EVANSTON SLOW ZONE REMEDIATION

CTA Track Maintenance

April 22, 2013

Page 2: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TODAY’S PRESENTATION

• Background

• Project Scope and Benefits

• What to Expect

• Tentative Project Schedule

• Track Renewal Process

• Efforts to Lessen Community Impact

Page 3: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

BACKGROUND

• Originally constructed in

1908-12

• Track last renewed in 1976

• Typical useful life of 25 years

• Currently over 6,700 feet

(16%) of track-related slow

zones

Page 4: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

PROJECT SCOPE & BENEFITS

• Goal to mitigate slow zones until

a major renewal is funded

• Selective track & spot tie renewal

• Project Duration: 7 Months

• Work will occur under single

tracks on nights and weekends

• Over 6000 ties replaced

• Customers will experience a

smoother, faster ride

Page 5: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

PROJECT SCOPE & BENEFITS

Page 6: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

WHAT TO EXPECT

• Sunday through Thursday night work

occurring between 9PM and 4:30AM

• Weekend daytime work between 7AM and

7PM

• Noise as work occurs

• Work zone lighting

• Minor delays to service and boarding

changes during single track operation

• Regular track maintenance will continue

weekdays 9AM – 2:30PM

Page 7: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TENTATIVE PROJECT SCHEDULE

Phase

Affected

Wards

Track

Footage

Track

Slow

Zone May Jun Jul Aug Sep Oct Nov

Mulford St. to South Blvd. 3, 8, 9 700 ft

South Blvd. to Lee St. 3, 4, 9 3700 ft 2875 ft

Lee St. to Church St. 2, 3, 4 5200 ft 2732 ft

Church St. to Milburn St. 1, 2, 5, 7 4100 ft 821 ft

Milburn St. to Isabella St. 7 3300 ft 1454 ft

Isabella St. to Linden 7 500 ft

Construction Notices will be distributed to adjacent properties before work

begins in each area.

Page 8: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Tie handler

• distributes new ties

• cleans up old ties

Page 9: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Tie inserter

• Removes old ties

• Inserts new ties

Page 10: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Production Spiker

• Drives spikes into ties

Page 11: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Ballast cars

• Drops new stone ballast to fill in the track

Page 12: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Ballast Regulator

• Distributes and shapes new stone ballast

Page 13: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

TRACK RENEWAL PROCESS

Production Tamper

• Sets track alignment

• Tamps (compacts) stone ballast

• Creates a solid, smooth ride

Page 14: Evanston project briefing 4 22 13

DRAFT Presentation: For Internal Use Only

EFFORTS TO LESSEN COMMUNITY IMPACT

• Pre-construction coordination meetings with

Evanston city officials

• Biggest, most disruptive work will occur in spring

and fall

• Structured work shift so that loudest work occurs

before midnight

• Biggest production will occur on weekends during

the day

• Presentation to City Council members outlining

project scope and schedule

• Distribution of construction activity notices prior to

beginning work in a given area

• CTA Contact: Ryan Mouw, [email protected]