environmental management plan the rural enegy ii …€¦ · i hung yen city 0.051 2 15.28 . 1 thu...

108
1 NORTH POWER COMPANY POWER NETWORK PROJECT MANAGEMENT UNIT WB credit VN: 4576 ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II Project Additional Financing Phase 03 Hung Yen province Hanoi, June 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 13-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

1

NORTH POWER COMPANY

POWER NETWORK PROJECT MANAGEMENT UNIT

WB credit – VN: 4576

ENVIRONMENTAL MANAGEMENT PLAN

The rural Enegy II Project

Additional Financing – Phase 03

Hung Yen province

Hanoi, June 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb231615
Typewritten Text
E2105v35
Page 2: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

2

TABLE OF CONTENTS

1. INTRODUCTION AND SCOPE OF WORK ................................................................................................ 5

1.1. OBJECTIVES OF THE PROJECT ....................................................................................................................... 5 1.2. NEED FOR SUBPROJECT INVESTMENT .............................................................................................. 5 1.3. COMMUNE SELECTION CRITERIA .................................................................................................................. 6

2. SUBPROJECT DESCRIPTION ................................................................................................................... 10

2.1. SUBPROJECT SCALE ............................................................................................................................. 10 2.2 SUBPROJECT SCHEDULE ..................................................................................................................... 12 2.3. SOME OF MAIN TECHNICAL SPECIFICATIONS FOR THE SUBPROJECT .................................... 12 2.4. SOME OF MAIN ACTIVITES FOR CONSTRUCTION AND INSTALLATION .................................. 15 2.5. BRIEF DESTCRIPTION OF NATURAL AND SOCIAL CONDISTION OF THE SUBPROJECT’S

PROVINCES ................................................................................................................................................... 17 2.6. INVESTMENT STRUCTURE OF THE SUBPROJECT.......................................................................... 18

3. LEGAL FRAMEWORK FOR SUBPROJECT’S ENVIRONMENTAL IMPACT ASSESSMENT ...... 19

3.1. VIETNAM REGULATIONS AND LAWS .............................................................................................. 19 3.2. WORLD BANK SAFEGUARD POLICIES ............................................................................................. 19

4. ASSESSMENT OF ENVIRONMENTAL IMPACTS ................................................................................. 21

4.1. CLASSIFICATION OF IMPACTS..................................................................................................................... 21 4.2. IDENTIFICATION OF POTENTIAL IMPACTS OF THE SUBPROJECT ................................................................ 21

5. ENVIRONMENTAL MANAGEMENT PLAN ........................................................................................... 29

6. ENVIRONMENTAL MONITORING ......................................................................................................... 34

7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN IMPLEMENTATION ............. 37

7.1 ARRANGEMENT FOR EMP’S IMPLEMENTATION .......................................................................................... 37 7.2 REPORTING PROCESS................................................................................................................................... 38 7.3 CAPACITY DEVELOPMENT AND TRAINING ................................................................................................... 38

8. COST ESTIMATION FOR IMPLEMENTATION OF EMP .................................................................... 40

9. PUBLIC CONSULTATION AND DISCLOSURE ..................................................................................... 41

9.1 PUBLIC CONSULTATION .............................................................................................................................. 41 9.2 DISCLOSURE ............................................................................................................................................... 43

Page 3: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

3

LIST OF TABLE

Table 1.1. Subproject communes

Table 2.1. Scale, site for new substation and new MV line

Table 2.2. The investment structure of the Subproject (VND)

Table 2.3. Subproject implementation schedule

Table 4.1. The assessment of Subproject's impacts

Table. 5.1. Mitigation measures applied for the Subproject

Table 6.1. Monitoring of mitigation measures

Table 6.2: Monitoring of environmental quality

Table 7.1. Arrangement for EMP’s implementation

Table 7.2 The environmental reporting requirement

Table 8.1. The cost estimation for future trainings

Table 8.2: Estimated costs for implementation of the EMP (VND)

APPENDIX

Appendix 1: List of EIA preparers

Appendix 2: Subproject's environmental permit

Appendix 3: Example of public consultation for environment impact assessment record

Appendix 4: Map of Subproject in Hung Yen

Appendix 5: Example commune-level data report format

Appendix 6: Example of site environmental management monitoring report (applied for

contractor’s report)

Appendix 7: Example of environmental performance monitoring report

Appendix 8: Summary of Impacted Assets by Subproject

Page 4: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

4

Abbreviations

CPC Commune People’s Committee

CRC Compensation and Resettlement Committee

D/L Distribution Line

DMS Detailed Measurement Survey

DONRE Department of Natural Resources and Environment

DOC Department of Construction

DOF Department of Finance

DOIT Department of Industry and Trade

DPC District People’s Committee

DP Displaced Persons

GOV Government of Vietnam

HH Household

IDA International Development Association

IMA Independent Monitoring Agency

LURC Land Use Right Certificate

NPC North Power Company

PMU Project Management Unit

PPC Provincial People’s Committee

PPP Project Provincial Power

ROW Right-of-Way

USD US Dollar

VND Viet Nam Dong

Page 5: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

5

1. INTRODUCTION AND SCOPE OF WORK

1.1. Objectives of the Project

The development objectives of the proposed Rural Energy II Project are to assist the

Government of Vietnam to alleviate poverty in the rural areas by providing basic

infrastructure service such as electricity and access to general services, for improving living

conditions and productivity. The Project will assist the Government of Vietnam to implement

its national objective of providing electricity to about 12 million rural households through:

- An effective strategy for rural electrification with special focus on provision of energy

to the remote mountainous areas;

- Rehabilitating, upgrading and expanding the rural power system in order to meet the

demand for power supply for future socio-economic development;

- Strengthening reliability and quality of power networks, reduce voltage and electricity

losses on the grid, lower rural consumption price, improve businesses efficiency and

rural power management ability of local power management boards;

- Refurbishment of the existing rural power network to increase reliability and quality

of supply, including reduction of technical and non-technical losses; this Subproject

incorporates 74 communes in 10 districts of Hung Yen province.

- Extension of existing power networks to supply additional households;

- Assisting local District and Commune committees to improve power system

management processes and improve business efficiency, to provide electricity

reliably, safely and at reasonably cost;

- Review rural power management models, to establish power management units of

legal standing, with economic independence and the managerial/technical skills to

operate effectively and profitably, repaying loaned funds;

- Expanding the use of renewable energy for the off-grid systems to serve the rural load

in the remote and isolated areas, where feasible and economically practicable;

1.2. NEED FOR SUBPROJECT INVESTMENT

Based on the forecast data on economic development, power demand and the current

situation of the existing power distribution network of the Subproject’s commune. The

existing distribution network is degraded, not synchronous. Power losses are very high. The

alignment of power lines was not well designed. Many types of poles existed in the network.

There ware also many types of electricity meters. In the past in order to save money, the

distribution lines were created to go across gardens, ponds etc. The conductor is overhead

type and not covered by any insulating materials, so it causes a lot of risk on safety to local

people. The Subproject is planned to implement in order to:

- Improve the quality of the existing distribution network in the Subproject’s

communes.

- Increase the safety management of the distribution network;

- Reduce power losses;

- Increase electricity supply for the Subproject’s communes;

- Change the form for management model of rural power network;

- Gradually modernize the distribution power network.

Page 6: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

6

1.3. Commune selection criteria

1.3.1. General criteria

- To be voluntary participants in the Subproject and understand requirements and

regulations of World Bank and the Government of Vietnam to carry out RE II Project

and RE II Project for The Additional Financing;

- To be willing to convert the communes power management model to legal local

distribution units to control LV networks;

- To have potential for economic development;

- To have an acceptable capital recovery rate;

- Revenue from power business can cover management, operation and funding costs.

1.3.2. Criteria for selection of communes for rehabilitation

- Power losses exceeds 20%; aged power networks degraded and require refurbishment;

- Power demand is substantial (over 500 households);

- Power demand for industrial production is substantial (over 20%);

- Number of electrified communes over 80%;

- Average power consumption rate power household in substantial; estimated annually

500 kWh/household.

1.3.3. Criteria for communes to be connected

- Number of households connected to power network is Provincial communes is below

the average (60%);

- Customers are able to pay cost of connection and subsequent power bills;

- Communes have potential for development in agriculture, forestry and handicraft,

which would be enhanced if electrified;

- Communes in the poorest communes list;

- Communes in the assistance program of World Bank.

- Communes are ready to adopt the management model of power network.

