fi-mm-residual_cost_of_import_planned_delivery_charges.pdf
TRANSCRIPT
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
1/16
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
2/16
CONFIDENTIALresidualcost.doc/001 Page2 Version001
Document Number
Document Number Document Date
residual cost.doc/001 17 November, 2007
Version History
Version Number Version Date Summary of Changes Ref: Minutes of Review
01 / 00117 November,2007
NA NA
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
3/16
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
4/16
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
5/16
CONFIDENTIALresidualcost.doc/001 Page5 Version001
1. Legend
ICONS EXPLANATION
Create (F5)
Change (F6)
Display (F7)
Copy (Shift+F9)
Delimit (Shift+F1)
Delete (Shift+F2)
Overview (Shift+F8)
Cancel (F12)
Save (Ctrl+S)
Back (F3)
Exit (Shift+F3)
Cancel screen (F12)
EXAMPLES EXPLANATION
The field is mandatory - it must be filled in order to proceed
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
6/16
CONFIDENTIALresidualcost.doc/001 Page6 Version001
2. Transaction Access Path
2.1. Required User Input
Access the Transaction screen.
2.2. SAP Screen Snap
2.3. Description
To Post a Logistics Invoice, you can access the transaction via following path:
Logistics --> Materials Management --> Logistics Invoice Verif ication --> Document Entry --> EnterInvoice (MIRO)
Alternatively, you can directly access the transaction by typing the transaction code in the command field:MIRO
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
7/16
CONFIDENTIALresidualcost.doc/001 Page7 Version001
3. Maintain Currency
3.1. Required User Input
Go to Header Tab - Basic Data &Enter "pkr" then press Enter.
3.2. SAP Screen Snap
3.3. Description
The currency field is automatically copied from the Allocation Document. However, if you want to post an
invoice to a separate / different currency then you should enter the currency code in the Header Databefore taking the Purchase Order reference.
Since Planned delivery cost for an import related PO is generally posted in local currency (PKR), so makesure that this currency is selected here.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
8/16
CONFIDENTIALresidualcost.doc/001 Page8 Version001
4. Screen Variant - Planned Delivery Cost
4.1. Required User Input
For Posting Planned delivery cost, Select 'Planned delivery cost' as shown.
4.2. SAP Screen Snap
4.3. Description
Make sure that the correct screen variant has been selected.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
9/16
CONFIDENTIALresidualcost.doc/001 Page9 Version001
5. Al locat ion to PO
5.1. Required User Input
Select Allocation category: Purchase Order/ Scheduling agreement &Enter the purchase Order number.
5.2. SAP Screen Snap
5.3. Description
Allocation of Invoice to Purchase Order copies all the condition items for Planned delivery cost to Invoice.
You have to select the one for which you want to make payments.
Since Goods Receipt has been posted for this PO, all delivery cost has been charged to the PO materialsaccording to Provisions kept in PO. Thats'why here you can see the posted amounts and relatedquantities.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
10/16
CONFIDENTIALresidualcost.doc/001 Page10 Version001
6. Selection of Delivery Cost
6.1. Required User Input
Select the item.
6.2. SAP Screen Snap
6.3. Description
You have to select the delivery cost for which you want to post invoice.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
11/16
CONFIDENTIALresidualcost.doc/001 Page11 Version001
7. Amount Change
7.1. Required User Input
Change the Item amount as per actual Invoice.
7.2. SAP Screen Snap
7.3. Description
It may not necessary that the Invoice for this delivery cost is exactly the same as the provisioned amount.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
12/16
CONFIDENTIALresidualcost.doc/001 Page12 Version001
8. Calculate Tax
8.1. Required User Input
Go to Header Tab - Basic Data &Set 'Calculate Tax' Indicator.
8.2. SAP Screen Snap
8.3. Description
To calculate the tax automatically make this selection.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
13/16
CONFIDENTIALresidualcost.doc/001 Page13 Version001
9. Invoice Amount
9.1. Required User Input
Enter "18400" then press Enter.
9.2. SAP Screen Snap
9.3. Description
Total amount inclusive of all taxes is maintained here.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
14/16
CONFIDENTIALresidualcost.doc/001 Page14 Version001
10. Invoicing Party
10.1. Required User Input
Click where shown.
10.2. SAP Screen Snap
10.3. Description
By default the PO vendor is copied as the invoice party here. But for the imports the delivery charges canbe paid to third parties. Hence, the invoicing party needs to be changed here.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
15/16
CONFIDENTIALresidualcost.doc/001 Page15 Version001
11. Simulate Invoice
11.1. Required User Input
Click on 'Simulate' button.analyze accounting entries.
11.2. SAP Screen Snap
11.3. Description
Note that the difference between the provision and actual is posted to a separate Price Difference
Account. This is because there is no sufficient stock coverage for this variance.
After analyzing the accounting entries, you can post the document.
-
7/27/2019 FI-MM-Residual_cost_of_import_planned_delivery_charges.pdf
16/16
CONFIDENTIALresidualcost.doc/001 Page16 Version001
12. Post Invoice
12.1. Required User Input
Click on 'Post' button.Note the Invoice Document Number displayed on message line.
12.2. SAP Screen Snap
12.3. Description
After Analysis, post the document.