introductionweb.cecs.pdx.edu/~far/past capstone projects/capsto… · web viewproduct design...
TRANSCRIPT
Spacer Cart MECHANICAL/STRUCTURAL ISSUE
ANALYSIS AND REDESIGN Product Design Specifications Report - Winter 2016
Sponsor company: Bonneville Power Administration
Contact Engineer: Kevin Machtelinckx
Academic Advisor: Huafen Hu, Ph.D.
Group member: Bao PhanCarlos JiménezRobert LawrenceAustin FerranteMackenzie Larson-WeberSam Levin Stephen Randall Joshua Ponder
2/16Table of Contents:
● Introduction ………………………..………………………………………….Page 3● Purpose of document ……………….………………………………………….Page 4● Mission Statement ……………….………………………………………….Page 4● Project Plan ………………………..………………………………………….Page 4● Customers Identification
○ External Customers ……….………………………………………….Page 7○ Internal Customers ……….………………………………………….Page 7
● Customers Feedback and Interview ………………………………………….Page 8● Project Design Specification ……….………………………………………….Page 9● Conclusion ………………………..………………………………………….Page 12● Appendix …………………………………………………………………...Page 13
List of Exhibits:1. Spacer Carts Mechanical/Structural Issues Analysis and Redesign, Machtelinckx, Kevin,
October 2015, BPA Internal Report.
3/16Introduction:
Since the United States established a
power grid, power transmission lines have
required maintenance. On modern high
voltage power transmission lines,
maintenance is often performed via a ‘Spacer
Cart’ which is hung on the transmission lines
themselves and can drive itself along the
lines using an onboard motor. There are
several companies which design and sell
these carts, but all have their own
advantages and drawbacks, none of them
are completely ideal. BPA (Bonneville Power
Administration), using their own fabrication
shop and in-house expertise, created their
own
‘Spacer Cart’ for use in transmission line repair.
However,
though the
‘Spacer Cart’ they
have created is
capable of
performing its
intended job,
several details in
regards to
usability and
safety were not
addressed during
its initial design, therefore they have requested the help of
Picture 2: Example of a spacer cart
Picture 1: Power Transmission Line
4/16a Portland State Capstone team in evaluating and
addressing different aspects of the ‘Spacer Cart’ design.
Purpose of Document:
The purpose of this PDS (Product Design Specification), as its name implies, is to define
the scope of the project and the requirement(s) due at final product delivery by the Portland
State University (PSU) Capstone Team, as defined by the customer, Bonneville Power
Administration (BPA). The document will outline a set of specifications that will be addressed by
the Capstone team, each specification being ranked in regard to its level of importance to the
customer.
Mission Statement:
The purpose of the project is the re-design of the spacer cart currently in use by BPA.
Overall project scope is limited to addressing safety/functionality limitations with the current
design. The goal of the new design is to reduce stresses in the frame caused by impacts
sustained during normal operation, and to address access and ease of use issues experienced
with both the supporting crossarms which connect and bring the suspension arms in-line, and
the pinch wheel assemblies which increase driving wheel traction with the conductors. These
new designs must all pass design envelopes specified by BPA for line clearance. BPA would
like a prototype available to them for testing by June 1, 2016.
Project Plan: Owing to the fact that there are several separate design goals and a large team, the
team has separated into 3 subgroups, each tasked with a single design goal: the frame
5/16redesign, the pinch wheel redesign, and the crossarm redesign. Table 1 below illustrates the
tentative dates and milestones for the project.
Table 1: Project Milestones
Plan Dates
Project Tasks Start Date End Date
External Search 1/25/16 2/1/16
PDS Report and Presentation 2/2/16 2/2/16
Internal Search 2/1/16 2/8/16
Concept Evaluation and Selection 2/8/16 2/12/16
Detailed Design 2/12/16 2/26/16
Design Review with BPA 2/29/16 2/29/16
Design Modifications 2/29/16 3/4/16
Final Design Review with BPA 3/7/16 3/7/16
Progress Report and Presentation 3/8/16 3/8/16
Fabrication 3/14/16 4/11/16
Laboratory Testing 4/18/16 4/22/16
Redesign (if needed) 4/22/16 4/29/16
Final Design Fabrication 5/2/16 5/30/16
Field Testing 6/1/16 6/1/16
6/16
Documentation 6/1/16 6/6/16
Final Presentation and Project End 6/8/16 6/8/16
7/16
8/16Graph 1: Spacer Cart project timeline
Customer(s) Identification:
External Customers:
● Linemen at BPA (end users)
○ Interest: A ‘Spacer Cart’ with features that are easier to use while performing
maintenance on the lines, such as the crossarm assembly and the pinch wheel
assembly.
● Fabrication Shop at BPA
○ Interest: Completed drawings and assembly instructions for fabricating
components of the ‘Spacer Cart’ per BPA drawing specification.
● Maintenance Department at BPA
○ Interest: Re-designed features on the ‘Spacer Cart’ that are durable and easy to
maintain.
● Kevin Machtelinckx, Project Engineer at BPA
○ Interest: A completed ‘Spacer Cart’ that meets all of BPA’s specifications.
