falck zepeda gmcc 2013 implications of biosafety regulatory costs and time delays on r&d
DESCRIPTION
Presentation I made at the GMCC13 conference in Lisbon. Here I discuss the implications for the public and private sector innovation from time and cost delays due to regulations. I pay special attention to the implications from such delays in terms of the type and number of public sector technologies addressing developing countries' problems of a public good nature.TRANSCRIPT
Program for Biosafety Systems ndash httppbsifpriinfo
Implications of Biosafety Regulatory Costs and Time Delays on RampD
Joseacute Falck Zepeda Senior Research Fellow
International Food Policy Research Institute - Program for Biosafety Systems (IFPRI - PBS)
Photos BtRR maize Isabela province Northern Luzon Philippines 2012 Philippines had
approximately 500000 hectares of BtRR maize under cultivation
Issue 1 Recuperating a specified return over time
Model 1 A simplified ldquotypicalrdquo biotechnology developer
bull Typical biotech investor Phillips McDougall 2011) ndash Invests US$ 136 million in a new
GM crop ndash Average time for regulatory
approval of 48 months
bull Financial implications of a 20 rate of return ndash Require a total Net Present Value
(NPV) of US$ 272 million ndash Each year of delay represents a
loss in NPV of US$ 227 million
Source Smyth McDonald and Falck-Zepeda 2013
Marginal loss of net cash flow from delays in regulatory approval process (IRR = 20)
00
100
200
300
400
500
1 2 3 4 5 6 7 8 9 10 11 12 13
Marginal Loss ()
Years
Source Smyth McDonald and Falck-Zepeda 2013
Threshold
If IRR is 50 then
threshold closer to 4
years
Issues and Implications
bull Regulatory delays have a negative impact on returns to investments
bull With a 20 rate of return expect year 6 of regulatory delay to be the trigger point for suspending investment in new RampD projects
bull Current regulatory approvals taking 48 months implies that the upper boundary has likely been reached
Source Smyth McDonald and Falck-Zepeda 2013
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Issue 1 Recuperating a specified return over time
Model 1 A simplified ldquotypicalrdquo biotechnology developer
bull Typical biotech investor Phillips McDougall 2011) ndash Invests US$ 136 million in a new
GM crop ndash Average time for regulatory
approval of 48 months
bull Financial implications of a 20 rate of return ndash Require a total Net Present Value
(NPV) of US$ 272 million ndash Each year of delay represents a
loss in NPV of US$ 227 million
Source Smyth McDonald and Falck-Zepeda 2013
Marginal loss of net cash flow from delays in regulatory approval process (IRR = 20)
00
100
200
300
400
500
1 2 3 4 5 6 7 8 9 10 11 12 13
Marginal Loss ()
Years
Source Smyth McDonald and Falck-Zepeda 2013
Threshold
If IRR is 50 then
threshold closer to 4
years
Issues and Implications
bull Regulatory delays have a negative impact on returns to investments
bull With a 20 rate of return expect year 6 of regulatory delay to be the trigger point for suspending investment in new RampD projects
bull Current regulatory approvals taking 48 months implies that the upper boundary has likely been reached
Source Smyth McDonald and Falck-Zepeda 2013
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Model 1 A simplified ldquotypicalrdquo biotechnology developer
bull Typical biotech investor Phillips McDougall 2011) ndash Invests US$ 136 million in a new
GM crop ndash Average time for regulatory
approval of 48 months
bull Financial implications of a 20 rate of return ndash Require a total Net Present Value
(NPV) of US$ 272 million ndash Each year of delay represents a
loss in NPV of US$ 227 million
Source Smyth McDonald and Falck-Zepeda 2013
Marginal loss of net cash flow from delays in regulatory approval process (IRR = 20)
00
100
200
300
400
500
1 2 3 4 5 6 7 8 9 10 11 12 13
Marginal Loss ()
Years
Source Smyth McDonald and Falck-Zepeda 2013
Threshold
If IRR is 50 then
threshold closer to 4
years
Issues and Implications
bull Regulatory delays have a negative impact on returns to investments
bull With a 20 rate of return expect year 6 of regulatory delay to be the trigger point for suspending investment in new RampD projects
bull Current regulatory approvals taking 48 months implies that the upper boundary has likely been reached
Source Smyth McDonald and Falck-Zepeda 2013
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Marginal loss of net cash flow from delays in regulatory approval process (IRR = 20)
00
100
200
300
400
500
1 2 3 4 5 6 7 8 9 10 11 12 13
Marginal Loss ()
