essex highways nrswa 22 nd august 2014. in event of an emergency fire alarm? electronic bell in the...
TRANSCRIPT
The Essex Permit Scheme
Background to Essex County Council
Essex County Council is responsible for some 8,000 Km of road network
Essex County Council Serves almost 1.4m residents across Essex
Essex County Council is the 2nd largest non-metropolitan county in England
Background to Essex County Council
Rank County Population Area(in km²)
Density(people/km²)
1 Kent 1,466,500 3,544 4142 Essex 1,396,600 3,464 4033 Hampshire 1,322,300 3,679 3594 Lancashire 1,171,600 2,903 4045 Surrey 1,135,500 1,663 683
6 Hertfordshire 1,119,800 1,643 682
7 Norfolk 859,400 5,371 160
9 West Sussex 808,900 1,990 406
10 Nottinghamshire 786,700 2,085 377
This is a list of top ten two-tier counties of England by population. (non-metropolitan counties also known as shire counties)
District Overview
Southend - Unitary
Thurrock - Unitary
Briefing Session Agenda
Permit Charges
Application Process
Introduction to Permit Schemes
Conditions and Permit Scheme Basics
Any questions
The Journey (Phase 1 & 2)
Introduction to Permit Schemes
Permit schemes were introduced by Part 3 of the Traffic Management Act 2004 (TMA) to improve authorities’ abilities to minimise disruption from street and highway works.
Permit Schemes provide a new way to manage activities in certain streets in the Public Highway.
Introduction to Permit Schemes
In permit streets, instead of informing a Street Authority about their intentions to carry out works in the area, all works promoters will need to obtain a permit for their works.
Permit schemes provide a change to the ‘Notification System’ under the New Roads and Street Works Act, 1991 (NRSWA).
The Strategic Objective
The strategic objective for the Permit scheme is to provide a capability to manage and maintain the local highway network for the safe and efficient use of road space, whilst allowing Promoters access to maintain their services and assets
The Permit Scheme Sub-ObjectivesTo proactively manage the local highway network to maximise the safe and efficient use of road space.
To improve the quality and timeliness of information and compliance with highway legislation from all activity promoters
To ensure the safety of those using the street and those working on activities that fall under the scheme, with particular emphasis on people with disabilities.
To protect the structure of the street and the integrity of the apparatus in it.
To ensure parity of treatment for all activity promoters particularly between statutory undertakers and highway authority works and activities.
Key Points to Permit Schemes
A permit is only valid for the period of time stated on the permit in TSS Streets.
A late start on site means duration lost. The end date cannot be ‘stretched’ without an approved variation. The start and end dates will be in calendar days, even though many aspects of the scheme will operate on working days.
Where a permit allows weekend and Bank Holiday work, then the permit start and end dates will accommodate that.
No Permit No Work !!
Key Points to Permit Schemes
Permit Schemes in England
What is happening out there ?
The view from ECC
How ECC made the decision to proceedWith an application for a scheme
LOPS SchemeWent live on 2010
Phase 4 2013
Kent Scheme
Northants SchemeSt Helens Scheme
Yorkshire Scheme
East of England
The CurrentPermit Scene
Oth
er s
chem
es o
n th
e w
ay
Lane
Ren
tal T
fL a
nd K
ent
GMRAPS 22 m
ore
applied
DfT
loca
lism
Agenda
Bucks/Norfolk etc
The Journey
Scrutiny Report to Feasibility Study
The Project idea was presented to Paul Bird
Phase 1 – Started on the 7th May 2014
Phase 1 – Deadline 31st July 2014 (DfT)
Phase 1 – Completed on 28th July 2014
Phase 2 – Started 1st August 2014
Phase 2 – Ends 1st April 2015
(Start to finish = 11 weeks/3 months | average 18 months for this phase)
Application Process
Consultation Process
Apply For Statutory Instrument
DfT Application
Give 1 month of Starting
Jun
e 1
4 – A
pril 1
52013/14 Feasibility Study/
Develop Scheme
2012 Could have joined
EEPS
Scheme Document
Outlines the Scheme
Part of DfT Application
It forms the Permit Schemes SI
Cost Benefit Analysis (CBA)
The Permit Matrix (Volumes & Costs)
Congestion data
Traffic Flow data
The CBA Looked at the following
Accident data
Set up costs
Entered into a QUADRO model to give a Cost Benefit Ratio:• The Essex Permit Scheme = 20.16 • Net Present Value (NPV) = £1 billion +
Permit Matrix (Fees)
DfT Permit Matrix (Mandatory)
Lighter touch on Non-TSS
DfT Guidance on fees 2013
Looked at Activity Volumes
Looked at current time to do checks
Looked at over & above time to do checks
Maximum Permit Fees
Essex Permit Fees
Fee levels per Permit or Provisional Advanced Authorisation Road Category 0-2
Strategic or Traffic Sensitive
Road Category 3 & 4 Non- Traffic Sensitive
Provisional Advanced Authorisation £100 £50
Major Activity – over 10 days £201 £80
Major Activity – 4 to 10 days £125 £40Major Activity – up to 3 days £60 £25Standard Activity £125 £40Minor Activity £60 £25Immediate Activity £50 £35
Variations
For permit variations, the Permit Authority will charge:-
• £45 for all works on category 0, 1 and 2 streets and category 3 and 4 streets that are traffic-sensitive.