Page 7: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

7

Table 1.1: Subproject communes

Sr.No District/commune

I Hung Yen City

1 Thu Sy commune

2 Bao Khe commune

II Tiên Lữ District

3 Cuong Chinh commune

4 Minh Phuong commune

5 Trung Dung commune

6 Tan Hung commune

7 Nhat Tan commune

8 Duc Thang commune

9 Vuong Town

10 Ngo Quyen commune

III Phu Cu District

11 Phan Sao Nam commune

12 Tran Cao Town

13 Tien Tien commune

14 Doan Dao commune

15 Tong Tran commune

IV Kim Dong District

16 Nghia Dan commune

17 Nhan La commune

18 Tho Vinh commune

19 Song Mai commune

20 Phu Cuong commune

21 Luong Bang Town

22 Ngac Thanh commune

V An Thi District

23 An Thi Town

24 Van Du commune

25 Bai Say commune

26 Quang Vinh commune

27 Bac Son commune

28 Tan Phuc commune

29 Dang Le commune

Page 8: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

8

Sr.No District/commune

30 Quang Lang commune

31 Xuan Truc commune

VI Khoai Chau District

32 Phung Hưng commune

33 Dai Hưng commune

34 Thanh Cong commune

35 Viet Hoa commune

36 Dan Tien commune

37 Tan Dan commune

38 Tu Dan commune

39 Binh Kieu commune

40 Khoai Chau Town

41 Da Trach commune

42 Binh Minh commune

43 Ham Tu commune

44 Dong Ket commune

VII Yen My District

45 Nghia Hiep commune

46 Tan Lap commune

47 Lien Xa commune

48 Yen My Town

49 Trung Hung commune

50 Minh Chau commune

51 Yen Hoa commune

52 Hoang Long commune

53 Yen Phu commune

54 Giai Pham commune

55 Dong Than commune

56 Ly Thuong Kiet commune

VIII My Hao District

57 Ban Town

58 Phan Đinh Phung commune

59 Di Su commune

60 Nhan Hoa commune

IX Van Giang District

Page 9: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

9

Sr.No District/commune

61 Me So commune

62 Lien Nghia commune

63 Vinh Khuc commune

64 Nghia Tru commune

65 Phung Cong commune

66 Van Giang Town

67 Long Hung commune

68 Thang Loi commune

X Van Lam District

69 Trung Trac commune

70 Nhu Quynh town

71 Lac Hong commune

72 Chi Dao commune

73 Lac Dao commune

74 Dai Dong commune

Page 10: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

10

2. SUBPROJECT DESCRIPTION

Name of Project: Vietnam rural Energy II project for the Additional Financing

Location: Hung Yen

Refer to appendix 4 for subproject’s commune site.

2.1. SUBPROJECT SCALE

Medium voltage part of the Subproject is consisted of:

- New constructed MV (10kV, 22kV and 35kV) lines are 38.06 km;

- New constructed Substations (22/0.4kV and 35/0.4kV) are 90 subs

Low voltage part of the Subproject is consisted of:

- Rehabilitation LV (0.4kV) lines are 344.96 km.

NPC will be the Owner for the Subproject.

Table 2.1: Scale, site for new substation and new MV line

Sr.No District/commune MV line

(km) Sub.

LV line

(km)

Total MV, LV length and number of

Substation. 38.06 90 344.96

Of which:

I Hung Yen City 0.051 2 15.28

1 Thu Sy commune 0.03 1 11.90

2 Bao Khe commune 0.02 1 3.39

II Tiên Lữ District 4.30 5 42.30

3 Cuong Chinh commune - - 5.57

4 Minh Phuong commune 1.00 1 3.50

5 Trung Dung commune 1.50 1 5.23

6 Tan Hung commune 0.40 1 4.17

7 Nhat Tan commune - - 13.31

8 Duc Thang commune - - 9.65

9 Vuong Town 0.20 1 0.86

10 Ngo Quyen commune 1.20 1 -

III Phu Cu District 3.35 5 7.83

11 Phan Sao Nam commune 0.80 1 4.27

12 Tran Cao Town 0.40 1 3.56

13 Tien Tien commune 1.10 1 -

14 Doan Dao commune 0.35 1 -

15 Tong Tran commune 0.70 1 -

IV Kim Dong District 4.12 10 17.21

16 Nghia Dan commune 0.14 2 3.92

17 Nhan La commune 1.00 1 1.87

18 Tho Vinh commune 0.58 2 5.82

19 Song Mai commune 0.40 1 3.56

20 Phu Cuong commune 1.10 2 1.74

Page 11: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

11

Sr.No District/commune MV line

(km) Sub.

LV line

(km)

21 Luong Bang Town - 1 0.30

22 Ngac Thanh commune 0.90 1 -

V An Thi District 2.65 10 42.22

23 An Thi Town 0.15 1 0.94

24 Van Du commune 0.08 1 1.75

25 Bai Say commune 0.41 1 0.67

26 Quang Vinh commune 0.07 1 0.18

27 Bac Son commune - - 4.80

28 Tan Phuc commune 0.53 2 8.96

29 Dang Le commune 0.45 1 10.46

30 Quang Lang commune 0.92 2 6.56

31 Xuan Truc commune 0.05 1 7.91

VI Khoai Chau District 9.25 15 38.91

32 Phung Hưng commune 0.58 1 5.40

33 Dai Hưng commune 2.10 1 -

34 Thanh Cong commune 0.50 2 3.10

35 Viet Hoa commune 0.10 1 5.95

36 Dan Tien commune 0.30 1 0.20

37 Tan Dan commune 0.90 1 3.13

38 Tu Dan commune 1.80 1 2.36

39 Binh Kieu commune 0.80 1 2.97

40 Khoai Chau Town 0.80 2 1.15

41 Da Trach commune 0.90 1 5.97

42 Binh Minh commune 0.20 1 -

43 Ham Tu commune 0.12 1 8.69

44 Dong Ket commune 0.15 1 -

VII Yen My District 4.98 12 84.38

45 Nghia Hiep commune 0.40 1 5.93

46 Tan Lap commune 0.45 1 6.64

47 Lien Xa commune 1.42 1 13.94

48 Yen My Town 0.03 1 4.16

49 Trung Hung commune 0.25 1 8.08

50 Minh Chau commune 0.90 1 9.32

51 Yen Hoa commune 0.40 1 5.44

52 Hoang Long commune 0.52 2 6.44

53 Yen Phu commune 0.43 1 9.10

Page 12: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

12

Sr.No District/commune MV line

(km) Sub.

LV line

(km)

54 Giai Pham commune - - 15.14

55 Dong Than commune 0.15 1 0.10

56 Ly Thuong Kiet commune 0.03 1 0.10

VIII My Hao District 1.48 3 32.15

57 Ban Town 0.70 1 5.16

58 Phan Đinh Phung commune 0.60 1 10.88

59 Di Su commune 0.18 1 15.52

60 Nhan Hoa commune - - 0.61

IX Van Giang District 5.84 13 44.18

61 Me So commune 0.96 2 10.74

62 Lien Nghia commune 1.75 1 13.24

63 Vinh Khuc commune 1.15 2 6.57

64 Nghia Tru commune 0.30 2 5.64

65 Phung Cong commune 0.12 1 7.68

66 Van Giang Town 0.05 3 0.16

67 Long Hung commune 0.83 1 0.05

68 Thang Loi commune 0.68 1 0.10

X Van Lam District 2.05 15 20.50

69 Trung Trac commune - - 4.40

70 Nhu Quynh town 0.58 5 10.50

71 Lac Hong commune 0.16 2 4.75

72 Chi Dao commune 0.21 3 0.45

73 Lac Dao commune 0.60 4 0.30

74 Dai Dong commune 0.50 1 0.10

2.2 SUBPROJECT SCHEDULE

Table 2.2: Subproject implementation schedule

+ Investment preparation 2/2011-6/2011

+ Construction preparation 07/2011-05/2012

+ Bid of procurement equipment 6/2012-8/2012

+ Bid of procurement civil works 7/2012-10/2012

+ Implementation 11/2012-10/2013

+ Completion 12/2013

2.3. SOME OF MAIN TECHNICAL SPECIFICATIONS FOR THE SUBPROJECT

MV substation

Page 13: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

13

To reduce the investment cost, facilitate site installation and uniform project

standards, the following is to be implemented:

All new substations are designed as outdoor type pole mounted. With substation

capacity S>75 kVA two pole type construction will be used. With substation capacity

S < 31.5 kVA one pole type construction is used.

Substation requiring relocation or new pole support structures are to be built as

outdoor type, mounted on poles.

The new substations are all pole mounted, as follows:

If capacity S>= 75 kVA, mounted on two poles;

If capacity S>= 31.5 kVA, mounted on 1 pole.

Substation poles are centrifugal concrete type of 10 m or 12 m length, Class C suitable for

any requirement.

Substation base (floor) is filled 0.3 m deep with soil and covered by mixture of cement and

broken bricks

MV lines

Voltage levels: MV lines are designed to accommodate any future voltage level, defined in

the power network development and planning scheme for Hung Yen Province. In the long-

term, voltage levels 35 kV, 22 kV of MV power networks are used, in conformance with

voltage of existing 110 kV and 35/22 kV substations and transformer station to be built in

2008

Branches supplying power to transformer station at 35 kV/22kV will be connected into the

existing 35 kV/22kV lines and designed at the 35 kV/22kV voltage level.

Pole size

All poles are 10m, 12m, 14m, 16m and 20m length of classes A,B,C,D. Pole size selection is

based on the safe clearance to ground, transportation and traffic structures, crossings,

development requirements, sharing of lines for MV and LV voltages. Pole strength is selected

from load requirements.

In general, the use of poles is as follows:

For single circuit lines: centrifugal concrete pole 10m, 12m.

For double circuit lines: centrifugal concrete pole 14m.

Stayed, crossing positions and special positions: 16m, 20m poles.

Poles are manufactured to Vietnam Standards and Regulations DNT-QDKT-44/2006.

Pole foundation

To support poles, cast in situ M150 concrete foundations are used.

Page 14: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

14

In the Subproject, MT1, MT2…MT8 type foundations are used. The selection of foundations

for each position is specified in the design stage, based on estimations of local soil,

geological and hydro-geological conditions.

For sand areas, types of cast in-situ excavated foundations: MO1, MO2, MO3, MO4 are used.

