feasibility study of concrete and brick waste recycling program using system dynamics modelling...
DESCRIPTION
SCIE (www.scie.org.au) JournalsTRANSCRIPT
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
25
Feasibility Study of Concrete and Brick Waste Recycling
Program using System Dynamics Modelling Approach
Dat Tien Doan1*
Thanwadee Chinda2
1. Master Student, Sirindhorn International Institute of Technology, Thammasat University, Thailand;
2. Assistant Professor, Sirindhorn International Institute of Technology, Thammasat University,
Thailand;
*Email address of corresponding author: [email protected]
Abstract
In Thailand, many infrastructures have been built, such as building, roads etc. to meet the needs of the
rapid development of economy. This, in turn, leads to the higher construction and demolition waste,
especially concrete and brick waste, with the lower landfill spaces. Recycling program is therefore
needed to properly manage the waste, and avoid the future environmental problems. This paper
investigates the feasibility of the concrete and brick waste recycling program in Bangkok, Thailand,
using a system dynamics modeling technique. The model consists of two main elements, namely the
total costs and the total benefits. Five factors, including the truck costs, the fuel costs to recycling
places, the labor costs, the training costs, and the machine costs, are under the total costs element.
While the total benefits element consists of four factors, namely the savings in leveling costs, the
savings in virgin materials, the savings in landfill charge, and the savings in fuel costs to landfills. The
simulation results show that it takes 21 years for the recycling program to worth the investment. The
government and construction companies could then use the study results as a guideline to plan for their
recycling programs.
Keywords: concrete and brick waste, recycling program, system dynamics modeling, Thailand
1. Introduction
In Thailand, the construction area has increased year by year, leading to the raising in the amount of
construction and demolition (C&D) waste in which concrete and brick waste made up the majority,
around 91.2 % (Sorpimai, 2008). However, almost such waste ends up at landfills whereas it can be
recycled or reused for different purposes, such as for levelling or for replacing sand and gravel in
aggregate. Plus, there are only two main landfills, Khampangsan and Phanomsarakham, to handle the
total waste originating in Bangkok, accounting for one fourth of the amount of waste in this country.
(Chinda et al., 2012a). This tendency may, in turn, lead to the shortage of landfills and negative impacts
on the environment in the near future.
Although C&D waste recycling has been researched for a long time, at least from 2001 according to
Yuan and Shen (2010), especially in developed countries. However, until now it has still received
inconsiderable attention from construction companies in Thailand in general and in Bangkok in
particular. And those published papers did not concentrate on economic factor, one of the essential
criteria that assists such companies consider whether they should investigate in recycling program or
not (Chinda et al., 2012b).
In this paper, the feasibility of the concrete and brick waste recycling program in Bangkok is
investigated by using a system dynamics modeling (SD) technique to help construction companies have
a better view in this activity. They could then use the study results as a guideline to plan for their
recycling programs. By doing this, landfills may receive less waste than they used to be and the
environmental pollution can be solved.
2. The development of concrete and brick waste recycling program model
SD, introduced by Forrester (1958), is an efficiency tool that can provide a deep insight of the behavior
of a complex system. It can be used to build the model in the real world that describe the
interrelationship between variables and create different scenarios that can be happened. Users‘
decision-making progress will be better because they can use this tool to predict the future situations.
Therefore, it has been used widely in many studies with various domains, especially in C&D waste in
recent years. Hao et al. (2007, 2008 and 2010) adopted SD method for C&D waste management,
evaluating the alternative of type in C&D waste recycling center was carried out by Zhao et al. (2011)
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
26
and Karavezyris et al. (2002) used SD method to forecast municipal solid waste.
The model in this paper consists of two main elements, namely the total costs and the total benefits.
Five factors, including the truck costs, the fuel costs to recycling places, the labor costs, the training
costs, and the machine costs, are under the total costs element. While the total benefits element consists
of four factors, namely the savings in leveling costs, the savings in virgin materials, the savings in
landfill charge, and the savings in fuel costs to landfills.
2.1 Total costs element
Figure 1 shows the total costs element that is the sum of five different factors; training costs, labor
costs, fuel costs to recycling places, truck costs, and machine costs, see (1).
Total costs = Training_Costs_submodel.Training_Costs + Labor_Costs_submodel.Labor_Costs +
Fuel_Costs_to_construction_sites_submodel.Fuel_Costs + Truck_Costs_submodel.Truck_Costs +
Machine_Costs_submodel.Machine_Costs (1)
Figure 1. The total costs element
2.1.1 Training costs factor
To have a higher productivity in concrete and brick waste sorting activity, new labors who are recruited
for this sector will be trained for five days before working. One way to save a large amount of money
for this is that trained workers in the first year will train others in the following years. In other word,
the costs for training (as shown in Figure 2) are only paid in the first year, see (2).
