evaluaciòn de kimberlitas

Upload: yaer-goitia-moreno

Post on 10-Jan-2016

6 views

Category:

Documents


0 download

DESCRIPTION

Kimberlitas

TRANSCRIPT

  • Stage 1

    Discovery (Exploration)

    Stage 1

    Discovery (Exploration)

    Purpose

    To determine if pipe is or has potential to be diamondiferous

    Purpose

    To determine if pipe is or has potential to be diamondiferous

    Stage 2

    Delineation Drilling

    Stage 2

    Delineation Drilling

    Purpose

    To determine size & geometry of pipe,

    multiple phases etc.

    Purpose

    To determine size & geometry of pipe,

    multiple phases etc.

    Stage 3

    Mini Bulk Sampling Using Large Diameter Coring

    Stage 3

    Mini Bulk Sampling Using Large Diameter Coring

    Purpose

    Commercial grade estimate & preliminary

    diamond value

    Core Treatment

    Commercial DMS plant

    Results

    Diamonds > 1.2mm recovered

    Purpose

    Commercial grade estimate & preliminary

    diamond value

    Core Treatment

    Commercial DMS plant

    Results

    Diamonds > 1.2mm recovered

    Stage 4

    Underground Bulk Sampling

    Stage 4

    Underground Bulk Sampling

    Purpose

    To recover >10,000 carats for valuation

    Sample Treatment

    Commercial DMS plant

    Results

    Diamonds > 1.2mm recovered

    Purpose

    To recover >10,000 carats for valuation

    Sample Treatment

    Commercial DMS plant

    Results

    Diamonds > 1.2mm recovered

    Evaluation of a Kimberlite PipeEvaluation of a Kimberlite Pipe

  • Pipe Metres Developed

    Tonnes Mined Carats Recovered

    A154S 1,300 2,585 12,763 A418 800 3,335 8,275

    Pipe Metres Developed

    Tonnes Mined Carats Recovered

    A154S 1,300 2,585 12,763 A418 800 3,335 8,275

    Underground Bulk Sampling - 1996Underground Bulk Sampling - 1996

  • Exploration 1991-95Exploration 1991-95

  • May 16, 2002 Bankable Feasibility Study:

    ! 25.7 million tonnes of proven and probable ore reserve ! Average grade of 4.2 carats per tonne (cpt)! 57% (11.7 million tonnes) of reserve is contained in the A-154S! A-154 South has a grade of 5.2 cpt and a diamond value of US$79 (CDN$116) per carat for an average rock value of US$412 (CDN$606) per tonne.

    May 16, 2002 Bankable Feasibility Study:

    ! 25.7 million tonnes of proven and probable ore reserve ! Average grade of 4.2 carats per tonne (cpt)! 57% (11.7 million tonnes) of reserve is contained in the A-154S! A-154 South has a grade of 5.2 cpt and a diamond value of US$79 (CDN$116) per carat for an average rock value of US$412 (CDN$606) per tonne.

    Production Data Estimated Values Of The Project (100%) (Cdn $)

    Life of mine 20 years

    Total diamond produced 107 million carats

    Project pre-production capital cost CDN$ 1.29 billion

    Nominal Annual Processing Capacity 1.5 million tonnes

    Annual Production (avg. first ten years) 7.1 million carats

    Average Diamond Price (avg. first ten years) CDN$ 109 /carat

    Cash operating cost (avg. first ten years) CDN$ 18 /carat

    Production Data Estimated Values Of The Project (100%) (Cdn $)

