) around the blades that contains and controls the

working fluid.

Fig(14): The Casing of gas turbine

Page 19: Final Report For Summer Training - Naif AlJuhani

13

2.6.2 Workshops

Workshops section have many departments, and the most important departments is

Welding, Turning, grinding, drilling and NDT. The objective of the workshop at general

and these three departments in particular is supporting or serve the turbines.

1- Welding Workshop:

Welding is a fabrication or sculptural process that joins materials,

usually metals or thermoplastics, by causing fusion, which is distinct from lower

temperature metal-joining techniques such as brazing and soldering, which do

not melt the base metal. In Fig(15), the welding machine used to control the current.

Fig(16) shows the electric rod which used in welding process. Fig(17) shows how the

process work.

Fig(15): Welding machine

Page 20: Final Report For Summer Training - Naif AlJuhani

14

Fig(16): Electric rod

Fig(17): Welding process

2- Turning Workshop:

Turning operation Fig(18) is one of the most basic machining processes. That is, the

part is rotated while a single point cutting tool is moved parallel to the axis of rotation.

Page 21: Final Report For Summer Training - Naif AlJuhani

15

Fig(18): Turning machine

3- Grinding Workshop:

Grinding is an abrasive machining process that uses a grinding wheel as the cutting tool

Fig(19).

Fig(19): Grinding machine

Page 22: Final Report For Summer Training - Naif AlJuhani

16

4- Drilling Workshop:

Drilling is a cutting process that uses a drill bit to cut a hole of circular cross-section in

solid materials. The drill bit is usually a rotary cutting tool, often multipoint Fig(20).

Fig(20): Drilling machine

5- NDT Workshop:

NDT means Non-destructive testing, and it's defined as a process of inspecting, testing,

or evaluating materials, components or assemblies for discontinuities, or differences in

characteristics without destroying the serviceability of the part or system. It's used

mostly to check if there are any cracks in the shafts, also to decide if the shaft should be

changed or it can be fixed according to the condition of the cracks.

6- Pumps workshop:

Pumps is very important workshop inside the plant. Each unit have different types of

pump as: Fuel pump, oil pump and water pump. In pump workshop there are common

problems. Table(2) will show many problems and it's causes.

Table(2): Common problems in pumps workshop

Problem Causes

Pump rotate but it doesn't pump liquid Suction line is dirty

Pump doesn't produce any pressure May be there is a leakage

Bearing is hot Need to check the lubrication

Page 23: Final Report For Summer Training - Naif AlJuhani

17

2.7 Environmental and social impact

A power plant can affect the environment by its construction and by its operation. These

effects can be for long or short time. A power plant and its auxiliary components take

up space on the ground, in the air, and the use water resources. Also, it may emit

pollutants into the air. It can also affect on the future uses of nearby land.

Inside the unit, we burn fuels to make either hot air needed to rotate power turbines

generating electricity. The burning of fuel creates exhaust gases and other products,

including air pollutants.

The construction and operation of a power plant can have noises effects on the

community in which the power plant is built. Construction of the power plant, Also, it

might have an effect on community aesthetics or business. Costs for community

services such as police, fire protection.

There also can be positive effects on the community such as jobs for local population

and provide the electricity for them.

2.8 Quality System

Saudi Arabia has a power transmission and distribution networks length 554,254 (km-

circuit) of high voltage lines and cables and range from 110 kV to 380 kV. The number

of settlements electrified reached 12,722. The company is looking forward to increasing

the efficiency and effectiveness of its main tasks of dealing with the generation,

transmission and distribution business and to achieve maximum benefit from its capital

projects by providing the best to our customers.(2)

Fig(21): Electrical power generating stations

Page 24: Final Report For Summer Training - Naif AlJuhani

18

3 THE TRAINING ENVIRONMENT

3.1 Work Environment

During the summer training, we took rotational in each section in plant. Where in each

week we have task with that section.

3.2 Regulation and standards

Supervisors: They have the primary responsibility for implementation of the

Personal Protective Equipment ( PPE ) program in their work are. They are

responsible for:

Ensuring PPE is available;

Providing PPE as required;

Providing PPE as required or upon request to all employees.