Internal Customers:
● Portland State Capstone Program
○ Interest: Completion of the Capstone project by meeting all sponsor expectations
and specifications.
● Dr. Faryar Etesami, Mechanical Engineering Professor overlooking Capstone Projects
○ Interest: Completion of design process, planning and execution following the
guidelines and parameters established in the Capstone program. Completion of
the Capstone project by meeting all sponsor expectations and specifications.
9/16
Customers Feedback and Interviews:
Initial interview with Kevin Machtelinckx, our primary BPA contact, was held on
November 20, 2015 at the BPA site in Vancouver. The project team met with Kevin, as well as
several other employees of BPA to discuss the mechanical and structural issues of the ‘Spacer
Carts’. Our team also also performed a physical inspection of the current ‘Spacer Cart’ design,
discussed the scope of work to be accomplished, and received a document detailing the current
mechanical and structural issues from Kevin M. A follow up meeting was held at the BPA facility
on January 13, 2016, in order to discuss, in more detail, the issues with the ‘Spacer Carts’ to
allow the Capstone team time to review the discussed project scope and provided
documentation. The Capstone team also detailed design envelope requirements with regard to
the Product Design Specifications during this meeting.
Product Design Specification:
Table 2: PDS - Performance
Performance
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
Angle of Incline BPA
Cart must climb/descend
a line at an angle.
degrees 35 Customer Defined Site Testing
Weight Rating BPA Working Load Limit lbs 550 Customer
Defined Site Testing
Pincher Wheels BPA
Must traverse on wire and pass armor
rod lip
inches ½ Customer Defined Site Testing
10/16
Table 3: PDS - Safety
Safety
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
Structural Frame BPA
Frame to withstand
vibrations and impact load
under working weight limit
(Impact Loads to be provided
by BPA)
Physical Testing 550
Withstand / support all
loads (Static / Dynamic) associated with normal
cart operation and WLL
Lab Testing
Safety Factor BPA
Establish safety factor
based on industry
standards(applicability to be defined
by BPA)
Specified applicable
design criteria
N/ACustomer/
Project Team Decision
Customer Interview
11/16
Table 4: PDS - Environment and Ergonomics
Environment and Ergonomics
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
Crossbar Redesign BPA
Crossbars should be
redesigned to be easier for
technicians to remove
Operation Efficiency
BPA Foreman Approval
Ease of Use Site Testing
Wind, Rain and Cold
EnvironmentBPA
Cart must withstand use in wind, rain
and cold environments
Duration-Years 5 Corrosion
Resistance Field Use
Operational Design
EnvelopeBPA
All physical modifications
must fall within
operational envelope
restrictions
Design envelope standardAppendix
A
All modifications fall within design
envelope restriction
Specified Design
Envelope
Physical Inspection
Table 5: PDS - Maintenance and Parts
Maintenance and Parts
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
12/16
Frame Reinforcement BPA
Years in service
without frame repair
Years 5 years Customer Defined
Site Testing, FEA
analysis
Table 6: PDS - Installation
Installation
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
Pinch Wheel Assembly BPA
Pinch Wheel mechanism to
be installed easily
Operation Efficiency
BPA Foreman Approval
Ease of Operation Site Testing
Cross-Arm Bar Assembly BPA
Cross-arm bar assembly to be easy to
use while on the line
Operation Efficiency
BPA Foreman Approval
Ease of Operation Site Testing
Table 7: PDS - Cost
Cost
Requirements Primary Customer
Metrics & Targets
Metric Target Target Basics
Verification
Cost must not exceed
original spacer cart production cost by a significant
amount
BPA N/A N/AA
relative value
BPA will decide what cost(s) are acceptable.
Record keeping of
budget expendi-tures and production
costs
13/16
Conclusions:
This document has outlined the specifications for the redesign of BPA’s spacer cart. The
main goal of the redesign is to address stress issues in the frame and increase ease of use on
some of the features. Secondary goals of the project are both to make the cart lighter and
cheaper if possible. We have met with Bonneville employees and engineers to discuss the
specific goals and outline a rubric of guidelines to follow during our design process. Also defined
in this report is a progress goal timeline which has been shared with BPA to update them on our
project milestones. For this project we will need to create 3D and 2D CAD models of our design
ideas for fabrication, perform FEA analysis utilizing the dynamic/static loading scenarios the cart
will undergo during operation, and verify all of our design criteria through physical failure testing
with a fabricated prototype. Fabrication will be done by BPA which will save the project team
labor hours and allow deeper focus on design goals. One of the project’s largest challenges is
prototype fabrication will take several weeks, therefore the project team must be certain that the
design is sound before delivery to BPA for fabrication. Given the aggressive timeline specified
there might exist only one shot to make a working prototype and meet final delivery deadlines.
By splitting into “sub-teams” focused on specific design areas/criteria, the large task of
redesigning the cart has been pared down to more manageable sub-tasks. This has allowed the
large project team to collaborate on design ideas while assigning individuals a specific task/goal
to accomplish.
14/16
Appendix:Section A. Design Envelope Restrictions
15/16
Figure 3: Design change limit envelope - Axial view
16/16
Figure 4: Design change limit envelope - Transverse view