1 The precast concrete element will be shifted to site using Truck Trailer
2 Erection Sequence
Footing (1 MT) (1.8 m*1.2 m* 0.25m)
Column (1 MT) ( 3.35 m
Tightening of Nuts
After sufficient number of Footing have been placed wall planks will be placed
Backfilling will be done before the close of days work
3 Erection Methodology
The precast member will be lifted through lifting hooks /holes provided in members using arrangement made of Steel Pipes , SW rope and D shackles/ ring attachments
Lifting shall be done using hooks in crawler type crane / crawler tractor suitably redesigned for lifting.
Member shall be placed in position previously prepared as per line and levels.