Ensuring PPE is being used by each affected employee during all job tasks

which require such protection;

Conducting specific hazard assessments for personal protective equipment

use upon request;

Documenting purchase and distribution of all PPE.

Environmental Health and Safety are responsible for:

Assessing the workplace to determine if hazards are present, or are likely

to be present, which necessitates the use of PPE.

Selecting and recommending PPE that properly fits each affected

employee.

Providing training in the proper use and care of PPE

Employees are responsible for:

Inspecting all PPE prior to its use.

Wearing PPE upon the direction of their immediate supervisor.

Participating in mandatory training.

Notifying their supervisor when new PPE is necessary.

Page 25: Final Report For Summer Training - Naif AlJuhani

19

3.3 The.Training.Timeline

Fig(22): The training timeline

Page 26: Final Report For Summer Training - Naif AlJuhani

20

4 ASSIGNED TASK AND PROJECT

4.1 Problem Definition

In this section of report, I will chose one of the unit inside power plant 3 which is unit

number 29. This unit from General Electric and it's model is 7001EA Fig(23). It created

in 1425 H. Table(3) will show some of specification of this unit.(3)

Fig(23): Gas turbine from GE ( 7001EA )

Table(3): Specification of Frame 7001EA

Frame 7001EA

Pin (bar) 1

Fuel Type Crude oil and Diesel

Pressure Ratio 12.6 : 1

Turbine Speed (rpm) 3600

Exhaust Temperature (K) 807.594

Output, Kw 85,580

Firing Temp K 1385.928

Compressor Stages 17

Turbine stages 3

Mass Flow (kg/s) 299

Page 27: Final Report For Summer Training - Naif AlJuhani

21

Now, I will find the temperature after compression:

𝑇2 = 𝑇1 (𝑃1

𝑃2)

𝑘−1𝑘

We assume T1 is equal to 300 K

𝑇2 = (300) (12.6)0.41.4

𝑇2 = 618.7 𝐾

We have all temperatures and pressure ratio. So we can draw Brayton cycle Fig(24)

Fig(24): Brayton cycle

We will find the brayton efficiency:

η = 1 −1

(𝑟)𝑘−1

𝑘

Where:

r: pressure ratio

Page 28: Final Report For Summer Training - Naif AlJuhani

22

η = 1 −1

(12.6)1.4−1

1.4

η = 51 %

The total mass flow rate enters to compressor is 299 kg/s. Where:

70% of mass flow rate is for cooling

30% of mass flow rate is for combustion chambers

So, the mass flow rate enter the combustion chambers is 89.7 kg/s.

Now, we will find work of compressor and work of turbine.

𝑊𝑐 = ( 𝑚𝑡 𝑐𝑝 𝑇1 ) − ( 𝑚𝑐.𝑐 𝑐𝑝 𝑇2 )

𝑊𝑐 = ( 299 × 1.005 × 300 ) − ( 89.7 × 1.005 × 618.7 )

𝑊𝑐 = 31.5 𝑀𝑊

𝑊𝑇 = ( 𝑚𝑐.𝑐 𝑐𝑝 𝑇2 ) − ( 𝑚𝑐.𝑐 𝑐𝑝 𝑇4 )

𝑊𝑇 = ( 89.7 × 1.9 × 1386 ) − ( 89.7 × 1.099 × 807.9 )

𝑊𝑇 = 156.6 𝑀𝑊

4.2 Literature Review and Data Collection

Gas turbines are one of the most widely-used power generating technologies. Gas

turbines are a type of internal combustion engine in which burning of an air-fuel

mixture produces hot gases that spin a turbine to produce power. It is the production of

hot gas during fuel combustion, not the fuel itself that the gives gas turbines the name.

Gas turbines can utilize a variety of fuels, including natural gas, fuel oils, and synthetic

fuels. Combustion occurs continuously in gas turbines, as opposed to reciprocating

engines, in which combustion occurs intermittently.