For marshy land areas, foundations should be reinforced by bamboo stakes, bamboo rafts to

strengthen the bearing capacity of foundations and to reduce stress against the foundation

surround.

Foundation depth is 10-12% of pole height plus 0.3m.

LV lines

Electricity pole

Concrete poles for most lines are H-section type, cast in workshops.

For 3 phase lines and branches along inter-District, inter-commune roads: 7.5m, 8.5m pole

sizes.

For two wire branches to communes: 6.5m, 7.5m pole sizes.

For 1 phase lines into household groups: 6.5m pole size.

A-B-C type poles according to bearing requirements of each position; manufactured to the

standard DNT-QDKT-44/2006.

For poles near vehicle transport areas: use 10 m, 12 m centrifugal concrete poles to ensure

safe clearances.

For MV, LV line co-sharing positions: use MV line concrete poles.

Most concrete poles are A and B-type poles, manufactured to standard DNT-QDKT-44/2006.

Square concrete poles and circular concrete poles are used at the following positions:

Straight, corner positions of 3 phase trunk lines: single poles; and

Corner anchor, straight anchor, end anchor: double poles.

If poles are installed near households, trafficable roads, double poles should be used at corner

anchoring, straight anchoring, end anchoring positions; stayed tension poles are used only at

such high bearing positions that double poles could not solve and tension poles are

conveniently placed;

Utilize existing poles which are of good quality and satisfy the standard when installing new

conductors.

Poles under 7.5m size are not used for 3 phase trunk lines.

Poles recovered from lines are to be returned to localities to allow people to re-use poles to

support supply lines to houses.

Pole foundation

To support line poles, cast in-situ M100 concrete block foundations are used:

For single poles: use MV1, MV2

Page 15: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

15

H double poles: use MV3.

The depth of foundations is in proportion to pole heights (about 10% of pole height)

If double poles cannot satisfy the high bearing requirements and are in tension pole positions,

it is required to use:

D14 tension poles with foundation in proportion to pole height. Tension poles contain

14 round hot dipped steel according to Vietnamese Standards;

MN 15-5 anchors buried 1.5-2.0m according to bearing requirements and site clearance;

MN 10-10-7 stayed-on-the-spot anchors in sand areas.

For lines across sand areas (rivers, coastal), cast in-situ M100 concrete excavated foundations

are used, in combination with pre-cast M200 reinforced concrete round pipes with 1000,

1200, 1500 diameter.

For reused pole positions, if conductor size increased by two or more sizes, must increase

concrete in the existing foundation to ensure bearing requirements are satisfied.

2.4. SOME OF MAIN ACTIVITES FOR CONSTRUCTION AND INSTALLATION

Site clearance

- Site clearance for both the MV and LV systems is undertaken by the local

Compensation and Site Clearance Board based on ROW handover by the Consultant.

- Compensation and site clearance shall be developed right in the bid process to ensure

the schedule.

- Site clearance must duly follow the Decree on safe protection of high voltage power

grids.

Transportation

a. Long distance transportation

- For electric equipment and materials:

+ Long distance transportation from the delivery place to store of the Investor is

implemented by specialized vehicle on road. Specialized vehicle is selected suitable to the

packing of goods specified in contracts.

+ Long distance transportation from the Investors’ store to construction site is

implemented by 5 7.5 ton vehicles, loading and unloading by 5 ton crane.

- With respect to materials provided by the Contractor:

+ Pole is transported by Kawaz vans, loaded and unloaded by 5 ton crane.

+ Structures of cross-arms and beams, auxiliaries are transported by 5 ton van,

loaded and unloaded by handicraft.

+ Cement, iron and steel are transported by 5 ton vehicle, and loaded and

unloaded by hand.

+ Stone, sand, rock, etc. are transported by 5-ton dumper truck..

b. Intermediate Transportation:

Page 16: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

16

All goods must be stored at site, such as: conductors, insulators, fittings, switchgear

equipment, capacitors, meters and cement must be laid on site by primitive vehicle in

combination with handicraft method.

c. Handicraft transportation:

- All materials should be laid at site by handicraft. The laying distance of each work

item and in each locality depends on specific conditions, in general, from 30m to 1000m.

Construction and Installation work

a. Soil digging and backfill

- Digging and backfilling soil for pole foundations and anchors, earthling system by

handicraft.

- Constructing foundation hole by tamping at base in combination with layer-by-layer

tamping.

- Foundation holes are opened wit slope roof, appropriate to depth and soil kind in

accordance with regulations to ensure safety.

b. Making concrete

- All concrete of foundations and anchors is mixed by 500 litter mixer. Only LV

foundation concrete could be mixed by hand.

- Pouring concrete by hand in combination with vibrator and crowbar.

- Maintaining concrete by watering, in dry and sunny season combined with covering

sacks to keep moisture.

c. Pole erection:

- Erecting round and square concrete poles by handicraft in combination with winch,

bracket, etc.

- With respect to the line along roads, it’s possible to use crane at once when pole is

transport to construction site.

- Installation of cross-arms, insulators, guy wires is implemented absolutely by

handicraft after erecting pole.

- Laying, stringing conductor, taking sag is implemented by handicraft in combination

with winches. When laying or stringing conductor across other lines, it needs to

arrange scaffold in accordance with regulation.

- Installing transformer by 5-ton crane in combination with handicraft when

transporting transformer to construction site.

- Installing equipment of substation and meters by handicraft.

Some machines in work site

- 5-ton crane for installing transformer

- 5 ton vehicle for transporting Cement, iron and steel

- 5-ton dumper truck Stone, sand, rock

- 5 7.5 ton vehicle electric equipment and materials

- Kawaz vans for transporting pole

Page 17: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

17

- 5 ton van for transporting cross-arms and beams, auxiliaries

2.5. BRIEF DESTCRIPTION OF NATURAL AND SOCIAL CONDISTION OF THE

SUBPROJECT’S PROVINCES

Geographical position and topography

Hung Yen is a plain province in Red river region. North of Hung Yen is Bac Ninh.

South of the province are Ha Nam and Thai Binh provinces, East side is Hai Duong province,

West is Ha Noi

Natural area of Hung Yen is 89,084 ha.

Population of Hung Yen is 1,116,000 people. All people in Hung Yen province are Kinh .

Hung Yen is consisted of 9 districts and one city. Hung Yen city is the center of the province.

Climate

Hung Yen has monsoon climate and has its specific characteristics. There are four different

seasons in the years, but two main seasons are

Hot season with temperature ranging from 25 to 27 oC, hottest month is in July;

Cool season with temperature ranging from 14 to 18 oC, coolest month is January.

Average rainfall: 1,450 mm to 1,650 mm

Average humidity: 85% - 87%

Land resource

Total natural land: 89,084 ha

Agricultural land: 50,867 ha

Use land: 15,305 ha;

Resident land: 6,539ha

Waste land: 7,305ha

Water resource

There are two big rivers crossing Hung Yen province, they are Red river, Luoc river

and some small other river are Sat, Chanh, Cuu An, Tam Do, Dien Bien rivers

Economic structure: Hung Yen Economic includes three main components, Agriculture,

Industry and service. In 2005, total GDP of province reaches 5,331 bil.VND, of which:

Agriculture is 32.5%, Industry is 35.5% and service is 32%

Agricultural and husbandry: rice cultivation, dry crop, fruits, tea etc.

Page 18: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

18

2.6. INVESTMENT STRUCTURE OF THE SUBPROJECT

Table 2.3: The investment structure of the Subproject (VND)

Items Amount

1 Construction work 90,347,686,030

2 Equipment 15,425,228,580

3 Other 12,397,188,963

4 Contingencies 11,817,010,357

Total 129,987,113,931

Page 19: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

19

3. LEGAL FRAMEWORK FOR SUBPROJECT’S ENVIRONMENTAL IMPACT

ASSESSMENT

3.1. VIETNAM REGULATIONS AND LAWS

The following laws and regulations are applied for subproject:

- Law on Protection of the Environment No. 52/2005/QH11 passed by the National

Assembly, dated 29 November, 2005 regulating the responsibilities of individuals,

organizations regarding environmental protection.

- Decree of Vietnamese Government No.80/2006/ND-CP dated 9 August, 2006 on

detail regulations and guidance on the implementation of some Articles of the

Environment Protection Law.

- Decree of Government No.21/2008/ND-CP dated 28 February, 2008 on revision and

addition of some Articles of Decree 80/2006/ND-CP dated 09 August 2006.

- Decree of Vietnamese Government No.29/2011/ND-CP dated 18 April, 2011

regarding regulations on strategic environmental assessment, environmental impact

assessment and environment protection commitments.

- Circular No.26/2011/TT-BTNMT dated 18 July, 2011 detailing some articles of

Decree No.29/2011/ND-CP dated 18 April, 2011 regarding regulations on strategic

environmental assessment, environmental impact assessment and environment

protection commitments

- Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on detailed

regulations and guidance on implementation of some Articles of the Law on

Electricity related to safe protection of high voltage networks.

- Decree of Government No.81/2009/ND-CP dated 12 October, 2009 on revision and

addition of some Articles of Decree 106/2005/ND-CP dated 17th August 2005 on

detailed regulations and guidance on implementation of some Articles of the Law on

Electricity related to safe protection of high voltage networks.

- Circular No.12/2011/TT-BTNMT dated 14 April, 2011 regarding the management of

hazardous wastes.

