example – rule 5
DESCRIPTION
Example – Rule 5. S1 = {1,3,2,4,6} S2 = {7,8,5,9,10,11} S3 = {12}. 42. 31. 23. 16. 20. 18. 15. 11. 25. 18. 12. 1. m = 3 stations. Cycle time c = 28 ->. BG = t j / (3*28) = 0,655. Example– Regel 7, 6 und 2. = 3. 1. 2. 1. 2. 2. 2. 2. 2. 2. 2. 2. 2. 1. 1. - PowerPoint PPT PresentationTRANSCRIPT
Layout and Design Kapitel 4 / 1(c) Prof. Richard F. Hartl
Example – Rule 5
t1=6 1
1 12
10 11 3
9 3 7
7 8
2 6
4 3
5 4
..1 10
t2=9 2
4 5
j 1 2 3 4 5 6 7 8 9 10 11 12
tj 6 9 4 5 4 2 3 7 3 1 10 1
PVj(5) 42 25 31 23 16 20 18 118 111215
Cycle time c = 28 -> m = 3 stations
BG = tj / (3*28) = 0,655
S1 = {1,3,2,4,6}
S2 = {7,8,5,9,10,11}
S3 = {12}
Layout and Design Kapitel 4 / 2(c) Prof. Richard F. Hartl
Example– Regel 7, 6 und 2
= 3 m
j 1 2 3 4 5 6 7 8 9 10 11 12
PVj(7)
PVj(6)
PVj(2)
1 2
1
1
1 1 11 1 1 1 1
1 1103
2 2 2 2 2 2 2 2 2
2 22
26 9 4 5 4 3 7
Apply rule 7 (latest possible station) at first
If this leads to equally prioritized operatios -> apply rule 6 (minimum number of stations for j and all predecessors)
If this leads to equally prioritized operatios -> appyl rule 2 (decreasing processing times tj)Solution: c = 28 m = 2; BG = 0,982
S1 = {1,3,2,4,5} ; S2 = {7,9,6,8,10,11,12}
Layout and Design Kapitel 4 / 3(c) Prof. Richard F. Hartl
More heuristic methods
Stochastic elements for rules 2 to 7: Random selection of the next operation (out of the set of
operations ready to be applied) Selection probabilities: proportional or reciprocally proportional
to the priority value Randomly chosen priority rule
Enumerative heuristics: Determination of the set of all feasible assignments for the first
station Choose the assignment leading to the minimum idle time Proceed the same way with the next station, and so on (greedy)
Layout and Design Kapitel 4 / 4(c) Prof. Richard F. Hartl
Further heuristic methods
Heuristics for cutting&packing problems Precedence conditions have to be considered as well E.g.: generalization of first-fit-decreasing heuristic for the bin
packing problem.
Shortest-path-problem with exponential number of nodes
Exchange methods: Exchange of operations between stations Objective: improvement in terms of the subordinate objective of
equally utilized stations
Layout and Design Kapitel 4 / 5(c) Prof. Richard F. Hartl
Worst-Case analysis of heuristics
Solution characteristics for integer c and tj
(j = 1,...,n) for alternative 2:
Total workload of 2 neigboured stations has to exceed the cycle time
Worst-Case bounds for the deviation of a solution with mStations from a solution with m* stations:
11 allfor 1
11 allfor 1
max
1
,...,m-k=ctSt
,...,m-k=cStSt
k
kk
m/m* 2 - 2/m* for even m and m/m* 2 - 1/m* for odd m
m < cm*/(c - tmax + 1) + 1
Layout and Design Kapitel 4 / 6(c) Prof. Richard F. Hartl
Determination of cyle time c
Given number of stations
Cycle time unknown Minimize cycle time (alternative 1) or Optimize cycle time together with the number of stations trying to
maximize the system´s efficiency (alternative 3).