Years
Source Smyth McDonald and Falck-Zepeda 2013
Threshold
If IRR is 50 then
threshold closer to 4
years
Issues and Implications
bull Regulatory delays have a negative impact on returns to investments
bull With a 20 rate of return expect year 6 of regulatory delay to be the trigger point for suspending investment in new RampD projects
bull Current regulatory approvals taking 48 months implies that the upper boundary has likely been reached
Source Smyth McDonald and Falck-Zepeda 2013
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Issues and Implications
bull Regulatory delays have a negative impact on returns to investments
bull With a 20 rate of return expect year 6 of regulatory delay to be the trigger point for suspending investment in new RampD projects
bull Current regulatory approvals taking 48 months implies that the upper boundary has likely been reached
Source Smyth McDonald and Falck-Zepeda 2013
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Issue 2 Recuperating an investment with increases in cost of compliance or delays in the onset of benefits
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Case study 1 Model investor case study (continued)
bull 136 million US$ with a recovery time of 10 years
bull 20 rate of return on investment in real terms ndash NPV of the investment is 272 million dollars
ndash Require a stream of nominal payments of 389 million per year
bull Allow same number of payments and value of each payment but increase time to onset of the benefits
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
NPV with increasing time to onset of benefits
(120000000)
(100000000)
(80000000)
(60000000)
(40000000)
(20000000)
-
20000000
40000000
0 2 4 6 8 10
NP
V (
US$
)
Year after onset of benefits
NPV
bull Keeping same number of payments + rate or return (20)
bull Losses from delays compared to the baseline of no-delay
Year 0 Year 1 Year 2 Sum of cash flows
389269139
389269139 389269139
Present value
163200000
136000000 108967421
NPV 27200000
- (27032579)
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Impact of risk and uncertainty on the stream of benefits over time
bull What happens to the riskiness of investments as the onset of benefits is pushed into a later date
bull Repeat NPV calculation for the ldquomodelrdquo investor using RISK to conduct simulation through repeated iterations
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Risk impacts and the stream of benefits
-120
-100
-80
-60
-40
-20
0
20
40
1 2 3 4 5 6 7 8
Valu
es
in M
illio
ns
Years of regulatory delay
5 - 95 +- 1 Std Dev Mean
Wider
dispersion
around the
mean hellip
the higher
the risk
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Impact of risk and uncertainty in the stream of benefits
bull Investment returns become riskier over time for a well characterized recovery path
bull What happens if developers forced to ldquoforsakerdquo the element of predictability ndash Ambiguity Cannot make a determination due to lack
of knowledge about parameters (eg completion of regulatory process)
ndash Uncertainty Unexpected events
bull Likelihood that an investment will not be made increases with increased uncertainty and ambiguity
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Case study 2 Net benefits from the adoption of GM crops in the Philippines
Bt eggplant
MVR tomato Bt rice PRSV resistant papaya
Net Benefits baseline (NPV in US$)
20466196 16748347 220373603 90765793
Effect of increasing
cost or time of
compliance
Source Bayer Norton and Falck Zepeda (2008)
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Contrasting baseline net benefit levels from GE crop adoption with higher costs in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Contrasting benefit levels from GE crop adoption with larger regulatory lags in the Philippines
Notes 1) Source Bayer Norton and Falck Zepeda (2008) 2) Baseline values for each technology expressed in millions US$ using a
discount rate for the estimation of Net Present Value = 5 3) Change in Net benefits defined as the total benefits estimated using the
economic surplus minus total regulatory costs
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Issues and implications
bull Regulatory costs are not likely to have a significant impact on the returns to investment
bull Exception are organizations that have budgetfinancial constraints
ndash National research organizations in developing countries
ndash International research systems developing public good products
ndash Small private firms in developing countries