Page 29: Final Report For Summer Training - Naif AlJuhani

23

Nowadays, Gas turbines are becoming increasingly used as power generators for a wide

variety of applications around the world. Originally they were developed solely for

aircraft propulsion where their inherent low specific weight (i.e. mass/unit power) made

them essential for high speed flight. they have been developed to a high degree of

efficiency both thermodynamically and mechanically. The lower efficiency of the gas

turbine will effect to the performance of the gas turbine itself, the waste of the fuel

because of the unburned hydrocarbon and the impact to the environment, while the gas

turbine with a incomplete combustion. To increase the performance in term of

efficiency, the gas generator speed is controlled from 1500 rotary per second to 1250

rotary per second. In order to increase the efficiency of the gas turbine, the power output

must high, because it is proportional to the efficiency. Besides low fuel consumption is

also important to evaluate an efficient gas turbine because it is inversely proportional to

efficiency of the unit.(4)

Gas turbine history:

1791: First patent for a gas turbine (John Barber, United Kingdom)

1904: Unsuccessful gas turbine project by Franz Stolze in Berlin (first axial

compressor)

1906: GT by Armengaud Lemale in France (centrifugal compressor, no useful

power)

191: First GT featuring intermittent combustion (Holzwarth, 150 kW, constant

volume combustion)

1923: First exhaust-gas turbocharger to increase the power of diesel engines

1939: World’s first gas turbine for power generation (Brown Boveri Company),

Neuchâtel, Switzerland (velox burner, aerodynamics by Stodola).

1946: National Gas Turbine Establishment formed from Power Jets and the RAE

turbine division bring together Whittle and Hayne Constant's work In Beznau,

Switzerland the first commercial reheated/recuperated unit generating 27 MW was

commissioned.

1963: Pratt and Whitney introduce the GG4/FT4 which is the first commercial aero

derivative gas turbine.

2011: Mitsubishi Heavy Industries tests the first >60% efficiency gas turbine (the

M501J) at its Takasago works.(5)

Page 30: Final Report For Summer Training - Naif AlJuhani

24

4.3 Knowledge integration with course work

In this part, I will list the college courses which are related to the training in power plant

three.

Material Science (CHE210): To know the kinds of materials and its properties

and changes in them.

Machine Element (MENG310): In this course, we studied bearings types and

the static and the dynamic loads on shaft.

Heat Exchanger (MEP460): We studied how can exchange the heat in

industrial by using different types of heat exchanger such as: shell and tubes heat

exchanger.

Gas Turbine (MEP474): In this course, we took chapters contain information

about gas turbine and its applications.

Pumps and Hydraulics (MEP492): In this course, we studied pumps, pumps

types, pump components, pumps selections and pumps connections: series and

parallel.

4.4 Safety and environmental issues

The Saudi Electricity company is care about the safety standards clearly. They provide a

personal protective equipment to the employees in the field. Also, the company making

a lot of tests like the hearing test for the employees periodically, to make sure that they

are safe. If they Figure out that any one of the employees has a health problem because

of his working place they directly transfer him to another place to avoid the

complications.

Personal protective equipments

Helmet:

This helmet Fig(25) used to protect the head from injury may come from objects falling,

bad weather, electric shock and any other possibilities. It's made of plastic to be non-

electrically conductive.

Page 31: Final Report For Summer Training - Naif AlJuhani

25

Fig(25): The Helmet

Ear plugs and ear muffs:

It's used mostly in areas where the level of employee exposure to noise equal to 85

decibel or more over 8 hours. These ear plugs Fig(26) and ear muffs Fig(27) protect the

ear from injury or any other damages.

Fig(26): Ear plugs

Fig(27): Ear muffs

Page 32: Final Report For Summer Training - Naif AlJuhani

26

Overall:

The overall Fig(28) is a protective clothing that designed to protect the body from

injury, heat, flame, radiation and chemicals liquids or anything else.

Fig(28): Overall

Gloves:

The gloves Fig(29) provide a protection from electric shocks and extreme heat.

Fig(29): The gloves

Safety glasses:

Safety glasses Fig(29) used to protect the eye during the welding, grinding or any cut

operations. It's also protect the eye from the gases, harmful vapors and liquids.

Page 33: Final Report For Summer Training - Naif AlJuhani

27

Fig(29): Safety glasses

Safety shoes:

Safety shoes Fig(30) is important to protect feet inside the plant.