- National Technical Regulations: QCVN05: 2009/BTNMT – Air quality – Standard

for ambient air quality; QCVN 26:2010 – National technical regulation on noise

3.2. WORLD BANK SAFEGUARD POLICIES

- OP/BP 4.01 Environmental Assessment;

- OP/BP 4.12 Involuntary Resettlement;

- The World Bank policy on access to information

Page 20: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

20

Detailed guidance on assessment methodologies and common impacts associated with

transmission subprojects are found in:

World Bank, 1991. Environmental Assessment Sourcebook, Volume 3.

IFC, 2007 Environmental, Health, and Safety Guidelines on Electric Power Transmission

and Distribution.

Framework for Applying Environment Safeguards to Rural Energy II Project and Rural

Energy II Project extension.

Page 21: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

21

4. ASSESSMENT OF ENVIRONMENTAL IMPACTS

4.1. CLASSIFICATION OF IMPACTS

The Environmental Impact Assessment focuses on the major environmental issues of

the Project’s Most Favoured Alternative. The potential impacts of the Project’s pre-

construction, construction, and operation phases were assessed as being in one of four

categories:

i. NO IMPACT. The potential impact of the Project activity is assessed as NO

IMPACT if the project activity is physically removed in space or time from the

environmental component.

ii. MAJOR IMPACT. An impact is said to be MAJOR if the project activity has

potential to affect an environmental component. Major impacts could be “Major

Negative” or “Major Positive.” The following criteria were used to determine whether

a given impact is MAJOR:

a) Spatial scale of the impact (site, local, regional, or national/ international);

b) Time horizon of the impact (short, medium, or long term);

c) Magnitude of the change in the environmental component brought about by

the Project activities (small, moderate, large);

d) Importance to local human populations;

e) Compliance with national, provincial, or district environmental protection

laws, standards, and regulations

f) Compliance with Vietnam’s international commitments. These include the

Convention on Wetlands of International Importance especially as Waterfowl

Habitat (RAMSAR), the Convention Concerning the Protection of the World

Cultural and Natural Heritage (World Heritage Convention), and the

Convention on International Trade in Endangered Species of Wild Fauna and

Flora (CITES); and

g) Compliance with World Bank guidelines, policies, and regulations.

iii. MINOR IMPACT. If an impact occurs but does not meet the criteria for a Major

Impact it is assigned the category MINOR. Minor impacts could be “Minor negative”

or “Minor Positive.”

iv. MITIGABLE IMPACT. The potential impact of a project activity on an

environmental component is said to be MITIGABLE if there is potential for a major

negative impact and the proposed mitigation measure will prevent the impact or

reduce the impact to acceptable levels.

4.2. IDENTIFICATION OF POTENTIAL IMPACTS OF THE SUBPROJECT

The Subproject will play an important role in the electrification program and in

implementation of the policy of poverty alleviation of 74 communes within 10 districts of

Hung Yen province. It will also promote the policy of industrialization and modernization of

the Government of Vietnam as well as create a great opportunity for overall socio-economic

development of the poor area.

When the distribution lines are constructed, there is a trend of local people to move to

live near the lines. The local people committee will have a proper planning accordingly to

support the development of the areas. These planning are included: road, residential area,

Page 22: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

22

industrial development and farming etc. The communes/districts will move toward its

planning.

Beside the significant beneficial impacts, the subproject may cause different adverse

impacts on the environment and local socio-economy. By using Environmental Screening

Data Checklist and Environmental baseline Checklist as guided in Framework for Applying

Environment Safeguards to Rural Energy II Project, The potential impacts of the Project are

described in Table 4.1.

Page 23: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

23

Table 4.1: The assessment of Subproject's impacts

No Impact Magnitude Description of the impacts

Pre-construction phase

1 Permanent and temporary land

acquisition

Along the route,

inside the ROW

- 652 m2 of Productive land will be permanently occupied.

- 3,172 m2 of Productive land will be temporarily occupied.

- Refer to Appendix 8 for more information and supporting – data;

- This impact is not significant in consideration with wide range of the

Subproject: 74 communes in 10 districts; more than 230,130 HHs will be

supplied electricity by the Subproject; this land is taken from 202 HHs

permanently and from 358 HHs temporarily.

2 Impact on Subproject affected

household

HHs have land

inside the ROW

-202 HHs will lose their land permanently;

- 358 HHs will have land that is temporarily occupied;

- Refer to Appendix 8 for supporting data;

- During designing of the Subproject, the alignment has been carefully

considered in order to avoid crossing houses and other structures; wrong

positioning of poles; minimizing temporary and minimizing land

acquisition.

3 Impacts associated with clearing

the ROW

Along the route

and inside the

ROW

- All of parts of trees that are higher than 4m need to be cut. The trees are

still remained.

- The lines are not going through any forested areas or areas with highly

ecological value.

- Acquired lands are mainly un-used land along the existing road, crossing

agricultural fields with very low ecological values.

- See Appendix 8 for information on number of trees to be cut. These trees

Page 24: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

24

No Impact Magnitude Description of the impacts

have value in economics (fruit trees) rather than environmental.

4 Health risk due to explosives,

chemical hazard

Subproject area - The area is very intensively used by local government and people. There

is no risk of explosives;

- No hazardous chemicals are used in the Subproject.

5 Loss of historical and cultural

properties

Subproject area - The routes are designed to avoid temples, churches and other cultural,

historical properties in the areas, so the Subproject will not effect any

cultural heritages

- During construction if there is any valuable historical or cultural

properties are found underground, the Contractor and Subproject owner

will report to local Department of Culture and information for further

consideration.

Construction phase

6 Surface water contamination At new pole’s

foundation,

Worker’s camp

- The water can be more turbid due to the soil residue from excavation of

the pole's foundation will enter to the water bodies by water run off.

7 Noise and vibration Subproject area,

work site

- Noise levels during construction will be required to comply with

Vietnamese standard QCVN 26:2010. Use of construction machinery will

be limited due to the small scale of the Subproject (distribution as opposed

to transmission lines), and the very short period of time involved in

construction activities.

- Noise and vibration are caused by: equipment, material transportation,

Subproject's vehicles, pole's erection and cable's pulling, generators (if

there is any)

8 Soil erosion New pole’s

foundation

- Soil excavation for pole's foundation;

- Vegetation cover is reduced due to ROW clearance and access roads’

construction.

Page 25: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

25

No Impact Magnitude Description of the impacts

- Subproject’s sites are in plain areas or in plain position, so the risk of soil

erosion is not high.

- In terms of soil erosion, the impact is considered to be minor due to the

small scale of the activities involved, the limited period over which they

will occur, and the spatially small areas to be affected. Furthermore, these

impacts could be reduced to less than minor with implementation of

mitigation measures

9 Air pollution Subproject area,

work site, local

roads

- Dust generated from soil excavation, especially during dry seasons.

- Dust caused by movement of vehicles transporting material and

equipment for Subproject construction.

10 Agricultural production due to

temporary acquisition of

productive land

Along the route,

inside the ROW

- Some of productive land will be required for a short period for

construction.

- Refer to Appendix 8 for supporting data

11 Traffic disturbance Subproject area,

local roads

- Transportation of material and equipment, soil excavation and cable

pulling activities will disturb the normal traffic in the areas during short

period of time;

- Equipment will be transported from receiving port to warehouses of the

Project owners by special trucks;

- From warehouses to construction the goods are transported by truck 5 to

7.5 tons and unloaded by 5 tones cranes;

- Construction materials will be transported by 10 to 12 tones trucks;

unloaded by 5 tones cranes;

- Steel constructions are transported by 5 tones trucks; unloaded by man

power;

- Road system in Hung Yen is very good so transportation will be very

Page 26: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

26

No Impact Magnitude Description of the impacts

convenient and will cause less impact to local traffic;

- Construction work will be mainly carried out along the rural roads with

high gathering of poles, construction materials. It will cause disturbance to

traffic in rural areas as well. But this disturbance in quite minor since the

construction duration at each site is short, rural transportation is not very

intensive and mainly by rudimentary vehicles like bicycles, motorbikes,

etc.

- Cable pulling crossing the roads can cause disturbance to transportation

also. But scaffolds are required in these crossing sections and will reduce

the traffic disturbance.

12 Road degradation Local roads - Heavy loaded vehicles might degrade the existing roads, which usually

are not very good in rural areas.

13 Biological environment impacts Along the route,

inside the ROW

- Some of trees will need to be cut. But these trees are common planted

species like agricultural or fruit trees.

- Some of insects are small animals will lose their habitat but the insects

and animals are common species. Area of loose habitats is small in

comparison with entire affected ecosystem. Main ecosystems that are

affected by the Subproject is agricultural, shrub trees along the roads etc.

- The trees that will be cut by the Subproject is mainly fruit trees, trees

along the roads, they have economic value rather than environmental

value.

14 Solid waste generated from soil

excavation

New pole’s

foundation, work

site

- The soil and construction materials can remain in the site;

- Contractors need to commit to return the working sites to the original

conditions and clean up the construction sites.

15 Environmental impacts caused

by construction worker

Subproject area,

worker camps

- Solid waste, wastewater disposal and hygiene condition.

- Possible dissemination of certain diseases from construction workers to

local people and vice versa.

Page 27: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

27

No Impact Magnitude Description of the impacts

16 Conflict between construction

worker and local people

Subproject

communes

- The conflicts might cause by difference in incomes, cultures, behaviors;

- Duration of construction work is very limited (about 6 months); local

people will be hired for simple work, only skill staff from other locations

are hired to do professional work; it estimated that the group of 15 persons

will be formed for each working team; so all of these figures reveals that

the risk of conflict is not very high and serious.