Layout and Design Kapitel 4 / 7(c) Prof. Richard F. Hartl
Iterative approach for determination of minimal cycle time
1. Calculate the theoretical minimal cycle time:
(or cmin = tmax if this is larger) and c = cmin
2. Find an optimal solution for c with minimum m(c) by applying methods presented for alternative 1
3. If m(c) is larger than the given number of stations: increase c by (integer value) and repeat step 2.
stations ofnumber minjt
c
Layout and Design Kapitel 4 / 8(c) Prof. Richard F. Hartl
Iterative approach for determination of minimal cycle time
Repeat until feasible solution with cycle time c and number of stations m is found
If > 1, an interval reduction can be applied: if for c a solution with number of stations m has been found and for c- not, one can try to find a solution for c-/2 and so on…
Layout and Design Kapitel 4 / 9(c) Prof. Richard F. Hartl
Example – rule 5
m = 5 stations
Find: maximum production rate, i.e. minimum cycle time
j 1 2 3 4 5 6 7 8 9 10 11 12
tj 6 9 4 5 4 2 3 7 3 1 10 1
PVj(5) 42 25 31 23 16 20 18 18 15 12 11 1
cmin = tj/m = 55/5 = 11 (11 > tmax = 10)
Layout and Design Kapitel 4 / 10(c) Prof. Richard F. Hartl
Example – rule 5
Solution c = 11:
{1,3}, {2,6}, {4,7,9}, {8,5}, {10,11}, {12}
Needed: 6 > m = 5 stations
c = 12, assign operation 12 to station 5
S5 = {10,11,12}
For larger problems: usually, c leading to an assignment for the given number of stations, is much larger than cmin. Thus, stepwise increase of c by 1 would be too time consuming -> increase by > 1 is recommended.
t1=6 1
1 12
10 11 3
9 3 7
7 8
2 6
4 3
5 4
.1 10
t2=9 2
4 5
Layout and Design Kapitel 4 / 11(c) Prof. Richard F. Hartl
Classification of complex line balancing problems
Parameters: Number of products Assignment restrictions Parallel stations Equipment of stations Station boundaries Starting rate Connection between items and transportation system Different technologies Objectives
Layout and Design Kapitel 4 / 12(c) Prof. Richard F. Hartl
Number of products
Single-product-models: 1 homogenuous product on 1 assembly line Mass production, serial production
Multi-product models: Combined manufacturing of several products on 1 (or more) lines.
Mixed-model-assembly: Products are variations (models) of a basic product they are processed in mixed sequence
Lot-wise multiple-model-production: Set-up between production of different products is necessary Production lots (the line is balanced for each product separately) Lotsizing and scheduling of products TSP
Layout and Design Kapitel 4 / 13(c) Prof. Richard F. Hartl
Assignment restrictions
Restricted utilities: Stations have to be equipped with an adequate quantity of utilities Given environmental conditions
Positions: Given positions of items within a station
some operation may not be performed then (e.g.: underfloor operations)
Operations: Minimum or maximum distances between 2 operations (concerning time
or space) 2 operations may not be assigned to the same station
Qualifications: Combination of operations with similiar complexity
Layout and Design Kapitel 4 / 14(c) Prof. Richard F. Hartl
Parallel stations
Models without parallel stations: Heterogenuous stations with different operations serial line
Models with parallel stations: At least 2 stations performing the same operation Alternating processing of 2 subsequent operations in parallel stations
Hybridization: Parallelization of operations: Assignment of an operation to 2 different stations of a serial line
Layout and Design Kapitel 4 / 15(c) Prof. Richard F. Hartl
Equipment of stations
1-worker per station
Multiple workers per station: Different workloads between stations are possible Short-term capacity adaptions by using „jumpers“
Fully automated stations: Workers are used for inspection of processes Workers are usually assigned to several stations
Layout and Design Kapitel 4 / 16(c) Prof. Richard F. Hartl
Station boundaries
Closed stations: Expansion of station is limited Workers are not allowed to leave the station during processing
Open stations: Workers my leave their station in („rechtsoffen“) or in reversed
(„linksoffen“) flow direction of the line Short-term capacity adaption by under- and over-usage of cycle time. E.g.: Manufacturing of variations of products
Layout and Design Kapitel 4 / 17(c) Prof. Richard F. Hartl
Starting rate
Models with fixed statrting rate: Subsequent items enter the line after a fixed time span.
