environmental impact assessment (eia) report for the ... · 2.7 description of the process and...
TRANSCRIPT
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 1-
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
REPORT FOR THE “SUSTAINABLE WASTE
MANAGEMENT AND RENEWABLE ENERGY”
At
Survey No. 85, Kannahalli Village,
Yeshwanthpura Hobli, Seegehalli Cross,
Magadi Road, Bangalore – 560 091.
Project Proponents
M/s. Noble Exchange Environment Solutions
Bangalore Private Limited,
Door No.200, 4th Cross, 5th Main,
ITI Layout, Mallathalli, Bangalore
Environmental Consultants
M/s. AQUA TECH ENVIRO ENGINEERS,
(Environmental Engineers & Consultants)
# 3391, 6th Main, 3rd Cross, RPC Layout,
Vijayanagar II Stage,
Bangalore – 560 040.
Tele Phone : 080 23141679
E-mail: [email protected]
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 2-
CONTENTS
Sl. No. Description Pg. No
FORM -1 1-12
EXECUTIVE SUMMARY 1-10
CHAPTER 1
INTRODUCTION
11-42
1.0 Purpose of the project 11
1.1 Category of the project 12
1.2 Identification of the project and project proponent 12
1.2.1 Introduction of the project proponent 12
1.2.2 Introduction to the project 13
1.3 Brief description of nature, size, location of the project
and its importance to the country, region
13
1.3.1 Nature, size and location of the project 13
1.3.2 Project at a glance 15
1.3.3 Need for the project and its importance to the
country/region
16
1.3.4 Biogas plant 20
1.3.5 Necessity to setup a biogas plant 21
1.3.6 Status of biogas plants in India 23
1.3.6.1 All India scenarios 23
1.3.6.2 Large scale biogas plants in India 25
1.3.6.3 State-wise targets and achievement 27
1.4 Scope of study - details of regulatory scoping carried
out(as per terms of reference)
30
1.4.1 Scope of study 30
1.4.2 Components of EIA report 31
1.4.3 Terms of reference (tor) 31
1.4.4 Generic structure of EIA document 40
CHAPTER 2
PROJECT DESCRIPTION
43-109
2.1 Type Of Project 43
2.2 Need For The Project 43
2.2.1 Location (maps showing general location, specific
location, project boundary & project site layout)
44
2.3 Site selection 44
2.4 Size or magnitude of operation 51
2.5 Proposed schedule for approval and implementation 51
2.5.1 Statutory licenses / approvals 52
2.6 Proposed layout plan 52
2.6.1 Landscape Development 53
2.7 Description of the process and treatment 56
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 3-
2.7.1 Present status 58
2.7.2 Collection and conveyance 59
2.7.3 Mode of transportation 60
2.7.4 Mode of transportation of food waste 60
2.8 Technology used for the treatment 62
2.8.1 Process involved 62
2.8.1.1 Pre-treatment 62
2.8.1.2 Feed processing:- 62
2.8.1.3 Digestion:- 62
2.8.1.4 Up gradation of biogas and conversion to CBG
(compressed bio gas)
63
2.8.1.5 Digested slurry 63
2.8.2 Process involved in digester 64
2.8.3 Food waste characterization 65
2.9 Technology and process description 66
2.9.1 General description of anaerobic digestion process 66
2.9.2 Process description 69
2.9.2.1 Pre- treatment / slurry preparation 69
2.9.2.2 Biogas digester design and sizing suitable for multi-feed
stock
70
2.9.2.3 Anaerobic digester 70
2.9.2.4 Bio digesters (primary and secondary stage) 72
2.9.2.5 Biogas storage 72
2.9.2.6 Biogas utilization and generation of CBG 73
2.9.2.7 CBG distribution: 76
2.9.2.8 Post treatment of digested slurry: 77
2.10 Characteristics of CBG, manure and nutrient rich water 77
2.10.1 CBG properties 77
2.10.2 Manure properties 78
2.10.3 Characteristics of nutrient rich water 79
2.10.4 Mode of transportation of CBG 81
2.11 Design data 82
2.12 Utilization of excess water separated from biogas plant
slurry
84
2.12.1 Plant details 87
2.12.2 Units involved in the waste processing: 87
2.13 Process equipment’s used in the plant 87
2.13.1 Maintenance scheduled for equipment 89
2.14 Waste composition and product specification 89
2.14.1 Utility of product and by-products 90
2.14.1.1 Biogas 90
2.14.1.2 Organic manure 90
2.14.1.3 Provision of storage yard for manure 91
2.14.1.4 Nutrient rich water 91
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 4-
2.14.1.5 Design parameters for Biogas plant 92
2.15 Schematic representation of the feasibility drawing 92
2.16 Mitigation measures incorporated into the project to meet
environmental standards, environmental operating
conditions or other EIA requirements (as required by the
scope)
94
2.16.1 Sources of pollution & pollution control measures adopted
in the plant
94
2.16.2 Water demand and wastewater/effluent discharge 94
2.16.2.1 Source of water supply 94
2.16.2.2 Water demand and wastewater discharge during
operation phase
94
2.16.3 Design details for proposed effluent treatment plant 96
2.16.3.1 Treatment scheme for wastewater 98
2.17 Air pollution an mitigation measures 106
2.17.1 Power 106
2.17.2 Air pollution sources 106
2.17.3 Noise generation and its management 107
2.17.4 Solid waste generation and management 107
2.18 Assessment of new & untested technology for the risk of
technological failure
108
CHAPTER 3
DESCRIPTION OF THE ENVIRONMENT
109-158
3.1 Study area, period, components & methodology 109
3.2 Establishment of baseline 112
3.2.1 Meteorological data 112
3.2.1.1 Temperature 114
3.2.1.2 Relative humidity 114
3.2.1.3 Rainfall 114
3.2.1.4 Atmospheric pressure 114
3.2.1.5 Inversion height 115
3.2.1.6 Cloud cover 115
3.2.1.7 Wind 115
3.2.2 Baseline monitoring 120
3.2.2A Sampling and analytical techniques 120
3.2.2.1 Air quality 123
3.2.2.1.2 Air quality 125
3.2.2.1.3 Observations 128
3.2.2.2 Noise environment 128
3.2.2.2.1 Observations 129
3.2.2.3 Water environment 131
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 5-
3.2.2.3.1 Reconnaissance survey 131
3.2.2.3.2 Surface water 132
3.2.2.3.2.1 Observations 134
3.2.2.3.3 Ground water 135
3.2.2.3.4 Observations 138
3.2.2.4 Soil and geology 138
3.2.2.5 Ecology 142
3.2.2.5.1 Flora 142
3.2.2.5.2 Fauna 144
3.2.2.6 Socio-economic environment 144
3.2.2.6.1 Demographic structure 145
3.2.2.6.2 Connectivity 149
3.3 Environmental features 151
3.4 Base maps of all environmental components 153
3.5 Significant environmental attributes 158
CHAPTER 4
ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
159-177
4.1 Details Of Investigated Environmental Impacts Due To
Project Location, Possible Accidents, Project Design,
Project Construction, Regular Operations, Final
Decommissioning Or Rehabilitation Of Completed Project
159
4.1.1 Project Location 160
4.1.2 Possible Accidents 161
4.1.2.2 Operation Phase 161
4.1.3 Project design 162
4.2 Environmental impacts due to the project construction,
regular operations and measures for minimizing &/or
offsetting adverse impacts identified & mitigation
measures
163
4.2.1 Actions likely to affect the environment 163
4.2.1.1 Air environment 163
4.2.1.1.1 Construction phase 163
4.2.1.1.2 Operation phase 164
4.2.1.2 Noise environment 165
4.2.1.2.1 Construction phase 165
4.2.1.2.2 Operation phase 166
4.2.1.3 Water environment 166
4.2.1.3.1 Construction phase 166
4.2.1.3.2 Operation phase 167
4.2.1.4 Land environment 167
4.2.1.4.1 Construction phase 167
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 6-
4.2.1.4.2 Operation phase 168
4.2.1.5 Ecological environment 168
4.2.1.5.1 Operation phase 168
4.2.1.5.2 Odor management 169
4.2.1.6 Socio-economic environment: assessment of potential
impacts
171
4.2.1.6.1 Impact on population composition 171
4.2.1.6.2 Impact on employment generation 171
4.2.1.6.3 Impact on income 172
4.2.1.6.4 Impact on historical, archeological and architectural sites 172
4.2.1.6.5 Impact on law & order 172
4.2.1.6.6 Public perception about the project 172
4.2.1.6.7 Public health 172
4.3 Irreversible & irretrievable commitments of
environmental components
173
4.4 Assessment of significance of impacts (criteria for
determining significance, assigning significance)
173
4.4.1 Impact matrix 173
4.4.2 Environmental impact assessment 175
CHAPTER 5
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
178-187
5.1 Alternatives For Technology 178
5.1.1 Technology Brief 178
5.1.1.1 General description of anaerobic digestion process 178
5.1.1.2 Advantages and Disadvantages of other methods of solid
waste disposal.
183
5.1.2 Health aspects/acceptance 186
5.1.3 Maintenance 186
5.2 Alternatives for site 186
CHAPTER 6
ENVIRONMENTAL MONITORING PROGRAMME
188-193
6.1 Measurement Methodology 188
6.2 Frequency, location, data analysis, reporting schedules
emergency procedures
188
6.2.1 Emergency procedures 190
6.3 Detailed budget 192
6.4 EMP implementation schedule 193
CHAPTER 7
ADDITIONAL STUDIES
194-206
7.1 Public Consultation 194
7.2 Risk Assessment 194
7.2.1 Introduction 194
7.2.2 Objective & scope 195
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 7-
7.3 Risk assessment & management plan 195
7.4 Disaster management 196
7.4.1 Actuation of the plan 198
7.4.2 Emergency equipment 198
7.4.3 Emergency response 198
7.4.5 Emergency control Centre (ECC) 201
7.4.6 Medical resources: 202
7.4.7 Response evaluation, testing and updating of the plan: 203
7.4.8 Preventive action 203
7.4.9 Reporting procedures 203
7.4.10 Emergency measures 204
7.4.11 Emergency lighting 204
7.4.12 Fire protection 204
7.4.13 Safety aspects for occupational hazard 205
7.5 Firefighting facility 206
7.6 Social impact assessment R&R action plans 206
CHAPTER 8
PROJECT BENEFITS
207-212
8.0 Introduction 207
8.1 Health benefit 207
8.2 Economic benefit 208
8.3 Market potential 209
8.3.1 Major markets for CBG and manure 209
8.3.2 Major markets for CBG and manure 210
8.4 Recycling of materials 211
8.5 Socio-economic benefits 211
CHAPTER 9
ENVIRONMENTAL COST BENEFIT ANALYSIS
213-218
9.1 Introduction 213
9.2 Uses of CBG 214
9.3 Main stages 214
9.4 Disadvantages 215
9.5 Discounting the future 217
9.6 Cost-benefit analysis for m/s. Noble exchange
environment solutions private limited (NEX)
218
CHAPTER 10
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
219-226
10.1 Introduction 219
10.2 Mitigation measures 220
10.3 Environmental management plan (EMP) 221
10.4 Environmental policy 224
10.5 Description of the administrative aspects of ensuring that 225
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 8-
mitigate measures are implemented & their effectiveness
monitored, after approval, implementation and during
operation
10.5.1 Environment management cell 225
CHAPTER 11
SUMMARY & CONCLUSION
227-229
11.1 Overall Justification For Implementation Of The Project 227
11.2 Explanation Of How Adverse Effects Have Been Mitigated 229
CHAPTER 12
DISCLOSURE OF CONSULTANTS ENGAGED
230-235
12.1 Environmental Consultants 230
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 9-
LIST OF TABLES
Table
no.
Description Pg. No
1.0 Use of Resources 3
2.0 Monitoring schedule for environmental parameters 9
1.1 State-wise list of biogas plants installed during last three years 29
1.2 Terms of Reference (TOR) 32
1.3 Generic structure of EIA document 41
2.1 Projected cost of the project 51
2.2 Time schedule for completion of the proposed project 52
2.3 Statutory licenses/approvals 52
2.4 Land-use pattern 52
2.4.1 Action plan for developing green belt 53
2.4.2 List of Flower baring trees and Fruit baring tress 54
2.5 Unit sizes 55
2.6 Details of the average Cattle dung and non-woody biomass feed-
materials available for the Plant
57
2.7 List of the areas contributing food waste to biogas plant with
quantities.
57
2.8 CBG properties 78
2.9 Manure properties 79
2.10 Slurry test report 80
2.11 Size of the proposed units 82
2.12 Plant details 87
2.13 List of process equipment’s used 88
2.14 CBG storage capacity 90
2.14.1 List of product generated from the project 91
2.15 Air pollution details 94
2.16 Water consumption and discharge 95
2.17 Sewage/effluent treatment and discharge 95
2.18 Source, quantity & treatment of industrial wastewater 95
2.19 Air pollution sources 106
2.20 Solid waste generation during the operation phase 107
3.0 Seasons 112
3.1 Meteorological data of Bangalore for the year 2013 113
3.2 Predominant wind directions 115
3.2 A Techniques adopted/protocols for ambient air quality
monitoring
120
3.2B Protocol for surface water quality monitoring 121
3.2 C Protocol for ground water quality monitoring 122
3.2 D Equipment’s used for noise & soil monitoring 123
3.3 Ambient air sampling stations 124
3.4 Air quality data analysis at all locations (during October 2014) 125
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 10-
3.4.1 Air quality data analysis at all locations (during November
2014)
126
3.5 Ambient air quality standards – MOEF as per the notification
dated 16th November 2009 for industrial, residential & rural
areas
127
3.6 Noise level monitoring stations 128
3.7 Summary of noise levels 129
3.8 Limits as per environmental protection rules, 1986 129
3.9 Water sampling stations 131
3.10 Surface water quality 133
3.11 Ground water quality 135
3.12 Soil sampling stations 138
3.13 Physico-chemical characteristics of soil 139
3.14 Location of sampling stations 141
3.15 Plants, vegetation & grasses 143
3.16 Fauna in the study area 144
3.17 Distribution of population 145
3.18 Distribution of literates and literacy levels in the study area 146
3.19 List of infrastructural facilities in the surroundings 147
3.20 Connectivity from the project site 150
3.21 Existing land-use pattern 153
3.22 Significant environmental attributes 158
4.1 Actions likely to affect environment 174
4.2 Environmental impact assessment 175
4.3 Impact matrix 177
5.1 Advantages and limitations 182
6.1 Monitoring schedule for environmental parameters
(construction & occupancy phase)
189
6.2 Financial allocation/budgetary provisions for monitoring
program
192
6.3 Implementation schedule for EMP 193
9.1 CBA for M/s. Noble exchange Environment Solutions Private
Limited (NEX)
218
10.1 Environmental management plan during construction phase 221
10.2 Environmental management plan during operation of the
facilities/utilities
222
10.3 Environmental management plan during storage, handling &
transportation of waste and byproducts
223
11.1 Possible effects and its mitigate measures from the proposed
project
229
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 11-
LIST OF FIGURES
Fig.
No.
Description Pg. No
1.1 Site Location Map 16
1.2 Composition of municipal solid waste in India 22
1.3 Potential biogas feed sources 24
1.4 Potential biogas applications 27
1.5 Projection of the state-wise targets and achievement under
NBMMP during 2013-14
28
2.1 Location map showing the project location 45
2.2 CDP map showing the location of the project and proposed land
use
46
2.3 Topo map 47
2.4 Site photos 48
2.5 Google map showing project site boundary 49
2.5.1 Land use pattern pie chart 53
2.6 Birds high of the project 55
2.7 Food waste generated at the hotels 58
2.7.1 Route map of collection of waste from the hotel 59
2.8 Bin/s given to each hotel for disposal of organic wastes in
segregated form
61
2.9 Biogas process 65
2.10 Scheme of reactions produced during anaerobic digestion 69
2.11 Process flow chart 74
2.12 Mass balance diagram 75
2.12.1 Bio gas double membrane roof photographs 76
2.13 Cascades carried over a crane mounted truck 81
2.14 Retention time design sheet 83
2.15 Hydraulic flow diagram for manure and recirculation 86
2.16 Feasibility and environmental assessment process 93
2.17 Water balance chart 96
2.18 ETP flow chart 105
3.1 Topo map of the study area 110
3.1 A Site plan 111
3.2 Wind rose diagrams 116
3.3 Photographs showing the noise monitoring during baseline
data collection October 2014
130
3.4 Kannahalli lake water sampling photographs during baseline
data collection
134
3.5 Water sampling photographs during baseline data collection
Project site Anikethananagar
137
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 12-
3.6 Soil sampling photographs during baseline data collection 140
3.7 Google map showing sampling locations 141
3.8 Google map showing surrounding hospitals 148
3.9 Google map showing surrounding schools and colleges 149
3.10 Google map showing connectivity 150
3.11 Topo map covering 5 km distance from the project site 152
3.12 Google map covering 1 km aerial distance from the project site 154
3.13 Google map covering 5 km aerial distance from the project site 155
3.14 Google map covering 10 km aerial distance from the project
site
156
3.15 Land use map of the project site 157
4.1 Vessel unloading of waste at site 171
5.1 Scheme of reactions produced during anaerobic digestion 181
6.1 Structure of onsite emergency preparedness and response 190
6.2 Emergency organization structure 191
6.3 Emergency coordinates 192
12.1 Organizational chart 232
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 13-
LIST OF ANNEXURE
Annexure Description
Appended at the end of
the report
E1 English Executive summary
E2 Kannada Executive summary
A HAZOP Studies and MSDS
B Copy of land records
C Environmental policy letter
1 Topo map of 15 Km radius
2 Project related drawings
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 1-
APPENDIX I
(See paragraph – 6)
FORM 1 (I) Basic Information
Sl. No.
Item Details
1. Name of the project
“Sustainable Waste Management and Renewable Energy”
2. S. No. in the schedule 7 (i)
3. Proposed capacity/area/length/ tonnage to be handled/command area/lease area/ number of wells to be drilled
250 tons/day of food and organic waste
4. New/Expansion/Modernization New project
5. Existing capacity/area etc., 5 Acres (20,234 sq m)
6. Category of Project i.e ‗A‘ or ‗B‘ B1
7. Does it attract the general condition? If yes, please specify
No
8. Does it attract the specific condition? If yes, please specify
No
9. Location Bangalore.
Plot/Survey/Khatha No. Survey No. 85
Village Kannahalli
Tehsil Seegehalli Cross
District Bangalore North Taluk
State Karnataka
10. Nearest railway station/airport along with distance in Km
Bangalore City Railway Station 17.5 Km.
11. Nearest Town, city, District Headquarters along with distance in Km.
Bangalore City at about 13.27 Km.
12. Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (complete postal addresses with telephone nos. to be given)
Kodegehalli Village Panchayat
13. Name of the applicant M/s. Noble Exchange Environment Solutions Bangalore Pvt. Ltd.,
14 Registered Address No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli, Bangalore.
15 Address for correspondence:
Name K. S. Girish Kumar
Designation (Owner/Partner/CEO) General Manager – Operations
Address M/s. NobleExchange Environment Solutions Bangalore Pvt. Ltd. No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli, Bangalore
Pin Code 560 056.
E-Mail [email protected]
Telephone No. +91 9845114494
Fax No. -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 2-
16 Details of Alternative Sites examined, if any. Location of these sites should be shown on a Topo sheet
Village-District-State 1. – NA 2. 3.
17 Interlinked Projects NA
18 Whether separate application of interlinked projects has been submitted?
NA
19 If yes, date of submission NA
20 If no, reason Proposed project is “Sustainable Waste Management and Renewable Energy”
21 Whether the proposal involves approval/clearance under: If yes, details of the same and their status to be given.
(a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991?
NA
22 Whether there is any Government Order/Policy relevant/relating to the site?
Yes, documents attached
23 Forest land involved (hectares) No
24 Whether there is any litigation pending against the project and/or land in which the project is propose to be set up?
(a) Name of the Court (b) Case No. (c) Orders/directions of the Court, if any
and its relevance with the proposed project.
No
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities /rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)
No No Change in Land Use as the Proposed project site is located in a area designated for putting up solid waste management facilities as per CDP
1.2 Clearance of existing land, vegetation and buildings?
No Land is clear of vegetation and has no encumbrances.
1.3 Creation of new land uses?
No The site is earmarked for Solid Waste Management facilities.
1.4 Pre-construction investigations e.g. bore holes, soil testing?
No
1.5 Construction works?
Yes Proposed project envisages constructions works in respect of putting up Anearobic Digesters and other units related to process and
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 3-
administrative buildings.
1.6 Demolition works? No Project site is vacant land and therefore demolition works are not anticipated.
1.7 Temporary sites used for construction works or housing of construction workers?
Yes Temporary labor camp and small go down will be constructed at site for labor stay and storage of materials.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations.
Yes The construction involved is for partly above and partly below structures depending on the site conditions which includes earth work accordingly like buildings, vehicle rafts, poly house for manure drying and CBG and other platforms.
1.9 Underground works including mining or tunneling?
No No underground work is needed
1.10 Reclamation works?
No No reclamation work included
1.11 Dredging? No -
1.12 Offshore structures? No -
1.13 Production and manufacturing processes?
Yes Production of biogas and finally CBG and manure will be done at site.