bull Regulatory delays have a significant negative impact on net returns
ndash Number and type of technologies
ndash More ldquohigher returnrdquo products and less public good products
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Issue 3 Regulatory and knowledge costbenefit tradeoffs
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Cost and benefit tradeoffs
bull Learning process and the avoidance of negative impacts
bull Face the issues of irreversibility ambiguity and uncertainty
ndash Irreversibility is one of foundation blocks of the precautionary principleapproach and regulatory protocols such as the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Case study 3 The case of fungal resistant bananas in Uganda
bull Ex ante study ndash used the real options approach
bull Conclusions
ndash If approval delayed forego potential annual (social) benefits of +- US$200 million
ndash Maximum total development costs cannot exceed US$108 million
Citation Kikulwe E J Wesseler and J Falck-Zepeda 2008 Introducing a Genetically Modified
Banana in Uganda Social Benefits Costs and Consumer Perceptions IFPRI Discussion Paper
767 Environment and Production Technology Division International Food Policy Research
Institute Washington D C USA
Copyright Kikulwe copy 2009
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Potential implications for decision making (1)
bull Gain more andor better information about technology impacts for decision making - may support valuable technologies
bull Need to balance gains in information additional costs amp effort and impacts on innovation
bull Potential for introducing uncertainty that can lead to an unworkable system especially with ill defined process
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Potential implications for decision making (2)
bull Additional requirements will increase the cost of regulatory compliance
bull Potentially regulatory delays will likely cause a
ndash reduction in the number of technologies especially those released by the public sector and cropstraits of a public good nature
ndash some public sector institutions may not be able to deploy technologies due to fixed costs necessary to enter market
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Socioeconomics regulatory delays and decision making
bull Policy option for parties to the Cartagena Protocol on Biosafety in Article 26
bull Multiple approaches possible for implementation bull Prudent to carefully evaluate tradeoffs including
implementation issues ndash Clearly defining scope and issues ndash Methods and assessment approaches ndash Integration with environmentalfoodfeed safety
assessment ndash Compliance with other international treaties ndash Consistency with national laws and regulations ndash Proportionality
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Time to change and develop functional biosafety and decision making systems
in an era of absolute transparency
ldquoTo continue making things as we have done until now is not an option we must develop a shared vision between agriculture and environment agendas and move towards a paradigm shiftrdquo ldquoWe must face the challenges with technology not ideologyhellipincluding developing proper governance and regulatory processes that workrdquo From a declaration of scientists and regulators at the 2012 Central American Conference on Agriculture and Environment (CIAA) at Zamorano University in Honduras
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
Joseacute Benjamin Falck-Zepeda Senior Research Fellow Leader Policy Team Program for Biosafety Systems
IFPRI 2033 K Street NW
Washington DC 20006-1002 USA
jfalck-zepedacgiarorg
Brief biopubs httpwwwifpriorgstaffprofilejose-falck-zepeda Blog httpsocioeconomicbiosafetywordpresscom
Follow me on Twitter josefalck
Obrigado Gracias
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety
1 The Parties in reaching a decision on import under this Protocol or under
its domestic measures implementing the Protocol
may take into account
consistent with their international obligations
socio-economic considerations arising from the impact of living modified organisms on the
conservation and sustainable use of biological diversity
especially with regard to the value of biological diversity to indigenous and
local communities
bull Applies to decision on import only or
bull National measures
bull Voluntary ndash NOT mandatory
bull Especially WTO
bull Strictly a specific focus and target group
bull Explicit impact indicator
Article 261 of the Cartagena Protocol on Biosafety