Experimental Areas Technical Meeting EATM, 1 Sep 2015
CLOUD newsAntti Onnela, PH-DT, CLOUD Technical and Resource coordinator, GLIMOS
https://indico.cern.ch/event/441526/
2
CLOUD programme in 2015
Spring 2015: CLOUD10-T technical run – completed• 20-24 April: Instruments arrive and installed on the CLOUD platform• 20 April – 20 May with contingency up to 7 June: Run• 21 May -8 June: Instruments depart
15 June – 6 July: T11 used by P349 experiment – run completed, P349 equipment removed from T11
July 2015: Installation of UV Laser for CLOUD in T11. – completed
Autumn 2015: CLOUD10 physics run• 21-25 September: Instrument arrival, installation and commissioning
o Note: The largest amount of instruments in any CLOUD run until now• 21 September – 14 December: Run (last 4 weeks with cosmics only, no beam)• 14-18 December: Instruments depart
EATM, 1.9.2015 / CLOUD, A.Onnela
3
Towards the CLOUD autumn run
Replacement of the exhaust ducts by rigid ones.
Contacts for this project:Antti Onnela / CLOUD, Francisco Josa / EN-CV
EATM, 1.9.2015 / CLOUD, A.Onnela
On the building balcony:• Removal of two of the three flexible ducts.• A second exhaust fan to be installed.
New exhaust duct routing
4
Towards the CLOUD autumn run
Replacement of the exhaust ducts by rigid ones.
Contacts for this project:Antti Onnela / CLOUD, Francisco Josa / EN-CV
Reserve this space for CLOUD use in- Sep-Dec 2015
EATM, 1.9.2015 / CLOUD, A.Onnela
On the building balcony:• Removal of two of the three flexible ducts.• A second exhaust fan to be installed.
New exhaust duct routing