1.14 Facilities for storage of goods or materials?
Yes Generated biogas will be stored in the above ground level gas tanks and the compressed biogas will be stored in CNG cylinders. The generated manure will be dried and disposed off there on.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents?
No The nutrient rich water from the project will be given to farmers. The project produces CBG, organic manure and nutrient rich water, all of which will be sold.
1.16 Facilities for long term housing of operational workers?
No No residential housing is proposed for the project
1.17 New road, rail or sea traffic during construction or operation?
No The project is well connected from the city by public transport city buses and BMTC busses ply at regular frequency.
1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?
No -
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?
No -
1.20 New or diverted transmission lines or pipelines?
No -
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?
No -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 4-
1.22 Stream crossings? Nil -
1.23 Abstraction or transfers of water form ground or surface waters?
No Ground Water abstraction through Bore well is planned
1.24 Changes in water bodies or the land surface affecting drainage or run-off?
No -
1.25 Transport of personnel or materials for construction, operation or decommissioning?
Yes Public transport which is already available will be used. Other commercial vehicles are being for construction purpose.
1.26 Long-term dismantling or decommissioning or restoration works?
No -
1.27 Ongoing activity during decommissioning which could have an impact on the environment?
No No Decommissioning activity is required
1.28 Influx of people to an area in either temporarily or permanently?
Yes Temporary construction labor and site engineers during construction and operational work force during operations of the plant (70-75 people during operation phase)
1.29 Introduction of alien species?
No -
1.30 Loss of native species or genetic diversity?
No -
1.31 Any other actions?
No -
2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources
which are non-renewable or in short supply):
Sl.No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate quantities /rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha)
No Non agricultural, non developed land.
2.2 Water (expected source & competing users) unit: KLD
Yes The water for the proposed project will be from Bore well Sources.
Total water requirement is about 10 KLD
2.3 Minerals (MT) No No minerals needed for operations or construction of the project.
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)
Yes Ready mix concrete needed during construction @ approximately 2500 m3 of M35 grade concrete. Ready mix concrete from various companies is available. Steel @ approximately 300 MT is needed during construction. Aggregates required for vehicle raft pitching required @ approximately 50 m3.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 5-
2.5 Forests and timber (source – MT) No NA
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)
Yes Power Requirement: Construction phase: Temporary power from BESCOM to operate construction machinery and Lighting for workers shed. Operational phase: Anticipated power requirement from BESCOM.
1 X 350 kVA capacity DG sets is proposed, which will serve as backup power supply during power failure. Fuel Requirement: Low Sulphur content Diesel of 70 L/hr for each DG set.
2.7 Any other natural resources (use appropriate standard units)
No -
3. Use, storage, transport, handling or production of substances or materials, which could
be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.
Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)
No -
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)
No -
3.3 Affect the welfare of people e.g. by changing living conditions?
No -
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,
NIL -
3.5 Any other causes
NIL -
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
Sl.No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes. No -
4.2 Municipal waste (domestic and or commercial wastes)
No 250 TPD of food waste from hotels will be processed to produce biogas and organic manure, thereby facilitates handling these wastes by municipal authority and produce value products through cleaner technology.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules)
No -
4.4 Other industrial process wastes No -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 6-
4.5 Surplus product
Yes The separated plastics, metals, non organics and glass will be sold for recycling to the recyclers who will pick up the separated wastes form the site.
4.6 Sewage sludge or other sludge from effluent treatment
No No sludge is generated form the plant. The separated solids are used of and sold as organic manure.
4.7 Construction or demolition wastes No -
4.8 Redundant machinery or equipment NIL -
4.9 Contaminated soils or other materials NIL -
4.10 Agricultural wastes No -
4.11 Other solid wastes NIL -
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources.
No No fossil fuels are used in the project.
5.2 Emissions from production processes NIL -
5.3 Emissions from materials handling including storage or transport
NIL -
5.4 Emissions from construction activities including plant and equipment
NIL -
5.5 Dust or odors from handling of materials including construction materials, sewage and waste
NIL No odour will be released as the technology used is anaerobic digestion and this takes care of all the generated waste which is then converted into biogas and organic manure.
5.6 Emissions from incineration of waste No NA
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)
No NA
5.8 Emissions from any other sources No NA
6. Generation of Noise and Vibration, and Emissions of Light and Heat: Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers
NIL The anaerobic digestion is a microbiologically controlled process. Hence no noise, vibration, heat is released. Unless the generated gas is flared in emergency cases, no heat is released and the gas flare is as per the standard norms. All the machinery used for the project is under 75 DB noise levels.
6.2 From industrial or similar processes NIL -
6.3 From construction or demolition NIL -
6.4 From blasting or piling NIL -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 7-
6.5 From construction or operational Traffic.
NIL During construction: From movement of vehicles carrying constriction materials. During Operation: From movement of trucks carrying waste.
6.6 From lighting or cooling systems Nil -
6.7 From any other sources NIL -
7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials
No No hazardous materials are accepted neither disposed on the site.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)
No About 148 m3/day of excess nutrient rich water will be produced every day. The discharged water meets the irrigation discharge standards.
7.3 By deposition of pollutants emitted to air into the land or into water.
NIL -
7.4 From any other sources.
NIL -
7.5 Is there a risk of long term build up of pollutants in the environment from these sources?
NIL -
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment Sl. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data.
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances
Yes All safety features are planned and will be executed as per the Petroleum & Explosives Safety organization (PESO) standards. The zone classification for gas up gradation area will be performed, wherever needed.
8.2 From any other causes No NA
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?
No NA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 8-
9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S. No.
Information/Checklist confirmation
Yes/No
Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting. utilities, ancillary development or
development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.)
• housing development • extractive industries • supply industries • other
Yes Yes No No No Yes
Net Positive Impact in terms of overall development of the Area is expected from the project. Direct & Indirect Employment opportunities are also created due to development of this project. The Proposed “Sustainable Waste Management and Renewable Energy” project involving solid waste processing (food wet waste generated from bulk generators)
9.2 Lead to after-use of the site, which could have an impact on the environment
NIL Carbon neutral gas will in fact save thousands of tons of CO2 emissions which are rampant due to the use of fossil fuels.
9.3 Set a precedent for later developments YES This project will set precedence for later multiple such projects coming up and hence will improve the urban waste management standards to make the city clean of organic de compostable waste.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects
Yes The area earmarked for the project is exclusively kept for solid waste management facilities and therefore cumulative effects are possible
(II) Environmental Sensitivity Sl.No. Areas Name/
Identity Aerial distance (within 15 km.) Proposed project location boundary
1 Areas protected under international conventions, national or local
NA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 9-
legislation for their ecological, landscape, cultural or other related value
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests
Yes Kannahalli Lake water – 1.66 km from the project site (South – East)
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
NA
4 Inland, coastal, marine or underground waters
NA
5 State, National boundaries
NA
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas
NA
7 Defence installations NA
8 Densely populated or built-up area NA
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)
NA
10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)
NA
11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)
NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)
NA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 10-
―I hereby undertake that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance, if any, given to the project will be revoked at our risk and cost. Date: 15-12-2014 Place: Bangalore
K.S. Girish Kumar, General Manager – Operations
For NobleExchange Environment Solutions Bangalore Private Limited (NEX),
Door No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli,
Bangalore. Signature of the applicant
With Name and Full address (Project Proponent / Authorized Signatory)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 1-
HAPTER 1
1. INTRODUCTION:
M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX), having its
registered office at Door No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli,
Bangalore, is proposes establishing ―Sustainable Waste Management and Renewable
Energy” Project. The project is for exclusively processing of waste organic food and
vegetable waste received from BBHA (Bruhat Bengaluru Hotels Association) or other
bulk generators such as vegetable markets, commercial malls, kalyan Mandapas,
modern retail stores, star hotels & restatuarnts, IT parks etc . The organic/
biodegradable waste would be collected from various hotels located in the jurisdiction
of BBMP (Bruhat Bengaluru Mahanagara Palike) to produce biogas through
biomethanation plant.
2. PURPOSE OF STUDY
As per the amended EIA notification dated 14th September, 2006 the project falls
under Category 7 (i) under caption ―Common Municipal Solid Waste Management
Facility (CMSWMF)‖. The project comes under B1 category as per MoEF, Office
Memorandum No. J-13012/12/2013-IA-II (I) dated 24th December, 2013 and
necessitates Preparation of Environmental Impact Assessment (EIA) report.
Environmental Clearance is sought from State Level Environment Impact Assessment
Authority (SEIAA), Karnataka.
The broad scope of this EIA study includes detailed characterization of baseline
environmental parameters/attributes (Ambient air, Water, Soil, Noise) selected for
study in the area of 10 km radius from the project site. The EIA Report is prepared,
based on studies carried out during the months of October to November, 2014. The
following are the salient tasks within the scope:
To assess the existing status of air, noise, water, land, biological and socio-
economic components of environment.
To identify and quantify significant impacts of various operations on environmental
components during construction & operation phases.
To evaluate proposed pollution control measures.
EXECUTIVE SUMMARY
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 2-
To prepare Environmental Impact statement outlining additional control
technologies to be adopted for mitigation of adverse impacts on the environment
and the surroundings.
In addition to the above, the report would discuss about the model TOR.
3. METHOD OF STUDY
The study is carried out based on guidelines of MoEF and identifies the nature of
activities involved and their impacts caused on various environmental parameters. It
subsequently suggests mitigation measures to be executed for safeguarding against any
environmental degradation. Finally, it suggests methods of implementing
environmental management plan.
4. PROJECT LOCATION
The Proposed “Sustainable Waste Management and Renewable Energy” project
involving solid waste processing (food wet waste generated from bulk generators) is
located at Survey No. 85, Kannahalli Village, Yeshwanthpura Hobli, Seegehalli Cross,
Magadi Road, Bangalore – 560 091. The site is located towards West of Bangalore city,
next to the Seegehalli bus depot and has very good connectivity by public transport to
city.
The site is connected by Magadi Road which is a State Highway no. 85 and an internal
asphalt road from the Main road which is of 2 Km in length approximately. The site
location is around 17 km from Bangalore city terminal.
5. USE OF RESOURCES
The use of resources is appended in the table 1.0.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 3-
Table:-1.0 USE OF RESOURCES
6. PROJECT IMPORTANCE
The land in which the project site is located, is owned by Bruhat Bengaluru Mahanagara
Palike and is earmarked for the treatment of waste. The land was handed over by the
Urban development Ministry of Karnataka State by an agreement between BBMP-BBHA -
NEX. The land is free from any encumbrances and is compounded. Out of the total plot
area of 29 acres, the service provider NEX has been granted 5 acres for the project
development, with permissive use for 20 years. The land is fully compounded and there
are no villages/residential area/factories up-to 500 meters from the boundaries of the
plot.
The project aims to process biodegradable organic food waste and eventually extract
biogas, thereby, upholding the concept of Waste to Energy; as the landfilling of
biodegradable waste can pollute the environment and produce Green House Gases
(GHG) which contributes to climate change. Biodegradable waste management is
gaining importance to prevent or reduce any damage to the environment such as
pollution to surface water, ground water, soil and air by landfilling, as far as possible.
The biogas plant might have the potential to offer an alternative energy solution, and
in addition to target the challenges of a modern society in energy supply, waste control
and pollution reduction.
The biogas plant here has been designed based on Anaerobic Digestion (AD) and
Continuously Stirred Reactor Technology (CSTR).
Sl. No. Details
1 Project Sustainable Waste Management and
Renewable Energy Project (to set up biogas
plant of 250 TPD capacity)
2 Total Plot Area 20,234 sq m (5 acres)
3 Air Pollution/ Noise
Generation Source.
1 X 350 kVA capacity DG set is provided
with adequate stack and acoustics.
4 Water supply source Bore well
5 Total water
requirement.
10,000 Litres/day
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 4-
7. ENVIRONMENTAL EVALUATION
BASELINE STATUS
Two months data has been collected during the months of October to November 2014
for environmental attributes like Air, Water, Soil, Noise, Ecology, Socio-economic etc.,
within a radius of 10 km to assess the baseline environmental status of the project
area. Secondary data from different Government, Semi-government and Private
agencies and sources are collected, interpreted, compiled and presented to
authenticate and draw a conclusion regarding the baseline status of the environment in
the study area.
AIR ENVIRONMENT
To evaluate the baseline status of the Ambient Air Quality, a short term survey was
conducted at site including Residential and Industrial area. Ambient air quality
standards – MoEF as per the notification dated 16th November 2009 for industrial,
residential and rural area were considered as standard. From the observations, it has
been concluded that the concentration of pollutants under consideration are well
within the specified limits of NAAQS for Industrial and Residential areas.
WATER ENVIRONMENT
Water samples (Surface / Ground water) were collected in the nearby areas and
analyzed for their Physico - Chemical characteristics to evaluate the existing status of
water quality and assess the impact of the project on water environment. It is observed
that the quality of water is within the acceptable limits and implementation of the
project will not have any significant impact.
NOISE ENVIRONMENT
Noise monitoring conducted around the site and other locations reveal that the noise
levels are within the prescribed limit specified by the statutory authorities for
industrial areas. Comparatively maximum noise levels observed at Seegehalli Bus Depot
and Channenahalli (77.9 & 76.1 dB) can be attributed to the movement of large
number of vehicles close to the monitoring station
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 5-
FLORA AND FAUNA
Ecology of the study area includes study of flora and fauna within the study zone. The
investigation included field observations, discussions with local people, forest officials
etc., The flora found in the area includes commercial plantations like Beetle, Casurine,
Areca, Coconut, Neelgiri etc. apart from other botanical species found in the study area.
The fauna found in the region does not show much diversity, as there is no suitable
habitat for the occurrence of ecologically important fauna. Fauna observed in the region
include domestic animals, reptiles and birds.
8. ENVIRONMENTAL MANAGEMENT PLAN
The Environmental management plan proposed for the Bio Gas plant during Construction
and Operation phase is as below.
CONSTRUCTION PHASE
Construction phase works include site clearance, site formation, building works,
infrastructure provision and any other infrastructure activities. The impacts due to
construction activities are short term and are limited to the construction phase. The
impacts will be mainly on air quality, water quality, soil quality and socioeconomics.
During biogas plant execution phase, all precautionary measures are taken for
controlling emissions, soil erosion and noise reduction.
OPERATION PHASE
AIR EMISSIONS
The sources of air pollution in the project site is DG set only.
IMPACT ON AIR QUALITY
No adverse impact on air environment is envisaged due to the project, as adequate
measures are proposed to be adopted and the DG will be used only in case of power
supply failure from BESCOM. For DG, measures such as adequate stack height is
proposed and is provided with suitable acoustics; and hence no adverse impact is
envisaged on existing environment.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 6-
WASTEWATER
Total wastewater generated at the facility accounting for 269 KLD is treated in the
integral / in-house ETP that is being set up in the facility.
IMPACTS ON WATER ENVIRONMENT
No adverse impact on the water environment is envisaged as adequate treatment
facilities and disposal options are envisaged for the wastewater. Also, the potable
water for operators of biogas will be augmented through borewell, and no adverse
impact on the water balance of the area and changes in ground water level and its
characteristics is anticipated.
NOISE ENVIRONMENT
The main sources of noise shall be from equipments, machinery, pumps, blowers and
Diesel Generator sets.
IMPACTS ON NOISE LEVEL
The diesel generator sets should be provided with integral acoustic enclosure at the
manufacturing stage itself. The noise producing machinery is provided with acoustic
enclosures/acoustic rooms to reduce the noise levels. Workers working near noisy area
will be provided with ear plugs.
SOLID WASTE
The domestic solid waste generated during operation phase is segregated, collected
and treated in anaerobic digester within the plant. The slurry from digester is
separated with screw press and then flocculated to separate water, and is then sent to
poly house equipped with exhaust fans and also subjected to solar thermal drying,
allowing extraction of moisture and evaporating it. The produced sludge will be used as
manure that is found as suitable for agriculture / horticulture activity.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 7-
9. ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION PHASE AND OPERATION PHASE
Sl. no.
Environmental components
Predicted impacts
Probable source of impact
Mitigation measures Remarks
A CONSTRUCTION PHASE:
1 Air emissions Minor negative impact.
• Land preparation and construction activity. • Vehicular traffic.
• Water spraying on roads in project site • Regular maintenance of vehicles
• No remarkable increase in dust emission and other air pollutants
2 Noise Minor negative
impact.
Heavy machineries and truck movement
• Construction work during day time only • Ear plugs to workers • Regular maintenance of machineries and trucks.
• Noise will be below stipulated standard
3 Water Quality
Minor negative
impact.
• Wastewater produced from labourers • Excavated material
• Treatment of wastewater There is no Labour colony will be provided, as the local employees will be engaged for construction period
4 Land Quality
Land preparation and construction activity
• Change in land use pattern • Overburden & construction waste may pollute soil
• Project site is open land allotted for waste management so no change in land use pattern • Reuse of construction waste in construction for backfilling
• Quantum of excavated soil. & construction waste will be small.
5 Ecology (Terrestrial and aquatic)
Minor negative
impact.
Land preparation for construction of plant
Construction work during day time only and vehicles will be maintained in good condition
Increase in noise will be very small
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 8-
6 Socio- Economic
No adverse impact
- Direct and indirect employment opportunities Aesthetic and hygienic environment will be created.
Improvement in Socioeconomic status of local people. Solid waste problem of the city will be reduced
B OPERATION PHASE:
1 Ambient air quality
Minor negative impact.
Particulate and gaseous emissions from DG set.
Odor from the Anaerobic digester.
The emissions from DG will be let out through stack of heights 3 m AGL.
The anaerobic digester will be air tight with sealant and other inflating bags. The methane gas after generation will be stored in secured manure.
DG sets shall be used only during power failure. Occupationally during the venting and maintenance which is temporary.
2 Noise Minor negative impact near noise generation sources inside the premises.
Operation of Equipment (Pumps / Blowers)
Operation of DG set.
Acoustics will be provided for noise generating equipments of the plant
DG set will be provided with acoustic enclosure.
-
3 Water quality Positive impact is envisaged as the effluent will be treated to the on land discharge standards.
Nil NA as the treated effluent will be treated.
NA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 9-
10. POST-PROJECT MONITORING PLAN
A comprehensive monitoring program is suggested in below table
Table: - 2.0 monitoring schedule for environmental parameters
Sl.
No.
Particulars Monitoring
frequency
Duration of
monitoring
Important
parameters for
monitoring
I Air quality
a Ambient air monitoring
1. Project premises Once in a month 24 hourly sample RSPM, SPM, SO2,
NOx
2. Stack monitoring Once in a month Grab SPM, SO2, NOx,
HC, CO
II Water and wastewater quality
b Water quality
i. Groundwater at two
locations (up-gradient and
down-gradient)
Once in a month Grab As per KSPCB
requirements
c Wastewater quality
i. Wastewater Once in a month Grab As per KSPCB
requirements
III Soil quality
1. Within project premises at 1
location
Once in a year Composite
sample
As per KSPCB
requirements
2. Ecological preservation and up-
gradation
Seasonal Visual
observations
Survival rate
IV Noise monitoring
1. Project premises Once in a year Day and night As per KSPCB
requirements
V Hazardous waste monitoring
1. Hazardous waste
characterization
Annually Day and night As per KSPCB
requirements
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 10-
11. CONCLUSION
The overall impact of the project is beneficial as the Wet organic
biodegradable food waste will be processed and value full product and by-
products will be extracted from the waste highlighting the concept of
‗Resource Recovery‘. Adopting this technique would help in diverting the waste
reaching landfill and open dumping of biodegradable waste; which abides by
the MSW Rule, 2000, that states biodegradable material should not be
deposited in the sanitary landfill. The project will help in total elimination of
costs to BBMP for pick-up, transportation and disposal of organic waste
resulting in net saving of over Rs. 27 Crores per year; with saving of over
Rs. 540 Crores over life span (20 years) of the project.
The impacts of air, noise, water, soil and biological environment are
insignificant and socio-economic impacts are predominantly positive. All the
relevant safety norms and precautionary measures would be incorporated in
the system. Results of analysis of water, air and soil samples revealed that the
proposed biogas plant will have no impact on the existing water, air and land
environment.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 11-
CHAPTER 1
INTRODUCTION
1. PURPOSE OF THE REPORT
Amendment of the Environmental Impact Notification No. S.O. 60 (E) dated
27.01.1994, issued by the MoEF, Govt. of India has made mandatory under
Schedule-I of EIA notification for 30 different activities to obtain NOC (No
Objection Certificate) from the State Pollution Control Board and
Environmental Clearance from the Ministry of Environment & Forests (MoEF),
Govt. of India. This amendment to the EIA Notification is effective from
14.09.2006. It is in this context that all such activities need to prepare
Environmental Impact Assessment (EIA) report and also appear before Public
Hearing to ascertain the response of Public for the project based on the
General and Specific conditions in the said notification.
