Masjid Annur Islamic Center
EXPANSION Project
Building For The Next Generation
SaturdayFebruary 12th , 2011
www.masjidannur.com 6990 65th Street Sacramento, CA 95823
www.masjidannur.com 6990 65th Street Sacramento, CA 95823
Vision:“To be the minaret of Islam in the Northwest”
Goals: Education for The Next Generation
Social Programs for the Entire Family Dawa and Outreach to the Community
Specialized Youth Programs
www.masjidannur.com 6990 65th Street Sacramento, CA 95823
EXPANSION - Why Now?
Overflowing at Jumah, Tarawweh, and Eid Prayers
- Need for social space for brothers and sisters.- Better facility for conferences and classes No adequate space for Annur Annual
Conference
A Dire Need for: Larger men’s Prayer Hall Larger sister’s prayer area Easily accessible Kitchen & Cafeteria Bookstore Larger and easily accessible babysitting rooms Youth designated game space
EXPANSION - Why Now? Al-Arqam Islamic School (AIS):
School enrollment has been increasing rapidly at an average rate of 12%.
Currently school has 17 classrooms many of which are small for number of students.
Science and computer labs are very small
High school needs more space (classrooms)
Having boys and girls designated classes/areas for grades 5th and up.
Proposed Floor Plans
1st Floor Expansion
Second Floor Expansion
2ND Floor Areas
New Stairs Four new stairs to be added to serve school staff and students
New Stair Enclosure
Circulation & Corridors Will have good amount of day lighting and fresh circulating air through operable skylights
Masjid Section A small area of the second floor will be dedicated to the Masjid staff and occasional Guests in addition to a janitor room and a book storage
Administration Section Offices, nurse room and meeting room centrally located between the boys and the girls sections
Boys Section Includes 8 classrooms, teacher room, Kitchen, restroom and storage
Girls Section Includes 9 classrooms, teacher room, restroom and a storage
Shared Spaces Section Includes an Auditorium, Library, 2 Science labs, 1 computer lab,1 activity & arts room and a recourse room. In addition 2 separate stairs connecting the 2nd floor to the existing Gymnasium will be provided
Design/Plans Status Update
The design is the actual sizing and shape of the steel, electrical wiring, panel sizing, ton age of the air-conditioning units, etc…
The plans is to transfer of these design specification into the paper trail (Plan sheets).
Target date for submitting plans is end of Feb 2011
Architectural
97% Percent of Completion.
ITEM DESIGN % PLANS %
Floor plans 100% 100%
Walls 100% 100%
Accessibility and Fire safety
100% 100%
Arch Details 90% 75%
Stairway enclosure 100% 100%
Elevators and stairways
100% 100%
Electrical
85% percent of completion
ITEM DESIGN % PLANS%
Lighting floor 100% 75%
Canopy lighting 80% 50%
Enclosure lighting 80% 50%
Air condition electrical 100% 100%
Energy compliant 100% 75%
Mechanical
85 % percent of completion
ITEM DESIGN % PLANS%
a/c system 100% 100%
Water and sewer 80% 50%
Energy compliant 90% 80%
Structural
90% percent of completion
ITEM DESIGN % PLANS%
Floor plans 100% 100%
Canopy 90% (?) 100%
Stairs 80% (?) 100%
Elevator 100% 100%
Demolition 100% 100%
www.masjidannur.com 6990 65th Street Sacramento, CA 95823
Your Role
Make sincere Duaa for Allah’s Guidance and Tawfeeq
Take ownership – this is your Masjid!
Raise awareness Invest in your Masjid Invite your family & friends
Donate Generously
Please send your donation to:Masjid AnnurPO Box 245082Sacramento, CA 95824-5082
Or donate online securely through our website
http://www.masjidannur.com/how-donate.php