fieltd operation schedule for preventive actions_for 317 255 in ubs_qatar and 317 109 in...
TRANSCRIPT
-
8/10/2019 Fieltd Operation Schedule for Preventive Actions_for 317 255 in UBS_QATAR and 317 109 in Jubail_KSA_R11
1/2
-
8/10/2019 Fieltd Operation Schedule for Preventive Actions_for 317 255 in UBS_QATAR and 317 109 in Jubail_KSA_R11
2/2
ID Task Name Duration Start Finish
51 Induced Over-Voltage Withstand Test and Partial Discharge Measurement 1 day Thu 11/13/14 Thu 11/13/14
52 Draining the oil partial ly in the main tank for disconnection of the ter tiary bushings, dr ianing the oil inLV Oil Cable Boxes, Re-storing LV links, De-gassing of SF6 in HV GIS, Re-storing HV links, Vacuuumfor 24 hours
1 day Fri 11/14/14 Fri 11/14/14
53 Filling the oil into the transformer partially and into LV Cable Boxes 1 day Sat 11/15/14 Sat 11/15/14
54 Filling SF6 gas into HV GIS 0 days Sat 11/15/14 Sat 11/15/14
55 Treating the oil in the main transformer 1 day Sun 11/16/14 Sun 11/16/14
56 Resting time for the oil in the transformer and preparations for energising 1 day Mon 11/17/14 Mon 11/17/14
57 Pre - Commissioning of the accessories on transformer 0 days Mon 11/17/14 Mon 11/17/14 11/17
F S SSep 27, '14 Nov 15, '14
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Page 2
Project: Project1Date: Wed 10/8/14