M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX),
having its registered office at Door no. 200, 4th Cross, 5th Main, ITI Layout,
Mallathalli, Bangalore, is establishing the “Sustainable Waste Management
and Renewable Energy” Project, that is exclusively meant for processing of
organic food waste and vegetable waste received from BBHA (Bruhat Bengaluru
Hotels Association) or other bulk generators. The organic/ biodegradable waste
would be collected from various hotels located in the jurisdiction of BBMP
(Bruhat Bengaluru Mahanagara Palike) to produce biogas through bio
methanation plant.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 12-
1.1 CATEGORY OF THE PROJECT
As per the amended EIA notification dated 14th September, 2006 the project
falls under Category 7 (i) under caption ―Common Municipal Solid Waste
Management Facility (CMSWMF)‖. The project falls under category B1 as per
MoEF, Office Memorandum No.J-13012/12/2013-IA-II (I) dated 24th December,
2013. The project comes under preview of General conditions of the
notification and will be appraised by State Environment Impact Assessment
Authority (SEIAA) and as per the guidelines; the proposed biogas project
necessitates preparation of EIA Report for obtaining clearance from the
concerned State Expert Appraisal Committee (SEAC).
1.2 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT
1.2.1 INTRODUCTION OF THE PROJECT PROPONENT
M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX),
having registered office at Door No. 200, 4th Cross, 5th Main, ITI Layout,
Mallathalli, Bangalore is establishing a biogas plant of 250 TPD capacity for
processing the food waste and vegetable/fruit peels generated from those
hotels located in the jurisdiction of BBMP, Bangalore.
As per the letter written to BBMP by Urban Development Directorate dated 14-
08-2013, the Revenue Department has granted 29 acres of land under Survey
No.85, Kannahalli Village, Seegehali Cross, Magadi Road, Bangalore, to BBMP
with the entire plot earmarked for treatment of waste over a lease term of 30
years. Amongst this, 5 acres has been lend to BBHA for a term of 20 years for
permissive use only, for processing of wet waste, with the ownership held by
BBMP itself. Copy of land documents is appended as Annexure-B.
The Bruhat Bengaluru Hotels Association with a view of reducing air, water and
soil pollution and also with an intention to minimize the pollution load, the
Association with the assistance of service provider has initiated to equip
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 13-
processing of wet organic food waste and extract bio methane. By the modern
technologies adopted to upgrade raw biogas, the quality of product is improved
by which the demand in market is increased. Establishment of biogas plant will
reduce the probable pollution load and reduce the odor nuisance to the nearby
residential developments due to windblown.
The plant will be designed to process 250 TPD of food waste and is expected to
generate about 25,135 cubic meters per day of biogas and 40 - 65 tons per day
of bio-fertilizer. Organic biodegradable waste for the plant would be made
available from those hotels & commercial establishments (Party Hall,
Choutries) in BBMP jurisdiction.
1.2.2 INTRODUCTION TO THE PROJECT
The land in which the project site is located is owned by Bruhat Bengaluru
Mahanagara Palike and is ear-marked for the treatment of waste. The land was
handed over by the Urban development Ministry of Karnataka State by a
concession agreement between BBMP – BBHA -NEX. The land is free from any
encumbrances and is compounded. Out of the total plot area of 29 acres, the
service provider NEX has been granted 5 acres for the project development, with
permissive use for 20 years. The land is fully compounded and there are no
villages/residential area/factories up to 500 meters from the boundaries of the
plot.
1.3 BRIEF DEESCRIPTION OF NATURE, SIZE, LOCATION OF THE
PROJECT AND ITS IMPORTANCE TO THE COUNTRY, REGION
1.3.1 NATURE, SIZE AND LOCATION OF THE PROJECT
M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX),
having office at Door No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli,
Bangalore, is establishing Biogas Plant of capacity 250 TPD for processing the
food waste generated from various hotels located in the jurisdiction of BBMP,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 14-
Bangalore. The NEX has obtained Authorization letter from KSPCB and further
submitted to get Consent for Establishment (CFE) from Karnataka State
Pollution Control Board that is being under consideration.
The biogas plant is located at Survey No.85, Kannahalli Village, Yeshwanthpura
Hobli, Seegehalli Cross, Magadi Road, Bangalore at a distance of around 17 km
from Bangalore city terminal. The co-ordinates of the plant - Latitude:
77°26'48.48" E; Longitude: 12°58'14.88" N and MSL: 962 m. Around 400 star
hotels and around 1400 BBHA Members are joined project/biogas plant as the
contributor of food waste. The location of biogas plant is as below in fig 1.1.
1. Yashwanthpur, West of Chord Road, Malleshwaram, Rajajinagar and Peenya
Industrial Area approximately 80-100 tones ( around 360 hotels, 150 Kalyana
Mantapas , 6 Malls and 300 Restaurants )
2. Gandhinagar, Corporation, MG Road, Residency Road surrounding areas
approximately 65-70 tones ( around 400 Hotels, 200 Restaurants, 3 Malls )
3. Race Course Road, Infantry Road, Shivajinagar, Ulsoor, Indiranagar, Old Airport
Road approximately 45-50 tones ( 150 Hotels, 60 restaurants, )
4. Bangalore South—Jayanagar, JP nagar, BTM layout, and surrounding
areasapproximately 40-50 tones. (1200 Hotes and Restaurants 130 Kalyana
Mantapas )
5. Part of Domlur, Koramangala, surrounding areas approximately 20-25
tones ( 120 Hotels, 175 restaurants and Malls )
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 15-
1.3.2 PROJECT AT A GLANCE
Sl.No. Details
1 Project Sustainable Waste Management and
Renewable Energy Project setting up a biogas
plant of capacity 250 TPD.
2 Project developers M/s. NobleExchange Environment Solutions
Bangalore Private Limited (NEX), having office at
Door No.200, 4th Cross, 5th Main, ITI Layout,
Mallathalli, Bangalore – 560 056.
3 Location of the
site
Survey No.85, Kannahalli Village, Yeshwanthpura
Hobli, Seegehalli Cross, Magadi Road, Bangalore
– 560 007.
4 Constitution of
the Organization
Private limited company
5 Longitude
Latitude
MSL
77o 26` 48.48‖ E
12o 58` 14.88‖ N
962 m from sea level
6 Total plot area 20,234 sq m (5 acres)
7 Project cost Rs. 50,00,00,000
(Rupees Fifty Crores Only).
8s Air
pollution/Noise
pollution
1 X 350 kVA capacity DG set id provided with
adequate stack and acoustics.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 16-
FIG 1.1: SITE LOCATION MAP
1.3.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE
COUNTRY/REGION
The biogas plant project site is granted by BBMP to BBHA as a permissive use
for 20 years. The site selection for biogas plant is evident that the land is
earmarked for the treatment of waste and the establishment of biogas plant to
process organic food waste generated from hotels will help in processing of
waste and extract fuel which reduces pollution load on the environment. The
biogas plant has been designed based on anaerobic digestion and Continuous
stirred flow tank reactor technology for 250 TPD capacity.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 17-
The treatment of organic food waste generated through the city commercial /
Hotels units is the need of hour. Organic waste, specifically food waste has been
identified as the input for this project; the reason will be highlighted below.
Why Food waste?
Bio degradable waste is any waste that can be decomposed by the natural
processes and converted into the elemental form. Example: kitchen waste, food
waste, garden waste, animal dump, oil and grease, tissue paper, etc.
The land filling of waste, especially bio-degradable waste can pollute the
environment and produce greenhouse gasses (GHG) which contribute to climate
change. Bio-degradable waste management is to prevent or reduce as far as
possible, any damage to the environment caused by land filling such as pollution of
surface water, ground water, soil, air and the production of greenhouse gasses
that contribute to climate change. Food waste is one of the single largest
constituent of municipal solid waste stream.
Easily Biodegradable – Food waste is highly biodegradable and has a much higher
volatile solids destruction rate (86-90%) than bio solids. This means that even
though additional material is added to the digesters, the end residual will only
increase by a small amount.
Renewable Energy Generation – Arguably, the most important reason that food
waste should be anaerobically digested is for capturing the energy content. Unlike
bio solids and animal manures, post-consumer food scraps have had no means of
prior energy capture. In fact, in a study done by East Bay Municipal Utility District
it was revealed that food waste has upto three times as much energy potential as
bio solids.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 18-
Environment Benefits of Organic Waste Management:
The open dump sites and poorly managed waste facility is a potential
threat/hazard to the public health and environmental quality. Improper solid
waste management deteriorates public health, causes environmental pollution,
accelerates natural resources degradation, causes climate change and greatly
impacts the quality of life of citizens.
A large portion of solid waste is lost in landfill. Landfills are associated with a
variety of chemical hazardous emission (e.g., carbon dioxide methane and
hydrogen sulphide). In addition several of these compounds have been classified as
carcinogenic by IARC (e.g. benzene and metal fumes such as cadmium). Human
exposure to these hazards could occur via inhalation of polluted air ingestion of
water or, in the case of occupational exposure, skin contact with polluted air or
water. The World Health Organization (WHO) has suggested that any potential
exposure to landfill-associated hazards is probably limited to within 1 km from a
landfill for air pathways, and 2 km for water pathways.
There is some evidence that landfill can be a hazard for the health of landfill
workers and populations leaving near landfill sites. In particular, a cross-sectional
study revealed that landfill workers report a higher prevalence of work-related
dermatological, respiratory and auditory problems than control workers.
An integrated scientific waste management facility is the most viable solution to
alleviate the waste issue in the country. Each waste stream is treated scientifically
and environmentally friendly way to ensure the maximum energy recovery, which
would otherwise cause serious public health and environmental damage. The
benefits of scientifically managed waste treatment facility are highlighted below:
Creates Hygienic & Healthy Living Environment for the citizens- Flies breed in
some constituents of solid wastes, and flies are very effective vectors that spread
disease. Mosquitoes breed in blocked drains and in rainwater that is retained in
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 19-
discarded cans, tire and other objects. Mosquitoes spread disease, including
malaria and dengue.
Improves the quality of land and soil- Land fill degrades the quality of land and soil
in the site. Presence of plastics and heavy metals in the soils make it unfit for
agriculture and emissions of methane and structural instability of the land make it
unfit for construction activities.
Avoids ground and surface water Contamination - Polluted water (leachate)
flowing from waste dumps and disposal sites can cause serious pollution of water
supplies, ponds and lakes. Chemical wastes (especially persistent organics) may be
fatal or have serious effects if ingested, inhaled or touched and can cause
widespread pollution of water supplies.
No air contamination due to gases, litter, dust & bad odor - The exposure to air-
borne bacteria is infectious. Toxic materials present in solid waste are
determinants for respiratory and dermatological problems, eye infections and low
life expectancy. The carbonaceous fractions and toxic elements like Cr, Pb, Zn,
etc., dominate the fine particle range.
Overcomes other problems due to Rodents, Pests, Fire, Bird menace, Slope failure,
Erosion etc. - The untreated waste (like abattoir waste) in the landfill attracts the
wild animals, which is contaminated and is not deemed right for the consumption.
Also, the straying wild animals are considered dangerous for the human habitats
staying in the vicinity.
Reduction in Greenhouse Gasses: MSW is the second largest anthropogenic
methane emitter and the largest greenhouse gas emitter. Methane is a
significantly more powerful greenhouse gas than carbon dioxide, with greater
potential for increasing global warming effects.
Better utilization of waste: Production of Energy (Heat & Electricity), the
replacement of conventional fuels can take a part load of the energy consumed by
various industries.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 20-
1.3.4 BIOGAS PLANT
A biogas plant is the name given to an anaerobic digester that treats farm
waste or energy crops or biodegradable wastes including sewage sludge and
food waste.
Benefits of Biogas plant
The production of an energy resource, biogas from the plant is a most
tangible benefit.
The biogas plant can be used at centralized as well as decentralized
level. Prominently, the construction and operation of biogas plants assists to
the decentralized power production which could be the main objective to
compromise with the energy commitments.
The biogas plant‘s feedstock materials are usually organic wastes (e.g.
animal manure, agro-industrial wastewater) which deteriorate the
environmental quality of the region where they are produced. The collection
and energy exploitation of these materials through anaerobic digestion, not
only provides significant amounts of green energy to the grid, but also
mitigates the pollution effects on the local ecosystems.
In context to environmental aspect:
production of clean energy from waste
reduced CO2 emissions of biogas in contrast to fossil fuels
recycling of previously unused energy resources
active environmental protection through energy-related recycling
waste recycling
production of high-quality, natural fertilizer
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 21-
Reduction of dependence on fossil fuel lies with the energy economic
benefit associated with the biogas plant resulting in generation of renewable
and sustainable energy source.
Emission issues
methane reduction through elimination of digestible organic mass
odor nuisance reduction through digesting substrates
Biogas plant will contribute in reducing greenhouse pollutant emission
from unregulated dumpsites.
Nutrient reclamation by organic waste, i.e., the application of digester
slurry to unproductive soils would eventually improve the soil quality, or even
unfertile land could be reclaimed.
1.3.5 NECESSITY TO SETUP A BIOGAS PLANT
Whether, the rapid development of India‘s tremendous economy is following a
path of exclusive fossil energy based growth or is diverting towards a
sustainable integration of renewable energies into their energy consumption, is
a question of how fast renewable energy companies are developing alternative
concepts and how fast these concepts become technically, economically,
socially accepted. The Composition of municipal solid waste in India is shown in
fig.1.2.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 22-
FIG 1.2: COMPOSITION OF MUNICIPAL SOLID WASTE IN INDIA
A major fraction of urban MSW in India is organic matter (51%)
Recyclables are 17.5% of the MSW and
The rest 31% is inert waste. The average calorific value of urban MSW is 7.3
MJ/kg (1,751 kCal/kg) and the average moisture content is 47%.
The landfilling of waste, especially bio-degradable waste can pollute the
environment and produce greenhouse gases (GHG) which contribute to climate
change. Biodegradable waste management is to prevent or reduce as far as
possible, any damage to the environment caused by landfilling such as pollution
of surface water, ground water, soil, air and the production of GHGs that
contribute to climate change. This also demands to extract biofuel,
incorporating waste to energy concept.
The biogas plant might have the potential to offer an alternative energy
solution, and in addition to target the challenges of a modern society in energy
supply, waste control and pollution reduction. In the following a short
assessment shall be undertaken to highlight the current status and future
developments of the biogas plant in India.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 23-
1.3.6 STATUS OF BIOGAS PLANTS IN INDIA
1.3.6.1 ALL INDIA SCENARIOS
In India, the key biomass feed-stocks available include rice husk-straw,
bagasse, sugarcane tops, leaves-trash, groundnut shells, cotton stalk, coconut
residues, mustard stalk and wastes from agricultural products. Possible feed
sources reported for biogas reactor available in India are shown in fig 1.3.
Different methods are used to improve biogas production and methane yield
such as use of additives with organic matter as substrate, slurry recycling,
operational parameter optimization for process, change in type of reactor and
other configuration of biofilm. Biogas is being generated form cattle dung and
kitchen waste since long but for highest yield the reactors are being optimized
not only in size and types but also the substrates are studied.
List of substrates used for biogas production are:
Biological additives
Powdered leaves of some plants and legumes
Agricultural residue
From grains and crops
From diary manure and algal biomass
Food, fruit and vegetable waste
Animal waste
Municipal waste
Cellulose containing substrates
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 24-
FIG 1.3: POTENTIAL BIOGAS FEED SOURCES
Substrates are consumed anaerobically to produce biogas and residue can be
used as superior fertilizer which is nutrient rich and odorless. Indian biomass
power technology capacity demand is likely to be constrained by food security
and the issue of high power generation cost, compared to the cheaper cost of
generating electricity from coal. Therefore improve technologies for energy
generation from biomass in feasible cost and methane capture from anaerobic
wastewater treatment makes economic sense to follow the waste to energy
prospect. According to EPA, it is possible to produce electricity for as little as
$0.038 per kWh assuming a 20 years capital repayment scope. This can be
compared favorably to national electricity rates that range from $0.057 to
$0.228 per kWh.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 25-
1.3.6.2 LARGE SCALE BIOGAS PLANTS IN INDIA
In India, we have many small scale plants established across the nation in dairy
farms with cattle herd of 8-10 animals. It does not require much of an investment
or time for installation and generates energy, which could be directly used for
electricity generation or converted to bio-CNG or bio-methane, and then utilized
for purposes similar to that of compressed natural gas. ‗Bio-CNG‘ is combustible
biogas that is cleaned to the specifications of natural gas, while bio-methane is
biogas with higher concentrations of methane and little carbon dioxide.
The amount of combustible gas produced by small scale biogas plants is less than
40,000 cubic meters. Medium-scale biogas plants produce gas of around 40,000-
200,000 cubic meters. These plants mainly utilize raw material such as municipal,
industrial and agricultural waste. Industrial waste would be organic by products
from industries such as food, beverage or pharmaceutical. Some mid-scale plants
owned by Pune Municipal Corporation (PMC) namely the Peshwe Park Project,
Yerwada project were set up in 2010 and now they have total 21 plants
collectively handling 163 Tons of organic waste per day. These are all organic
waste to electricity project.
Tata Consultancy Services (TCS) one of the leading IT Company has constructed
plant within their premises which is processing/treating organic waste obtained
from their canteen leading to production of 200 cubic meters of biogas every day.
MNC automobile company Volkswagen also have a portable biogas plant installed
within their premises, the plant treats/processes 500 kg of organic waste per day
to produce 40 cubic meters of biogas, which is then used to heat stoves kitchen
rather than power generation. However, direct conversion of biogas to energy is
under research till now with help of fuel cell. The current employed technique is
utilizing biogas as a fuel for combustion engines, which in turn power an electric
generator to produce electricity.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 26-
Large scale biogas plants are the ones where more than 2,00,000 cubic meters of
gas is produced. Here all kinds of organic materials are used for production. Since
a large amount of gas is generated, it is directly converted into electricity. The
largest biogas plant in India is in Satara district, Maharashtra. Here 25,000 cubic
meters of biogas is generated every day from 600 tons of sugarcane waste
obtained from sugar mills in the vicinity. Gas obtained is converted to compressed
biogas (CBG) and used as fuel. This plant uses an advanced Continuous Stirred
Tank Reactor for faster anaerobic process.
Another large biogas plant is made under the National Biogas & Manure Programme
by the Ministry of New & Renewable Energy. This plant produces nearly 9,36,000
cubic meters of biogas per day. They came up with technology of pre-fabricated
digesters to reduce the losses made by these plants. Further, the NBMMP project
supports 13 regional development and training centers to empower people with
the right knowledge for business in this area.
People are becoming aware and have begun to build such plants on small and large
scale in various parts of the country. City dwellers are yet to realize the immense
business opportunity of utilizing municipal or industrial waste for biogas
generation. There are many Indian firms who deal with the construction of biogas
plants such as Jain Irrigation System Ltd., Indian Biogas Association etc. If we
provide them with information about the source of material and amount, land
available, and money, these companies can build these plants on a turnkey basis,
planning an constructing the entire set-up.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 27-
FIG 1.4: POTENTIAL BIOGAS APPLICATIONS
1.3.6.3 STATE-WISE TARGETS AND ACHIEVEMENT
The Ministry of New and Renewable Energy (MNRE) has implemented a National
Biogas and Manure Management Programme (NBMMP) for setting up family type
biogas plants mainly in rural areas including remote villages.
Under the programme, a target of setting up 1.06 lakh biogas plants has been
fixed under NBMMP for the year 2013-14. State-wise targets and achievement
under national biogas and manure management programme during the year
2013-14 is shown below.
Potential Biogas Applications
Farm use
Electricity generation through electricity generator for farming applications
Fuel for irrigation pumps
Refrigeration systems (cold storage)
Municipal use
Savings in waste management activity
Biogas supply to household in way of “waste treatment to money”
Electricity generation which can be used for running waste and wastewater treatment plants
Household use
Direct burning use, cooking, room heating, water heating
Hot water boilers and process heating
Industrial use
Supply to canteen (savings on LPG)
Earning of carbon credits
Use in forced-air furnaces
Electricity generation for internal local requirement
As a vehicular fuel
Converting the biogas to compressed natural gas (CNG) for transportation
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 28-
FIG 1.5: PROJECTION OF THE STATE-WISE TARGETS AND ACHIEVEMENT UNDER
NBMMP DURING 2013-14
Biogas is a very profitable option especially for the villages where traditional
sources of energy are hard to come by. The State-wise number of households
covered by family type biogas plants during each of the last three years is given
in below table 1.1.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 29-
TABLE 1.1: STATE-WISE LIST OF BIOGAS PLANTS INSTALLED DURING LAST THREE YEARS
Sl. No. Name of State/ UT Numbers of Family type Biogas Plants installed
2010-11 2011-12 2012-13
1 Andhra Pradesh 16275 15346 16153
2 Arunachal Pradesh 175 150 190
3 Assam 6732 6581 7397
4 Bihar 350 3285 300
5 Chhattisgarh 3832 4779 3933
6 Goa 18 65 58
7 Gujarat 6105 2631 5623
8 Haryana 1379 1819 1303
9 Himachal Pradesh 445 426 362
10 Jammu & Kashmir 114 136 294
11 Jharkhand 913 750 641
12 Karnataka 14464 12363 13485
13 Kerala 3941 3483 3991
14 Madhya Pradesh 16742 12415 11946
15 Maharashtra 21456 22220 19023
16 Meghalaya 1275 1390 670
17 Mizoram 100 100 500
18 Nagaland 1171 1325 750
19 Odisha 6050 7186 7002
20 Punjab 23700 14173 12127
21 Rajasthan 275 498 526
22 Sikkim 358 635 251
23 Tamilnadu 1493 1531 1321
24 Tripura 89 117 219
25 Uttar Pradesh 4603 4759 3923
26 Uttarakhand 2082 2114 1831
27 West Bengal 17000 19986 10522
28 Delhi/ New Delhi 1 1 0
29 KVIC, Mumbai * * *
Total 1,51,138 1,40,264 1,24,341
* Annual achievements of KVIC, Mumbai have been distributed among States.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 30-
1.4 SCOPE OF STUDY - DETAILS OF REGULATORY SCOPING CARRIED
OUT(AS PER TERMS OF REFERENCE)
The purpose of EIA/EMP is to critically analyze the environmental impacts due
to construction and operation of Sustainable Waste Management and
Renewable Energy project with respect to feed material transportation,
processing of waste, treatment and disposal of treated effluent, disposal of
sludge/slurry and mitigation measures to reduce the pollution and to delineate
an Environmental Management Plan along with recommendations and
suggestions. TORs have been considered for preparation of Environment Impact
Assessment studies for the project.
