ASSEMBLY ,ERECTION AND TESTING OF GOLIATH CRANE

GROUP NO.1ASHWIN KATOCHKARAN KAULSHRIKANT LAMTURE

Page 2: FINAL OF GOLIATH CRANE

OUTLINE

IntroductionPurposeClients involvedSpecificationPartsFabricationFuture development

Page 3: FINAL OF GOLIATH CRANE

INTRODUCTION-GANTRY (GOLIATH ) CRANETrolley runs horizontally along rails on

girder.

Wheels run on the gantry rail, perpendicular to the trolley travel direction.

Variable sizes and can move very heavy loads.

Mostly used in shipyards or industrial installations

Page 4: FINAL OF GOLIATH CRANE

PURPOSE

Construct, maintain and assemble the ship.

Final fitting of parts.

Overall time of construction will reduce.

Quick and efficient transporter of the parts from Module Shop.

Page 5: FINAL OF GOLIATH CRANE

CLIENTS INVOLVEDContract of the Crane Awarded to: M/S McNally

Bharat, India.Designer of Crane : M/S KONE,

Germany.Crane Auxiliary to be handled by: M/S Royal

Haskoning, Netherlands.Erection of crane : M/S Fagiole,

U.K.Quality Inspection and Control : M/S IRS

(Indian Register of Ship), India.Chief Consultant : M/S H.M.B.

U.K.

Page 6: FINAL OF GOLIATH CRANE

SPECIFICATION

SPAN-138 metersCRANE CAPACITY-300 TONHEIGHT OF LIFT-50 meters(Above Rails) - 5 meters (Below Rail

Level)POWER SUPPLY -3phase 3.3 kv,50hzTRAVELLING SPEED – 0-40m/min

depending on load.

Page 7: FINAL OF GOLIATH CRANE

SPAN

Page 8: FINAL OF GOLIATH CRANE

MAJOR PARTS

GIRDERLEGSUPPER TROLLEYLOWER TROELLYSERVICE CRANEBOGI BALANCERWHEELS

Page 9: FINAL OF GOLIATH CRANE

DRAWING

Page 10: FINAL OF GOLIATH CRANE

GIRDER

Trapezoidal and hollow. Reduce bending force. Save material and cost

Page 11: FINAL OF GOLIATH CRANE

GIRDER(CONTD.)

Extend over the whole width .

Section should bear maximum reaction and moment.

Full length and short diaphragms should be inserted .

To transmit the load to the web plates.

To limit the maximum stress in the trolley rail.

Page 12: FINAL OF GOLIATH CRANE

TYPES OF DIAPHRAGMS

Page 13: FINAL OF GOLIATH CRANE

LEGS

Page 14: FINAL OF GOLIATH CRANE

LEGS(CONTD.)

Moving and supporting the crane.

Hinged leg and fixed leg.

Fixed leg consists of Lift for operator

Provides rigidity .

Hinged leg maintains flexibility.

Page 15: FINAL OF GOLIATH CRANE

UPPER TROELLY AND LOWER TROELLY

UPPER TROLLEY: Two rope drums of 100 ton capacity

each. Operator’s cabin.

LOWER TROLLEY: Main hoist and auxiliary hoist. Capacity of 150 and 50 ton

respectively.

Page 16: FINAL OF GOLIATH CRANE

SERVICE CRANE: Located on girder at hinged legs Used for maintenenance

BOGI BALANCER: Placed beneath the legs. Primary and secondary .

WHEELS: Placed below the bogie balancer Motion of crane on the rails.

Page 17: FINAL OF GOLIATH CRANE

PARTS-BOGIE BALANCER

Page 18: FINAL OF GOLIATH CRANE

FABRICATION MATERIAL :S355j2G3

EN 10025(European Standard).

S: Means that this is a structural steel.

355: Minimum yield strength (min Re=355 N/mm sq.)

J2: Min. Charpy test value= 27J at -20 deg.C

G3: Supply condition. Normalized or normalized rolled.

Page 19: FINAL OF GOLIATH CRANE

FABRICATION(CONTD.)SAND BLASTING : 75-85 micron layer is formed . Checked for defects such as pinholes

etc.

WELDING : Flux core welding Arc welding

Page 20: FINAL OF GOLIATH CRANE

FABRICATION(CONTD.)

MECHANICAL CONNECTIONS: High tensile bolts .

Fastening shall be applied.

Fastening should be corrosion resistance, surface finish and metric size.

Page 21: FINAL OF GOLIATH CRANE

FUTURE DEVELOPMENT

Analysis on PRO-E and ANsys.

Load estimation on girder and hook.

Assembly of fabricated parts of Crane.

Erection of crane using foundation,hyraulic jack, skid ways etc.

Testing of crane.

Page 22: FINAL OF GOLIATH CRANE

REFERENCES

TENDER DOCUMENT AT MAZAGAON DOCK LIMITED

FABRICATION SHEETS AND DRAWINGS GIVEN BY PROJECT IN-CHARGE AT M.D.L.