field trip llanos 34 - investis...

22
Field Trip Llanos 34 February 2017

Upload: others

Post on 04-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Field Trip – Llanos 34

    February 2017

  • 2

    SPEED our Philosophy

    AFETY

    ROSPERITY

    MPLOYEES

    NVIRONMENTAL

    VELOPMENT

    HSE - Introduction

  • LAYOUT CAMPO TIGANA

    3

    CONVENCIONES1. Parqueadero.2. Cargadero3. Tanques4. Calderas.5. Manifold.6. Plataforma Pozos

    7. Generación.8. CCM .9. Variadores10. Shelter de Química.11. Laboratorio.12. Campamento13. Unidad médica.

    1

    6

    5

    4

    3

    9

    7

    8

    7

    234

    12

    11

    1013

  • 4

    LAYOUT CAMPO TIGANA SUR

    CONVENCIONES1. Parqueadero.2. Cargadero3. Tanques4. Calderas.5. Manifold.6. Filtración.7. Inyección

    8. Plataforma Pozos.9. Generación.10. CCM11. Variadores.12. Química.13. Tk Prueba.14 Tratadores.15 Decantadores.

    1

    2

    3

    4

    4

    55

    56

    113

    10

    9

    8

    7

    9

    12

    13

    14

    15

  • 5

    Hazardous Areas

    HIGH

    PRESSURE

    HIGH

    TEMPERATURE

    NO MOBILE

    PHONES

    AUTHORIZED

    PERSONNEL

    ONLY

    HSE - Introduction

  • 6

    Keep calm.

    Follow the brigade instructions.

    If the alarm sounds continuously, walk to the muster point.

    Go back to your activities when the Area Authority allows. Remember to reactivate your PTW and Risk analysis.

    ALARMS: One whistle: Emergency Continuous sound: Evacuation

    Emergencies HSE - Introduction

  • 7

    Safety guide

    Mobile phones are not allowed in operational

    areas.

    Use your PPE (hat, glasses, safety boots, long

    sleeve).

    Smoking only in authorized areas.

    Complete a JSA before you begin your work.

    Remember: You can stop the work if an unsafe act or condition could endanger people, environment or operation.

    HSE - Introduction

  • 8

    HSE - IntroductionProactive Observation Program

    Observe Own Report

    Safe or unsafe acts or conditions

    General recommendations

    Congratulations !!!

  • 9

    HS Performance 2016

    ROAD SAFETY

    • Health activities to prevent illness.

    • Infirmary, medical attention, MEDEVAC

    • Nutrition, gym, recreational activities

    HEALTH / WELLNESS

    EMERGENCY PLAN

    Trained brigades, drills and permanent

    monitoring

    SIMOP – HAZARD/ RISK

    IDENTIFICATION AND CONTROL

    Road Safety campaigns and road control,

    involving all contractors and GPK

    passengers.

    166 Drills

    511Trainings

    170Safety

    Inspections

    2500+ JSA 53 POP

    TRIR: 1.63 LTIR: 0.82

    Risk control (Meetings, PTW, JSA, etc.) to

    prevent incidents

  • 10

  • Tigana Field

    1 Km

    Jacana FieldAruco Field

    Max Field (FW Block)

    Tarotaro Field

    Tua Field

    Structural Map Top Fm. Guadalupe

    Tilo Field Chachalaca Field

    S8

    S3 S5

    S4

    S6

    S2

    S7

    S1

    Coquito

    Jacana Sur

    Curucucu

    Jacamar

    Chiricoca CaicaPellar

    Vaco

    Carpintero

    Sinsonte

    Llanos 34

    * Information included in the map above is subject to change and may also be subject to partner or regulatory approval

  • Colombia: 75% of 2017 CAPEX Allocated to Llanos 34 Block

    1 Km

    Oil Fields

    Exploration Prospects

    Guaco Prospect

    Sinsonte Prospect

    Curucucu Prospect

    Jacamar Prospect

    12

    1Q

    1Q2Q

    2Q

    3Q

    3Q

    4Q

    1Q

    OBJETIVES IN 2017:

    1. To further define

    the potential of

    Tigana/Jacana

    complex (12-16

    development /

    appraisal wells)

    during 1Q, 3Q

    and 4Q

    2. Exploration

    drilling of new

    prospects in 2Q

    * Information included in the map above is subject to change and may also be subject to partner or regulatory approval