Training costs = IF Year = 1 THEN New_Sorting_Labors*Cost_per_Labor*(1+Inflation_Rate) ELSE 0
(2)
Figure 2. Training costs factor
2.1.2 Labor costs factor
In this part, the costs are based on the number of labors working in recycling sector, see (3). And the
total amount of waste that is sorted (as shown in Figure 3) will help to define the number of workers,
see (4). In each year, the total sorted waste is computed by the working productivity of new recruited
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
27
labors and current labors.
Labor costs = IF Year = 0 THEN 0 ELSE (Final_Total_New_Sorting_Labors +
Final_Total_Regular_Labors)*Number_of_Working_Days*Wage_per_Labors*(1 +
Inflation_Rate)^Year (3)
Final sorted waste = IF Year = 0 THEN 0 ELSE IF Year=1 THEN
Sorting_Productivity*(Final_Total_New_Sorting_Labors*(Number_of_Working_Days –
Number_of_Training_Days) + Final_Total_Regular_Labors* Number_of_Working_Days) ELSE
Sorting_Productivity*( (Final_Total_Regular_Labors + Final_Total_New_Sorting_Labors -
Final_Training_Group - Final_New_Sorting_Labors)* Number_of_Working_Days +
(Final_Training_Group+Final_New_Sorting_Labors)*(Number_of_Working_Days –
Number_of_Training_Days)) (4)
Figure 3. Labor costs factor
2.1.3 Truck costs factor
In order to transport the concrete and brick waste to landfills or recycling places, construction
companies need to buy or hire trucks. In this paper, trucks will use natural gas vehicle (NGV) instead
of diesel to save the cost for fuel, according to Jaroonrat Engineering company. The truck costs are sum
of buying costs and renting costs, see (5). The costs for buying new trucks are calculated based on nine
factors; including NGV installation cost, cost for new trucks, big maintenance cost, selling trucks
savings, regular maintenance cost, tire cost, insurance cost, driver cost, and route cost, see (6). While
six elements are used to define the costs for rent; regular maintenance cost, tire cost, insurance cost,
driver cost, rental trucks cost and route cost, see (7).
Truck costs = Buying_Costs + Renting_Costs (5)
Buying costs = NGV_Installation_Cost + Cost_for__New_Trucks + Big_Maintenance_Cost -
Selling_Trucks_Saving + (Regular_Maintenance_Cost + Tire_Cost + Insurance_Cost + Driver_Cost +
Route_Cost)*Bought_Trucks (6)
Renting costs = (Regular_Maintenance_Cost + Route_Cost + Tire_Cost + Insurance_Cost +
Driver_Cost + Rental_Trucks_Cost)*Number_of_Rented_Trucks (7)
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
28
2.1.4 Fuel costs factor
Figure 5 shows the way to determine the fuel costs. They are the product of the fuel cost per kilometer
and the distance from construction sites to recycling places, see (8).
Fuel costs = Distance*Fuel_Costs_per_km (8)
Figure 4. Truck costs factor
Figure 5. Fuel costs factor
Figure 6. Machine costs factor
2.1.5 Machine costs factor
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
29
Machines will be bought to crush brick and concrete. The number of machines depends on the total
waste that labor sorted (as shown in Figure 6). And its costs are shown on (9).
Machine costs = Number_of_Bought_Machines*Cost_per_Machine*(1+Inflation_rate)^Year (9)
2.2 Total benefits element
Figure 7 shows the total benefits element that is the sum of four factors; including savings in fuel costs
to landfill, savings in landfill charge, savings in levelling costs, and savings in virgin materials, see
(10).
Total benefits = Savings_in_Fuel_Costs_to_Landfill_submodel.Fuel_Costs
Savings_in_Landfill_Charge_submodel.Savings_in_Landfill_Charge
Savings_in_Leveling_Costs_submodel.Savings_in_leveling_cost
Savings_in_Virgin_Materials_submodel.Savings_in_virgin_materials (10)
Figure 7. The total benefits element
2.2.1 Savings in fuel costs to landfill factor
When the waste recycling program is applied by construction companies, fuel costs are saved (as
shown in Figure 8). That is because the average distance from construction sites to recycling places is
less than the distance from construction sites to landfills, see (11).
Savings in fuel costs to landfill = Distance*Fuel_Costs_per_km +
Number_of_Trucks*(Regular_Maintenance_Cost + Tire_Cost) (11)
Figure 8. Savings in fuel costs to landfill factor
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
30
Figure 9. Savings in landfill charge factor
2.2.2 Savings in landfill charge factor
A large amount of money can be saved from landfill charge because almost concrete and brick waste is
reused or recycled rather than being transported to landfills (as shown in Figure 9). (12) shows the way
to determine the savings.