Fig(30): Safety shoes

4.5 Work Plan

Our supervisor Engineer Abdullah AlJunadi share the work plan in first day which is in

table(4).

Table(4): Work plan

Task Name Start date Department Assigned

Lecture 1st week OPT All Team Members

Working in Department 2nd week W/C All Team Members

Working in Department 3rd week W/C All Team Members

Working in Department 4th week MB All Team Members

Working in Department 5th week MB All Team Members

Working in Department 6th week MB All Team Members

Working in Department 7th week IC2-el3 All Team Members

Page 34: Final Report For Summer Training - Naif AlJuhani

28

4.6 Economic factor

In Fig(32), it shows applying new consumption for all categories of Service

according to Council of Ministers' decree No.95 Dated 17/03/1437:

Fig(32): Electricity cost in Saudi Arabia

4.7 Implementation

The Saudi electricity company and Jeddah power plant 3 have inaugurated the

kingdom's first independent project for the production of electrical power, Arab news

has reported. The Jeddah Power Plant 3, which was implemented at a total investment

of about 4 billion SR, adds 480 MW of new generating capacity boosting the kingdom's

electricity network. (6)

4.8 Impact analysis

As any industry field, Power Plant 3 use petroleum products which give off the

following emissions when they are burned as fuel:

Carbon dioxide (CO2)

Carbon monoxide (CO)

Sulfur dioxide (SO2)

Nitrogen oxides (NOX)

Nearly all of these byproducts have negative impacts on the environment and human

health:

Carbon dioxide is a greenhouse gas and a source of global warming.

SO2 causes acid rain, which is harmful to plants and to animals that live in water, and it

worsens or causes respiratory illnesses and heart diseases, particularly in children and

the elderly.

Page 35: Final Report For Summer Training - Naif AlJuhani

29

NOX contributes to ground-level ozone, which irritates and damages the lungs. (7)

4.9 Evaluation

In the end of summer training program in Power Plant 3, my supervisor Eng.

Abdullah AlJunedi thank me and my friends from King Abdul-Aziz University for

our discipline in attendance and out behavior. He gives us some advices and

recommendations.

Page 36: Final Report For Summer Training - Naif AlJuhani

30

5 CONCLUSIONS AND RECOMMENDATIONS

5.1 Achievement of expected learning outcomes

At the end of this training, I have a good idea about the field and the workplace after

graduation. The training gives me chance to see what I learned in university in the

real. In the training, I saw some applications such as: Gas turbine, Heat exchanger

and how it works. Also, we covered some safety section in the plant such as: Human

safety, fire protection and the unit protection which is the unit can protect itself by

sensor if there is a dangers case.

5.2 Recommendations to enhance future training in this company

- Respect the work time.

- Team work and how to deal with other staff.

- How to deal with safety equipment.

- The information about gas turbine and its main function it is how it is work

5.3 Recommendations to enhance future training of KAU engineering students

My recommendation for student from our university is a Providing a good impression of

the King Abdul-Aziz University.

Page 37: Final Report For Summer Training - Naif AlJuhani

31

REFERENCES:

1. https://www.se.com.sa/ar-sa/Lists/List8/Attachments/1/IPP-Program-Report.pdf

(Visited on 23/9/2016).

2. http://bv.com/Projects/Saudi-Electricity-Company (Visited on 23/9/2016).

3. https://powergen.gepower.com/FactSheet/7E.03-fact-sheet-2016.pdf (Visited on

23/9/2016).

4. http://www.wartsila.com/energy/learning-center/technical-comparisons/gas-turbine-

for-power-generation-introduction (Visited on 23/9/2016).

5. http://theinventors.org/library/inventors/blenginegasturbine.htm (Visited on

23/9/2016).

6. http://bv.com/Projects/Saudi-Electricity-Company (Visited on 23/9/2016).

7. http://environment-ecology.com/energy-and-environment/92-how-does-fuel-impact-

the-environment.html (Visited on 23/9/2016).

Page 38: Final Report For Summer Training - Naif AlJuhani

32

APPINDIX A