1.4.1 SCOPE OF STUDY
Preparation of EIA report complying with the TOR issued by the SEAC.
Collecting baseline data on different environmental parameters for the
period from October to November.
Impact assessment and suggestion of mitigation measures to minimize
the impacts.
Preparation of Environmental Management Plan and Environmental
Monitoring Plan
Primary and secondary data collection for preparing EIA/EMP report.
Submission and presentation of salient features of EIA/EMP report to the
SEAC for getting Environmental Clearance.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 31-
1.4.2 COMPONENTS OF EIA REPORT
Depending on nature, location and scale of the project, EIA report contains the
following components:
Air Environment
Noise Environment
Water Environment
Land Environment
Biological Environment
Land Environment
Socio-Economic and Health Environment
Environmental Monitoring Program
Environment Management Plan.
1.4.3 TERMS OF REFERENCE (TOR)
Terms of references were specified to this project by State Level Expert Appraisal
Committee (SEAC), Karnataka during their 115th Meeting held on 11th& 12th August
is given below. The EIA studies were conducted based on these TOR and
accordingly the EIA report is prepared. The list of TOR and their compliances is
appended in the table 1.2 below.
Terms of Reference (TOR) for the biogas plant established for processing of
organic waste generated from various hotels & other commercial
establishments located in the jurisdiction of BBMP is tabulated below.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 32-
TABLE 1.2: TERMS OF REFERENCE (TOR)
Sl.No. Description Details provided in the
chapter/section
1 Executive summary of the project Executive summary of the
project is appended in the EIA
report (Page no. 1 to 10).
2 Justification of the project Justification/need for the
project is detailed in chapter-1
under section 1.3.3
3 Promoters and their background Project proponent details are
appended in Chapter-1 under
section 1.2.1
4 Regulatory framework Detailed regulatory framework
is appended in the Chapter -2,
Section 2.15
5 Project location and plant layout The location of project and
layout plan is detailed in
Chapter-2, Fig 2.6.
6 Infrastructure facilities including
power sources
Detailed in Chapter -2, section
2.17.
7 Total cost of the project along
with realistic estimates and cost
for environment protection
measures.
Projected cost of the project is
detailed in chapter-2 under
section 2.4
8 Project site location along with
site map of 10 km area and site
details providing various
industries, surface water bodies,
forests etc.
Topo map indicating project
site location with15 km radius
is appended as annexure - 2
9 Present land use based on
satellite imagery for the study
area of 10 km radius. Location of
National Park/Wild life
Sanctuary/Reserve forest within
10 km radius of the project.
Google Map Covering 10 Km
Aerial Distance From The
Project Site is appended in
chapter 3 fig:- 3.15 and land
use map of the project site is in
fig :- 3.16
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 33-
10 Site-specific micro-meteorological
data using temperature, relative
humidity, hourly wind speed and
direction and rainfall is necessary.
Details appended in chapter-3
under section 3.2
11 Details of the total land and
break-up of the land use for green
belt and other uses.
Detailed in table 2.4 and fig :-
2.5.1
12 List of products along with the
production capacities
Detailed in Chapter – 2, section
2.7
13 List of raw material required and
source.
Detail is appended in chapter-2
table 2.6.
14 Manufacturing process details
along with the chemical reactions
Technology and process
description is detailed under
section 2.7 & 2.8 in chapter-2.
15 Design details of ETP & digesters Design details of anaerobic
digester tank and ETP is
detailed under section 2.8 &
2.16.3.1 in chapter-2.
16 Details of water and air pollution
and its mitigation plan
Mitigation measures for air
pollution is addressed in section
2.17 of chapter-2.
17 Ambient air quality at 6 locations
for within the study area of 10
km, aerial coverage from project
site. Location of one AAQMS in
downwind direction. The NAAQ
standards issued on 16.11.2009 by
MoEF shall be followed.
Ambient air quality monitoring
and the sampling station details
are addressed under section
3.2.2.1 of chapter-3.
18 Ambient air quality modeling for
plant.
The only air pollution source
from the project is from DG set
and therefore since there are
no other sources of air pollution
ambient air quality modeling is
not envisaged..
19 One season (non-monsoon) data
for air, water and noise
monitoring.
Details are appended under
section 3.2.2 of chapter-3.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 34-
20 Details regarding existing status of
plant with respect to existing
stacks emission data.
The project is fresh proposal as
the existing stacks emission
data is not required.
21 An action plan to control and
monitor secondary fugitive
emissions as per CPCB norms and
their control
Detailed in chapter – 4.
22 Determination of atmospheric
inversion level at the project site
and assessment of ground level
concentration of pollutants from
the stack emission based on site-
specific meteorological features
The air pollution source from
the project is DG set since
dispersion studies and modeling
of gaseous pollutants is not
contemplated
23 Permission for the drawl of ground
water from the CGWA. Water
balance cycle data including
quantity of effluent generated,
recycled, reused and discharged.
Application is submitted to
Karnataka Ground water
Authority and quantity of
effluent generated, recycled,
reused and discharged is
detailed in Chapter – 2, section
2.16.
24 Ground water monitoring
minimum at 6 locations should be
carried out. Geological features
and geo-hydrological status of the
study area and ecological
status(Terrestrial and Aquatic)
Surface and ground water
quality detail is affixed under
section 3.2.2.3 of Chapter-3.
25 The details of solid and hazardous
wastes generation, storage,
utilization and disposal
particularly related to the
hazardous waste.
Details of solid waste is
addressed under section 2.17.4
of Chapter-2.
26 Risk assessment for storage and
handling of chemicals/solvents
including engineered systems and
HAZOP study
Risk assessment is detailed in
section 7.2 of Chapter -7.and
HAZOP study for methane is
detailed in Annexure- A
27 Occupational health of the
workers should be incorporated
Occupational health detail is
briefed under section 7.4.13 of
Chapter-7.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 35-
28 Scheme for rainwater harvesting Rain water harvesting plan will be implemented to collect, and store rainwater to replenish the underground water. The rainwater thus collected can be used for irrigation and greenery development in the premises. This water can also be used to supplement the fresh water requirement in the plant.
29 Socio-economic development
activities should be in place
Detailed in Chapter-3 of section
3.2.2.6
30 Note on compliance to the
recommendations mentioned in
the CREP guidelines
The proposed project is for
concept of food waste to
energy thereby fulfills the
primary responsibility of
environmental protection
through scientific processing of
solid waste and resources
recovery.
31 Detailed Environment
Management Plan (EMP) with
specific reference to details of air
pollution control system, water
and wastewater management,
monitoring frequency,
responsibility and time bound
implementation for mitigation
measure should be provided.
EMP is detailed in chapter-10
32 EMP should include the concept of
waste-minimization,
recycle/reuse/recover
techniques, Energy conservation
and natural resource
conservation.
Detailed in Section 4.2, Chapter
4
33 Any litigation pending against the
project and/or any
direction/order passed by any
court of law against the project,
if so, details thereof.
None
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 36-
34 Action plan for developing green
belt in 33% of the plot area
Detailed in detailed in section
2.6.1 and fig: - 2.6 of
Chapter – 2.
35 Additional Corporate
Environmental Responsibility
i) a) Does the company
have a well laid down
Environment Policy
approved by its Board of
Directors? If so, it may
be detailed in the EIA
report.
b) Does the Environment
Policy prescribe for
standard operation
process/procedures to
bring into focus any
infringement/deviation/
violation of the
environmental or forest
norms/conditions? If so,
it may be detailed in
the EIA.
ii) What is the hierarchical
system or
Administrative order of
the company to deal
with environmental
issues and for ensuring
compliance with the
Environmental
Clearance conditions
details of this system
may be given.
iii) Does the company have
a system of reporting of
non-
compliances/violations
Environment Policy approved by
its Board of Directors is
appended as annexure -C.
Detailed in section 10.5.1 of
Chapter -10.
The reporting of non-
compliance to the top
management (Board of
Directors of the company
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 37-
of environmental norms
to the Board of
Directors of the
company and/or
shareholders or
stakeholders at large?
This reporting
mechanism should be
detailed in the EIA
report.
and/or shareholders or
stakeholders) will be through
lower management, Middle
management of the project.
36 Corporate Social Responsibility
related to Environmental issues.
The very establishment of the
project is to ensure
environmental protection
through concept of waste to
energy which will ensure waste
minimization in scientific
manner and resource recovery.
As a Social corporate
Responsibility related to
Environmental issues the
project will develop and
implementation effective
environmental management
plan details are appended in
Chapter – 4.
37 Additional TOR prescribed by the
State Expert Appraisal Committee
(SEAC), Karnataka
a) Quantification of food
waste for the proposed
project
a) Biogas plant of 250 TPD
capacity for processing
the food waste and
vegetable/fruit peels
generated from those
hotels.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 38-
b) Mode of transportation
indicating routes/area, of
the food waste
c) Mitigation measures for
odor management
d) Process description and
contingency plan in case of
breakdown of digesters
e) HAZOP studies to be
conducted
f) Risk assessment
management
g) Monitoring of gases in the
plant.
h) Salt percentage from the
manure generated to be
ascertained
i) Study on occupational
hazards
j) Effluent management
b) Detailed in chapter 2,
section 2.7.2.
c) Detailed in chapter -4,
section - 4.2.1.5.2.
d) Process description is
detailed in chapter 2,
section 2.7.
e) HAZOP studies is
appended in annexure –A
f) Risk assessment is
detailed in section 7.2 of
Chapter -7.
g) Gas detectors with alarm
system will be installed
in strategic locations to
detect any fugitive
emission or leakage of
methane etc.
h) Salt percentage from the
manure generated is
detailed in section
2.10.2 of Chapter – 2.
i) Occupational health
detail is briefed under
section 7.4.13 of
Chapter-7.
j) Effluent treatment and
its management is
appended in section
2.16.3 of Chapter -3.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 39-
k) Exploring the possibility of
converting carbon dioxide
generated into liquefied
carbon and carbon fuel.
l) Mechanism to replace solid
waste (molecules) from
plant.
k) The possibility of
converting CO2
generation from LPG and
Carbon fuel will be
explored through
intensive research in due
course.
l) Molecular sieves disposal
– the biogas up-gradation
process uses molecular
sieves for absorption of
CO2. Generally these are
generally zeolite based
alumina silica sieves. The
life of these sieves is
between 6 – 8 years after
which they need to be
replaced. Total of 230
Kg‘s of sieves will be
used for scrubbing the
biogas. Since the sieves
will be used at a very
low operating pressure,
the life span is large.
The disposal of the
replaced sieves will be in
accordance to Hazardous
Waste Disposal rules
India 2003. The
aluminosilicate sieves
will be given to suitable
approved treatment
facilities for disposal.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 40-
m) Scheme proposed to make
entire storage and
operational area to be
impervious.
n) PP to study and propose the
plan for development of
green belt around the
project area with native
species of fruit yielding,
shade bearing, trees,
shrubs etc.
m) Impervious lining will be
provided to such areas
where raw waste will be
handled to ensure that
there is no spills to
release out.
n) During operational phase
more than 33% of the
plant area will become
green under
landscape/land cover
and planting native
species of fruit yielding,
shade bearing, tress
shrubs etc., detailed in
section 2.6.1 of
Chapter – 2.
1.4.4 GENERIC STRUCTURE OF EIA DOCUMENT
This EIA report presents the existing baseline scenario and the assessment and
evaluation of the environmental impacts that may rise during the construction
and operational phases of the project. This report also highlights the
Environmental Monitoring Program during the construction and operation
phases of the project and the post project monitoring program. In terms of the
EIA Notification of the MoEF dated 14th September 2006 as amended Dec.
2009, the generic structure of the EIA document will be as under:
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 41-
TABLE: 1.3 GENERIC STRUCTURE OF EIA DOCUMENT
SL. NO. CHAPTERS NAME DESCRIPTION
CHAPTER 1: INTRODUCTION
Introductory information is presented in this
Chapter. The introduction provides a
Background to the project and describes the
objective of this document. This Chapter also
includes the outline of the project and its
proponent. The purpose and organization of the
report is also presented in this chapter.
CHAPTER 2:
PROJECT
DESCRIPTION
This Chapter includes Project Description and
Infrastructure Facilities delineating all industrial
and environmental aspect of M/s. Noble Exchange
Environment Solutions Bangalore Private Limited
(NEX) Construction and operation phase activities
as well as process details of proposed scenario.
This Chapter gives information about storage and
handling, water and wastewater quantitative
details, air pollution and control system, sludge
storage facility, utilities, greenbelt and safety
measures for proposed plant.
CHAPTER 3:
DESCRIPTION OF
THE ENVIRONMENT
This Chapter provides Baseline Environmental
Status of Environmental components
(Primary data) delineating meteorological details
of the project site and surrounding area.
CHAPTER 4: ANTICIPATED
ENVIRONMENTAL
IMPACTS &
MITIGATION
MEASURES
This Chapter presents the analysis of impacts on
the environmental and social aspects of the
project as a result of establishment of plan and
thereby suggesting the mitigation measures.
CHAPTER 5:
ANALYSIS OF
ALTERNATIVES
This chapter includes the justification for the
selection of the project site from Environmental
point of view as well as from economic point of
view so that the technology will be affordable to
the member units of the industrial area.
CHAPTER 6:
ENVIRONMENTAL
MONITORING
PLAN
This chapter will include the technical aspects of
monitoring, the effectiveness of mitigation
measures which will include the measurement
methodologies, frequency, location, data
analysis, reporting schedules etc.,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 42-
CHAPTER 7: ADDITIONAL
STUDIES
This chapter will detail about the Public
Consultation sought regarding the project. It will
also identify the risks of the Project in relation to
the general public and the surrounding
environment during construction and operation of
the project and thereby presents Disaster
Management Plan.
CHAPTER 8
& 9:
PROJECT BENEFITS
&
ENVIRONMENTAL
COST BENEFIT
ANALYSIS
The realization of the project activity is envisaged
to impart benefits to the areas in concern. This
Chapter will identify the benefits from the
project and summarize them.
CHAPTER 10: ENVIRONMENTAL
MANAGEMENT
PLAN
It is the key Chapter of the report and presents the mitigation plan, covers the institutional and monitoring requirements to implement environmental mitigation measures and to assess their adequacy during project implementation.
CHAPTER 11: SUMMARY AND
CONCLUSION
This chapter summarizes the information given in
Chapters in this EIA/EMP report and the
conclusion based on the environmental study,
impact identification, mitigation measures and
the environmental management plan.
Names of consultants engaged in the preparation
of the EIA/EMP report along with their brief
resume and nature of Consultancy rendered are
included in this chapter
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 43-
CHAPTER 2
PROJECT DESCRIPTION
2.1 TYPE OF PROJECT
The proposed project is a biogas plant of capacity 250 TPD being established
for processing of the organic wastes comprising mainly wet food waste,
vegetable/fruit peels & other organic waste generated from bulk generators
like hotels & restaurants, commercial malls, IT parks and choultries etc.
located within the BBMP limits.
The project is proposed at Survey No.85, Kannahalli Village, Yeshwanthpura
Hobli, Seegehalli Cross, Magadi Road, Bangalore.
2.2 NEED FOR THE PROJECT
The site selection for the setting up of biogas plant is evident that the total 29
acres plot owned by BBMP is already earmarked for treatment of waste and the
project site is located in the middle of this plot. The establishment of biogas
plant will help in recovery of the organic food waste to extract biogas, thereby
diverting the waste reaching landfill; in turn influencing on reduced GHG
emissions and reducing the pollution load on environment. The project
emphasizes on resource recovery and waste to energy concepts of waste
management. There are 400 numbers of hotels who have joined to contribute
the feed material to the plant. The member units will send the generated food
waste to the facility via specially designed drip free trucks meant for the
transportation of this feed material. The biogas plant has been designed based
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 44-
on anaerobic digestion (AD) and continuously stirred reactor (CSTR) technology
for a capacity of 250 TPD.
Discussion about need of the project is detailed in Chapter -1 section 1.3.3
2.2.1 LOCATION (MAPS SHOWING GENERAL LOCATION, SPECIFIC
LOCATION, PROJECT BOUNDARY & PROJECT SITE LAYOUT)
The Proposed ―Sustainable Waste Management and Renewable Energy‖ project
involving solid waste processing (food wet waste generated from bulk
generators) is located at Survey No. 85, Kannahalli Village, Yeshwanthpura
Hobli, Seegehalli Cross, Magadi Road, Bangalore – 560 091.
The site is located towards West of Bangalore city off Magadi Road next to the
Seegehalli bus depot and has very good connectivity by public transport to city.
Location map, photographs showing site views, Google image is appended in
the subsequent sections.
2.3 SITE SELECTION
The site is selected on the basis of the CDP map where in the proposed location for
the project is comes under the area earmarked for Solid Waste Management
facilities.
The proposed project site is at a distance of about 17 km (aerial distance) from
Bangalore City railway station at Latitude- 12o 58` 14.88‖ N. Longitude- 77o 26`
48.48‖ E with 962 m above MSL. Expected water, power requirement & other
utilities are available around the site. The location map showing the project
location, CDP map, Top[o map, site photos and Google map is shown in
fig 2.1, 2.2, 2.3, 2.4 & 2.5.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 45-
FIG 2.1: LOCATION MAP SHOWING THE PROJECT LOCATION
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 46-
FIG 2.2: CDP MAP SHOWING THE LOCATION OF THE PROJECT AND
PROPOSED LANUSE
Sources: - BDA Revised Master Plan 2014
Scale:-1/10,000
CDP map with Index is appended as annexure – 2.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 47-
FIG 2.3: TOPO MAP
Sources: - Survey of India
Scale: 1: 50,000
PROJECT SITE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 48-
FIG 2.4: SITE PHOTOS
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 49-
FIG 2.5: GOOGLE MAP SHOWING PROJECT SITE BOUNDARY
Note:-
Longitude: - 12o58'14.88" N
Latitude :- 77o26'48.48" E
MSL :- 962 m
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 50-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 51-
2.4 SIZE OR MAGNITITUDE OF OPERATION
The biogas plant proposed is sized to handle and process 250 TPD capacity of food
waste and is the largest capacity plant at present in India to handle food wastes
The total capital investment on the project is Rs. 50,00,00,000/- (Rupees Fifty Crores
only).The break- up of the cost on the project is as detailed in the below table 2.1
Table 2.1: Projected cost of the project
Sl. No. Details Cost in Crores
1 Infrastructure cost 8.4
2 Plant & Machinery 32.9
3 Design & Project Implementation/ Contingency 5.5
4 Preliminary expenses 3.2
Total plant cost 50.00
2.5 PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION
The time schedule for completion of the proposed project is given in the
following table 2.2.
Table 2.2:- Time schedule for completion of the proposed project
Particulars Time schedule
Approval Janaury, 2015
Civil works December, 2014
Erection & installation of machinery December, 2014
Completion Janaury, 2015
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 52-
2.5.1 STATUTORY LICENSES / APPROVALS
Table 2.3 Statutory Licenses/Approvals
Sl.
No.
Statutory licenses / approvals Status
Karnataka State Pollution Control Board Obtained
State Environment Impact Assessment Authority Under process.
BESCOM Applied
PESO ―Consent to Establish‖ obtained
KGWA Application submitted
2.6 PROPOSED LAYOUT PLAN
The land is owned by Bruhat Bangalore Municipal Corporation and is ear marked for
the treatment of waste. The land was handed over by the Urban development
Ministry Govt. of Karnataka State by a concession agreement between BBHA, NEX and
BBMP. The land is free from any encumbrances and is compounded. Out of the total
plot area of 29 acres, NEX has been granted 5 acres for the project development.
The land is fully compounded and there are no villages/residential area/factories up
to 500 meters from the boundaries of the plot.
Activity wise breakup of the plot area is shown in the following table 2.4
TABLE 2.4: LAND-USE PATTERN
Sl.