Savings in landfill charge =
Fuel_Costs_submodel.Reused_and_Recycled_Waste*Landfill_Charge_per_ton*(1 +
the_Increasing_Percentage_of_Landfill_Charge)^Year_stock (12)
2.2.3 Savings in levelling costs factor
Concrete and brick waste can be reused directly to replace the role of sand or gravel for some activities
such as levelling roads or building (as shown in Figure 10). These savings are affected by the price of
material that is replaced by concrete and brick waste, see (13).
Savings in levelling costs = Reused_Waste*Sand_Price*(1 +
the_Increasing_Percentage_of_Sand_Price)^Year (13)
Figure 10. Savings in levelling costs factor
2.2.4 Savings in virgin materials factor
New aggregate can be created by recycling concrete and brick waste. Such waste will be crushed by
machines to generate standard aggregate (as shown in Figure 11). And the price of aggregate will have
an impact on these savings see (14).
Savings in virgin materials = Machine_Costs_submodel.Recycled_Waste* Aggregate_Price*(1 +
the_Increasing_Percentage_of_Aggregate_Price)^Year (14)
Figure 11. Savings in virgin materials factor
2.3 Financial statement
After defining the total costs and benefits, the feasibility of the recycling program will be assessed by
using net present value (NPV) method (as shown in Figure 12). (15) and (16) help to determine the
financial statement and NPV result.
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
31
Financial statement = Total_Benefits-Total_Costs (15)
NPV result = ∑ Financial_Statement/(1+Rate_of_Return)^Year (16)
3. Results
This dynamic model is stimulated with the iThink program and all the data input is taken from
construction companies in Bangkok. Figure 13, 14, 15 and Table 1, 2, 3 show the results of the study.
Figure 13 indicates that the labor costs make up the majority of the total costs, while the truck costs
fluctuate every ten years. That is because the huge amount of concrete and brick waste needs a large
number of labors, leading to the highest cost and every ten years, construction companies will buy new
trucks to replace the old ones.
In terms of the total benefits (as shown in Figure 14), savings in landfill charge stand at the highest
position and they will increase dramatically every five years owing to the raising in the landfill charge.
Figure 15 shows that although the total benefits are greater than the total cost in the tenth year,
construction companies will get the profit in the twenty first year.
Figure 12. Financial statement
Figure 13. The total costs graphical result
1: Training costs 2: Labor costs 3: Fuel costs to recycling places 4: Truck costs 5: Machine costs
Table 1. Total costs result (Bath)
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
32
Year Training
costs
Labor costs Fuel costs to
Recycling places
Truck costs Machine
costs
Initial
1
0.00
374,418.00
0.00
1,455,763,270.50
0.00
17,388,725.82
0.00
365,532,764.22
0.00
5,427,636.98
2
3
4
5
6
7
8
9
10
11
…
20
21
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
…
0.00
0.00
1,521,090,656.66
1,589,282,516.13
1,660,450,535.27
1,734,875,056.44
1,812,434,438.20
1,893,505,623.02
1,978,140,782.57
2,066,569,415.04
2,158,757,459.51
2,255,131,212.83
…
3,029,271,038.16
3,120,627,639.85
18,917,949.42
20,382,411.69
21,953,175.08
23,843,090.89
25,660,921.03
27,839,489.73
29,941,026.09
32,450,230.13
34,877,301.31
37,765,032.87
…
68,473,987,33
72,952,090.33
66,905,469.68
71,824,065.71
76,933,524.17
97,292,191.56
89,860,897.09
97,171,374.54
103,193,054.91
111,377,245.79
91,334,544.37
567,016,512.46
…
103,915,665.29
782,347,275.30
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8,760,151.15
…
0.00
12,218,711.97
Figure 14. The total benefits graphical result
1: Savings in fuel cots to landfill 2: Savings in landfill charge
3: Savings in levelling costs 4: Savings in virgin materials
Table 2. Total savings result (Bath)
Year Savings in fuel
costs to landfill
Savings in landfill
charge
Savings in levelling costs Savings in virgin
materials
Initial
1
0.00
80,573,200,43
0.00
583,425,285.00
0.00
8,968,671.54
0.00
385,423,721.76
2
3
86,361,019.75
91,694,189.47
595,882,110.00
608,598,465.00
13,244,040.66
18,267,724.31
402,767,789.24
420,892,339.75
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
33
4
5
6
7
8
9
10
11
…
20
21
97,352,113,78
104,254,060.14
110,663,481.32
118,444,144.57
125,706,298.03
134,481,682.04
142,711,604.86
152,613,332.19
…
250,209,703.79
263,931,460.73
621,556,515.00
1,047,445,245.00
1,069,671,314.25
1,092,393,596.25
1,115,563,383.00
1,139,230,397.25
1,919,438,743.61
1,960,048,125.34
…
5,841,569,565.31
5,882,460,552.27
24,137,713.41
30,990,584.81
38,926,406.05
48,125,772.42
58,744,687.71
70,985,141.72
85,028,022.06
8,478,319.94
…
102,488,301.05
13,001,200.42
439,832,495.04
459,624,957.32
480,308,080.40
501,921,944.02
524,508,431.05
548,111,310.92
572,776,319.91
769,565,898.39
…
1,143,648,141.83
1,327,902,564.68
Figure
15.
