erke group, ptc sc13 building stone columns with bfs system greece
TRANSCRIPT
-
7/29/2019 ERKE Group, PTC SC13 building stone columns with BFS system Greece
1/1
T Stars Narcs Fndatn Ctra
Cntr (SNFCC) at t Farn Dta ara
n Atns, Grc, as bn dsgnd by
Rnz Pan, n f t st fas
arctcts n sstanab arctctr.
The SC13 workingin a project of 27,920 mof stone columnsfor a cultural center, Greece.
The SNFCC will house the Greek National Opera,
the Greek National Library and a large urban park.
This 187,800 m2 project will have a cost o US$803
million, nanced entirely by the Stavros Niarchos
Foundation, and once completed in 2015 it will be
turned over to the Greek State.
The Renzo Pianos Building Workshop has created
an emissions neutral acility. The environmentalqualities o the Cultural Centre are crucial to the
design.
The top o the complex emerges rom a hilltop and
cantilevers out over the slope and is covered with a
*LEED is a national certifcation system developed by the U.S. Green Building Council (USGBC) to encourage the
construction o energy and resource-efcient buildings that are healthy to live in. It is a voluntary, market driven
building rating system based on existing proven technology
The positive thing about the machine
is that it is built for constructing stone columnswith a very sophisticated electronic system and
a good data log system. Stone columns can
reach diameters up to 80 or 90 cm depending
on the ground conditions with good quality and
continuity.
Said Aristidis Kontogiannis, Project Engineer.
GRouPS oF GRAvel PileSGRAvel Pile
DiAmeTeRelevATioNS ASl (Ab Sa l)
CoNSTRuCTioN
DePTh FRom
woRkiNG
SuRFACe
CleAR leNGTh
FRom CuT-oFF
(xcaatn
srfac)
Group
designation
Names
o Gravel Piles
in Groups
Quantities
o Gravel Piles
in Groups
W orking s ur a ce E xc av at ion , c ut -o Bot to m, p i le e nd
D (m) Z
(m) Zf(m) Z
b(m) l
(m) l (m)
G1 1~226 226 0.60 -0.50 -1.00 -8.00 7.50 7.00
G2 227~395 169 0.60 -0.50 -1.00 -9.00 8.50 8.00
G3 396~800 405 0.80 -0.50 -1.50 -10.00 9.50 8.50
G4 801~2181 1381 0.80 -0.50 -1.50 -12.00 11.50 10.50
G5 2182~2672a 493 0.60 -0.50 -1.50 -11.50 11.00 10.00
G6 2673~2883 211 0.60 -0.50 -1.00 -11.00 10.50 10.00
large green roo that connects directly to the park.
As part o its sustainability plan, the SNFCC eatures
a canal that unctions as anti-fooding protection
or the site, as well as a water recycling system that
provides or on-site irrigation.
A green roo above the structure oers shade and
cooling, and a 2.5 acre solar photovoltaic system will
be set atop to generate power or both the library
and opera. One o the goals o the complex is to
achieve LEED Platinum certication*.
The Italian-Greek joint venture, Impregilo-TERNA,
has undertaken the construction o the Stavros
Niarchos Foundation Cultural Center (SNFCC).
Enviprosystems SA has been appointed as sub
contractor or the ground treatment and oundation
works.
The ground treatment works will involve the
construction o 9975 meters o 600 mm diameter
stone columns and 17945 meters o 800 mm
diameter stone columns. The main equipment used
to achieve this important quantity o stone columns
was the PTC Stone Column rig SC13.
The stone columns were built ollowing a 2x2m
triangular grid and their depth was determined by
the soils conditions. The Vibrolance penetrated the
soil up to the layer containing clay sand with gravel.
Detailed inormation concerning the stone column
characteristics and the scope o the work done can
be seen in the ollowing table:
Gravel pile typical construction detail(Not to scale)
Gravel pile typical placement grid(Not to scale)
KEY FACTS
- Total work: 27920 m of stone
columns
- 9975 meters of 600 mm
- 17945 meters of 800 mm
- SC13 worked at a max. depth
of 11.5 m.
PTC - Job report - Ground improvement
27 28