No.
Particulars Area (SQM) In Percentage
(%)
1 Total plot area 20,101 100
2 Ground coverage area 6,523 32.45
3 Hard paved area including roads 6,177 30.72
4 Landscape/Green-belt area 7,401 36.82
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 53-
FIG 2.5.1:- LAND USE PATTERN PIE CHART
2.6.1 LANDSCAPE DEVELOPMENT
During operational phase more than 33% of the plant area will become green
under landscape/land cover and planting native species of fruit yielding, shade
bearing, tress shrubs etc., is appended in the table 2.42 and action plan for developing
green belt is detailed in table 2.4.1.
TABLE 2.4.1: ACTION PLAN FOR DEVELOPING GREEN BELT
Sl. No. Description Action plan
1 Commencement of the project. Landscape planning and
developing
2 Parallel to commencement of the
project.
Plating of sampling, seedlings and
mulching’s etc.,
3 During the course of operation of
the plant.
Full scale of development of
landscape and its maintenance.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 54-
TABLE 2.4.2:- LIST OF FLOWER BEARING TREES
Sl. No. Flower bearing Tree names
1 Jasmine Sampige
2 Rose
3 Hibiscus
4 Mallige
5 Kaadusampige
LIST OF FRUIT BEARING TREES
Sl. No. Tree name
1 Guava
2 Mango
3 Sapota
4 Pomegranate
5 Jack fruit
6 Banana
7 Nallis
8 Jambul (Nerale)
9 Papaya
Layout Plan of the project with location of different entities are shown in the
below fig 2.6
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 55-
FIG 2.6:- BIRDS EYE OF THE PROJECT
The sizes of the units is detailed in the table 2.5
TABLE 2.5: UNIT SIZES
Sl. No. Description Size
1 Digester tanks 32m dia x 8.5 m height
2 Hydrolisation and manure tanks 9 m dia x 9 m height
3 Feed buffer tanks 6m dia x 3.5 m height
4 Fire hydrant tank 400 m3
5 Waste segregation room 1141 m2
6 Pumping platforms 60 m2
7 CBG platform 840 m2
8 Polyhouse foundation 2034 m2
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 56-
2.7 DESCRIPTION OF THE PROCESS AND TREATMENT
The basic design assumptions of the proposed process involves critical examination
of its ability to operate within an expected range of waste characteristics
(quantity, composition) and an assessment of biogas potential and its utilization,
wastewater discharge and outlets for digested residue (or any products there
from). The basic technical assumptions used in this case are summarized below:
i) A continuous operation for food waste is represented by 365 days in a
year.
ii) Composition of waste brought into the site as feeder include 250 TPD
food waste and 3 TPD cattle dung.
iii) The waste, after processing would generate 83.5 m3 of biogas per ton.
The quantity of solid rejects to be disposed amounts to about 10% of
incoming waste.
iv) Methane content in biogas is 65% and the rest is carbon dioxide which is
further upgraded to improvise CH4 content accounting to greater than
92%.
v) Waste itself has enough water required for shredding/crushing; the daily
water required is for washing and cleaning which accounts for 2-3
m3/day.
The total quantity of waste that will be received to the site is provided in
Table 2.6 and List of the hotels contributing food waste to biogas plant is
shown in table 2.7.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 57-
Table 2.6: Details of the average Cattle dung and non-woody biomass feed-
materials available for the Plant
Sl. No.
Description/ Feed materials
Availability
Tones per day Tones per year
1 Hotel wet waste
(Vegetable waste, Kitchen
Waste precooked and post
cooked food waste, oil garden
waste, Abattoir waste.
250
91,250
2 Cattle dung 3 1095
Total 253 92,345
Table 2.7: List of the areas contributing food waste to biogas plant with quantities
Sl.
No.
Location of the hotels Capacity
(TPD)
1 Yashwanthpur, West of Chord Road, Malleshwaram,
Rajajinagar and Peenya Industrial Area
80-90
2 Gandhinagar, Corporation, MG Road, Residency Road
surrounding areas
45-50
3 Race Course Road, Infantry Road, Shivajinagar, Ulsoor,
Indiranagar, Old Airport Road
35-45
4 Bangalore South—Jayanagar, JP nagar, BTM layout, and
surrounding areas
35-40
5 Part of Domlur, Koramangala, surrounding areas 20-25
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 58-
2.7.1 PRESENT STATUS
Those hotels located within the jurisdiction of BBMP and sending the
generated food waste to the proposed project facility are listed below.
Fig 2.7 is showing the food waste generated at the hotels.
Fig 2.7: Food waste generated at the hotels
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 59-
2.7.2 COLLECTION AND CONVEYANCE
Route map of collection of waste from the hotel is appended in the below fig 2.7.1
Project Site
Indicating hotels located zone
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 60-
2.7.3 MODE OF TRANSPORTATION
Food and kitchen waste will be transported to the site via compacting trucks which
ensure all leachate is collected in the tank situated underneath the truck. The
collected leachate is pumped to the biogas system.
2.7.4 MODE OF TRANSPORTATION OF FOOD WASTE
Those hotels/restaurants/kitchens from which the NEX collects organic waste is
referred to as ―off load points‖. Each hotel is given a bin/s for disposal of the
organic wastes in a segregated form. These bins are essentially kept on an auto
weighing platform called the ―Off-loader‖ with load cells measuring the weight of
each load at every hotel/restaurant (off-loaders of varying capacity:
240L/660L/1100L). The off-loader also communicates with the central processing
unit at the site, via GSM, the load at each off load point. This reads the weight of
each site and informs the system whether the waste bin is full in capacity at that
particular site. The information is processed and each truck/tipper is hence
instructed to pick up the waste from that particular off load point. The
trucks/tippers perform various load duties and will be designed in the off load
points and the feasibility of maneuvering the same through narrow lanes and
roads.
All sizes of bins will have an auto loading arrangement. The brief management of
the garbage collection system is such where the load at every off load point is
recorded and the due receipt is handed over to the member with an
acknowledgement of the record of the weight. The waste is then loaded on to the
trucks and the bins are replaced on the off-loaders for the next day‘s collection.
The waste is again weighed at the receiving site to ensure there is no pilferage.
The trucks/tippers will be of international standard and will ensure that no waste
is compressed while being transported as compression results into loss of water in
the waste and hence will not be advisable for anaerobic digestion. This also
ensures that there is no leachate or dripping from the trucks. The trucks will be
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 61-
regularly maintained at a workshop for vehicle maintenance at the site. The trucks
will be received at the site and directed to a weighing bridge where the weight for
the truck is recorded and verified as against the data received from the truck. The
image of bin/s given to each hotel for disposal of organic wastes in segregated
form is shown in fig 2.8.
Fig 2.8: Bin/s given to each hotel for disposal of organic wastes in
segregated form
Total trucks needed for collection of waste – 20 Nos.
Trucks selected for collection of waste are 16 ton chassis body of Ashok Leyland
with compactor type design. The trucks will collect the waste but the compression
plate will not compact it in order to avoid any loss of moisture out of waste.
However, the compactor plate will be used to push the waste into waste receiving
hoppers at project site. Each truck has a capacity to carry 8 tons of waste and the
selected models have a power steering to ensure maneuverability in lanes and
roads. Waste will be collected in 2 shifts @ 150 tons each. Trucks will have weight
recording load cells for pick-up of waste bins and a printer to assign a copy of
quantity of waste collected from each bulk waste generator. A receipt of which
can be printed in the collection phase.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 62-
2.8 TECHNOLOGY USED FOR THE TREATMENT
Anaerobic digestion (AD) is the prominent technology used for degradation of
biodegradable organic waste; employing Continuously Stirred Reactors (CSR).
2.8.1 PROCESS INVOLVED
2.8.1.1 PRE-TREATMENT:-
Vehicles or trucks are transporting organic waste into the waste inward and
segregation area, where the organic matter is manually separated from in-organic
material on automatic running conveyor belt system. Only organic substrates can
be used for the production of biogas. Here the waste load is rechecked thereby
tallying with the collection load at the off load points and ensuring a pilferage free
management.
2.8.1.2 FEED PROCESSING:-
The segregated biodegradable Organic waste is crushed and converted into slurry
along with re-circulate from the main digestion process and fed to the feed Buffer
Tanks. The crushing process is implemented prior to the anaerobic digestion in
order to increase the surface area and to promote an accelerated degradation of
the organic matters. The waste is then hygenised to bring it to the world standards
of treating the waste. This ensures that the pathogens are killed as well adds to a
zero odor of the waste.
2.8.1.3 DIGESTION:-
The biological degradation of the substrates takes place in the first and second
stage digesters. Under anaerobic conditions, a temperature of 40.0°C and a
continuous mixing, biogas is being produced by the conversion of the dissolved
organic matters. The process is basically a bacterial decomposition of wet organic
matters, comprising of the hydrolysis of insoluble biodegradable organic food
matters, the acidiogenesis forming acids from smaller soluble organic molecules
and the methanogenesis, where biogas is produced.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 63-
The digesters are insulated with expanded polystyrene and covered with coated
sheets from outside. This is to avoid heat losses and overheating due to external
conditions.
A. PRIMARY DIGESTERS –The primary digester accepts the crushed waste mixed
with re-circulated slurry to convert the same into acids, basically final product
being acetates. This waste then breaks down into biogas and isolates cellulosic
mass.
B. SECONDARY DIGESTERS –The cellulosic mass separated is then taken for a
longer retention time to be converted into biogas by further break down. Total for
both primary and secondary reactors the total retention time is 45 days.
2.8.1.4 UP GRADATION OF BIOGAS AND CONVERSION TO CBG
(COMPRESSED BIO GAS):-
The generated biogas consists of various gases such as Methane, Carbon di Oxide,
Hydrogen sulfide (in minor quantities) and moisture in vapour form. The generated
gas is scrubbed with the help of molecular sieves to remove the CO2 and contain
around 95 – 97% pure methane and the rest CO2.
2.8.1.5 DIGESTED SLURRY:-
The digested slurry can be upgraded to an organic bio-fertilizer. The separated
water from the slurry can be re-used for the processing of the next day‘s
operations. The slurry will be used as re-circulate inoculums for the next day‘s
waste processing. The treated water can be used for flushing or gardening as well
as the daily addition for the biogas plant usage.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 64-
2.8.2 PROCESS INVOLVED IN DIGESTER
Biogas is formed when organic matter is digested in the absence of oxygen; this
process is called anaerobic digestion. The digestion is made by enzymes and
bacteria during the below described four main steps. The flow chart of biogas
process is shown in fig 2.9.
HYDROLYSIS – In this step the organic polymers are broken down by
enzymes which are emitted when fermentative bacteria attach to the
molecules in the waste. Proteins are broken down to amino acids,
carbohydrates to sugars and lipids to fatty acids. The carbohydrates take a
few hours to break down and the fats a few days. Lignocellulose and lignin
are only hydrolyzed to a limit extent. The residue from the anaerobic
digestion contains about 40-50% of lignin and 40-50% of cellulose and
hemicellulose.
ACIDIOGENESIS – During this step the molecules from the previous step is
broken down further by bacteria, without the help from enzymes. The main
products from acidification are short chained fatty acids, alcohols, carbon
dioxide gas and hydrogen gas. The carbon dioxide and hydrogen gas can be
converted into methane directly by methanogenic bacteria.
ACETOGENESIS – In this step the fatty acids and the alcohols are broken
down to smaller components, mainly carbon dioxide, acetate and hydrogen
gas. During acetogenesis, hydrogen and carbon dioxide are reduced to
acetic acid; this is made by homoacetogenic microorganisms. The
acetogenic bacteria produces H2, but the break-down of long-chain fatty
acids to acetate can only take place during a very low hydrogen partial
pressure.
METHANOGENESIS – This is the last step in the process, where different
methanogenic bacteria convert carbon dioxide, hydrogen gas and acetate
into methane. These bacteria cannot operate in the presence of oxygen.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 65-
FIG 2.9: BIOGAS PROCESS
2.8.3 FOOD WASTE CHARACTERIZATION
The solid waste fed to the digester is solely biodegradable and constitute of
organic food waste that has a much higher volatile solids destruction rate (86-90%)
than bio solids. This implies that even though the additional material is added to
the digester, the end residual will only increase by a small amount.
The brought in wet waste from the bulk generators comprise of 85% water, 10%
solids and 5% gas. The wastes processed at the facility include organic food and
vegetable/fruit waste.
Daily 3 tons of Cattle dung with 18 % T.S. or specially developed nutrients will be
added along with 250 tons of organic solid food waste to ensure a stable
microbial reaction and a smooth functioning of the digester performance.
Complex organic matter
carbohydrates, protein, fats
Soluble organic molecules
sugars, amino acids, fatty acids
Volatile fatty acids
H2, CO2 Acetic acid
CH4+CO2
1
2
3 3
4 4
1. Hydrolysis
2. Acidogenesis
3. Acetogenesis
4. Methanogenesis
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 66-
Quantity of the addition will be adjusted with feeding rate if the T.S. is higher
and is to be maintained.
2.9 TECHNOLOGY AND PROCESS DESCRIPTION
Anaerobic digestion is the prominent technology used for degradation of
biodegradable organic waste; employing Continuously Stirred Reactor (CSTR).
2.9.1 GENERAL DESCRIPTION OF ANAEROBIC DIGESTION PROCESS
Anaerobic Digestion (AD) is a biological process that happens naturally when
bacteria breaks down organic matter in environments with little or no oxygen. It is
effectively a controlled and enclosed version of the anaerobic breakdown of
organic waste in landfill which releases methane.
Almost any organic material can be processed with AD, including food scraps, fats,
oils & grease (FOG), tissue paper, garden waste, sewage and animal waste.
The two main products of AD are biogas & a solid residual.
An anaerobic digestion system is the central processing plant that converts the
organic waste slurry into Biogas, which is further converted into Compressed Bio
gas (CBG) /Electricity. Waste water from the system is re-circulated to ensure
zero fresh water requirement or discharge. By-product generated from the process
will be nitrogen rich, organic fertilizer that replaces conventional chemical
fertilizers for farming and gardening purpose.
This eco-friendly gas can be used either for cooking purpose or producing
electricity as per the client‘s requirement. The plant also produces odorless and
nitrogen rich Organic Manure as by-product of the process on daily basis. The
organic manure is a cost effective and eco-friendly replacement to conventional
chemical fertilizers used for gardening and landscape purpose.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 67-
The digestion process begins with bacterial hydrolysis of the input materials in
order to break down insoluble organic polymers such as carbohydrates and make
them available for other bacteria. Acetogenic bacteria then convert the sugars and
amino acids into carbon dioxide, hydrogen, ammonia, and organic acids.
Acetogenic bacteria then convert these resulting organic acids into acetic acid,
along with additional ammonia, hydrogen, and carbon dioxide. Methanogens finally
are able to convert these products to methane and carbon dioxide.
There are a number of bacteria that are involved in the process of anaerobic
digestion including acetic acid-forming bacteria (acetogens) and methane-forming
archaea (methanogens). These organisms feed upon the initial feedstock, which
undergoes a number of different processes converting it to intermediate molecules
including sugars, hydrogen & acetic acid before finally being converted to biogas.
Different species of bacteria are able to survive at different temperature ranges.
Ones living optimally at temperatures between 35-40°C are called mesophiles or
mesophilic bacteria. Some of the bacteria can survive at the hotter and more
hostile conditions of 55-60°C, these are called thermophiles or thermophilic
bacteria. Methanogens come from the primitive group of archaea. This family
includes species that can grow in the hostile conditions of hydrothermal vents.
These species are more resistant to heat and can therefore operate at
thermophilic temperatures, a property that is unique to bacterial families.
As with aerobic systems, the bacteria in anaerobic system while growing and
reproducing microorganisms within them require a source of elemental oxygen to
survive.
In an anaerobic system there is an absence of gaseous oxygen. In an anaerobic
digester, gaseous oxygen is prevented from entering the system through physical
containment in sealed tanks. Anaerobes access oxygen from sources other than the
surrounding air. The oxygen source for these microorganisms can be the organic
material itself or alternatively may be supplied by inorganic oxides from within the
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 68-
input material. When the oxygen source in an anaerobic system is derived from the
organic material itself, then the 'intermediate' end products are primarily alcohols,
aldehydes, and organic acids plus carbon dioxide. In the presence of specialised
methanogens, the intermediates are converted to the 'final' end products of
methane, carbon dioxide with trace levels of hydrogen sulfide. In an anaerobic
system the majority of the chemical energy contained within the starting material
is released by methanogenic bacteria as methane.
Populations of anaerobic microorganisms typically take a significant period of time
to establish themselves to be fully effective. It is therefore common practice to
introduce anaerobic microorganisms from materials with existing populations. This
process is called 'seeding' the digesters and typically takes place with the addition
of sewage sludge or cattle slurry.
The methane producing bacteria consume these to produce methane and carbon
dioxide.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 69-
Fig 2.10: Scheme of reactions produced during anaerobic digestion
2.9.2 PROCESS DESCRIPTION
The operations will be done in continuous mode. Every day waste will be received
and processed in 12 hours. The waste will be fed into the digester during 24 hours
in a distributed mode and excess slurry and manure will be generated during 24
hours.
The steps involved are described below.
2.9.2.1 PRE- TREATMENT / SLURRY PREPARATION:
Under pre-treatment, the vehicles or trucks are transporting organic waste into
the waste inward and segregation area, where the organic matter is manually
separated from in-organic material on automatic running conveyor belt system.
Only organic substrates can be used for the production of biogas. Here the waste
load is rechecked thereby tallying with the collection load at the off load points
and ensuring a pilferage free management.
The segregated biodegradable Organic waste is crushed and converted into slurry
along with re-circulate from the main digestion process and fed to the feed Buffer
Tanks. The crushing process is implemented prior to the anaerobic digestion in
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 70-
order to increase the surface area and to promote an accelerated degradation of
the organic matters. The waste is then hygenised to bring it to the world standards
of treating the waste (under the EC 1774/2002 standard). This ensures that the
pathogens are killed as well adds to a zero odor of the waste. Also it helps the
recovery of the ΔT that is lost in heat losses from the digesters.
2.9.2.2 BIOGAS DIGESTER DESIGN AND SIZING SUITABLE FOR MULTI-FEED
STOCK:
The proposed plant works on a collection-flow-process. Organic vegetable and
biodegradable food waste is guided into the two primary digesters with the help of
an eccentric screw pump, several times per day. Additionally, fresh and recycled and
treated water from the same plant is pumped into these digesters. The treated
sludge is pumped to the two secondary digesters when indicators show a certain level
within the digesters is reached.
All three digesters are fully mixed by high quality submersible agitators and will be
operated in a mesophilic (40°C) temperature range. This combination leads to a
stable process with good hygienisation results and a minimized effort as far as area
requirements and digester volume are concerned. On the other hand it aims at
maximum gas yield which results in maximum greenhouse gas reduction. The
digesters are standing cylindrical tanks made of reinforced concrete and are
equipped with a wall heating system. The digesters are covered with a double
membrane.
2.9.2.3 ANAEROBIC DIGESTER:
The anaerobic digester system includes a fixed vertical anaerobic digester with
fixed dome and a biogas storage system. The fixed digester has a waste inlet
which is coupled up with a waste crusher. The crusher acts as a homogenizer as
well as a blending machine for mixing the waste with the re-circulated water.
From there the liquid goes through into the under-ground feeding tank and passes
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 71-
through a specially designed hydrolysis tank to the main anaerobic digester. The
specially designed stirring mechanism inside the digester makes sure that no
clogging, no froth and no scum formation inside the digester occur. The stirring
mechanism is designed in such a way that it can be suited for any kind of
biodegradable substrate. The heat and temperature maintenance system inside
the feeding buffer tank takes care of a stable temperature inside the digester. The
heat and the temperature are either maintained by immersing the external
heaters or the heat from the biogas engine can be recovered with the help of heat
exchangers (which the biogas generator supplier has to supply). Further a digester
effluent outlet is connected to the substrate buffer tank and via the re-circulation
system and the substrate manifold it is again pumped in the required amount to
hydrolyze the feeding material. The generated biogas is collected in the biogas
storage system after removing the condensate through the condensate
remover/moisture trap. The biogas plant is designed for minimum manual
operation. Since the volume of daily waste to be processed is known, the plant is
designed low on automation. The daily operations, emergency shut down and
adjustment to change operating conditions are carried out manually with the help
of an electric control panel provided along with the biogas plant. The design of the
plant is robust and highly skilled supervision is not required. The plant can be
operated by semi-skilled personnel with simple visual inspection techniques.
The Waste Management system is a series of interconnected parts with four basic
components: digesters, a gas-handling system, a storage lagoon to hold treated
waste (liquid waste, or slurry), and a biogas cleaning and compression unit to
convert the biogas into bio CNG or electricity, as well as smaller components such
as mixers, pumps, a solid feeder, and valves. The biogas plant is controlled by a
central computer (PLC & SCADA system) to guarantee operational safety and
ensure continuous operation to achieve maximum biogas yields.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 72-
2.9.2.4 BIO DIGESTERS (PRIMARY AND SECONDARY STAGE):
The solids that are fed into the tank along with water are stored inside the Bio
Digesters for decomposition or degradation of the Volatile Solids (VS) (Organic Dry
Matter) present inside the feed substrate (organic waste). The degradation is done in
two primary digesters of similar volume. Each digester is comprised of a concrete
tank: 32 meters in diameter and 8.5 meters high with a liquid volume of 6300 m3 and
a head space of 401.9 Nm3 in the tank + 4800 m3 in the gas holding roof for gas
storage.