  • 13

    Execution Colombia

    • Increased reserves vs. year 2015

    • 4 new exploratory prospects identified in Llanos 34

    • Exploratory well Chiricoca in Mirador formation showed presence of

    hydrocarbons through electrical logs. Currently this well is on completion

    • Successful drilling campaign with 6 operated wells drilled, 4 in Jacana field

    (100% successful)

    • Average Production increased 18% compared to avg. 2015

    • Exit rate 14% greater than 31/12/2015

    • La Cuerva: closed in January, reopened in July 2016 with positive cash

    flows

    • Significant costs reductions: OPEX / bbl in Llanos 34 dropped 24% (4.1

    $/bbl):

    • Reduction related with main Llanos 34 fields electricity generated by

    gas coming from Llanos 32 block (GPK @10% WI in this block)

    • WO average cost decreased 18% compared with 2015

    • Drilling costs declined 21% vs. 2015

    • CAPEX 2016: $22 MM (28% lower than 2015)

    • Tigana own facility finished. Commissioning for January 2017.

    • Jacana facilities expansion

    • Llanos 62 commitments transferred to Llanos 34 (block with better

    perspectives)

    • 22 Km2 of retained area in Llanos 34 Block for exploratory prospects

    • Improvements in commercial contracts compared with 2015 conditions

    • Perfect track record with communities (No downtime due to community

    blockades)

    • Zero non productive days between ending Short Term Test and obtaining

    permit to produce the well.

    • 2 incidents with loss time vs. 3 in 2015

    CAPEX $60-70MM

    2017 WORK PROGRAM

    Base Case @$45-50/bbl

    • 16 development wells (operated)

    • 3 Exploratory well

    • Civil works & facilities

    • Average production 2017: 21-22 kbopd

    2016 REVIEW

    2016 PRODUCTION

    Exit Production

    38,2 kboe/d

    Avg. Production

    33,4 kboe/d

  • Bloque Llanos 34 Tigana & Jacana Complex

  • Max

    • Multiple Water Oil Contacts defined by history production/pressure matching in Tigana Field, using

    lineaments with possible differences between petrophysical and/or fluid properties.

    Tigana & Jacana Complex – Structural map Guadalupe fm

    Tigana

    SouthWest

    Tigana

    South

    Tigana

    Tigana

    North

    RESERVOIR COMPARTMENTS AND WOC

    Jacana

    Jacana 6

    Jacana

    Upside

    TIGANA FIELD

    • Discovered in December 2013

    • 10 Producing Wells

    • One disposal well

    • 14.1 – 29° API

    • Main Reservoirs Mirador &

    Guadalupe

    JACANA FIELD

    • Discovered in August 2015

    • 6 Producing Wells

    • 15.1 – 16.1° API

    • Main Reservoirs Mirador &

    Guadalupe

    Tigana

    Upside

    * Information included in the map above is subject to change and may also be subject to partner or regulatory approval

  • 6.6 5.6 5.4

    4.3 3.4

    0

    2

    4

    6

    8

    10

    12

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    2012 2013 2014 2015 2016

    Num

    erbe

    rs W

    ells

    $MM

    Average cost per well (D&C)

    Wells drilled

    34.6

    17.2 18.3 14.8 10.5

    -

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    40.0

    2012 2013 2014 2015 2016

    Da

    ys

    16

    Colombia Operations Drilling Performance

    12.0

    00 m

    6.8

    00 m

    29.6

    00 m

    REENGINEERING RESULTS

    COST PER WELL (D&C)

    0.00

    0.10

    0.20

    0.30

    0.40

    0.50

    0.60

    2015 2016

    $M

    M

    USD PER METER DRILLED. 2-3 STEP CSG

    1,649

    1,2681,198

    872723

    0

    500

    1,000

    1,500

    2,000

    2012 2013 2014 2015 2016

    $/M

    COST PER WO/WS

    DRILLING DAYS PER WELL

  • 17

    Llanos 34 Production History

    0

    5,000,000

    10,000,000

    15,000,000

    20,000,000

    25,000,000

    30,000,000

    35,000,000

    0

    6000

    12000

    18000

    24000

    30000

    36000

    42000

    01/05/2012 01/05/2013 01/05/2014 01/05/2015 01/05/2016

    Cu

    mm

    ula

    tive

    Pro

    du

    cti

    on

    (b

    ls)

    Dail

    y P

    rod

    ucti

    on

    (b

    op

    d)