Models with variable starting rate: An item enters the line once the first station of the line is idle Distances between items on the line may vary (in case of multiple-
product-production)
Layout and Design Kapitel 4 / 18(c) Prof. Richard F. Hartl
Connection between items and transportation systems
Unmoveable items: Items are attached to the transportation system and may not be
removed Maybe turning moves are possible
Moveable items: Removing items from the transportation system during processing is
Post-production Intermediate inventories
Flow shop production without fixed time constraints for each station
Layout and Design Kapitel 4 / 19(c) Prof. Richard F. Hartl
Different technologies
Given production technologies Schedules are given
Different technologies Production technology is to be chosen Different alternative schedules are given (precedence graph)
and/or
different processing times for 1 operation
Layout and Design Kapitel 4 / 20(c) Prof. Richard F. Hartl
Objectives
Time-oriented objectives Minimization of total cycle time, total idle time, ratio of idle time, total
waiting time Maximization of capacity utilization (system`s efficieny) – most relevant
for (single-product) problems Equally utilized stations
Further objectives Minimization of number of stations in case of given cycle time Minimization of cycle time in case of given number of stations Minimization of sum of weighted cycle time and weighted number of
stations
Layout and Design Kapitel 4 / 21(c) Prof. Richard F. Hartl
Objectives
Profit-oriented approaches: Maximization of total marginal return Minimization of total costs
Machines- and utility costs (hourly wage rate of machines depends on the number of stations)
Labour costs: often identical rates of labour costs for all workers in all stations)
Material costs: defined by output quantity and cycle time Idle time costs: Opportunity costs – depend on cycle time and number of
stations
Layout and Design Kapitel 4 / 22(c) Prof. Richard F. Hartl
Multiple-product-problems
Mixed model assembly:Several variants of a basic product are processed in mixed sequence on a production line.
Processing times of operations may vary between the models Some operations may not be necessary for all of the variants Determination of an optimal line balancing and of an optimal
sequence of models.
Layout and Design Kapitel 4 / 23(c) Prof. Richard F. Hartl
multi-model Lot-wise
mixed-model
production With machine set-up
Set-up from type „X“ to type „Y“ after 2
weeks
Layout and Design Kapitel 4 / 24(c) Prof. Richard F. Hartl
mixed-model Without set-up Balancing for a
„theoretical average model“
Layout and Design Kapitel 4 / 25(c) Prof. Richard F. Hartl
Balancing mixed-model assembly lines
Similiar models: Avoid set-ups and lot sizing Consider all models simultaneously
Generalization of the basic model Production of p models of 1 basic model with up to n operations;
production method is given Given precedence conditions for operations in each model j = 1,...,n
aggregated precendence graph for all models Each operation is assigned to exactly 1 station Given processing times tjv for each operation j in each model v
Given demand bv for each model v
Given total time T of the working shifts in the planning horizon
Layout and Design Kapitel 4 / 26(c) Prof. Richard F. Hartl
Balancing mixed-model assembly lines
Total demand for all models in planning horizon
Cumulated processing time of operation j over all models in planning horizon:
p
vvbb
1
jv
p
vvj tbt
1
Layout and Design Kapitel 4 / 27(c) Prof. Richard F. Hartl
LP-Model
Aggregated model: Line is balanced according to total time T of working shifts in the
planning horizon.
Same LP as for the 1-product problem, but cycle time c is replaced by total time T
m,...,k= ,...,n j= S j
x kjk 1and1allfor
otherwise0
operation if1
Layout and Design Kapitel 4 / 28(c) Prof. Richard F. Hartl
LP-Model
Objective function:
nk
m
kxkxZMinimize
1 … number of the last station (job n)
Constraints:
for all j = 1, ... , n ... Each job in 1 station
for all k = 1, ... , ... Total workload in station k
for all ... Precedence conditions
for all j and k
x jkk
m
1
1
x tjkj=
n
j1
T
k x k xhkk
m
jkk
m
1 1
x ,jk 0 1
h,j E
Layout and Design Kapitel 4 / 29(c) Prof. Richard F. Hartl
Example
v = 1, b1 = 4 v = 2, b2 = 2
v = 3, b3 = 1 aggregated model
t12=51
012
1111 4
9 17
48
16
63
54
110
112
35
t13=81
312
811 1
9 37
138
46
03
54
110
132
25
t11=6 1
1 12
10 11 3
9 4 7
7 8
2 6
4 3
5 4
1 10
7 2
5 5
t1=42 1
7 12
70 11 21
9 21 7
49 8
14 6
28 3
35 4
7 10
63 2
28 5
Layout and Design Kapitel 4 / 30(c) Prof. Richard F. Hartl
Example
Applying exact method:
given: T = 70
Assignment of jobs to stations with m = 7 stations:S1 = {1,3}S2 = {2} S3 = {4,6,7} S4 = {8,9} S5 = {5,10} S6 = {11} S7 = {12}
Layout and Design Kapitel 4 / 31(c) Prof. Richard F. Hartl
Parameters
... Workload of station k for model v in T
... Average workload of m stations for model v in T
Per unit:
... Workload of station k for 1 unit of model v
... Avg. workload of m stations for 1 unit of model v
Aggregated over all models:
... Total workload of station k in T
kv v jv jkj
n
b t x
1
v v jvj
n
b t m /
1
kv jv jkj
n
t x1
v jvj
n
t m/1
t S tk kvv
p
( )
1
Layout and Design Kapitel 4 / 32(c) Prof. Richard F. Hartl
Example – parameters per unit
’kv
Station k
Avg.