2.9.2.5 BIOGAS STORAGE:
The digesters are installed with a top dome covering of imported German make gas
rubber bladders with two layers and an approximate pressure of 4-5 milibars
maintained between the two layers. This maintains a natural air pocket insulation
layer from the top. A blower of 0.25 HP maintains a constant pressure between the
bladders constantly. Total headspace for gas in the bladders is approximately 6702
Nm3 Biogas. The digesters are fitted in with hot water circulation lines embedded
inside the concrete. These lines are essential as the ambient temperature of 40oC
must be maintained and the gas production is maximized at this temperature. The
technology used is CSTR (continuously stirred reactors). A total of Agitators
(imported from Germany) of 17.5 kWh are installed for horizontal turbulence and a
10 kWh mixer is installed to counter the flow with a vertical turbulence. This ensures
extremely homogenous mixing of the slurry inside the digesters.
The feed material is digested of the VS content in it to produce a gas comprising of
maximum methane CH4 and the rest containing of CO2 and H2S. This gas is called
biogas. After primary digestion the feed material is taken to be digested in a
secondary digester for further storage and degradation of VS. This ensures that the
biodegradable waste is fully degraded and maximum efficiency is attained out of the
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 73-
biogas generation plant. A total of 20,881 Nm3 gas is expected to be recovered from
the daily Organic waste that is digested.
2.9.2.6 BIOGAS UTILIZATION AND GENERATION OF CBG:
Biogas that is produced after the digestion process consists of Methane (CH4) and
Carbon-dioxide (CO2) along with some trace gases such as Water vapour, Hydrogen
Sulphide, Nitrogen, Hydrogen and Oxygen.
Carbon Dioxide and trace gases such as Water vapour and H2S must be removed
before the biogas can be used because:
1) The Hydrogen Sulphide gas is corrosive
2) Water vapour may cause corrosion when combined with H2S on metal surfaces and
reduce the heating value.
The produced gas will be scrubbed to contain minimum 95% Methane and the rest of
CO2 at the end of scrubbing. The scrubbing is done by using simple water scrubbing
where water is regenerated to be used for next cycles. The Process flow char and
mass Balance diagram is appended as figure 2.11 & 2.12.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 74-
FIG 2.11 PROCESS FLOW CHART
Food waste received
Waste receiving hoppers
Waste segregation conveyors
Feed buffer tanks
Hydrolisation tank
Primary digester tank
Secondary digester
tank
Manure storage
tank
Nutrient rich
water
Manure drying
Polyhouse
Manure
separation
tank
ETP
Bio Gas
CBG
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 75-
FIG 2.12: MASS BALANCE DIAGRAM
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 76-
2.9.2.7 CBG DISTRIBUTION:
CBG will be transported over trailers. The CBG cascades will be permanently
mounted over the trailers to avoid handling/loading/unloading at the customer end
as well as at the site. The trailers will have separate truck heads for supply of full
cascades and bringing back the empty cascades from the customer end. Biogas
Double membrane roof photographs are appended in fig 2.12.1.
Biogas generated is used for CBG production. This CBG will be sold to nearby
industries to replace their fossil fuels such as furnace oil. The use of CBG currently
not allowed as vehicular fuel in India. The generated CBG will be stored and
transported in cascades containing of cylinders. These high pressure cylinders will be
PESO approved and mounted on trailers for transportation. The process flow chart is
shown in figure 2.11
FIG: - 2.12.1 BIOGAS DOUBLE MEMBRANE ROOF PHOTOGRAPHS
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 77-
2.9.2.8 POST TREATMENT OF DIGESTED SLURRY:
The secondary digester will release 467 m3/day of effluent after digestion of the
required HRT. The daily overflow will contain around 4-5% TS in the slurry. The
suspended solids out of this slurry can be effectively removed with a FAN separator.
The separator uses a simple screw technique to generate high pressure and allow
maximum separation of the solids. The overflow out of the separator will contain
approximately 1.5% TS and is redirected to the organic chemical treatment with a
specialized solution developed in house by NEX. This efficiently brings the dissolved
solids from the separated water at the second stage of separation to around 200
ppm. The separated water is then directed to the water storage lagoon for further
aeration treatment to bring the COD to the acceptable pollution control board limits.
This water can then be used for flushing and to adjust the daily water mass for the
anaerobic digestion. The final volume of discharge will be 140 m3 of separated water
after secondary separation. This water can be let out for farming activities or can be
re-circulated into the separated manure with some organic mass like coconut husk,
for composting into the poly houses to be built at the site. The heat from the
generator, as mentioned above, will be used for drying the water and evaporation.
This process can ensure zero discharge of the plant.
Total separated manure will contain approximately 70% moisture. This can further
pelletized to allow effective distribution and packing of the remnant product.
2.10 CHARACTERISTICS OF CBG, MANURE AND NUTRIENT RICH WATER
2.10.1 CBG PROPERTIES
The Compressed Bio Gas properties is shown table 2.8.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 78-
TABLE 2.8: CBG PROPERTIES
1. Key Terms : Compressed Biogas (CBG) or Bio- CNG with > 95%
Methane content
2. Required
Quantity :
16500 – 17,500 Kg’s/day x 365 days/year
3. Upgraded Biogas (CBG) :
The up graded Biogas is of high quality and standard:
Wobbe index : 44.6 to 44.7
Methane (CH4) : > 95%
Carbon dioxide (CO2),
Oxygen (O2), nitrogen (N2), others : <5%
Total sulphur (S) content : 23 mg/m3 (max.)
Water content : 32 mg/m3 (max.)
Octane No : 130(min)
Gross calorific value : 8257 to 8340 Kcal/m3
Flash point : -1880C
Density : 0.77771 Kg/m3
Availability : 365days/year
4 Transportation : Stored in cylinders and cascades. Cascades of various
capacity is available.
2.10.2 MANURE PROPERTIES
Characterized via test conducted taking two samples:
Separated solids from anaerobic digestion of food waste
Settled solids from anaerobic digestion of food waste
The manure properties is shown table 2.9.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 79-
TABLE 2.9: MANURE PROPERTIES
Sl.
No
TESTS Unit Freshly separated
solids from
anaerobic
digestion of food
waste.
Settled solids slurry
from anaerobic
digestion of food
waste
1 Total Kjedhal Nitrogen as
(N)
% 1.8874 0.1408
2 Total Phosphorus as (P) % 5.2043 0.7895
3 Total Pottasium as (K) % 0.7050 0.0651
4 Phosphorus as (P2O5) % 11.9195 1.8082
5 Pottassium as (K2O) % 0.8492 0.0784
6 Total Organic Carbon % 6.9707 0.7339
7 Total Solids % 15.7422 4.8663
8 Moisture by even drying @
1050C
% 84.2578 95.1337
2.10.3 CHARACTERISTICS OF NUTRIENT RICH WATER
The nutrient rich water will be generated from the anaerobic digester and it will
be aerated and re used for process and the slurry test report is appended in the
table 2.10.
Suspended Solids: 160 mg/l (range up to 200mg/l)
pH value: 7.2 – 7.3 (range 5.5 – 9.0)
Oil & grease: 4-5 mg/l (range up to 10 mg/l)
BOD: 70 - 85 mg/l (range up to 100 mg/l)
Arsenic: NIL (up to 0.2 mg/l)
Cyanide: NIL (up to 0.2 mg/l)
Alpha emitters micro cure: NIL(range up to 10-8)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 80-
Beta emitters micro cure: NIL (range up to 10-7)
Manganese: 1.5 mg/l (range 2 mg/l)
Iron: NIL (range 3 mg/l)
Vanadium, Nitrate Nitrogen & Sulphates: NIL
TABLE 2.10: - SLURRY TEST REPORT
Sl No.
TEST FINDING Bio Gas Plant Slurry
01 Total Solids 5454.00 mg/L
02 Total Suspended Solids 304.00 mg/L
03 pH 8.52
04 Chlorides (CI) 1183.84 mg/L
05 Hexavalent Chromium (Cr) 0.0909 mg/L
06 Total Chromium (Cr) 0.1212 mg/L
07 Hydrogen Sulphide as (H2S) 2.83 mg/L
08 Sodium (Na) 803.19 mg/L
09 Boron (B) Nil
10 Total Oil & Grease 33.00
11 Total Kjeldahl Nitrogen (N) 1343.00 mg/L
12 Total Potassium (K) 857.00 mg/L
13 Total Phosphorus (P) 587.6 mg/L
14 Total dissolved solids 5150.00 mg/L
15 Magnesium (Mg) 126.30 mg/L
16 COD 1442.49 mg/L
17 BOD (27oC, 3 days) 460.00 mg/L
18 Total Organic Carbon 162.7 mg/L
19 Lead (Pb) 0.0610 mg/L
20 Mercury (Hg) 0.014 mg/L
21 Arsenic (As) Nil
22 Cadmium (Cd) 0.0124 mg/L
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 81-
2.10.4 MODE OF TRANSPORTATION OF CBG
The produced CBG will be filled in cylinders and cascades at 250 BarG pressure and
transported like CNG. Each cylinder has 75 water litres capacity and at 250 BarG
pressure, each cylinder will carry 12.5 Kg of CBG. Each cascade has 40 such
cylinders and therefore each cascade will carry 500 Kg of CBG. These cascades will
be carried over a crane mounted truck, and will be loaded and unloaded at site
and customers end respectively. The image depicting the transport of CBG in
cascades which will be carried over a crane mounted truck is appended in fig 2.13.
Fig 2.13: Cascades carried over a crane mounted truck
Total trucks needed for delivery of CBG – 3 Nos.
Special trucks with Palfinger crane will be purchased. The self-crane mounted
trucks will load and unload the cascades at site and customers end respectively.
Each cascade is selected to carry 500 Kg. Hence 26 deliveries will be made every
day. Every half of the day a delivery is made to the customer. This process is
customer specific. If need be a trailer with 2 cascades mounted can be purchased
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 82-
based on customer requirement and permissions. Trailer will have 2 fixed cascades
and a truck head will deliver the trailers and park them at customer site. Thus, 13
trailers will be purchased with 26 cascades mounted on them.
2.11 DESIGN DATA
Size of the proposed units are shown in the below table 2.11.
TABLE 2.11: SIZE OF THE PROPOSED UNITS
Sl. No. Unit Size
1 Digester tanks 32m dia x 8.5 m height
2 Hydrolisation and manure tanks 9 m dia x 9 m height
3 Feed buffer tanks 6m dia x 3.5 m height
4 Fire hydrant tank 400 m3
5 Waste segregation room 1141 m2
6 Pumping platforms 60 m2
7 CBG platform 840 m2
8 Polyhouse foundation 2034 m2
Retention time design sheet is appended in the below fig 2.14.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 83-
FIG 2.14:- RETENTION TIME DESIGN SHEET
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 84-
The proposed facility includes the following:
Digester tanks – 32 m dia x 8.5 m height
Hydrolisation and manure tanks – 9 m dia x 9 m height
Feed buffer tanks – 6 m dia x 3.5 m height
Fire hydrant tank – 400 m3
Waste segregation room – 1141 m2
Pumping platforms – 60 m2
CBG Platform – 840 m2
Polyhouse foundation – 2034 m2
Road work within the site – 4018 m2
Free space – approx 39%
2.12 UTILIZATION OF EXCESS WATER SEPARATED FROM BIOGAS
PLANT SLURRY
The Project of treating minimum 250 tons food waste per day will generate a
total excess water of 148 m3 per day. This water is a result of two streams –
1. Excess water from the manure separator
2. Excess water after sludge dewatering with organic poly electrolyte and
sludge settling
This excess water will have around 0.38% solids. The excess water is a discharged
stream of separating organic manure from the total slurry. This water will be
accepted into a tank and will have a CoD of 850 mg/l and a BoD of around 75
mg/l. This water will be stored into a tank measuring 8 meters in height and 9
meters in diameter with a volume of 540 m3. The discharged water tank will have
a retention capacity of around 3.5 days. The tank will be equipped with a air
diffuser with a 3.2 kW air blower attached to it. The blower will continuously blow
air at 1.5 BarG pressure through the air diffuser @ flow rate of 135 m3/hour. This
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 85-
allows a lot of excess suspended solids to settle down as well as clears off gas
bubbles surrounding the solids in the slurry and allows them a very efficient
settling. This ensures a CoD removal and brings it down to the levels of 175 mg/l
and suspended solids to less than 120 mg/l. The BoD is maximum destroyed in the
anaerobic digestion plant as the almost all of it is converted to biogas. The BoD
after the excess water storage tank will be less than 60 mg/l.
The pH of the water will be around 7.2 and the air dissolution ensures the nitrogen
levels removal as well. The water is suitable for the Irrigation, gardening, and
sanitation & hygiene purpose and can be supplied to either the neighbouring farms
for irrigation or agriculture use. This water should be ideally spread @ 0.3 m3/m2
for efficient use. Drip irrigation of such water is the best utilization for maximum
crop yield and lowest evaporation losses.
There are no heavy dissolved metals not contaminants in the water as this is the
excess water out of food waste or kitchen waste coming from hotels and
contaminants/heavy metals like arsenic, lead etc. are not a part of incoming
waste stream. Hence the outlet stream doesn‘t have the traces of the same. The
floating layer, if any or the settled solids in the tank will be directed to the poly
house composting of separated organic manure. The poly house has a retention
capacity for total sludge for 6 days. The entire poly house has concrete floor with
leachate collection facility if and when required. The poly house composting also
has air blowers to remove the evaporated moisture and this ensures efficient
working even during the monsoon season.
Total organic manure expected out of the poly house is around 65 tons per day
with 30% dry matter with non-drip consistency and can be transported and sold.
The Hydraulic flow diagram for manure and recirculation is appended as fig 2.15.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 86-
FIG 2.15: HYDRAULIC FLOW DIAGRAM FOR MANURE AND RECIRCULATION
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 87-
2.12.1 PLANT DETAILS
The plant details is shown in the below table2.12.
TABLE: - 2.12 PLANT DETAILS
Plant capacity To process 250 TPD of food waste
Waste characteristic adopted
for design- organic waste
250 TPD food waste (wet organic waste) and
3 TPD cattle dung
TS= 20-25%
Balance = Moisture
Type of process Anaerobic digestion of biodegradable waste in
a continuous stirred reactor
Process temperature Mesophilic (40oC)
Hydraulic retention time Primary digester: 25 days
Secondary digester: 25 days
2.12.2 UNITS INVOLVED IN THE WASTE PROCESSING:
Solid feeder
Feed preparation pit
Primary digester (2 in no.)
Secondary digester (2 in no.)
Separator
2.13 PROCESS EQUIPMENTS USED IN THE PLANT
The list if process equipment used is shown in table2.13.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 88-
TABLE 2.13: LIST OF PROCESS EQUIPMENTS USED
Sl.No Description Capacity Qty
Pre-treatment, processing ,digestion and gas up-gradation with compression
1 Weigh Bridge 40T 1
2 Waste unloading hopper 8 TPH, 4.8 mtr. Length x 3 mtr. Width x
4 mtr Height
3
3 Belt conveyor 9.2 TPH, 15.8 mtr. Length x 1.22 mtr Width
3
4 Belt Conveyor for refuse
waste
1.2 TPH, 15.87 mtr. Length x0.75 mtr
Width
3
5 Waste crushing system with
multi crusher, chopper and
lobe pump
16.5, kW, 23 TPH 3
6 Metal detector 0.6 TPD 6
7 Submersible pump 2.2 kWh, 30 LPS 3
8 Waste double screw pumps 22 kW, 50 m Head 6
9 Submersible agitator 10 kW 6
10 Submersible agitator 7.5 kW 9
11 Submersible agitator 13 kW 6
12 Twin lobe gas blowers 15 kW 3
13 Gas up-gradation system 15 kW 3
14 High pressure Gas
compressor
80 kW, 303 Sm3/h 3
15 Air compressors 7.5 kW 2
16 Centrifugal air blower 2.2 kW 1
17 Screw press for manure
separation
5.5 kW 2
18 Slurry Flocculator SS 310, 0.75 kW 1
19 Tractor with filter 40 HP 1
20 Fire hydrants pumps (electric) 10 kW 2
21 Fire hydrant pumps (diesel) 10 kW 1
22 Float level controllers 4-20 mAmp WIKA 6
23 Pressure transmitters 4-20 mAmp WIKA 12
24 Temperature transmitters 4-20 mAmp WIKA 8
25 Control gate valves Fail safe shut type, knife gate with SS 316
body, electro- pneumatically actuated
16
26 Control Gas Butterfly Valves Fail safe shut type, knife gate with SS 316
body, electro- pneumatically actuated
9
27 Gas twin lobe blower 24.5 kW, 2000 m3/hr, nitrile resistant
lobes with CI casting body
2
28 Gas flare Ioniser activated SS 316 stack flare with
riser, flame arrester, spark ignition and pilot flame, 4 meters above ground
1
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 89-
29 Gas flow meters Orifice principle gas flow meter, SS316
body, flow regulator and 4-20 mAmp
signal to PLC
1
30 Gas analyser Online stationery gas analyzer for 3
gases with automatic air calibration, SS
316 body with sampling at 15 second
intervals
1
31 Mercaptain gas injector Pneumatic pump actuated mercaptian
gas injector dosing pump working on
pulsation principles for gas odor
physical leakage detection
1
32 Electric transformer 250 KVA transformer for step down
from 11 KVA current to 420 Volts, 3
phase
3
33 Power distribution panel with
electric meter
PDB panel for incoming power with
electric meter
1
34 PLC system SKADA based PLC programming system
with 75 I/O’s and incomer panels with
MCB’s and barriers for data signals
1
2.13.1 MAINTENANCE SCHEDULE FOR EQUIPMENT –
1. High pressure Compressor – once every year around 80 hours/year
2. Air compressors – once every 6 months
3. Crushing machines – once every 6 months
4. Submersible Agitators – once every 3 years
5. Pumps and valves – periodical maintenance and once every 2 years full
overhaul
6. Gas double membrane roof – replacement after every 9-10 years
7. Other electrical and instrumentation equipment – periodical and calibration
of all instruments once every 6 months.
2.14 WASTE COMPOSITION AND PRODUCT SPECIFICATION
The brought in wet waste constitutes of 75-80% water, 20-25% Total solids; on
subjecting to anaerobic digestion produces 65% methane. The gas is then scrubbed
and cleaned to render it up to 95% or above, thereby having the calorific value
ranging between 8,257 to 8,340 kCal /m³.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 90-
2.14.1 UTILITY OF PRODUCT AND BY-PRODUCTS
The value full product and by-product produced at the facility are biogas and
manure/nutrient rich water respectively.
The details of products generated from the project is appended in the
table: - 2.14.1.
2.14.1.1 BIOGAS
The generated compressed biogas is sent to the bottling plant set up at the site,
abiding by the PESO Rules and Regulations. At the bottling plant, industrial
cylinders / tankers are made with the end users as hotel in the priority; else, the
cylinders will be sold to restaurants, bakery or industries to use as fuel for the
boilers as a substitute to furnace oil/LPG. The capacity of CBG Storage area is
shown in table 2.14.
TABLE 2.14: CBG STORAGE CAPACITY
Cascade
Storage
Capacity
(Ltr.)
No. of
Cylinders
Per
cascade
(Nos.)
Cascade
Dimensions
in mm
L
Cascad
e
Width
W
Stora
ge
Of
CBG
H
Storage
Of
CBG
(Ton)
Approx
Total weight
of cascade
Sm3 kg’s kg’s
900 12 1615 1820 1130 1.6 192 150 1750
1200 16 1615 1820 1450 2 256 200 2200
1500 20 1920 1820 1450 2.6 321 250 2850
2025 27 2595 1820 1450 3.55 433 338 3888
2250 30 2900 1820 1450 3.9 481 375 4275
3000 40 3515 1820 1450 5.2 641 500 5700
4500 60 5085 1820 1520 7.5 962 750 8250
Current selection is for 3000 water liters capacity cascade which stores 500 kg‘s of
CBG x 26 cascades= 1300 kg‘s CBG storage capacity.
2.14.1.2 ORGANIC MANURE
Organic manure is used in farming. This has found most suitable for horticulture
activities and grape farming. Organic manure is extensively used in producing the
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 91-
organic vegetables and the demand for which is growing. Provides humus to the
soil and is rich in phosphorous and organic carbon. Organic carbon improves the
soil water holding capacity. Around 65 tons/day will be produced and sold.
2.14.1.3 PROVISION OF STORAGE YARD FOR MANURE
Daily around 68 tons of wet manure with 80% moisture, will be generated at site.
For storing this, the facility will host around 1760 sq m of poly house. The
generated manure will be stored, dried to contain 60% moisture before it is sold.
