excavation program & permit training - duke university

26
Facilities Management Utilities & Engineering Services Duke Excavation Program & Permit Training Aug. 4, 2011

Upload: others

Post on 24-Apr-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Excavation Program & Permit Training - Duke University

Facilities Management

Utilities & Engineering ServicesDuke

Excavation Program & PermitTraining

Aug. 4, 2011

Page 2: Excavation Program & Permit Training - Duke University

Agenda

Why are we here?

Overview of NC Underground Damage Prevention Act g g

New Duke University Excavation Program

New Excavation Permit

Other Possible Process Improvements

Next Steps - Restarting Projectsp g j

Facilities Management

Utilities & Engineering ServicesDuke

Page 3: Excavation Program & Permit Training - Duke University

Why Are We Here? - Recent Events1. Fiber Cut #1 (06/23/11): Miller-Long working on the North Concourse project under BE&K ( ) g g p j

cut into the ductbank 30 minutes after telling Duke Utility Locator & BE&K site rep that they were done digging. Ductbank was properly marked. Root Cause: Process Not Followed

2 Chilled Water Line Cut (07/25/11): MIS working on Learning Center Utility project under2. Chilled Water Line Cut (07/25/11): MIS working on Learning Center Utility project under DUES cut into the chilled water return line feeding the Bryan Research Center. MIS had requested a locate that morning and Duke Utility Locator gave them a time he would arrive. The backhoe operator decided to begin the work and hit the line as Duke Utility Locator was getting out of his truck at the siteLocator was getting out of his truck at the site. Root Cause: Process Not Followed

3. Natural Gas line (08/01/11): During a locate with Duke Utility Locators for the Open Space Project next to the Cancer Center, an MIS employee was helping probing and hit the 2” plastic line with a metal tipped fiberglass probe line. Root Cause: Wrong Tool For Job

4. Fiber Cut #2 (08/02/11): Bateman Civil Survey, as sub-contractor to S&ME, working on the WCSP project under OPM to locate utilities jack hammered into the OIT ductbankthe WCSP project under OPM to locate utilities, jack hammered into the OIT ductbank after saw cutting the roadway. Neither Bateman Civil Survey, S&ME, nor OPM contacted DUES or NC One-Call for locating. Bateman assumed that the month-old locate on the nearby chilled water lines was sufficient. Root Cause: Process Not Followed

Facilities Management

Utilities & Engineering ServicesDuke

Root Cause: Process Not Followed

Page 4: Excavation Program & Permit Training - Duke University

08/02/11 Fiber Cut

Facilities Management

Utilities & Engineering ServicesDuke

Page 5: Excavation Program & Permit Training - Duke University

Why Are We Here? - Short Term Process Improvements

1 D l P li & E t bli h E ti P it1. Develop Policy & Establish an Excavation Permit

2. 48 Hour Stand Down

3. Awareness Campaign - Train all PM’s & other Duke departments, contractors on processp

4. Highlight projects with potential for high impact to utilities

5. Indentify High Risk Zones

6. Establish policy on require a vacuum truck to locate gas lines like 44KV lines

Facilities Management

Utilities & Engineering ServicesDuke

Page 6: Excavation Program & Permit Training - Duke University

Facilities Management

Utilities & Engineering ServicesDuke

Overview of NC Underground Damage Prevention Act

Page 7: Excavation Program & Permit Training - Duke University
Page 8: Excavation Program & Permit Training - Duke University
Page 9: Excavation Program & Permit Training - Duke University
Page 10: Excavation Program & Permit Training - Duke University

Excavator must maintain 30” clearance between the edge of the

When excavating within 30” of an underground utility, the exact

clearance between the edge of the underground utility and the cutting edge of any mechanized equipment

location shall be determined by the use of hand tools or vacuum

excavation. Avoid the use of picks.

Page 11: Excavation Program & Permit Training - Duke University

Developing system to print utility drawings with

standard color codesstandard color codes

Page 12: Excavation Program & Permit Training - Duke University

Facilities Management

Utilities & Engineering ServicesDuke

New Duke University Excavation ProgramNew Duke University Excavation Program

Page 13: Excavation Program & Permit Training - Duke University

Excavation Program

Program is effective immediately

The goals were to document the process have been using and to g p galign it with state law

Additional steps were created to minimize impact or damage to Additional steps were created to minimize impact or damage to utilities in high risk areas

See Excavation Program SOP 1 0 See Excavation Program SOP 1.0

Page 14: Excavation Program & Permit Training - Duke University

Excavation High Risk Zones or Major Construction Projects

Definitions Definitions– High Risk Zone - any area where damage to the underground utility

infrastructure can have an impact to significant number of buildings on campus, to hospitals, to patient clinics or to research facilitiesMajor Construction Project any new building or building addition on Duke– Major Construction Project - any new building or building addition on Duke property

Duke Project Manager or Supervisor/Manager, at least one week before request for locate of utilities shall request Duke Utilities & Engineeringrequest for locate of utilities, shall request Duke Utilities & Engineering Services (DUES) Operations/Project Manager to have a Pre-Excavation Meeting with all appropriate parties

Meeting shall cover:– Review scope of excavation – Excavation/project schedule – Drawings of planned work g p– Drawings of any logistical issues (traffic impact, etc.) – Name of contractor(s) doing work – Temporary utilities or shutdowns if required– Review Risk Mitigation Plan

