EPD CONSENT AGENDA
PROGRESS REPORT
REPORT DATE: July 10, 2006
![Page 2: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/2.jpg)
FY 2005 YEAR TO DATE TOTALS
MANHOLE INSPECTIONS TAB 1 GLOBAL POSITIONING LOCATIONS MANHOLE REPAIRS TAB 2 TV INSPECTION TAB 3 ROOT CONTROL TAB 4 HYDRAULIC CLEANING TAB 5 EASEMENT CLEARING TAB 6 AERIAL STREAM CROSSING INSPECTIONS TAB 7
COMBINED TOTALS BY FISCAL YEAR TAB 8
![Page 3: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/3.jpg)
MANHOLE INSPECTIONS/GLOBAL POSITIONING LOCATIONS
INFLOW/INFILTRATION SECTION 4860 OF 5000
SYSTEM MAINTENANCE** 4 OF 80
** MANHOLE INSPECTIONS ONLY
TAB 1
![Page 4: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/4.jpg)
97%
1%
General Maintenance **
Inflow/Infiltration Section
Manhole Inspections/Global Positioning Locations
% Completed
** Manhole Inspections Only
TAB 1
![Page 5: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/5.jpg)
MANHOLE REPAIRS
CONTRACTED (RAISED) 2,069 OF 3,200
GENERAL MAINTENANCE 7 OF 40
TAB 2
![Page 6: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/6.jpg)
65%
18%
General Maintenance(Repaired)
Contracted (Raised)
Manhole Repairs
% Completed
TAB 2
![Page 7: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/7.jpg)
TV INSPECTION
INFLOW/INFILTRATION SECTION 40,802’ OF 50,000’ SYSTEM MAINTENANCE 48,320’ OF 55,000’
TAB 3
![Page 8: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/8.jpg)
82%
88%
General Maintenance(CountyWide)
Inflow/Infiltration Section
TV Inspection
% Completed
TAB 3
![Page 9: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/9.jpg)
ROOT CONTROL
PHASE 1 21,720’ OF 21,720’
River Cove EstatesNickajack ForestRussell HeightsPineland SpringsLake Shore EstatesCovered Bridge CrossingFox Fire ForestLaurel CliffsLaurel EstatesBriar CrestLake Laurel Estates
PHASE 2 383,283’ OF 383,283’
Casey Park
River Cove Estates
Heartford Woods
Sherwood Estates
Creekview Estates
Shannon Springs
Garrison Estates
Civitania Woods
Frontier Trails
TAB 4
![Page 10: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/10.jpg)
TAB 4ROOT CONTROL
PHASE 3 102,291’
ALPINE FORESTCHIMNEY SPRINGSHOLLY OAKSMADISON HALLCOCHISEORCHARD RIDGEGREEN ACRESCOBB HEIGHTS
PHASE 4
![Page 11: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/11.jpg)
100%100%100%
0%
Phase 4
Phase 3
Phase 2
Phase 1
Root Control
TAB 4
![Page 12: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/12.jpg)
HYDRAULIC CLEANING
GENERAL MAINTENANCE 178,959’ OF 400,000’ (COUNTY WIDE)
TAB 5
![Page 13: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/13.jpg)
45%
General Maintenance(CountyWide)
Bar 1
Hydraulic Cleaning
% Completed
TAB 5
![Page 14: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/14.jpg)
EASEMENT CLEARING
PHASE 1 210,000’ OF 210,000’
PHASE 2 0’ OF 0’
TAB 6
![Page 15: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/15.jpg)
100%
0%
PHASE 2
PHASE 1
Easement Clearing
% Completed
TAB 6
![Page 16: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/16.jpg)
AERIAL STREAM CROSSING INSPECTIONS
INFLOW/INFILTRATION SECTION 321 OF 400
SYSTEM MAINTENANCE 8 OF 30
TAB 7
![Page 17: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/17.jpg)
80%
27%
SYSTEM MAINTENANCE
INFLOW/INFILTRATION
AERIAL STREAMCROSSING INSPECTIONS
TAB 7
![Page 18: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/18.jpg)
212,220
719,766
257,692
596,173
163,812
668,980
334,879
17,833
203,523
713,877
520,796
226,798
145,047
508,831
575,367
66,569
89,122
507,294
178,959
210,000
TV Inspection
Root Control
Hydraulic Cleaning
Easement Clearing
FY 2002 FY 2003 FY 2004 FY 2005 FY 2006
Totals by Fiscal Year
Linear Feet
TAB 8
![Page 19: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/19.jpg)
26,345
17,828
3,366
15,617
6,435
3,935
15,898
5,992
4,196
13,913
4,254
4,258
4,864
4,860
2,069
Manhole Inspections
Global PositioningLocations
Manholes Raised
FY 2002 FY 2003 FY 2004 FY 2005 FY 2006
Each
Totals by Fiscal YearTAB 8
![Page 20: EPD CONSENT AGENDA PROGRESS REPORT](https://reader035.vdocuments.us/reader035/viewer/2022062408/56813af5550346895da37969/html5/thumbnails/20.jpg)
453
28
1,193
283
747
75
226
38
329
7
Aerial StreamCrossing Inspections
Manhole Repairs
FY 2006
FY 2005
FY 2004
FY 2003
FY 2002
Totals by Fiscal Year
Tab 8
Each