    Life of mine 20 years

    Total diamond produced 107 million carats

    Project pre-production capital cost CDN$ 1.29 billion

    Nominal Annual Processing Capacity 1.5 million tonnes

    Annual Production (avg. first ten years) 7.1 million carats

    Average Diamond Price (avg. first ten years) CDN$ 109 /carat

    Cash operating cost (avg. first ten years) CDN$ 18 /carat

  • Diamond Deposits Worldwide US $/tonneDiamond Deposits Worldwide US $/tonne

    0 50 100 150 200 250 300 350 400 450US$/Tonne

    A154S

    Snap Lake

    A418

    Panda

    Jwaneng

    Venetia

    Udachnaya

    A-154 N

    Misery

    Koala

    Jubilee

    A-21

    Sable

    Fox

    Orapa

    Argyle

  • Diavik Diamond MineFull Development 2015

    Near Term GoalNear Term Goal

  • North Rock Pile

    Till

    Airstrip

    Processed KimberliteContainment

    Till

    South Rock Pile

    Camp andProcess Plant

    Dike

    Dike

    Ice R

    oad

    400 0 400 800 1200 1600 2000

    Scale in Metres

    Water TreatmentPlant

    Dike

    A418

    A154SA154N

    A21

    Diavik Mine 2015Diavik Mine 2015

  • Full and Safe ClosureDiavik Site - 2025

    Full and Safe ClosureDiavik Site - 2025

    The Longest-Term GoalThe Longest-Term Goal

  • Com

    munity Participation Throughout

    Com

    munity Participation Throughout

    Overall Project Benefits! 3-Years of Construction

    Capital Expenditure $1.3 billion! Northern Purchasing >38% northern

    ! Average 800 construction jobs 40% northern

    ! 20-years of Mining Operations Workforce > 450

    ! > 66% northern

    ! 40% Aboriginal

    ! $30 million annual salaries

    $100 million annual purchasing ! > $70 million northern

    ! > 40% of value of resource (> $3 billion) accrues to governments

    ! 3-Years of ConstructionCapital Expenditure $1.3 billion

    ! Northern Purchasing >38% northern

    ! Average 800 construction jobs 40% northern

    ! 20-years of Mining Operations Workforce > 450

    ! > 66% northern

    ! 40% Aboriginal

    ! $30 million annual salaries

    $100 million annual purchasing ! > $70 million northern

    ! > 40% of value of resource (> $3 billion) accrues to governments

  • 2001 - 2002 Construction Highlights

    ! Winter road seasons7,200 loads of fuel, supplies & construction

    materials trucked safely to site

    ! Winter road seasons7,200 loads of fuel, supplies & construction

    materials trucked safely to site

    ! Constructing mine plant ! process plant! water treatment plant ! sewage treatment plant ! diesel power plant ! maintenance complex ! permanent accommodations! explosives facility

    ! Constructing mine plant ! process plant! water treatment plant ! sewage treatment plant ! diesel power plant ! maintenance complex ! permanent accommodations! explosives facility

    ! Constructing Earthworks ! Roads, Collection ponds & foundations ! Dams, A154 dike ! Prepare first open pit

    ! Constructing Earthworks ! Roads, Collection ponds & foundations ! Dams, A154 dike ! Prepare first open pit

  • Diavik Diamond Mine SiteDiavik Diamond Mine Site

    August 2002

  • Diavik Plant Site

    August 2002

    Diesel power plant

    Diesel power plant Boiler

    plantBoiler plant

    Permanent Accommodations

    Permanent Accommodations

    Administration / Maintenance Complex

    Administration / Maintenance Complex

    Process PlantProcess PlantFuel

    TanksFuel

    Tanks

    Sewage TreatmentSewage

    Treatment

  • September 2002

    Diavik A154 DikeDiavik A154 Dike

    July 2001

    August 2001

    September 2001

    November 2001

    August 2002

  • Working with Communities Contributing to Community Capacity

    Advisory Training Employment Business Scholarships

  • GREAT B

    EAR LAK

    E

    GREA

    T SLA

    VE LA

    KE

    Kilometres

    00 200200100100

    FortFortLiardLiard

    FortFortSimpsonSimpson

    FortFort

    Norman Norman WellsWells

    Edzo

    RiverRiver

    Lupin Mine

    ResolutionResolution

    TulitaTulita

    YELLOWKNIFERaeWha Ti

    WekwetiGameti

    HayHay

    Ekati

    DelineDeline

    Lac de Gras

    ARCTIC CRICLE

    Fort Fort SmithSmith

    NUNAVUTTERRITORY

    Diavik Diamonds Project

    EnterpriseEnterprise

    Fort ProvidenceFort ProvidenceJean Marie RiverJean Marie River

    WrigleyWrigley

    Nahanni Nahanni ButteButte

    BathurstBathurst InletInlet

    KugluktukUmingmaktokUmingmaktok

    LutselkeDettahNdilo

    Trout LakeTrout Lake

    NORTHWEST TERRITORIES

    YUKON

    MACKENZIE RIVER

    Neighbouring CommunitiesNeighbouring Communities

  • Providing Employment Providing Employment

    Total Construction Workforce averaged 800

    Total Construction Workforce averaged 800

    Northern44%Southern

    56%

    Aboriginal people are about half of the Northern construction workforce

    Aboriginal people are about half of the Northern construction workforce

  • Providing Business Benefits

    Northern73%

    Other27%

    ! Construction contracts worth approximately $1 billion

    ! Over $730 million withnorthern companies

    ! Doubles Diavik's 38 per cent commitment

    ! $500 million with Aboriginal firms and their JVs

    ! Construction contracts worth approximately $1 billion

    ! Over $730 million withnorthern companies

    ! Doubles Diavik's 38 per cent commitment

    ! $500 million with Aboriginal firms and their JVs

  • Diavik Conclusions! Constructing Canadas premier diamond mine ahead of

    schedule and on budget

    ! Ensuring workplace safety

    ! Meeting / exceeding environmental commitments

    ! Successfully training northerners

    ! Meeting northern employment commitments

    ! Exceeding northern business commitments

    ! Community Advisory Participation

    ! Contributing to Community Capacity

    ! Looking forward to diamond production, February 2003

    ! Constructing Canadas premier diamond mine ahead of schedule and on budget

    ! Ensuring workplace safety

    ! Meeting / exceeding environmental commitments

    ! Successfully training northerners

    ! Meeting northern employment commitments

    ! Exceeding northern business commitments

    ! Community Advisory Participation

    ! Contributing to Community Capacity

    ! Looking forward to diamond production, February 2003

  • Canada: A Brilliant Future

    Ekati and Diavik

    SUPERIOR CRATONBUFFALO HEAD

    TERRANE Otish Mountains

    SLAVE CRATONSLAVE CRATON

    Outline of VariablyOutline of VariablyOutline of VariablyOutline of VariablyReworked Reworked Reworked Reworked Archean Archean Archean Archean RocksRocksRocksRocksOutline of OldestOutline of OldestOutline of OldestOutline of Oldest Archean CratonsArchean CratonsArchean CratonsArchean Cratons

    Coronation District

    Buffalo Head Hills

  • Diavik DiamondsDiavik Diamonds

  • Acknowledgements:Acknowledgements:

    Aber

    NAVIGATOREXPLORATION CORP.

    Ashton Mining of Canada