The poly houses are concrete floored and will act as a solar thermal drying process
facility for extracting the required moisture and evaporating it. Exhaust fans will
be fitted in the poly house to carry over the moisture and the carried air will be
passed through beds of coconut shell fiber. This will ensure all the air is filtered
through. Considering the solar radiation available at site which is on an average
4.5 kWhr/sq m, around 1230 sq m will be used for active manure processing and
drying. The rest of the area will be used for manure loading/packing etc.
2.14.1.4 NUTRIENT RICH WATER
Water separated after separation of organic manure, is passed through the reverse
osmosis process to be filtered. This water matches the ―land of irrigation‖
standards mentioned by pollution control board and the clearance from pollution
control board is also acquired. This water is rich in minerals as the source of the
same is from the food waste received. Out of the daily discharge, 60% is reutilized
in the processing of the waste and the rest (around 148 m3/day) excess, is
distributed to neighboring farmers who are more than willing to accept it into the
farm lands. The farms are adjacent to the fencing of the said plot of biogas
installation.
TABLE 2.14.1:- LIST OF PRODUCTS GENERATED FROM THE PROJECT
Sl. No. Product Quantity
1 CBG 25,135 m3/day
2 Manure 68 Tons/day
3 Nutrient rich water 148 m3/day
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 92-
2.14.1.5 DESIGN PARAMETERS FOR BIOGAS PLANT
Input waste – 250 MT/day
Type of input for design - Food/vegetable slaughter house/organic biomass waste.
TS in input – 25%
VS of TS – 92%
Destruction of VS expected – 85%
Organic loading rate – 3.28 KgVS-1/m3 DV-1
CoD in input – 3,00,000 – 5,00,000 ppm
Design load as per CoD – 0.82 KgCoD-1 / m3DV-1
CoD at outlet slurry – 1850 mg/l
CoD after treatment < 110 mg/l
Total retention time in design – 43 days
Biogas expected – 100 m3/MT fresh waste
2.15 SCHEMATIC REPRESENTATION OF THE FEASIBILITY DRAWING
A schematic representation of the overall feasibility and environmental assessment
process is shown in fig 2.16.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 93-
Fig 2.16: Feasibility and environmental assessment process
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 94-
2.16 MITIGATION MEASURES INCORPORATED INTO THE PROJECT TO MEET
ENVIRONMENTAL STANDARDS, ENVIRONMENTAL OPERATING CONDITIONS
OR OTHER EIA REQUIREMENTS (AS REQUIRED BY THE SCOPE)
2.16.1 SOURCES OF POLLUTION & POLLUTION CONTROL MESASURES
ADOPTED IN THE PLANT
DG set is the only air pollution source. Air pollution details is detailed in below
table 2.15.
Table 2.15:- Air pollution details
A Air pollution details
1 Sources of air pollution DG set (350 KVA)
2 Air pollution control units
provided
3 m above the roof level stack height
will be provided.
2.16.2 WATER DEMAND AND WASTEWATER/EFFLUENT DISCHARGE
2.16.2.1 SOURCE OF WATER SUPPLY
Water supply for the proposed project is from Bore well.
2.16.2.2 WATER DEMAND AND WASTEWATER DISCHARGE DURING
OPERATION PHASE
Total number of employees: 75 people
Per capita water demand : 45 LPCD
Total water requirement : 3,375 LPD or say 4000 LPD = 4 KLD
Total wastewater generated: 3,600 LPD = 3.6 KLD
The total quantity of water required for the plant is about 4 KLD. The water
consumption and discharge is as presented below. Water consumption and
discharge details are shown in the table 2.16. The water balance chart is
appended in fig 2.17.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 95-
Table 2.16: Water consumption and discharge
Water consumed for Consumption(LPD) Discharge (LPD)
(a) Domestic 4,000 3,600
(b) Industrial purpose 2,000 2,63,000
(From wet waste)
Process NIL -
Washing/cleaning 2,000 ***** 2,000
(c) Gardening/Landscape development 4,000 -
Total 10,000 2,68,600 LPD or say
269 KLD
Note:
LPD = L/day; KLD = kilo liter/day
******* The process does not require any fresh water during daily operations and
daily water needs can be easily satisfied through self-generated process water.
The floor washing and cleaning water requirements will be around 2000 liters/day.
The treatment methods and the final disposal of each type of wastewater
generated is appended in the table 2.17 below.
Table 2.17: Sewage/effluent treatment and discharge
Sewage/effluent
generated from
Treatment units provided Final disposal point
(a) Domestic Domestic waste water will be
treated in ETP.
Re-used for landscape
Development.
(b) Industrial Waste water generated from
digester will be treated in 300
KLD ETP.
Re-used for landscape
Development.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 96-
FIG 2.17:- WATER BALANCE CHART
Wastewater generated 0.9 KLD
2.16.3 DESIGN DETAILS FOR PROPOSED EFFLUENT TREATMENT PLANT
The following scheme of effluent treatment will be implemented:
Stage 1: The slurry from the digester will be fed to the manure storage buffer tank
and then to the manure separator from FAN separator model PSS 1.2-780 x 2 nos.
Here the fibrous solids from the slurry will get separated out from the
slurry, and we expect a solid efficiency of 60% to be achieved on TS basis.
Domestic water
Demand
4 KLD
Treated in Effluent Treatment Plant and
treated water used for gardening
Water Consumption is 10 KLD
Washing or
cleaning 2 KLD
Gardening
4 KLD
Domestic waste
water generation
3.6 KLD
263 KLD
(From wet waste)
and 2 KLD
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 97-
The separated solids will be discharged from the slurry at a DM content of
30%, and the filtered slurry, can be called as filtrate, will be sent to the
second stage of treatment.
Stage 2: Here the filtrate/separated water from the FAN separators will be
collected and held for a period of about 24 hours.
This liquid will be subject to aeration, achieved through a series of fine
bubble diffusers, to free the filtrate from entrapped gases allowing for the
suspended solids to easily settle down.
Part of the clarified water will be taken from the overflow of this tank for
recirculation. The settled sludge from the bottom of this tank will be taken
to the next stage of the process.
Stage 3: This is a settling tank which receives the settled sludge from the bottom
of the tank in the previous step.
Here the sludge solids are thickened further with the help of a little dose of
suitable polyelectrolyte and the clear water is taken by overflow of this
tank for recirculation/disposal as required
The thickened sludge from the bottom the tank is then taken to the solar
treatment facility.
Excess water will be discharged and used for agriculture. This water will
have the characteristics, which is suitable for discharge on the land for
irrigation purpose.
Stage 4: Here the thickened sludge form the poly separation unit as well as
manure separated from FAN separator are composted, dried in poly houses.
Here a total of 6 days retention space is provided for efficient drying from
30% TS to 50% TS of the separated solids. These are then used as organic
manure
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 98-
The organic manure is also sprayed with nutrients for enrichment. The
manure thus generated and enriched will be transported in bulk to the
clients for sale
Around 33 – 35 m3 of water will be evaporated from the poly house drying,
which ensures 100% functioning even when the humidity in air is high or
during rainy season.
Around 1760 sq, meters of space will be allocated for this purpose with
complete RCC concrete flooring to avoid seepage in the ground.
The poly house will be equipped with a tractor with a tiller machine attached
behind for efficient mixing and moisture removal process.
TABLE 2.18: SOURCE, QUANTITY & TREATMENT OF INDUSTRIAL
WASTEWATER
Type of
wastewater
Source Quantity,
KLD
Treatment Re-use of treated
wastewater
Domestic Waste
water
Waste water
form workers 3.6 ETP 148 nutrient rich water will
be used for ―on land
application for irrigation‖
standards stipulated by
pollution control board.
Industrial waste
water
Waste water
form Digester
265 ETP
2.16.3.1 TREATMENT SCHEME FOR EFFLUENT
DESIGN DETAILS FOR THE PROPOSED EFFLUENT TREATMENT PLANT DESIGN
ASSUMPTIONS:
Total quantity of Raw effluent = 300 m3/Day = 12.5 m3/ hr. BOD 3 @ 270 C = 450 mg. / ltr.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 99-
DESIGN DETAILS OF TREATMENT UNITS.
1. BAR SCREEN:
* Size of the Unit : 0.4 m x 0.5 m x 1.0 m long
* Function : To separate coarse matter from the
Raw effluent
2. EQUALISATION TANK
OBJECTIVE: To equalize the flow and pollutant concentration. Generally, 6 - 8 hrs.
Hydraulic retention time is given for equalization tank.
Provide one no. Equalization tank of 8 hrs hydraulic retention.
Q max = 300 m3/day
Average flow rate = 12.5 m3/hr
Tank volume required = 12.5 x 8 = 100 m3
Size of the unit = 5.3 m x 5.3 m x 3.5 m SWD
* Average BOD of effluent at the inlet of the Pre-aeration tank.
: 150 mg/lit.
* Total organic load with 20 % BOD reduction considered.
: 30 mg/lit.
Organic load = BOD X Flow rate
1000
* Total organic load in the system : 450 X 300 / 1000
= 135 Kgs/day.
* Total oxygen required assuming that
2 Kgs of O2/kg of BOD Removed : 2 X 135
= 270 Kgs/day.
Therefore Actual Air required for pre aeration: 270
----------------------------------
1.2 X 0.21 X 0.6 X 0.7 X 0.25
= 10,204.08 m3/day
* Air required for pre aeration : 425.17 m3/hr.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 100-
3. RAW EFFLUENT PUMP
* Volume of effluent : 300 m3/day or 12.5 m3/Hr
* Discharge rate : 12.5 m3/Hr @ 10 – 12 m head.
* Function : To transfer Raw effluent from pre-
aeration/equalization tank to
Aeration tank
4. AERATION TANK
* Flow : 300 m3/day or 12.5 m3/Hr
* F/M : 0.15
* MLSS : 4000 mg/liter
(i) Calculation of volume of aeration tank:
BOD X Flow rate
Volume = ----------------------
F/M X MLSS
Assume F/M = 0.15
MLSS = 4000 mg/l
* Therefore Volume of the Tank required : 450 X 300 ---------------- 0.15 X 4000
= 225 m3
*Considering 30% extra for Sludge Recirculation
Volume of Aeration Tank required : 67.5 m3
Therefore total volume of aeration tank required = 225 + 67.5
: 293 m3
Assume SWD to be 2.5m
Therefore plan area required = 293 /2.5
= 118 m2
* Size of Aeration Tank Required : 6.9 m x 6.9 m x 2.5 m SWD
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 101-
(ii) Calculation of total organic load:
* Average BOD of effluent at the inlet of Aeration tank neglecting BOD
Reduction with pre-aeration : 450 mg/lit.
Organic load = BOD X Flow rate
1000
* Total organic load in the system : 450 X 300 / 1000
= 135 Kg/day.
* Total oxygen required assuming that
2 Kgs of O2/kg of BOD Removed : 2 X 135
= 270 Kgs/day.
(iii) Calculation of air requirement:
Assume alpha =0.6 and β= 0.7
Consider oxygen transfer at 0.25 m depth =25%,
Density of Air: 1.2 Kg/m3
Percentage of Oxygen in Atmospheric air 21
Therefore Actual Air required for pre aeration : 270
------------------------------------
1.2 X 0.21 X 0.6 X 0.7 X 0.25
= 10,204.08 m3/day
Assuming duration of air supply as 24 hours per day
Air required = 425 m3/hr
(iv) Calculation of diffuser required:
Considering 8 m3/hour diffusion of air through the diffuser /m length
Number of diffusers required = 425/8
= 53.12 or say 54 diffusers
* Type of aeration : Membrane Fine porediffused
aeration system
* Function :To aerate the contents of the
aeration tank and to sustain the
biological activity so as
to reduce the organic load.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 102-
5. HOPPER BOTTOM SECONDARY SETTLING TANK
* Size of the unit : 4.4 m x 4.4 m x 2.5 m SWD
* Volume of the unit : 50 m3
* Detention time available : 4.0 Hours.
* Function : To separate the biological flocs from
the overflow of the aeration tank.
6. SLUDGE RECYCLE PUMP
* Volume of Sludge : 108 m3/day.
* Discharge rate : 4.5 m3/Hr @ 8 – 10 m head.
* Type of pump : Horizontal centrifugal with CI open
impeller self-priming type coupled
to motor of required speed with B
Class insulation and IP 55]
protection hood.
* Function : To re-circulate the return sludge to
aeration tank to maintain the
required MLSS and transfer excess
sludge to sludge drying beds or
Aerobic Digester.
7. POLY HOUSE:
The sludge hence, separated through poly separation and through settling tank will
be pumped out into the poly house for drying. This sludge generally has 15-18% TS
and rest of moisture. This moisture is allowed to e evaporated through thermal
drying process carried out in the poly house for 4 days. The resultant manure will
have around 30% TS and 70% moisture. This can be packed in bags and sold. The
water is nutrient rich water and can be used for farm lands or ―land of irrigation‖.
Inside the poly house we have a tractor with a tiller attached to it to mix and
move thoroughly the manure for better evaporation. This tractor runs for 8
hours/day. The poly house is fitted with a moisture trapping membrane filter duct,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 103-
for suction of air to the North side and an air blower to deliver the air outside to
the South end. The suction air will be void of moisture from air during high
humidity seasons due to the membrane filter. Molecular sieves will be used as the
membrane filter for moisture. Negative pressure will be maintained inside the
polyhouse to ensure that the moisture released by evaporation is sucked out. The
air delivered out will be passed through a bed of wood chips or coconut shells
which will be used to remove odour, if any.
8. ONLINE DOSING PUMP:
Provide Milton Roy Asia LMI / prominent make metering pump of
dosing capacity 4-6 LPH with 1000 liters capacity dosing tank.
9. FLOCULATOR:
Total quantity of Raw Sewage = 200 m3/Day = 8.3 m3/ hr.
Detention time = 0.3 hr
Volume of Flash Mixer : 8.3 x 0.3 = 2.49 m3
Assume depth as 1.2 m
Area of Flash Mixer : 2.08 m2
Diameter of Flash Mixer : 1.62 m
10. LAMELLA CLARIFIER:
Flow: - 12.5 m3/hr
Sizes: 1.4 x 2.6 m x 4.0 m
11. Thermal Sludge holding system/drying process
Thermal Drying process :- this process is designed to handle and dry solids. The
solids separated from the process are led into the poly houses. The solar thermal
load is considered at Bangalore at 4.5 kWhr/day (8 hours) during semi sunny
season and 10% higher during summer and 20% lower during rainy season. With this
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 104-
an evaporation quotient of 1.2 times higher is considered due to exothermic
reaction happening during composting. Inside the polyhouse any time the
temperature is always higher by 4-5○ C. Considering an evaporation of 16 m3 of
moisture from the manure every day and the latent heat requirement of 560
kCal/lit of water for evaporation, if the feeding is 250 tons per day of food waste,
we need around 1200 m2 of surface area which allows the manure to compost for 4
days. In this we also follow the manure enrichment process.
12. FINAL COLLECTION TANK :
Total quantity of Raw Sewage = 200 m3/Day
Average flow = 8.3 m3/hr
Provide 12 hr holding capacity
Volume of the tank required= 100 m3
Providing SWD 3.0 m
Final collection tank size is 5.8 m x 5.8 m x 3.0 m SWD
13. BLOWER CAPACITY:
Blower capacity required : Equalization tank + Aeration Tank +
Final collection tank + 10% extra
= 100 + 67.5 + 100 + 10%
= 267.5 + 26.75 = 294.25: 300 m3/hr
Note: The capacity of Common Twin Lobe Roots Air blower suitable to discharge
about 300 m3/hr @ 0.5 KSC – 2 Nos (1 W + 1 SB). The common blower shall supply
the air required for the Aeration System (Aeration Tank & Aerobic Digester) and
other primary, intermittent and final storage units of the treatment plant
(Equalization Tank, Pre-filtration and Filtered Water Tank)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 105-
FIGURE 2.18: ETP FLOW CHART
FLOW CHART OF PROPOSED EFFLUENT TREATMENT PLANT (300 KLD)
43 tons manure for drying beds
Separator model
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 106-
2.17 AIR DPOLLUTION AN MITIGATION MEASURES
2.17.1 POWER:
The power requirement for the project will be augmented from BESCOM. Further
one diesel generator of 350 kVA capacity is proposed to be installed to serve as an
alternative source of power supply to this unit.
2.17.2 AIR POLLUTION SOURCES:
The major air pollution sources from the plant is DG set. These sources are
provided with stacks of adequate height so as to disperse the emanating flue
gases. Air pollution sources details are shown in the table 2.19.
Table 2.19: Air Pollution Sources
Sl. No. Stack Details Stack Attached to
Physical Details D.G Set
1. Capacity 1 X 350 kVA
2. Fuel quantity 70 L/hr
3. Fuel used Ultra Pure Low Sulfur Content
Diesel
4. Stack height Chimney of 3 m (Above roof level)
5. Stack diameter 80 mm
Emission Details
1. Sulphur dioxide 0.01914 g/s
2. Suspended Particulate Matter (SPM)
0.00104 g/s
3. Oxides of Nitrogen 0.03129 g/s
4. Carbon monoxide 0.27118 g/s
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 107-
2.17.3 NOISE GENERATION AND ITS MANAGEMENT:
The main sources of noise from the proposed project is movement of vehicles on
the roads during transportation of waste from hotels and the DG set for which
acoustic enclosure is proposed. Also ambient noise levels will be ensured within
the ambient standards by inbuilt design of mechanical equipment and building
apart from vegetation (tree plantations) along the periphery and at various
locations within the plant premises.
2.17.4 SOLID WASTE GENERATION AND MANAGEMENT:
The quantity of solid waste generated from the proposed plant is detailed in the
following table 2.20.
Table 2.20: Solid waste generation during the operation phase
Total no. of employees 75
Assuming per capita solid waste generation rate as 0.20 kg/capita/day
Quantity of solid waste generated 15 kg/day
Organic solid waste : 60 % of the total waste 9 kg/day
Inorganic solid waste : 40 % of the total waste 6 kg/day
Disposal of domestic solid waste The domestic wastes are segregated
at source, collected in bins treated in
anaerobic digester within the plant.
The Solid waste generated from the proposed Bio Gas Plant is in the form of
Manure/ Slurry from Digester and the same will be used as bio fertilizer.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 108-
2.18 ASSESSMENT OF NEW & UNTESTED TECHNOLOGY FOR THE RISK OF
TECHNOLOGICAL FAILURE
The biogas plant is being established to process the food waste from various hotels
located in the jurisdiction of BBMP. The plant has been designed and executed
based on Anaerobic digestion (AD) and Continuously stirred tank reactor (CSTR)
technology for 250 TPD capacity.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 109-
CHAPTER 3
DESCRIPTION OF THE
ENVIRONMENT
3.1 STUDY AREA, PERIOD, COMPONENTS & METHODOLOGY
STUDY AREA: An area, covering 10 km radial distance around the project site is
considered as the study area for conducting baseline studies.
PERIOD: Baseline study in this Environmental Impact Assessment report was
conducted for a period of three months during October 2014 to November 2014.
COMPONENTS: Air, noise, water & soil analysis studies were carried out. Survey of
the flora & fauna in the surroundings & demographic pattern of the survey area
were also studied.
METHODOLOGY: Baseline environmental studies were conducted to know the
status of various environmental attributes, viz. climatic and atmospheric conditions,
air, water, noise, soil, land use pattern, ecological, socio-economic environment.
The studies involved conducting field studies and analyzing various parameters that
might be affected due to the plant and conducting socio-economic survey among the
people. Secondary data was collected from State/Central Government
organizations, semi-Government and public sector organizations.
The Topo map of the study area and Site Plan is appended as in fig 3.1 & 3.1 A.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 110-
FIG 3.1: TOPO MAP OF THE STUDY AREA
Project site
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 111-
FIG 3.1 A: SITE PLAN
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 112-
3.2 ESTABLISHMENT OF BASELINE
3.2.1 METEOROLOGICAL DATA
Assessment of the micro and macro meteorology is important from the standpoint of
understanding the nature and extent of air pollution in the study area. Climate has
an important role in the build-up of pollution levels. The climatic condition of the
area may be classified as moderately or seasonally dry, tropical or temperate
savanna climate with four seasons in a year. Winter is critical for air pollution build-
up because of frequent calm conditions with temperature inversions resulting in
poor atmospheric mixing, natural ventilation and high emission loads.
The classification of months according to the seasons is given in the following table3.0
TABLE:-3.0 SEASONS
Season Period
Summer March to May
Monsoon June to September
Post monsoon October to November
Winter December to February
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 113-
The metrological data reflecting minimum, maximum temperature in 0C, relative humidity in %, rainfall in mm/hr, wind speed in m/s, mixing height in m, cloud cover in tenths and atmospheric pressure in mb for the year 2013 obtained from modeling studies carried out using U.S. EPA AERMOD dispersion model, 1996 – 2013 Lakes Environmental Software, Version 7.1.0 has been appended as table 3.1.