    Date

    Production History Llanos 34 Block

    Oil

    Cummulative Production

  • 18

    Llanos 34 Block - Tua Operations, Facilities and Infrastructure

    PRODUCTION HISTORY

    SUMMARY

    Lifting method Electrical Submersible Pump

    Facilities on the field Only a production facility

    Platforms 3 Platforms

    Flowlines Production flows to Tua Facility through flowlines

    Discovery Date June/2012

    # Producing Wells 10

    TUA FACILITY

    Separation capacity 40.000 bbl/d

    Storage capacity 13.000 bbl (1.6 days of current production)

    Management Gas 600.000 scfpd

    Loading bays 4 bays

    Water managment Injected. 18.000 bbl/d at 1,700 psi in Tua-10 Well

    Power generation 2.4 Mw by produced gas and Compressed Natural Gas

  • 19

    Llanos 34 Block - Tigana Operations, Facilities and Infrastructure

    TIGANA FACILITY (Rented)

    Separation capacity 14.000 bbl/d

    Storage capacity 12.000 bbl (0.7 days of current production)

    Loading bays 4 bays

    Water managmentInjected in Tigana Sur 3 Well; 10000 bwpd@

    2000 Psi

    Power generation 1.8 Mw by Compressed Natural Gas

    TIGANA SUR FACILITY (Owned)

    Separation capacity 20.000 bbl/d

    Storage capacity 19.000 bbl (1.1 days of current production)

    Loading bays 4 bays

    Water managmentInjected in Tigana Sur 3 Well; 10.000 bwpd @

    2000 psi

    Power generation 0.8 Mw by Compressed Natural Gas

    PRODUCTION HISTORY

    SUMMARY

    Lifting method Electrical Submersible Pump

    Facilities on the field 2 production facilities (One rented, one owned)

    Platforms 3 platforms

    FlowlinesProduction flows to Tigana Sur Facility through

    flowlines

    Discovery Date December/2013

    # Producing Wells 10

    Tigana FacilityTigana South

    Facility

  • 20

    Llanos 34 Block - Jacana Facilities and Infrastructure

    PRODUCTION HISTORY

    JACANA FACILITY (UNDER CONSTRUCTION)

    Separation capacity 20.000 bbl/d

    Storage capacity 13.500 bbl (1.1 days of current production)

    Loading bays 4 bays

    Water managment To be transported to Tigana or Tarotaro

    Power generation 1.7 Mw by compressed natural gas

    SUMMARY

    Lifting method Electrical Submersible Pump

    Facilities on the field Only a production facility

    Platforms 2 Platforms

    Discovery Date August/2015

    # Producing Wells 6

    Loading trucks

    Process & Storage Tanks

  • Disclaimer

    The material that follows comprises information about GeoPark Limited (“GeoPark” or the “Company”) and its

    subsidiaries, as of the date of the presentation. It has been prepared solely for informational purposes and should not

    be treated as giving legal, tax, investment or other advice to potential investors. The information presented or

    contained herein is in summary form and does not purport to be complete.

    No representations or warranties, express or implied, are made as to, and no reliance should be placed on, the

    accuracy, fairness, or completeness of this information. Neither GeoPark nor any of its affiliates, advisers or

    representatives accepts any responsibility whatsoever for any loss or damage arising from any information presented

    or contained in this presentation. The information presented or contained in this presentation is current as of the date

    hereof and is subject to change without notice, and its accuracy is not guaranteed. Neither GeoPark nor any of its

    affiliates, advisers or representatives makes any undertaking to update any such information subsequent to the date

    hereof.

    This presentation contains forward-looking statements, which are based upon GeoPark and/or its management’s

    current expectations and projections about future events. When used in this presentation, the words “believe,”

    “anticipate,” “intend,” “estimate,” “expect,” “should,” “may” and similar expressions, or the negative of such words and

    expressions, are intended to identify forward-looking statements, although not all forward-looking statements contain

    such words or expressions. Additionally, all information, other than historical facts included in this presentation,

    regarding strategy, future operations, drilling plans, estimated reserves, estimated resources, future production,

    estimated capital expenditures, projected costs, the potential of drilling prospects and other plans and objectives of

    management is forward-looking information. Such statements and information are subject to a number of risks,

    uncertainties and assumptions. Forward-looking statements are not guarantees of future performance and actual

    results may differ materially from those anticipated due to many factors, including oil and natural gas prices, industry

    conditions, drilling results, uncertainties in estimating reserves and resources, availability and cost of drilling rigs,

    production equipment, supplies, personnel and oil field services, availability of capital resources and other factors. As

    for forward-looking statements that relate to future financial results and other projections, actual results may be

    different due to the inherent uncertainty of estimates, forecasts and projections. Because of these uncertainties,

    potential investors should not rely on these forward-looking statements. Neither GeoPark nor any of its affiliates,

    directors, officers, agents or employees, nor any of the shareholders or under shall be liable, in any event, before any

    third party (including investors) for any investment or business decision made or action taken in reliance on the

    information and statements contained in this presentation or for any consequential, special or similar damages.

