Evergreen Trails Master Plan
Presentation to Evergreen Parks and Recreation District Board of Directors
June 23, 2015
Presentation Outline
1. Project Overview2. Recap of Stakeholder and Public Outreach3. Recommended Trail Plan4. Next Steps5. Questions/Comments
Project Partners• Great Outdoors Colorado Grant Funding• Downtown Evergreen Economic District• Jefferson County Transportation and Engineering• Jefferson County Planning and Zoning• Jefferson County Open Space• Jefferson County Public Health• Evergreen Parks and Recreation District• Denver Mountain Parks
Desired Outcomes
• Build community understanding and support• Identify feasible, implementable, fundable projects• Be ready for construction funding opportunities
Project Process Overview• Community Engagement• Agency and Stakeholder Participation• Assess Existing Conditions and Previous Plans• Identify Opportunities• Develop Recommendations• Validate Recommendations• Create Implementation Plan• Finalize Recommendations and Plan
PUBLIC OUTREACH
Public Meeting #1 – Community Concerns and Connectivity Needs
May 20, 2014
”
Public Meeting #2 – Concept Alternatives and Visual Preference Survey
August 19, 2014
Public Meeting #3 – Draft Recommendations
December 10, 2014
”
Focused Outreach PRESENTATIONS
• Evergreen Rotary Club Meeting Presentation
• Evergreen Pathfinders Meeting Presentation
• Evergreen Pathfinders Community Meeting Presentation
• EDBA Board Presentation
• EDBA General Meeting Presentation
OTHER• Highland Haven area meeting
with local property owners
• Evergreen High School Administration meeting
• Church of the Hills Discussion
• Team Evergreen meeting update
• Local resident individual meetings
Website and Media Updates• Project Website
www.trails4evergreen.org
• Team Evergreen Website• DEED Website
_________________________• Canyon Courier• Yourhub• Justaroundhere.com• myMountaintown.com
RECOMMENDED TRAIL PLAN
Meadow Drive Trail and Bike Lanes
River Trail
Cub Creek Trail
SH 74 and Lower Meadow Drive Intersection
SH 74 and Lower Meadow Drive Intersection Looking East
Downtown Crossing Improvements
Downtown Crossing Improvements - Alternate Universe
Evergreen Parkway Crossing Improvements
Way-Finding SystemFamily of Signs that:• Establish character and identity for area;• Provide auto and pedestrian level directional
information;• Increase visibility of key destinations;• Address visitor audience
Next Steps
• Finalize Plan with Stakeholder Partners• Complete Implementation Plan
– Cost estimates– Project agency lead– Cooperating agencies– Applicable grant funding sources
• EPRD Next Steps Discussion
Questions/Comments