First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
European Laboratories for Distributed Energy Resources
Thomas Degner, Philipp StraussISET e.V.Königstor 59D-34119 KasselGERMANY
www.der-lab.net
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Outline
-Introduction, task for DER laboratories
-Selected European DER laboratories:-CESI (Italy) DG test facility with new generator technologies-ISET (Germany) DG test facility with focus on inverter technologies-Labein (Spain) Distributed Generation Laboratory-Arsenal Research (Austria) Testing laboratory for system
components for Photovoltaic and other DG applications
-Examples
-Co-operation
-Conclusion
2
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Quality Management -> Standards & Certification
Laboratories forTest & Verification of Concepts
Tasks for DER Laboratories
Safety Reliability
Efficiency Quality
DER Power Supply System
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Preparation of Standards
Interdisciplinary committees which bundle general system aspects:
IEC TC 8 “System aspects for electrical energy supply”IEC TC57 “Power system control and associated communication”
IEC 61850 “Communication networks and systems in substations”
IEEE1547™ “Standard for interconnecting distributed resources with electric power systems”
-> Laboratory work is required to prepare the development of standards
3
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Distributed Power Generation Test Facility at CESI / Italy
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
2003 CESI
MV and LV supplyMV and LV supply
Switching andSwitching andinterconnection boardsinterconnection boards
2 X 800 2 X 800 kVA kVA MVMV--LV LV TransformersTransformers
2 x 500 2 x 500 kVAkVA power bus bars power bus bars
Supply BoardsSupply Boards
4
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
2003 CESI
Test facility: Test facility: Energy storage for Power Energy storage for Power Quality Quality (2)(2)
Output Voltage between
450 and 850 Vdc
Discharge time 30 seconds
Operative speed 36000 r.p.m.
Temperature range
-20 °C ÷ +40°C
Estimated life 20 year
Number of full discharge
10 million
Manufacturer URENCO
100 kW Flywheel
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
2003 CESI
CESI CHP system based on 100 kWCESI CHP system based on 100 kW microturbinemicroturbine
TURBEC T100 Microturbine and gas compressor
5
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Characteristics: 105 kWe167 kWth
Dynamic response:start up time 15minshut down 1min
10 kW power step down/upvariation in 5 - 10 sec
Turbec T100 microturbine
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
CESI Test Facility web interface
By means of a simple personal computer equipped with a standard browser, a network connection and the proper authorisations it is allowed to interface the Test Facility
6
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Test and Certification Centre for DER at ISET, Germany
•Tests concerning grid integration with focus on•Grid control•Local generator control•Power and communication interfaces
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
DER available at ISET: diesel gensets & CHP
30 kVAdiesel genset
20 kVAspeed variablediesel genset
5.5 kVACHPunit
12.5 kVAdieselgenset
7
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
DER available at ISET: machine sets for simulating grid, diesel gensets, wind turbines, loads
80 kVA
15 kVA
5 kW
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
DER available at ISET: inverter coupled DG
6 x 3.3kVA battery Inverters (for 1-phase system or 3-phase systems)
22 PV-inverters for grid parallel operation (rated 1-3 kW)
70 kVA battery inverter
inverter
8
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Distributed Generators of DeMoTec
3 independent LV busbars
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Distributed Generators of DeMoTec
Crossbar switch cabinet
9
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Distributed Generators of DeMoTec
MV network
-3x transformer 10 kV / 100 kW-Line equivalent circuits, emulatingcables and lines up to 30km length-3 terminals
LV Network simulator(< 1 km length)
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Communication Concept realised in DeMoTeC
- communication with field controllers by use of Internet technology- telegram format: vendor independent “XML-RPC over HTTP”- application of IEC 61850 compliant namespaces and data models is
currently being explored
10
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
11
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Bus ines s unit Re newable Energy Technolo g ie s
Profile & key facts about a rsena l resea rch
• Independent re sea rch and te s ting ins titution loca ted in Vienna
• Part of Aus tria ’s la rges t ins titute for applied resea rch
• Accredited te s ting ins titution in the fie ld of DER
• Inte rna tional and na tiona l s tandardisa tion
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Bus ines s unit Re newable Energy Technolo g ie s
Labora tory facilities for DER components 1
• Tes t fie ld for DER inverte rs – 3-phase ne twork
s imula tors– Programmable PV
array s imula tors– Protection tes t
equipment
• PV-labora tory
– Sola r s imula tors
– Indoor and outdoor te s ting facilities
12
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Bus ines s unit Re newable Energy Technolo g ie s
Labora tory facilities for DER components 2
• MV, HV and high current tes t lab– up to 120 MVA, ~ 150 kA – 600 kVRMS, 2500 kV cres t– EMC
• Tes t bench for rota ting genera tors
• Environment s imula tions : – Tempera ture , humidity – pressure , corros ive gases – sa lt, ice , snow– wind, vibra tion, shock, solar radia tion
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Example: Unbalanced Load switching
Load switching test (1phase):75 kVA battery inverter, 9 kVA pure resistive load on phase L1
(unbalanced)
13
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Example: Connection test
Connection test:75 kVA battery inverter, connection to 15kVA inductive generator
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Example: Operation of inverter based grids
Current and voltages of the short circuit
Short circuit in a distributed mini-grid
14
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Example: Operation of inverter based grids
Transitions between different power flow conditions and island operation
Parallel operation of public grid and inverter generator
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
European Research Projects on RES and DER
Cluster of research projects supported by the European Commission
Area coordinator for laboratory activities: P. Strauss/ISET www.der-lab.net
www.ired-cluster.org
15
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
European Laboratories for DER
ISET
Arsenal Research
CESI
LABEIN
UMIST / UKDGcentre
Laboratories of the European research cluster
Information exchange already started
NTUA/CRES
Extension and Integration of Laboratories planned
CEA
KEMA
Risoe
TULodz
TUSofia
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Planned Networking and External Co-operation
Standardisationbodies:
•IEC•CENELEC•IEEE•TC8•…
International Co-operation with world class research groups in :•USA & Canada•Japan•Russia•…
Manufacturers:•Siemens•Areva•Schneider•ABB•…
DSOs/TSOs:•EdF•RWE•Iberdrola•…
Interest Groups:•Cogen•EPIA•EWEA•…
European Group of DER Laboratories & Pre-standardisation
16
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Conclusions
The change of the electricity supply towards distributed generation requires
new quality criteria, new test and certification proceduresnew standards
DER laboratories may play a significant role in the preparation of new standards and requirements for DER
Extensive information exchange and collaborative research between labs is required
The chance of close international co-operationbetween DER laboratories at an early stage is to get a common understanding of the standardisationrequirements for an efficient future power supply’s systems technology.
First International Conference on the Integration of RES and DER, 1.-3. December 2004, Brussels
Acknowledgement
We acknowledge the funding of our work by the
Federal Ministry for the Environment, Nature Conservation and Nuclear Safetyin the framework of the projects:
•Vernetzung modularer Systeme, FKZ Nr. 0329900B•SIDENA - Safety Aspects of Decentralised Net-coupled Energy Production Plants•DINAR - Integration of Decentralised RenewableEnergy Supply Plants•MOEL – Integration of countries from Middle and Eastern Europe
European Commission DG Researchin the framework of the projects
•IRED•DISPOWER, Contract no. ENK5-CT2001-00522•Microgrids, Contract no. ENK5-CT2002-00610•DGFACTS, Contract no. ENK5-CT2002-00658•DGnet