17 Health and Safety Work site,

Subproject area

- Accidents might happen during construction if the safety issues are not

well considered.

Operation phase

18 Development and poverty

alleviation

Subproject area - Increase the quality of life for local peoples.

- Support agricultural production and other services including health and

education

19 Habitat fragmentation and

increase access to wild lands

Subproject area - No new road or access roads are constructed

- No line crossing the forest, wetland or other natural habitats.

20 Health and safety Subproject area - Electric shock and accidents occurring if the proper safety issues are not

paid proper attention

21 EMF Subproject area - With voltage just up to 35 kV, the EMF is not a problem.

22 Impacts on aircrafts Subproject area - The height of pole is less than 50 m. There will not be any problem with

avian and aircrafts

23 Oil hazardous waste

contamination

Subproject area - The Subproject has the potential to cause oil contamination from leakage

from transformers. The transformers used are small, with a 20 liter or less

capacity. Operation records for similar transformers show that the chance

of container breakage that could cause an oil spill is almost zero.

Therefore, a risk of oil contamination caused by the Subproject from either

of these two sources is extremely low, if not negligible.

Page 28: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

28

No Impact Magnitude Description of the impacts

- No PCBs containing oil and other hazardous chemicals will be used.

- Oil refilling should be done in workshop

Page 29: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

29

5. ENVIRONMENTAL MANAGEMENT PLAN

Table. 5.1. Mitigation measures applied for the Subproject

No Impact Mitigation measures applied

Pre-construction phase

1 Permanent and temporary land

acquisition

- Careful site survey, consult with local peoples for optimum route selection.

- Avoid ecologically high value areas (forest, reserve area, wetland etc.).

- Proper compensate the impacts.

2 Impact on Subproject affected

household

- Routes should be selected to minimize the need to relocate houses

- Increase the span between towers, increase the tower height, use hanging substation etc. to minimize the

impacts on Subproject affected households.

- Compensate for the impacts.

3 Impacts associated with clearing

the ROW

- Work with Subproject affected households during clearance of ROWs to minimize impacts to

surrounding trees and other constructions;

- Not allow using any herbicides and defoliant to clear the trees within ROWs.

- Not allow burning the wooden residue after tree cutting.

4 Health risk due to explosives,

chemical hazard

- Not necessary to apply any mitigation measure

Construction phase

5 Surface water contamination - Soil excavation is managed to carry out in the shortest period.

- Construction material will be kept in the store with cover to protect from rain.

- Select a right place for concrete mixing.

- Residue from earthwork should be removed from the site to proper places (soil residue can use for

garden filling; concrete residues are removed by contractor to the permitted places).

Page 30: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

30

No Impact Mitigation measures applied

6 Noise and vibration - Use the construction machines that have noise level under permitted limits.

- Carefully consider night work. No night work is permitted to carry out in populated and sensitive areas

like hospital, residential, student camp.

7 Soil erosion - Excavate and earth-moving activities in erosion prone areas will be schedule in the dry seasons, after the

harvest time and during the shortest duration of time.

- Land surface recovery after the pole erection.

8 Air pollution - Minimize the construction time in each site. Spray water regularly on dirt piles and any other areas that

could create dust

- Use wind fences in case of strong wind.

- Minimize use of diesel generators.

9 Agricultural production due to

temporary acquisition of

productive land

- Carry out the construction work after harvest time.

- Compensate for the loss of agricultural productivity

- Return the construction areas to the useful state after the work.

10 Traffic disturbance - Minimize the construction work (excavation, cable pulling) in traffic intensive sites.

- Use warning signs in construction sites.

- Cooperate with local authority for traffic arrangement.

- Avoid high-traffic areas

11 Damaging the existing road

system

- Construction Contractor needs to commit to not use heavy vehicles that might cause damage to the

existing road system in the area.

- Not allow vehicles with heavy load of construction material and equipment to enter the road system. The

load should be separated to acceptable levels that the road can resist for.

- Repair the road when there is any damage occurred.

12 Solid waste generated from soil - Construction contractor need to commit to clean the site and disposal solid waste in the permitted places.

Page 31: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

31

No Impact Mitigation measures applied

excavation - Reuse as much as possible an excavated soil for refilling foundation.

13 Environmental impacts caused by

construction worker

- Minimize the impact of solid waste: Solid waste should be disposed properly by local collecting system

or dumping in permitted areas of communes.

- Arrange hygiene toilets for workers;

- Provide clean water for camping areas. Control discharge of waste water from camping sites. Not allow

discharge waste water directly to clean water sources such as rivers, stream, which are supplying water for

residential areas.

14 Conflict between construction

worker and local people

- Hire as much as possible local citizens for the simple construction work to avoid the influx of migrants.

- In cases where the worker camps are near the communes, the Employer could request that the Contractor

provide accurate, timely and regular information about the construction team to the People’s Committees

in affected areas. With open communication and information, the People’s Committee and Contractor will

be able to make a joint informed decision about the management of construction team accommodation.

- Rectify the impact: The general conditions of Contract should state: after the Subproject finished, all

camps will be completed removed and the campsites will be rectified to their original conditions.

15 Health and Safety - Organize the health care service in each group of workers.

- Inform workers the safety regulations and procedures, do not hire any local people who are not trained

in working safety

- Equip safety facilities for the workers, prohibit unauthorized persons entering construction sites,

especially dangerous areas.

Operation phase

16 Development and poverty

alleviation

- Not necessary to apply any mitigation measure

17 Habitat fragmentation and increase

access to wild lands

- Return unnecessary access roads to the previous state.

Cooperate with local Department of Forest to regular control the use of access roads by local people in the

remote or forested areas.

Page 32: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

32

No Impact Mitigation measures applied

- Train electrical technicians and local peoples about the way to handle with any bird net meet during

ROW clearing.

18 Health and safety - Disseminate the information on electricity safety regulations to the users.

- Follow the regulation of Government on network protection.

- Regular training for local technicians and people on safety issues.

- Not allow burning the woody residues after ROW clearing.

19 Reduction of air pollutants

generated by diesel generators

- Not necessary to apply any mitigation measure

20 EMF - Not necessary to apply any mitigation measure

21 Impacts on avian and aircrafts - Not necessary to apply any mitigation measure

22 Oil hazardous waste contamination - Oil refilling of transformers should be done in the Workshop.

- No PCBs will be used.

Page 33: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

33

Table 5.2: The Measures applied for managing the social impacts

TT Contents Measures

1

Information and media programs

This program must be informed to local authorities and local people at the time subproject started through

the public consultation meeting or the public media During construction phase, information of subproject,

Contractor, construction plan and hot line to resolve all complains of environment and social will be

published at the work site or commune office

2 Compensation and complain

policies.

Compensation and complain policies will be implemented under WB’s policy and Regulation of Viet

Nam

Pls. see RP report for detail

3 Monitoring and evaluation system

The implementation of EMP and RP will be monitored and evaluated day to day by NPC and local

authorities. Inside, an agency of independent monitoring will be hire to external monitoring during the

implementation of EMP and RP.

Page 34: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

34

6. ENVIRONMENTAL MONITORING

Table 6.1. Monitoring of mitigation measures

Issues Location Methods

Construction phase

1. Dust generation mitigation Work site, material dump site, material transportation Observing

2. Air pollution mitigation Transportation and construction machine at work site

such as machine of mixing cement ...

Observing

3. Noise mitigation Work site, local roads through residential and/or

sensitive areas

Observing and Consultation

with local residents

4. Wastewater mitigation Work site, worker camp Observing

5. Erosion and sedimentation mitigation Work site, material warehouse, worker camp and river,

stream, lake near the work site

Observing

6. Managing material warehouses and

borrow areas

Contractor warehouse, pole’s foundation Observing

7. Solid wastes and hazardous wastes

mitigation

ROW, Worker camp, work site, construction machine Observing

8. Vegetation clearance mitigation Along the route inside the ROW Observing

9. Traffic congestion mitigation Rural roads in the subproject area Observing, consulting the

local residents

10. Disruption of regular activities and

services

Residential areas Consulting the local

Authorities and residents

11. Restoration of the affected areas Waste disposal areas, worker camp, warehouse, work Observing and Consulting the

Page 35: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

35

Issues Location Methods

site, rural roads and borrow pits local Authorities and

residents

12. Labor and public safety Work sites Observing, Consulting the

worker, base on provisions of

Vietnam’s labor safety.

13. Information and communication Subproject communes Consulting the local

Authorities and residents

14. Chance finds Work site Observing

Operation phase

1. Health and safety with operation workers

and local resident

Subproject area Consulting the worker and

local residents

2. Risk of incidents, fire Subproject area Consulting the worker and

local residents

Page 36: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

36

Table 6.2. Monitoring of environmental quality (if necessary)

Determination Parameter Location Methods The timing/frequency

1. Ambient Air

quality

- PM10, CO, SO2, and NOx Construction sites and

transportation routes near

residential areas (to be

determined)

Use of specialized

equipment

During construction phase

when it is large wind

2. Noise Leq (dBA) Residential areas near

construction sites (to be

determined)

Use of sonometer Complaints by local

residents during

construction phase

Page 37: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

37

7. ARRANGEMENT FOR ENVIROMENTAL MANAGEMENT PLAN

IMPLEMENTATION

7.1 ARRANGEMENT FOR EMP’S IMPLEMENTATION

The responsibilities for implementing Environmental Management Plan as following:

Table 7.1: Arrangement for EMP’s implementation

UNIT RESPONSIBILITIES

Subproject Owner (NPC

through PMU)

Ultimately responsible for overall subproject

management, including environmental management.