Financial statement graphical result
1: Financial statement 2: NPV result
Table 3. Financial statement result (Bath)
Year Financial statement NPV result
Initial
1
0.00
-786,095,936.79
0.00
-701,871,372.14
2
3
4
5
6
7
8
9
10
-508,659,116.12
-542,036,305.00
-576,458,397.28
-213,695,491.63
-228,386,974.29
-257,631,030.03
-286,752,063.33
-317,588,359.04
434,985,385.26
-1,107,371,305.27
-1,493,182,040.76
-1,859,531,773.68
-1,980,788,334.58
-2,096,496,283.43
-2,213,035,477.71
-2,328,849,826.51
-2,443,375,372.78
-2,303,321,720.76
Australian Journal of Asian Country Studies
SCIE Journals
Australian Society for Commerce Industry & Engineering
www.scie.org.au
34
11
…
20
21
22,032,766.54
…
4,136,255,021.20
3,499,150,060.65
-2,296,987,826.51
…
-222.242,142.58
101,437,828.24
4. Conclusion
This paper uses a system dynamics modeling technique to predict whether the concrete and brick waste
recycling program worth investing. And the results of the model reveal that landfill charge plays an
important role in such program. Therefore, once the government imposes a high landfill charge,
construction companies will surely apply recycling program instead of transporting waste to landfill.
However, as a financial statement shown above, in the beginning years, companies need a lot of capital
so as to pay for equipment and recruit labors, so it is hard for small and medium companies to put such
program into practice. Thus, both government and companies should work together to make this
program more effective. For example, the government can encourage companies participate in this
activity by reducing tax or supporting a part of capital.
There are some limitations in this study. Firstly, all the data is taken from companies in Bangkok, so the
results might be different when applying in other areas. Users ought to adjust this model to make it
more precise. Secondly, there might be more types of costs and benefits in the real situation to add in
the model. For instance, if recycling program was applied by companies, they could gain a benefit from
brand image which could help to attract more customers and get more profit.
References
Forrest, J.M. (1958). Industrial dynamics: a major breakthrough for design makers. Harvard Business
Review, Vol. 26, pp. 37-66.
Chinda, T., Leewattana, N., and Leeamnuayjaroen, N. (2012a). The study of landfill situations in
Thailand. In Proceedings of the 1st Mae Fah Luang University International Conference 2012 (1
st
MFUIC2012) [CD-ROM], 8 p.
Chinda, T., Pornpromtada, K., Wadhanakul, N., and Chavengbenjaporn, S. (2012b). Investigation of
factors influencing construction waste recycling decisions. In Proceedings of the 3rd
International
Conference on Engineering, Project and Production Management (EPPM2012), 10-11 September
2012, Brighton, United Kingdom, pp. 327-334.
Hao, J. L., Hill, M. J., and Huang, T. (2007). A simulation model using system dynamic method for
construction and demolition waste management in Hong Kong. Construction Innovation, Vol. 7, pp. 7-
21.
Hao, J. L., Hill, M. J., and Shen, L. Y. (2008). Managing construction waste on-site through system
dynamics modelling: the case of Hong Kong. Engineering, Construction and Architectural
Management, 15, pp.103–13.
Hao, J. L., Tam, V. W. Y., Yuan, H. P., Wang, J. Y., Li, J. R. (2010). Dynamic modeling of construction
and demolition waste management processes: an empirical study in Shenzhen, China. Engineering,
Construction and Architectural Management, 17, pp.476-492.
Jaroonrat Engineering company. Retrieved from
http://jrr1.jaroonrat.com/ActionController01.php?action=products/ngvActionE
Karavezyris, V., Timpe, K. P., and Marzi, R. (2002). Application of system dynamics and fuzzy logic to
forecasting of municipal solid waste. Mathematics and Computers in Simulation, Vol. 60, pp. 149-58.
Sorpimai, K. (2008). Estimation of Construction and Demolition Waste: Case of Bangkok Metropolitan
Region. M.Sc. Thesis, AIT, Thailand.
Yuan, H., & Shen, L.(2011) Trend of the research on construction and demolition waste management.
Waste management 31: 670–679.
Zhao, W., Ren, H., Rotter, V. S. (2011). A system dynamics model for evaluating the alternative of type
in construction and demolition waste recycling center – The case of Chongqing, China. Resource,
Conservation and Recycling, 55, pp.933-944.