• £35 for all works on category 3 and 4 non traffic-sensitive streets
Discounts
Suggested discounts in Scheme document
Coring Performance
First Time Permanent ratio
Collaboration
Permit Scheme Requirements
Regulation 19 provides that it is a criminal offence for an undertaker or someone acting on its behalf to undertake works without a permit.
Regulation 20 provides that it is a criminal offence for undertaker or someone acting on its behalf to undertake works in breach of a condition.
For the first time, the field force are affected !!
Conditions (HAUC UK)
English HAUC National Condition Text
Consistency across new schemes
Currently draft version 14
Sign off expected early Sep 14
Future changes possible via HAUC
NRSWA Timescales
Table 1: Matrix of notice periods and response times
Notice Period Validity Period Response Time S 54 Ss 55/57 S 54 Ss 55/57 S54 Ss55/57 S 74
Major 3 months 10 days 15 days 5 days 1 month
5 days 5 days
Standard 10 days 5 days 5 days 5 days
Minor 3 days 2 days 2 days 2 days
Immediate 2 hours after
any time during works
2 days
New Roads and Street Works Act 1991 Code of Practice for the Co-ordination of Street Works and Works for Road Purposes and Related Matters. Third Edition - Revised August 2009
Permit Timescales
Works Type Minimum Notice Period
Validity Period Response Period
PAA Appl’n PAA* Appl’n* PAA Appl’n
Var’n
Major 3m 10d 15d 5d 1m 5d 2d
Standard 10d 5d 5d 2d
Minor 3d 2d 2d 2d
Immediate – Urgent/ Emergency
-2h 2d 2d
*The validity periods only apply to permits in Category 3 or 4 Non Traffic Sensitive streets; Otherwise the permit start and end dates cannot be varied.
Basic MAJOR Works PERMIT Life Cycle
Provisional Advanced Authorisation
Send FORWARD PLANNING Notice more than 3 months in
advance (optional)
Permit Application
Send Section 74 WORKS STOP Notice
Send Section 74 ACTUAL START Notice
Send Section 70 REGISTRATION Notice
Perm
it Au
thority
100% Response
Maybe YES
Maybe NO
Basic MINOR Works PERMIT Life Cycle
Three Day Permit Application
Send Section 74 WORKS STOP Notice
Send Section 74 ACTUAL START Notice
Send Section 70 REGISTRATION Notice
Perm
it Au
thority
100% Response
GRANT?REFUSE?
Basic STANDARD Works PERMIT Life Cycle
Ten Day Application
Send Section 74 WORKS STOP Notice
Send Section 74 ACTUAL START Notice
Send Section 70 REGISTRATION Notice
Perm
it Au
thority
100% Response
Existing NRSWA Structure
Traffic Manager
NRSWA Manager
Co-Ordinators
Inspectors
High level overview
Covers main job roles
New Structure
Traffic Manager
Streetworks Manager(operational)
Co-Ordinators
Inspectors
Permit Manager(Permit Scheme)
Senior Performance Officer
Performance Officer
Invoicing Officer
Senior Permit Officer
Permit Officers
Any Questions?
The Essex Permit Scheme