Coordination and management of overall Subproject

implementation,

Preparing, guiding and supervising implementation of

the EMP.

Responsible for operation of the Subproject including

operation stage environmental management and

monitoring activities.

Resolving grievances from affected communities

Civil Works Contractor Responsible for compliance and implementing of

mitigation measures in the EMP. This includes:

+ Applying mitigation measures for potential negative

impacts as described in the EMP

+ To actively communicate with local resident and to

prevent disturbances for social and environment during

the construction phase.

+ Reporting on problems and solutions to the PMU.

+ Reporting to local government and the PMU if the

environmental accidents occur and coordinate with

other agencies and parties to resolve.

Offering changes of the mitigation measures when they

are unsuitable to the subproject

Local Authority Review, appraise and approve the EMP for this

subproject

Supervise compliance with environmental protection

measures as indicated in the EMP report

Receive grievances related to the subproject

implementation from local communities and work with

the subproject owner to resolve these grievances

Affected Community Monitor compliance with mitigation measures

conducted by civil contractors

Provide information about environmental and social

Page 38: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

38

UNIT RESPONSIBILITIES

issues related to the subproject implementation that

need to be further addressed for PMU

Feedback to local authorities/Subproject owner about

EMP report and non-complying mitigation measures by

Contractors

7.2 REPORTING PROCESS

Reporting responsibilities and frequency for the EMP implementation described in the table

below:

Table 7.2: The environmental reporting requirement

No. Item Reported by Submitted to Frequency

1 Implementation of

mitigation measures

and site

environmental

management

Contractors NPC’s PMU Once before starting

construction and then

once a month.

2 Monitoring of

implementing

mitigation measures

and environmental

management

NPC’s PMU NPC’s and

WB

Every six months

7.3 CAPACITY DEVELOPMENT AND TRAINING

The following training has been conducted to date:

1) May 2002: Training Workshop on preparation of EIA reports for power transmission

and distribution projects

2) August 2003: Hands-on learning-by doing training for improving environmental

reports.

3) September 2003: Hands-on workshop for environmental assessment of transmission

and distribution projects.

4) May 2004: Training on preparation of EMP according to newly environmental

templates developed by WB experts.

5) November 2004: Launch workshop for RE 2 projects. One important section of the

workshop is implementation of EMP for Rural Energy projects.

6) July 2005: Training on social assessment and resettlement issue in transmission and

distribution projects under the WB loans.

Future training includes the following:

Page 39: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

39

1) Workshop on sharing experience of EMP implementation for PMU staffs and

contractors. This training is planned to carry out before implementing construction by

NPC’s PMU.

2) Training on Monitoring EMP implementation for project commune authorities and

Affected Community according to WB requirement by NPC’s PMU before

implementing construction.

3) Annual regular training of NPC’s PMU on safety issue for staff

4) Annual regular information dissemination for local people on electricity safety by

local Power.

Page 40: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

40

8. COST ESTIMATION FOR IMPLEMENTATION OF EMP

Table 8.1: The cost estimation for future trainings

No Training Cost (VND)

1 Workshop on sharing

experience of EMP

implementation for PMU

staffs and contractors

20 persons x 1 day x 1,000,000 VND/person =

20,000,000 VND

(including 5 PMU staffs and about 15 staffs of

Contractors)

2 Training on Monitoring EMP

implementation for subproject

commune authorities and

affected communities

1 persons/commune x 1 day x 500,000 VND/person x 74

communes = 37,000,000 VND

TOTAL 57,000,000 VND

Table 8.2: Estimated costs for implementation of the EMP (VND)

No Item Amount

1 Mitigation measures Included in construction cost

2 Monitoring costs Included in construction cost

3 Training costs 57,000,000

TOTAL 57,000,000

Page 41: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

41

9. PUBLIC CONSULTATION AND DISCLOSURE

9.1 PUBLIC CONSULTATION

9.1.1 Consultation Measure and information consultation

During preparation stage of the Subproject started from earlier April 2010, 74

meetings with local authorities and local residents at 74 Subproject communes were carried

out in order to consult public on subproject and EMP

The contents of the meetings include:

- General information about Subproject: Name, Subproject owner, scale of Subproject,

Subproject districts and communes;

- Potential environmental impacts that may cause by the Subproject;

- Mitigation measures that will be applied in order to minimize environmental impact;

- Time schedule for Subproject implementation.

- Contact address for receiving of public comments on environmental concerns of the

Subproject.

9.1.2 Time and Place of the meetings

Sr

No District Place Time of Meeting

1. Hung Yen city All of the Office of Commune

People Committee 01/4/2010-02/4/2010

2. Tien Lu All of the Office of Commune

People Committee 01/4/2010-03/4/2010

3. Phu Cu All of the Office of Commune

People Committee 03/4/2010-05/4/2010

4. Kim Dong All of the Office of Commune

People Committee 01/4/2010-04/4/2010

5. An Thi All of the Office of Commune

People Committee 03/4/2010-07/4/2010

6. Khoai Chau All of the Office of Commune

People Committee 05/4/2010-17/4/2010

7. Yen My All of the Office of Commune

People Committee 09/4/2010-18/4/2010

8. My Hao All of the Office of Commune

People Committee 20/4/2010-25/4/2010

9. Van Giang All of the Office of Commune

People Committee 22/4/2010-28/4/2010

10. Van Lam All of the Office of Commune

People Committee 24/4/2010-29/4/2010

9.1.3 Participants

The Participants of the meetings include representatives of the Commune People Committee,

Farmer Association, Women Association , and other public organizations, hamlet chiefs,

representatives of Subproject’s affected households, and consulting agency

Page 42: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

42

9.1.4 Comments from the Participants

Main comments received from participants are summarized as bellows:

- Construction work should carry out in dry season, after harvesting;

- Contractor should clean and return construction sites to the previous condition;

- Consultant should inform local about construction work as soon as they can so people

can have a plan to harvest agricultural products in their affected lands.

- Avoid carrying out construction work in steep sites to avoid soil erosion.

- Subproject owner should pay compensation before construction period.

- Contractors and Consultants should inform soon about land acquisition so affected

peoples can have their working plan in un- affected land

- Related parties should consider reducing the electricity tariff for farmers in this area.

- Head and responsible people of the villages should convince people to release the

land on time for Contractor;

- Compensation should be done equally and clearly

- There is a need to support households that are heavily affected by the Subproject

- Construction work should be planned to carry out in the shortest time to avoid losses

in agricultural production.

All local authorities and local people are willing to implement the subproject as soon as

possible;

9.1.5 PMU’s Feedback

The environmental impact of subproject is not serious due to the nature of the impact

is small and the scope is reasonable

The mitigation measures will be presented in the EMP as part of this report. The

mitigation measures will be incorporated in the tender documents that the contractor must

comply and the contractor shall submit an organizational chart of the construction site,

construction methods and mitigation measures for investors to approve the bidding results

The construction contractors will have to report the organizational chart of

construction site, make the temporary residence statement for workers and coordinate with

local government to administer these workers

The Subproject team will complete all procedures for preparing the Subproject

investment and require the investor to arrange capital for the subproject

All of the concerns, comments of local people were recorded and considered by

consultants and Subproject’s owner during designing of the Subproject and development of

EMP for the Subproject.

Page 43: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

43

9.2 DISCLOSURE

The Vietnamese copies of EMP report, RP and the subproject summary will be sent to

the local authorities (district level and commune level) for disclosure at the subproject area.

The expected time will be in the end of July, 2012

The English and Vietnamese copies of EMP report will also be sent to the World

Bank for disclosure in the VDIC and InfoShop. The time for disclosure is estimated in July,

2012.

Page 44: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

44

REFERENCES

1 Draft of Resettlement Action Plan of the Project, 2009

2 Environmental Status Report of Hung Yen province in 2008 - DoNRE

3 World Bank Environmental Assessment Source Book

4 Statistical Yearbook 2008 – Statistical Publisher

5 Sourcebook of Protected Areas in Viet Nam – Bird Life International

6 Subproject's feasibility study

7 Framework for Applying Environment Safeguards to Rural Energy II Project- WB 2004.

Page 45: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

45

APPENDIX 1

--------------------

LIST OF EIA PREPARERS

1 Tran Van Khuong Vice Director

2 Nguyen Xuan Hai Staff

3 Trinh Phan Sinh Staff

4 Pham Van Toan Staff

5 Chu Sy Binh Staff

Page 46: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

46

APPENDIX 2

--------------------

PROJECT'S ENVIRONMENTAL PERMIT

Page 47: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

47

Page 48: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

48

APPENDIX 3

--------------------

EXAMPLE RECORD OF PUBLIC CONSULATION

FOR ENVIRONMENT IMPACT ASSESSMENT

Page 49: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

49

Page 50: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

50

Page 51: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

51

Page 52: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

52

Page 53: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

53

Page 54: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

54

Page 55: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

55

Page 56: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

56

Page 57: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

57

Page 58: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

58

Page 59: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

59

Page 60: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

60

Page 61: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

61

Page 62: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

62

Page 63: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

63

Page 64: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

64

Page 65: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

65

Page 66: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

66

Page 67: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

67

Page 68: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

68

Page 69: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

69

Page 70: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

70

Page 71: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

71

Page 72: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

72

Page 73: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

73

Page 74: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

74

Page 75: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

75

Page 76: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

76

Page 77: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

77

Page 78: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

78

Page 79: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

79

Page 80: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

80

Page 81: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

81

Page 82: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

82

Page 83: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

83

Page 84: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

84

Page 85: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

85

Page 86: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

86

Page 87: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

87

Page 88: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

88

Page 89: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

89

Page 90: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

90

Page 91: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

91

Page 92: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

92

Page 93: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

93

APPENDIX 4

--------------------

MAP OF PROJECT IN HUNG YEN

Subproject’s commune site/

vị trí các xã thuộc dự án

Page 94: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

94

APPENDIX 5

--------------------

EXAMPLE COMMUNE-LEVEL DATA REPORT FORMAT

Project’s Commune

Reporting Period

Environmental Impacts:

Impact / Mitigation Measure Commune

Representative

Comments

Community

Comments

Project vehicles or activities increased ambient dust levels

Project vehicles or activities increased ambient noise

levels

Project activities polluted local rivers or lakes

Project cleared vegetation and this caused environmental

impacts

Project activities created impacts on agricultural and/or

residential land

Project activities impacted cultural property

Project construction caused traffic impacts

Project caused solid waste or liquid waste impacts

Project caused Social and health impacts of workers

Accidents

Dust suppression measures

Erosion and sediment controls

Sitting of materials etc. to avoid exacerbation of flood

effects, chemical pollution etc.

Waste management practices

Project activities caused any impact on birds, animals and

rare flora

Project vehicles damaged the roads

Other

Recommendations

......................................................................................................................................................

......................................................................................................................................................

......................................................................................................................................................

......................................................................................................................................................

Signature of Commune Representative:

Title of Commune Representative:

Date:

---------------------------------------------------------------------------------------------------

Page 95: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

95

APPENDIX 6

--------------------

Example of Site Environmental Management Monitoring Report

(Applied for Contractor’s Report)

Project name: Project location:

Name of Contractor:

Commencement of Project report or monthly report:

Date of report:

No Impact Mitigation measures implemented Comment

Construction phase

1 Surface water contamination

2 Noise and vibration

3 Soil erosion

4 Air pollution

5 Agricultural production due to

temporary acquisition of

productive land

6 Traffic disturbance

7 Damaging the existing road

system

8 Solid waste generated from

soil excavation

9 Environmental impacts caused

by construction worker

10 Conflict between construction

worker and local people

11 Health and Safety

Name of person prepared this Report:

Title:

Address: Telephone:

Page 96: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

96

APPENDIX 7

--------------------

Example of Environmental Performance Monitoring Report

(This Example can be used for environmental monitoring report of Technical

supervisor consultant, SMIC)

Project name:

Project location:

Type of Report:

Monthly report (Yes/No): Quarterly Report to PMU (Yes/No):

Quarterly Report to the WB (Yes/No): SMIC report (Yes/No):

Date of report:

N

o

Parameter Assessment of

Consultant/ community

complaints

Comments/

Recommendations

During Construction

1 Surface water turbidity and soil erosion

2 Noise level around construction sites and

adjacent residential areas

3 Dust

4 Tree cutting and access roads management

and control

5 Solid waste and site cleaning up after the

construction

6 Workers' sanitation facilities and safety

management

7 Transportation disturbance

8 Road degradation

9 Status of application of safety measures

10 Construction material management

11 Management of redundant soil

12 Impact on wild life and natural resources

13 Evidence of biodiversity loss (if there is

any)

14 Evidence of loss of historical and cultural

properties

15 Other environment related issue (if there is

any)

During operation

16 Maintaining of ROW

Page 97: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

97

N

o

Parameter Assessment of

Consultant/ community

complaints

Comments/

Recommendations

17 Impact on wild life and natural resource

Report prepared by: Position:

Page 98: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

98

APPENDIX 8

--------------------

SUMMARY OF SUBPROJECT IMPACTS

1. Summary of Land acquisition by the Project

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Productive land Other

Grand total 202 652 1,967 2,619

Hung Yen City

1 Thu Sy commune 1 2 6 8

2 Bao Khe commune 3 8 24 32

Sub_total 1 4 10 30 40

Tiên Lữ District

3

Cuong Chinh

commune 1 2 6 8

4

Minh Phuong

commune 4 8 24 32

5

Trung Dung

commune 1 5 15 20

6

Tan Hung

commune 2 6 18 24

7 Nhat Tan commune 2 6 19 25

8

Duc Thang

commune 1 1 4 5

9 Vuong Town 3 7 21 28

10

Ngo Quyen

commune 2 6 18 24

Sub_total 2 16 42 125 167

Phu Cu District

11

Phan Sao Nam

commune 3 15 45 60

12 Tran Cao Town 2 5 16 21

13 Tien Tien commune 4 6 19 25

14

Doan Dao

commune 4 10 31 41

15

Tong Tran

commune 2 3 8 11

Sub_total 3 15 39 119 158

Kim Dong District

Page 99: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

99

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Productive land Other

16

Nghia Dan

commune 2 4 12 16

17 Nhan La commune 4 17 50 67

18 Tho Vinh commune 3 12 36 48

19 Song Mai commune 2 7 21 28

20

Phu Cuong

commune 1 4 12 16

21 Luong Bang Town 3 12 36 48

22

Ngac Thanh

commune 4 9 28 37

Sub_total 4 19 65 195 260

An Thi District

23 An Thi Town 2 3 9 12

24 Van Du commune 3 9 27 36

25 Bai Say commune 2 8 24 32

26

Quang Vinh

commune 4 11 32 43

27 Bac Son commune 1 3 9 12

28 Tan Phuc commune 3 10 30 40

29 Dang Le commune 1 6 17 23

30

Quang Lang

commune 2 7 20 27

31

Xuan Truc

commune 3 7 22 29

Sub_total 5 21 63 190 253

Khoai Chau

District

32

Phung Hưng

commune 2 7 22 29

33

Dai Hưng

commune 4 12 36 48

34

Thanh Cong

commune 4 12 35 47

35 Viet Hoa commune 5 14 42 56

36 Dan Tien commune 2 5 14 19

37 Tan Dan commune 4 11 34 45

38 Tu Dan commune 2 12 36 48

Page 100: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

100

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Productive land Other

39

Binh Kieu

commune 3 11 34 45

40 Khoai Chau Town 2 13 40 53

41 Da Trach commune 4 14 43 57

42

Binh Minh

commune 2 8 23 31

43 Ham Tu commune 3 9 26 35

44 Dong Ket commune 3 14 41 55

Sub_total 6 40 141 426 567

Yen My District

45

Nghia Hiep

commune 3 10 30 40

46 Tan Lap commune 2 3 10 13

47 Lien Xa commune 1 7 20 27

48 Yen My Town 3 10 29 39

49

Trung Hung

commune 2 9 26 35

50

Minh Chau

commune 3 8 25 33

51 Yen Hoa commune 2 12 35 47

52

Hoang Long

commune 3 10 30 40

53 Yen Phu commune 2 8 24 32

54

Giai Pham

commune 4 11 33 44

55

Dong Than

commune 2 8 24 32

56

Ly Thuong Kiet

commune 6 20 59 79

Sub_total 7 33 115 345 460

My Hao District

57 Ban Town 2 14 41 55

58

Phan Đinh Phung

commune 4 11 32 43

59 Di Su commune 2 12 35 47

60

Nhan Hoa

commune 1 7 22 29

Page 101: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

101

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Productive land Other

Sub_total 8 9 43 130 173

Van Giang District

61 Me So commune 4 14 43 57

62

Lien Nghia

commune 5 18 53 71

63

Vinh Khuc

commune 3 14 41 55

64

Nghia Tru

commune 4 14 42 56

65

Phung Cong

commune 4 9 27 36

66 Van Giang Town 3 8 24 32

67

Long Hung

commune 2 3 9 12

68

Thang Loi

commune 3 8 24 32

Sub_total 9 28 87 263 350

Van Lam District

69

Trung Trac

commune 2 5 15 20

70 Nhu Quynh town 4 9 27 36

71

Lac Hong

commune 2 8 24 32

72 Chi Dao commune 3 8 24 32

73 Lac Dao commune 4 12 36 48

74 Dai Dong commune 2 6 18 24

Sub_total 10 17.00 48 144 192

2. Summary of Temporary Affected Land by the Project

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Area Rice

Land

Crop

Land

Other

land

Grand total 358 2,403 1,308 9,291 13,003

Hung Yen City

1 Thu Sy commune 4 53 - 133 186

2 Bao Khe commune 5 28 17 113 158

Sub_total 1 9 81 17 246 344

Page 102: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

102

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Area Rice

Land

Crop

Land

Other

land

Tiên Lữ District

3

Cuong Chinh

commune 3 - 11 28 39

4

Minh Phuong

commune 6 28 17 113 158

5

Trung Dung

commune 3 28 - 70 98

6

Tan Hung

commune 4 17 17 85 119

7 Nhat Tan commune 4 8 - 19 27

8

Duc Thang

commune 2 27 8 87 122

9 Vuong Town 5 26 14 100 140

10

Ngo Quyen

commune 3 17 17 85 119

Sub_total 2 30 151 83 587 821

Phu Cu District

11

Phan Sao Nam

commune 5 45 39 210 294

12 Tran Cao Town 4 11 18 72 101

13

Tien Tien

commune 6 24 11 87 122

14

Doan Dao

commune 7 28 29 142 199

15

Tong Tran

commune 3 15 - 36 51

Sub_total 3 25 122 97 547 766

Kim Dong District

16

Nghia Dan

commune 4 11 11 55 77

17 Nhan La commune 7 45 48 231 324

18 Tho Vinh commune 5 45 23 170 238

19

Song Mai

commune 3 39 - 98 137

20

Phu Cuong

commune 3 23 - 58 81

21 Luong Bang Town 5 56 11 168 235

22 Ngac Thanh 6 36 17 132 185

Page 103: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

103

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Area Rice

Land

Crop

Land

Other

land

commune

Sub_total 4 33 255 110 912 1,276

An Thi District

23 An Thi Town 3 17 - 43 60

24 Van Du commune 5 51 - 128 179

25 Bai Say commune 3 28 17 113 158

26

Quang Vinh

commune 6 43 17 151 211

27 Bac Son commune 3 17 - 43 60

28 Tan Phuc commune 5 28 28 140 196

29 Dang Le commune 4 11 20 76 107

30

Quang Lang

commune 3 17 20 91 128

31

Xuan Truc

commune 5 29 13 104 146

Sub_total 5 37 241 114 889 1,244

Khoai Chau

District

32

Phung Hưng

commune 4 19 23 104 146

33

Dai Hưng

commune 7 48 20 170 238

34

Thanh Cong

commune 6 39 26 161 226

35 Viet Hoa commune 8 11 67 195 273

36 Dan Tien commune 4 18 9 66 92

37 Tan Dan commune 7 50 13 157 220

38 Tu Dan commune 4 33 34 167 234

39

Binh Kieu

commune 5 33 29 155 217

40 Khoai Chau Town 4 41 33 185 259

41 Da Trach commune 7 50 29 197 276

42

Binh Minh

commune 4 34 9 106 149

43 Ham Tu commune 5 39 9 119 167

44 Dong Ket 6 52 37 223 312

Page 104: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

104

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Area Rice

Land

Crop

Land

Other

land

commune

Sub_total 6 71 466 336 2,005 2,807

Yen My District

45

Nghia Hiep

commune 5 11 45 140 196

46 Tan Lap commune 3 7 11 45 63

47 Lien Xa commune 4 19 19 94 131

48 Yen My Town 5 37 18 136 190

49

Trung Hung

commune 4 36 14 123 172

50

Minh Chau

commune 5 18 29 117 164

51 Yen Hoa commune 4 45 20 161 226

52

Hoang Long

commune 4 45 11 140 196

53 Yen Phu commune 4 17 28 113 158

54

Giai Pham

commune 6 39 22 153 214

55

Dong Than

commune 4 34 11 113 158

56

Ly Thuong Kiet

commune 10 80 31 276 386

Sub_total 7 58 386 257 1,611 2,254

My Hao District

57 Ban Town 4 56 20 189 265

58

Phan Đinh Phung

commune 6 28 31 146 205

59 Di Su commune 4 45 20 161 226

60

Nhan Hoa

commune 5 30 11 102 143

Sub_total 8 19 159 81 598 837

Van Giang

District

61 Me So commune 7 58 22 200 280

62

Lien Nghia

commune 9 67 31 244 342

63 Vinh Khuc 5 56 20 189 265

Page 105: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

105

Sr

No

District/

Commune

Number

of HHs

Land Categories Total

Area Rice

Land

Crop

Land

Other

land

commune

64

Nghia Tru

commune 7 56 22 195 273

65

Phung Cong

commune 6 28 22 125 175

66 Van Giang Town 5 34 11 113 158

67

Long Hung

commune 3 17 - 43 60

68

Thang Loi

commune 5 34 11 113 158

Sub_total 9 47 350 138 1,222 1,710

Van Lam District

69

Trung Trac

commune 4 17 11 70 98

70 Nhu Quynh town 6 28 22 125 175

71

Lac Hong

commune 4 34 11 113 158

72 Chi Dao commune 5 34 11 113 158

73 Lac Dao commune 6 45 22 168 235

74

Dai Dong

commune 4 34 - 85 119

Sub_total 10 29 192 77 674 943

3. Number of trees to be cut

Sr

No

District/

Commune

Category of Tree Total

Banana Guava Mango Bamboo

Grand total 456 64 32 405 957

Hung Yen City

1 Thu Sy commune 6 1 1 - 8

2 Bao Khe commune 6 2 - - 8

Sub_total 1 12 3 1 - 16

Tiên Lữ District

3 Cuong Chinh commune 3 - 1 - 4

4 Minh Phuong commune 12 - - - 12

Page 106: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

106

Sr

No

District/

Commune

Category of Tree Total

Banana Guava Mango Bamboo

5 Trung Dung commune 6 1 - 1 8

6 Tan Hung commune 5 2 - 2 9

7 Nhat Tan commune 3 - - - 3

8 Duc Thang commune 4 1 - - 5

9 Vuong Town 12 - - 6 18

10 Ngo Quyen commune 9 - 1 3 13

Sub_total 2 54 4 2 12 72

Phu Cu District

11 Phan Sao Nam commune 5 1 - 5 11

12 Tran Cao Town 7 1 - 5 13

13 Tien Tien commune 6 3 - 2 11

14 Doan Dao commune 9 1 - 5 15

15 Tong Tran commune 4 1 - 2 7

Sub_total 3 31 7 - 19 57

Kim Dong District

16 Nghia Dan commune 7 1 1 3 12

17 Nhan La commune 9 2 2 4 17

18 Tho Vinh commune 5 1 1 4 11

19 Song Mai commune 5 - - 3 8

20 Phu Cuong commune 6 1 - 5 12

21 Luong Bang Town 5 2 - 5 12

22 Ngac Thanh commune 6 3 - 6 15

Sub_total 4 43 10 4 30 87

An Thi District

23 An Thi Town 10 - 1 4 15

24 Van Du commune 7 1 - 7 15

25 Bai Say commune 4 - - 4 8

26 Quang Vinh commune 10 1 - 8 19

27 Bac Son commune 3 1 - 1 5

28 Tan Phuc commune 5 - 1 7 13

29 Dang Le commune 5 1 - 4 10

Page 107: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

107

Sr

No

District/

Commune

Category of Tree Total

Banana Guava Mango Bamboo

30 Quang Lang commune 2 1 1 2 6

31 Xuan Truc commune 7 1 - 4 12

Sub_total 5 53 6 3 41 103

Khoai Chau District

32 Phung Hưng commune 4 - 2 5 11

33 Dai Hưng commune 10 1 - 5 16

34 Thanh Cong commune 6 1 - 8 15

35 Viet Hoa commune 10 1 1 12 24

36 Dan Tien commune 7 - 1 4 12

37 Tan Dan commune 12 1 - 5 18

38 Tu Dan commune 4 - - 4 8

39 Binh Kieu commune 5 1 1 7 14

40 Khoai Chau Town 2 1 - 9 12

41 Da Trach commune 8 - 1 10 19

42 Binh Minh commune 6 1 - 6 13

43 Ham Tu commune 6 1 - 6 13

44 Dong Ket commune 5 1 - 4 10

Sub_total 6 85 9 6 85 185

Yen My District

45 Nghia Hiep commune 5 - 1 9 15

46 Tan Lap commune 3 - 1 3 7

47 Lien Xa commune 5 1 - 4 10

48 Yen My Town 4 - - 6 10

49 Trung Hung commune 2 1 - 9 12

50 Minh Chau commune 9 - 1 7 17

51 Yen Hoa commune 8 1 - 9 18

52 Hoang Long commune 5 1 - 7 13

53 Yen Phu commune 3 1 - 5 9

54 Giai Pham commune 6 1 - 2 9

55 Dong Than commune 5 - - 9 14

56 Ly Thuong Kiet commune 13 1 1 14 29

Page 108: ENVIRONMENTAL MANAGEMENT PLAN The rural Enegy II …€¦ · I Hung Yen City 0.051 2 15.28 . 1 Thu Sy commune 0.03 1 11.90 2 Bao Khe commune 0.02 1 3.39 . II . Tiên Lữ District

108

Sr

No

District/

Commune

Category of Tree Total

Banana Guava Mango Bamboo

Sub_total 7 68 7 4 84 163

My Hao District

57 Ban Town 1 1 - 9 11

58

Phan Đinh Phung

commune 6 1 1 10 18

59 Di Su commune 3 1 - 4 8

60 Nhan Hoa commune 6 1 - 6 13

Sub_total 8 16 4 1 29 50

Van Giang District

61 Me So commune 10 1 1 10 22

62 Lien Nghia commune 12 1 2 16 31

63 Vinh Khuc commune 6 1 1 7 15

64 Nghia Tru commune 8 1 1 11 21

65 Phung Cong commune 6 1 1 6 14

66 Van Giang Town 4 1 1 7 13

67 Long Hung commune 5 1 - 4 10

68 Thang Loi commune 6 1 1 4 12

Sub_total 9 57 8 8 65 138

Van Lam District

69 Trung Trac commune 5 1 - 7 13

70 Nhu Quynh town 8 1 1 6 16

71 Lac Hong commune 5 1 - 7 13

72 Chi Dao commune 6 1 1 7 15

73 Lac Dao commune 8 1 1 9 19

74 Dai Dong commune 5 1 - 4 10

Sub_total 10 37 6 3 40 86