Facilities Management

Utilities & Engineering ServicesDuke

Review Risk Mitigation Plan

Page 15: Excavation Program & Permit Training - Duke University

Risk Mitigation Plan

Identify potential risks to damaging utilities Impact to the utility systems Plans to mitigate or minimize riskg

Risk or Potential System

Risk Mitigation Plan

Task # Job TaskRisk or Potential 

FailureSystem Affected Impact to System Risk Mitigation Plan

1

2

3

Must be approved by all system owners or their designees See Excavation Risk Mitigation Form 1.0

Facilities Management

Utilities & Engineering ServicesDuke

Page 16: Excavation Program & Permit Training - Duke University

Excavation High Risk Zones

Facilities Management

Utilities & Engineering ServicesDuke

Page 17: Excavation Program & Permit Training - Duke University

Excavation High Risk Zones - Medical Center, Uni. Research

Facilities Management

Utilities & Engineering ServicesDuke

Page 18: Excavation Program & Permit Training - Duke University

Excavation High Risk Zones - Chiller Plant 1 & Substation 4

Facilities Management

Utilities & Engineering ServicesDuke

Page 19: Excavation Program & Permit Training - Duke University

Excavation High Risk Zones - EC Steam Plant, Substation 3

Facilities Management

Utilities & Engineering ServicesDuke

Page 20: Excavation Program & Permit Training - Duke University

Facilities Management

Utilities & Engineering ServicesDuke

New Excavation PermitNew Excavation Permit

Page 21: Excavation Program & Permit Training - Duke University

Excavation Permit Process1 If work area is in a High Risk Zone or a major construction project (new1. If work area is in a High Risk Zone or a major construction project (new

building or building addition), then Pre-Excavation Review must be held prior to project starting. If it is not, go to Step 2.

2. Contractor completes Permit Request Form and is signed off by Duke Project Manager or representative

3. Contractor or requestor must attach a drawing(s) and sketch(es) of planned work

4. Contractor performing the work calls NC One-Call Center to request utility locate 48 hours or more prior to need date

5 D k Utilit L t t t t ( i t d t) t t ti t t5. Duke Utility Locator contacts requestor (superintendant) to set up time to meet 6. Duke Utility Locator will coordinate marking of utilities within the 48 hour period

and provide a drawing of known utilities in area to be attached to the permit 7. Duke reviews markings and requirements with equipment operator 8 B th D k Utilit L t d i t t i ti it8. Both Duke Utility Locator and equipment operator signs excavation permit 9. Contractor can now begin work 10. If work goes on beyond NC One-Call Ticket end date, go to Step 2 to request

new permit 11 If k d b k d d i i i d h D k U ili11. If work area needs to be remarked during permit period contact the Duke Utility

Locator

See Excavation Permit 1.0

Facilities Management

Utilities & Engineering ServicesDuke

Page 22: Excavation Program & Permit Training - Duke University

Facilities Management

Utilities & Engineering ServicesDuke

Next Steps - Restarting ProjectsNext Steps Restarting Projects

Page 23: Excavation Program & Permit Training - Duke University

All Active Projects Must Start at Beginning of Process

A Pre-Excavation Meeting must be held for all active projects as defined by the program

Time-slots for Pre-Excavation Meetings:– Thursday 8/4 at 1:00, 2:00, 3:00, & 4:00– Monday 8/8 at 9:00, 10:00 & 11:00y ,– Others times TBD

Projects not requiring a Pre-Excavation Meeting should apply for a Projects not requiring a Pre Excavation Meeting should apply for a Excavation Permit

Permits will be acted on a priority basis Permits will be acted on a priority basis

Facilities Management

Utilities & Engineering ServicesDuke

Page 24: Excavation Program & Permit Training - Duke University

Project Locations

Page 25: Excavation Program & Permit Training - Duke University

Current Projects List as of 7/26/11

Active work on Campus– Learning Center– Research Precinct Steam– Multipurpose Field House

K 4

Upcoming work and/or Surveys– Baldwin Auditorium– Nursing School– Diet Center

P ki B k S E i– K‐4– Open Space– Chiller Plant #2– WCSP– Carpentry Shop

– Perkins Book Storage Expansion– WCSP Phase 3

– Carpentry Shop– DMP– Cancer Center– North Concourse– Buildings 5,9,10g , ,– Lemur– Gardens– Williams Field– Central Campus Apartments– Fiber Optic Loop Downtown– Main Street Bridge and Water 

replacement

Facilities Management

Utilities & Engineering ServicesDuke

Page 26: Excavation Program & Permit Training - Duke University

Other Possible Process Improvements1 Add temporary resources to help with locating and inspecting work sites1. Add temporary resources to help with locating and inspecting work sites

daily2. Set up additional contract locating resource to help with surges in work3. Review need for additional locating equipmentg q p4. Develop pre-construction reviews for projects requiring excavation or

changes to utility plants5. Hold people and contractors accountable6. Establish penalties for contractors not following process7. Develop dynamic map of current and planned excavation projects8. Process to send out list of active projects weekly 9. Develop contractor grading system10. Require utilities to be relocated to proper depths when grades are changed

due to a construction project

THANK YOU FOR YOUR SUPPORT & PATIENCE!

Facilities Management

Utilities & Engineering ServicesDuke