Model v 1 2 3 4 5 6 7 `v
1 10 7 11 10 6 10 1 7,86
2
3
11 11 7 8 4 0
8
7,4311
13 12 14 3 8 3 8,71
x 4
x 2
x 1
Layout and Design Kapitel 4 / 33(c) Prof. Richard F. Hartl
Example - Parameters
kv
Station k
Avg.
Model v 1 2 3 4 5 6 7 v
1 40 28 44 40 24 40 4 31,43
2
3
t(Sk) 70 63 70 70 35 70 7 55
22 14 16 8 22 0 14,86
8 1213 14 383
22
8,71
Layout and Design Kapitel 4 / 34(c) Prof. Richard F. Hartl
Conclusion
Station 5 and 7 are not efficiently utilized
Variation of workload kv of stations k is higher for the models v as for the aggregated model t(Sk)
Parameters per unit show a high degree of variation for the models. Model 3, for example, leads to an high utilization of stations 2, 3, and 4.
If we want to produce several units of model 3 subsequently, the average cycle time will be exceeded -> the line has to be stopped
Layout and Design Kapitel 4 / 35(c) Prof. Richard F. Hartl
Avoiding unequally utilized stations
Consider the following objectives Out of a set of solutions leading to the same (minimal) number of
stations m (1st objective), choose the one minimizing the following 2nd objective:
...Sum of absolute deviation in utilization
Minimization by, e.g., applying the following greedy heuristic
p
vvkv
m
k 11
Layout and Design Kapitel 4 / 36(c) Prof. Richard F. Hartl
Thomopoulos heuristic
Start: Deviation = 0, k = 0
Iteration: until not-assigned jobs are available:
increase k by 1
determine all feasible assignments Sk for the next station k
choose Sk with the minimum sum of deviation
= + (Sk)
p
vvkvkS
1)(
Layout and Design Kapitel 4 / 37(c) Prof. Richard F. Hartl
Thomopoulos example
T = 70
m = 7
Solution:
9 stations (min. number of stations = 7):S1 = {1}, S2 = {3,6}, S3 = {4,7}, S4 = {8}, S5 = {2},
S6 = {5,9}, S7 = {10}, S8 = {11}, S9 = {12}
Sum of deviation: = 183,14
Layout and Design Kapitel 4 / 38(c) Prof. Richard F. Hartl
Thomopoulos heuristic
Consider only assignments Sk where workload t(Sk) exceeds a value (i.e. avoid high idle times).
Choose a value for : small:
well balanced workloads concerning the models Maybe too much stations
large: Stations are not so well balanced Rather minimum number of stations [very large maybe no
feasible assignment with t(Sk) ]
Layout and Design Kapitel 4 / 39(c) Prof. Richard F. Hartl
Thomopoulos heuristic – Example
= 49
Solution:
7 stations:S1 = {2}, S2 = {1,5}, S3 = {3,4},
S4 = {7,9,10}, S5 = {6,8}, S6 = {11}, S7 = {12}
Sum of deviation: = 134,57
Layout and Design Kapitel 4 / 40(c) Prof. Richard F. Hartl
Exact solution
7 stations:
S1 = {1,3}, S2 = {2}, S3 = {4,5}, S4 = {6,7,9 }, S5 = {8,10}, S6 = {11}, S7 = {12}
Sum of deviation: = 126
kv
Station k Avg.
Modelv 1 2 3 4 5 6 7 v
1 40 28 40 36 32 40 4 31,43
2 22 22 16 12 10 22 0 14,86
3 8 13 7 8 14 8 3 8,71
t(Sk) 70 63 63 56 56 70 7 55
Layout and Design Kapitel 4 / 41(c) Prof. Richard F. Hartl
Further objectives
Line balancing depends on demand values bj Changes in demand Balancing has to be reivsed and
further machine set-ups have to be considered
Workaround: Objectives not depending on demand
… sum of absolute deviations in utilization per unit
kv vv
p
k
m
11
Layout and Design Kapitel 4 / 42(c) Prof. Richard F. Hartl
Further objectives
Disadvantages of this objective:
Large deviations for a station (may lead to interruptions in production). They may be compensated by lower deviations in other stations
... Maximum deviation in utilization per unitmax
,max k v
kv v