    Statements related to resources are deemed forward-looking statements as they involve the implied assessment,

    based on certain estimates and assumptions, that the resources will be discovered and can be profitably produced in

    the future. Specifically, forward-looking information contained herein regarding "resources" may include: estimated

    volumes and value of the Company's oil and gas resources and the ability to finance future development; and, the

    conversion of a portion of resources into reserves.

    The information included in this presentation regarding estimated quantities of proved reserves in Chile, Colombia,

    Brazil, and Peru as of December 31, 2015; are derived, in part, from the reports prepared by DeGolyer and

    MacNaughton, or D&M, independent reserves engineers. Certified reserves refers to net reserves independently

    evaluated by the petroleum consulting firm, D&M. Certain reserves data, such as those based on the D&M report,

    were prepared under SEC standards, and certain other data were prepared under Petroleum Resources Management

    System (PRMS) standards.

    The information included in this presentation regarding estimated exploration resources in Chile, Colombia, Brazil, and

    Peru as of December 31, 2015; are derived, in part, from the reports prepared by Gaffney, Cline & Associates, or

    GCA. The accuracy of any resource estimate is a function of the quality of the available data and of engineering and

    geological interpretation. Results of drilling, testing and production that postdate the preparation of the estimates may

    justify revisions, some or all of which may be material. Accordingly, resource estimates are often different from the

    quantities of oil and gas that are ultimately recovered, and the timing and cost of those volumes that are recovered

    may vary from that assumed.

    Prospective Resources are those quantities of petroleum that are estimated, as of a given date, to be potentially

    recoverable from undiscovered accumulations by application of future development projects. Prospective Resources

    have both an associated “chance of discovery” and a “chance of development” (per PRMS). Prospective Resources

    are further subdivided in accordance with the level of certainty associated with recoverable estimates, assuming their

    discovery and development, and may be sub-classified based on project maturity. There is no certainty that any

    portion of the Prospective Resources will be discovered. If discovered, there is no certainty that it will be commercially

    viable to produce any portion of the resources. Prospective Resource volumes are presented as unrisked. The risk or

    chance of finding a minimum hydrocarbon volume that can flow to surface is presented as Geological Chance of

    Success (GCoS).

    Certain data in this presentation was obtained from various external sources, and neither GeoPark nor its affiliates,

    advisers or representatives has verified such data with independent sources. Accordingly, neither GeoPark nor any of

    its affiliates, advisers or representatives makes any representations as to the accuracy or completeness of that data,

    and such data involves risks and uncertainties and is subject to change based on various factors.

    This presentation contains a discussion of Adjusted EBITDA, which is not an IFRS measure. We define Adjusted

    EBITDA as profit for the period before net finance cost, income tax, depreciation, amortization and certain non-cash

    items such as impairments and write-offs of unsuccessful exploration and evaluation assets, accrual of stock options

    and stock awards and bargain purchase gain on acquisition of subsidiaries. Adjusted EBITDA is included in this

    presentation because it is a measure of our operating performance and our management believes that Adjusted

    EBITDA is useful to investors because it is frequently used by securities analysts, investors and other interested

    parties in their evaluation of the operating performance of companies in industries similar to ours. Adjusted EBITDA

    should not be considered a substitute for financial information presented or prepared in accordance with IFRS.

    Adjusted EBITDA, as determined and measured by us, should also not be compared to similarly titled measures

    reported by other companies.

    Rounding amounts and percentages: Certain amounts and percentages included in this document have been rounded

    for ease of presentation. Percentage figures included in this document have not in all cases been calculated on the

    basis of such rounded figures but on the basis of such amounts prior to rounding. For this reason, certain percentage

    amounts in this document may vary from those obtained by performing the same calculations using the figures in the

    financial statements. In addition, certain other amounts that appear in this document may not sum due to rounding.

    21