TABLE 3.1: METEOROLOGICAL DATA OF BANGALORE FOR THE YEAR 2013
Month Temperature 0C
Relative
humidity %
Precipitation
rate (mm/hr)
Atmospheric
pressure (mb)
Wind
speed
(m/s)
Inversion /
mixing
height
(m)
Cloud
cover
(tenths)
Min Max Max Min Min Max Min Max Min Max Day Night Min Max
Jan 12.4 25.6 84.8 58.3 0 1.27 909 919 0 6.7 2303 2477 2 10
Feb 13.1 28.9 76.9 44.8 0 1.52 908 915 0 5.1 2517 1786 2 5
Mar 16.4 29.5 69 38.8 0 1.02 907 917 0 6.2 2798 2057 2 6
Apr 18.2 30.8 76.7 50.7 0 3.81 908 914 0 5.1 2910 1799 2 5
May 18.5 32 82.7 61.0 0 2.54 905 913 0 6.2 3319 2317 2 5
June 17.9 30.9 88.6 71.7 0 4.83 904 913 0 10.3 2828 4000 2 10
July 17.4 29.4 89 75.5 0 3.81 904 912 0 8.7 2691 3638 2 10
Aug 17 28.5 88.9 74.5 0 4.06 904 912 0 7.2 2678 2779 3 10
Sept 17.2 29.5 91.4 75.3 0 2.29 905 912 0 7.2 2802 2801 2 10
Oct 16.8 28.8 88.5 73.5 0 2.03 904 913 0 5.7 2575 2046 3 10
Nov 16.8 25.9 93.5 78.1 0 3.81 905 915 0 6.2 2177 2247 2 10
Dec 11.8 24.4 87.6 66.8 0 1.52 906 914 0 6.7 1756 2522 2 10
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 114-
3.2.1.1 TEMPERATURE The mean maximum temperature is observed at (32°C) in the month of May and the mean minimum temperature at (11.8°C) is observed in the month of December. In the summer season the mean minimum temperature is observed during the month of March (16.4°C). During the monsoon the mean maximum temperature is observed to be 30.9°C in the month of June with the mean minimum temperature at 17°C during August. By the end of September with the onset of post monsoon season (October - November), day temperatures drop slightly with the mean maximum temperature at 28.8°C in October and mean minimum temperature is observed at 16.8°C for both October & November. The values are presented in table 3.1.
3.2.1.2 RELATIVE HUMIDITY Minimum and maximum values of relative humidity have been recorded. The minimum humidity is observed to be at 38.8% in the month of March and the maximum is 91.4% in the month of September. The mean minimum values of humidity during summer, monsoon, post-monsoon and rainy seasons are 38.8%, 71.7%, 73.5% & 44.8% during the months of March, June, October and February respectively. Similarly the maximum values are 82.7%, 91.4%, 93.5%, 87.6% in the months of May, September, November & December during the summer, monsoon, post monsoon & winter seasons. The values are presented intable 3.1.
3.2.1.3 RAINFALL The monsoon in this region usually occurs twice in a year i.e. from June to September and from October to November. The maximum annual rate of precipitation over this region ranges between 1.02 to 4.83 mm/hr.
3.2.1.4 ATMOSPHERIC PRESSURE The maximum and the minimum atmospheric pressures are recorded during all seasons. In the summer season, the mean maximum and minimum pressure values are observed to be 917 mb in the month of March and 905 mb in the month of May respectively. During monsoon season, the maximum pressure is 913 mb and minimum 904 mb. The maximum pressure during the post-monsoon season is observed to be 915 mb in November and minimum pressure is 904 mb in the month of October. During the winter season the minimum atmospheric pressure is 906 mb in December and the maximum is 919 mb in the month of January. The values are presented in table 3.1.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 115-
3.2.1.5 INVERSION HEIGHT
The maximum inversion heights at the project site during the day time & night
time for all the months of the year is as given in the table 3.1. The maximum
mixing height of 4000 m is observed during the month of June during the night
time and 3319 m during the month of May during the day time. The minimum
inversion heights are 1756 m in the month of December during the day and
1786 m during the night in the month of February.
3.2.1.6 CLOUD COVER
The minimum cover measured in the unit of tenths is 2 and the maximum
observed cloud cover is 10.
3.2.1.7 WIND The data on wind patterns are pictorially represented by means of wind rose
diagrams for the entire year as figure 3.2 (for different seasons) and
predominant wind direction is appended in table 3.2.
TABLE: - 3.2 PREDOMINANT WIND DIRECTIONS
Season Period Wind direction Average wind
speed in m/sec
Summer March to May North West 2.73
Monsoon June to September East 4.09
Post monsoon October to November South West 3.26
Winter December to February North West 3.21
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 116-
FIG 3.2: WIND ROSE DIAGRAMS
1. MARCH TO MAY (SUMMER SEASON)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 117-
2. JUNE TO SEPTEMBER (MONSOON SEASON)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 118-
3. OCTOBER TO NOVEMBER (POST MONSOON SEASON)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 119-
4. DECEMBER TO FEBRUARY (WINTER SEASON)
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 120-
3.2.2 BASELINE MONITORING
3.2.2A SAMPLING AND ANALYTICAL TECHNIQUES
AIR QUALITY
PM10 and PM2.5 have been estimated by gravimetric method. Modified West and
Gaeke Method (IS: 5182 Part – II, 1969) has been adopted for estimation of SO2.
Jacobs – Hochheiser Method (IS: 5182 Part-VI, 1975) has been adopted for the
estimation of NOx. N D I R S (Non-Dispersive Infra Red Spectroscopic) Method
(IS: 5182 Part-X, 1999) has been adopted for the estimation of CO and
Electrochem sensor method has been adopted for the estimation of Ozone.
Spectrophotometric method for ammonia, AAS (Atomic Absorption
Spectrophotometry) method for lead. Summary of the analytical techniques
and their references are appended in table 3.2A
TABLE: 3.2 A: TECHNIQUES ADOPTED/PROTOCOLS FOR AMBIENT AIR
QUALITY MONITORING
SL.
No
Parameters Techniques Technical
Protocol
Minimum
detectable limits
as provided by lab
1 Sulphur Dioxide (SO2) West & Gaeke IS:5182 (P2) 4 mcg
2 Nitrogen Dioxide
(NO2)
Jacob & Hochheiser IS:5182 (P6) 1 mcg
3 Particulate Matter PM10 Gravimetric IS:5182 (P15) 5 mcg
4 Particulate Matter PM2.5 Gravimetric - 5 mcg
5 Ozone (O3) Electrochem sensor - NIL
6 Ammonia as NH3 Spectrophotometric Handbook of
air pollution
analysis
NIL
7 Carbon monoxide as
CO
NDIR IS: 5182 (P-10) 10 mcg
8 Lead as Pb AAS IS:5182 (P22) 0.01 mcg
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 121-
TABLE: 3.2 B: PROTOCOL FOR SURFACE WATER QUALITY
MONITORING
Sl.
No.
Parameter/Test Protocol
Physical parameters
1 pH IS: 3025 (P 11)
2 Suspended solids IS: 3025 (P 17)
3 Color & odor IS: 3025 (P 4&5)
4 Oil & grease IS: 3025 (P 39)
Chemicals parameters
5 Total dissolved solids IS: 3025 (P 16)
6 Ammoniacal nitrogen, as N IS: 3025 (P 34)
7 Total kjeldahl nitrogen, as N IS: 3025 (P 34)
8 Biochemical Oxygen Demand at
270 C for 3 days
IS: 3025 (P 44)
9 Chemical Oxygen Demand APHA
10 Chlorides, as Cl IS: 3025 (P 32)
11 Sulfates, as SO4 IS: 3025 (P 24)
12 Nitrates, as NO3 IS: 3025 (P 34)
13 Phosphates, as PO4 IS: 3025 (P 31)
14 Phenolic compounds, as C6H5OH IS: 3025 (P 43)
15 Total hardness, as CaCO3 IS: 3025 (P 21)
16 Calcium, as Ca IS: 3025 (P 40)
17 Magnesium, as Mg IS: 3025 (P 46)
18 Nitrates, as NO2 IS: 3025 (P 34)
19 Alkalinity, as CaCO3 IS: 3025 (P 23)
20 Fluoride, as F IS: 3025 (P 60)
21 Electrical conductivity APHA
22 Dissolved oxygen, mg/L -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 122-
TABLE: 3.2 C: PROTOCOL FOR GROUND WATER QUALITY
MONITORING
Sl.
No.
Parameter/Test Unit Protocol
1 Color True color units IS: 3025 (P 4)
2 Odor - IS: 3025 (P 5)
3 Taste - IS: 3025 (P 8)
4 Turbidity NTU IS: 3025 (P 10)
5 pH - IS: 3025 (P 11)
6 Chlorides as Cl mg/L AN-S-003
7 Total hardness as CaCO3 mg/L IS: 3025 (P 21)
8 Calcium as Ca mg/L IS: 3025 (P 40)
9 Magnesium as Mg mg/L IS: 3025 (P 46)
10 Total dissolved solids mg/L IS: 3025 (P 16)
11 Sulfates as SO4 mg/L AN-S-003
12 Copper as Cu mg/L IS: 3025 (P 42)
13 Iron as Fe mg/L IS: 3025 (P 53)
14 Manganese as Mn mg/L IS: 3025 (P 59)
15 Nitrate as NO3 mg/L AN-S-003
16 Fluoride as F mg/L AN-S-003
17 Phenolic compounds as
C6H5OH
mg/L IS: 3025 (P 43)
18 Mercury as Hg mg/L IS: 3025 (P 48)
19 Cadmium as Cd mg/L IS: 3025 (P 41)
20 Selenium as Se mg/L IS: 3025 (P 56)
21 Arsenic as As mg/L IS: 3025 (P 37)
22 Cyanide as CN mg/L APHA
23 Lead as Pb mg/L IS: 3025 (P 47)
24 Zinc as Zn mg/L IS: 3025 (P 49)
25 Anionic detergents as MBAS mg/L Annex K of
IS:13428
26 Chromium as Cr+6 mg/L IS: 3025 (P 52)
27 Residual free chlorine mg/L IS: 3025 (P 26)
28 Alkalinity as CaCO3 mg/L IS: 3025 (P 23)
29 Aluminum as Al mg/L IS: 3025 (P 55)
30 Boron as B mg/L APHA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 123-
TABLE: 3.2 D: TABLE: 3.2 D: EQUIPMENTS USED FOR NOISE & SOIL
MONITORING
Noise levels were measured using integrated sound level meter & soil quality
using pH meter, Conductivity meter, Turbidity Meter, Flame Photometer, Spectro
photometer, Mercury Analyser, Oven, Electronic Balance
3.2.2.1 AIR QUALITY
The baseline air quality was established by monitoring major air pollutants like suspended particulate matter, oxides of sulfur & nitrogen at various locations near the project site. High volume samplers were used for ambient air sampling. Suspended
Particulate Matter (SPM) i.e. PM2.5& PM10, sulfur dioxide (SO2), oxides of
nitrogen (NOx), NH3, Pb, O3, C6H6, Benzo(a) pyrene in particulate phase, As, Ni
and CO, etc. were determined. Samples were collected continuously from all
the stations for 24 hours. Samples thus collected were analyzed for various
pollutants as above.
Baseline data for ambient air quality was collected during the months of October, November 2014.The sampling stations along with their distance and direction from the project site, ambient air quality monitoring stations, wind rose diagram showing the direction of the blowing wind during the analysis period, ambient air quality analysis data for SPM, SO2
, NOx& National Ambient Air Quality Standards specified by MoEF are detailed subsequently. To study the existing ambient air quality, monitoring was done by Bangalore
Test House, Bangalore, NABL Accredited lab during the months of October &
November 2014.
The observations made during the study period are presented under the
forthcoming sub-sections.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 124-
METHODOLOGY ADOPTED FOR THE STUDY
The baseline status of the ambient air has been established through a
scientifically designed ambient air quality monitoring network. The following
criteria were taken into account during selection of the sampling stations:
Topography of the area
Human settlements within the study area
Safety, accessibility and non-interference with general routine of the people residing near the station
Prediction of maximum concentration of the air pollutants through dispersion modeling for the proposed source details using prevailing meteorological conditions in the region
Détails of ambiant air sampling stations are shown in table 3.3.
TABLE 3.3: AMBLENT AIR SAMPLING STATIONS
Sl.
No.
Code no. Name of the station Direction from
the site
Distance from
site (km)
1 A 1 Project site - -
2 A 2 Anikehantana Nagar South 0.35
3 A 3 Channenahalli South West 0.50
4 A 4 Seegahalli Bus Depot North- West 0.65
5 A 5 Seegehalli
(Downwind
direction)
North 0.30
6 A 6 Kannahalli South – East 1.21
Note:
PM10& PM2.5 - Particulate matter; SO2 – Sulfur dioxide; NOx – Oxides of
nitrogen; NH3 – Ammonia ; C6H6 – Benzene; As – Arsenic; Ni – Nickel; Pb –
Lead; O3 – Ozone; CO – Carbon monoxide; ND – not detected
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 125-
3.2.2.1.2 AIR QUALITY:
Ambient air quality analysis was conducted at 6 locations from October to
November 2014. The analysis reports are appended in the table 3.4 below and
Ambient air quality standards – MoEF as per the notification dated 16th
November 2009 for industrial, residential & rural areas is detailed in table
3.5.
TABLE 3.4: AIR QUALITY DATA ANALYSIS AT ALL LOCATIONS (DURING
OCTOBER 2014)
Sl.
No.
Parameter 24 Hrs concentration (µg/m3)
Monitoring station
A 1 A 2 A 3
A 4 A 5 A 6
1 PM2.5, µg/m3 27.0 29.1 26.6 29.0 23.4 28.2
2 PM10, µg/m3 26.5 46.0 28.3 39.5 23.8 44.0
3 SO2, µg/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
4 NOx, µg/m3 6.8 11.1 13.6 13.7 12.5 10.2
5 NH3, µg/m3 NIL Nil Nil Nil Nil Nil
6 Pb, µg/m3 <0.01 <0.004 <0.004 <0.004 <0.01
7 O3, µg/m3 NIL Nil Nil Nil Nil Nil
8 C6H6, µg/m3 ND ND ND ND ND ND
9 Benzo(a)
pyrene in
particulate
phase, ng/m3
<1.0 <1.0 <1.0 <1.0 <1.0 <1.0
10 As, ng/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
11 Ni, ng/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
12 CO, mg/m3 Nil Nil Nil Nil Nil Nil
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 126-
TABLE 3.4.1: AIR QUALITY DATA ANALYSIS AT ALL LOCATIONS
(DURING NOVEMBER 2014)
Sl.
No.
Parameter 24 Hrs concentration (µg/m3)
Monitoring station
A 1 A 2 A 3
A 4 A 5 A 6
1 PM2.5, µg/m3 43.9 26.3 26.3 30.7 35.1 39.5
2 PM10, µg/m3 62.0 54.3 57.2 63.4 58.0 55.0
3 SO2, µg/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
4 NOx, µg/m3 7.1 8.0 6.2 8.9 7.0 7.4
5 NH3, µg/m3 <20 <20 <20 <20 <20 <20
6 Pb, µg/m3 0.02 0.006 <0.004 0.01 <0.004 <0.004
7 O3, µg/m3 NIL Nil Nil Nil Nil Nil
8 C6H6, µg/m3 ND ND ND ND ND ND
9 Benzo(a)
pyrene in
particulate
phase, ng/m3
<1.0 <1.0 <1.0 <1.0 <1.0 <1.0
10 As, ng/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
11 Ni, ng/m3 <4.0 <4.0 <4.0 <4.0 <4.0 <4.0
12 CO, mg/m3 Nil Nil Nil Nil Nil Nil
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 127-
TABLE 3.5: AMBIENT AIR QUALITY STANDARDS – MOEF AS PER THE
NOTIFICATION DATED 16TH NOVEMBER 2009 FOR INDUSTRIAL,
RESIDENTIAL & RURAL AREAS
Air quality parameter Concentration
24 hrs Annual
1 Particulate matter (size less than 10
µm), PM10, µg/m3
100 60
2 Particulate matter (size less than
2.5 µm), PM2.5 ,µg/m3
60 40
3 Sulfur-di-oxide, µg/m3 80 50
4 Nitrogen dioxide, µg/m3 80 40
5 Ammonia (NH3), µg/m3 400 100
6 Benzene (C6H6), µg/m3 - 5
7 Benzo(a) pyrene in particulate
phase, ng/m3
- 1
8 Arsenic (As), ng/m3 - 6
9 Nickel (Ni), ng/m3 - 20
10 Lead (Pb), µg/m3 1 0.5
11 Ozone (O3), µg/m3 180 – 1 hr 100 – 8 hrs
12 Carbon monoxide, mg/m3 4 – 1 hr 2 – 8 hrs
Note:
24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring
Whenever and wherever monitoring results on two constitutive days of monitoring exceed the limits specified above for the respective category, it shall be considered adequate reason to institute regular or continuous monitoring and further investigation.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 128-
3.2.2.1.3 OBSERVATIONS It has been observed that the maximum concentration of all the parameters monitored at all the locations are within the limits specified by MoEF (as per the notification dated 16th November 2009 for industrial, residential & rural areas). Marginally high values at Seegehalli Bus depot are due to the frequent movement of vehicles.
3.2.2.2 NOISE ENVIRONMENT
The proposed project M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX),will result in moderate increase in traffic during the construction phase due to movement of construction materials, tools and tackles, laborers required for construction.
The lowest & highest noise levels and the limits as per Environmental
Protection Rules, 1986 for both industrial and commercial areas are presented
in the following tables 3.8 and summary of noise levels is shown in table 3.7.
And the Photographs Showing the Noise Monitoring during Baseline Data
Collection October 2014 is shown in fig 3.3
TABLE 3.6: NOISE LEVEL MONITORING STATIONS
Sl. No. Code
no.
Name of the station Direction from the
site
Distance from site
(km)
1 N 1 Project site - -
2 N 2 Anikehantana Nagar South 0.35
3 N 3 Channenahalli South West 0.50
4 N 4 Seegahalli Bus Depot North- West 0.65
5 N 5 Seegehalli
(Downwind direction)
North 0.30
6 N 6 Kannahalli South – East 1.21
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 129-
TABLE 3.7: SUMMARY OF NOISE LEVELS
Sl. No. Code No. Name of the Station Lowest
dB (A)
Highest
dB (A)
1 N 1 (October) Project site 48.1 50.8
2 N 1 (November) Project site 50.8 66.4
3 N 2 Anikehantana Nagar 42.0 57.2
4 N 3 Channenahalli 62.6 76.1
5 N 4 Seegahalli Bus Depot 50.9 77.9
6 N 5 Seegehalli
(Downwind
direction)
42.4 49.8
7 N 6 Kannahalli 49.8 65.2
TABLE 3.8: LIMITS AS PER ENVIRONMENTAL PROTECTION RULES, 1986
Limits as per Env. Protection Rules, 1986 in dB(A)Leq
Industrial area Commercial area Residential area
Day Night Day Night Day Night
75 70 65 55 55 45
3.2.2.2.1 OBSERVATIONS
The baseline noise levels have been monitored at different locations as indicated in the table above. It has been observed that the maximum noise levels at all the locations are within the limits specified for industrial areas. Comparatively high noise levels at Seegehalli Bus Depot (77.9 dB (A)) can be attributed to the movement of large number of trucks, lorries, government buses and other vehicles close to the monitoring station.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 130-
FIG 3.3 :- PHOTOGRAPHS SHOWING THE NOISE MONITORING DURING BASELINE
DATA COLLECTION OCTOBER 2014
PROJECT SITE ANIKETHANANAGAR
CHANNENAHALLI SEEGEHALLI BUS DEPOT
SEEGEHALLI KANNAHALLI
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 131-
3.2.2.3 WATER ENVIRONMENT
3.2.2.3.1 RECONNAISSANCE SURVEY
The impact has been assessed on randomly selected surface and ground water sources falling within the impact zone.
In order to assess the existing water quality, the water samples were collected
from five different locations within the study area and analyzed as per the
procedure specified in standard methods for examination of water and
wastewater published by American Public Health Association and Bureau of
Indian Standards (APHA/BIS). Name of the locations, orientation with respect
to the project site along with the type of source, the analytical data for
surface water quality and ground water quality at all locations has been
depicted in the following tables 3.10 & 3.11.
TABLE 3.9: WATER SAMPLING STATIONS
Sl.
No.
Code
No.
Name of the Station Direction
from site
Distance
from
site (km)
Source/ Type
1 W 1 Project site - - Ground Water
2 W 2 Anikehantana Nagar South 0.35 Ground Water
3 W 3 Channenahalli South West 0.50 Ground Water
4 W 4 Seegahalli Bus Depot North-
West
0.65 Ground Water
5 W 5 Seegehalli
(Downwind
direction)
North 0.30 Ground Water
6 W 6 Kannahalli South –
East
1.21 Ground Water
7 SW 7 Kannahalli Lake water South –
East
1.66 Lake Water
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 132-
3.2.2.3.2 SURFACE WATER The water requirement of about 10 KLD for the proposed Project will be met by
Bore Well water supply source.
There are no major perennial rivers within the study area, which otherwise would have served as a source of fresh water. The results of the analysis of surface water samples collected from Kannahalli lakes is appended in the following table and Kannahalli Lake Water Sampling Photographs During Baseline Data Collection is shown in fig 3.4.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 133-
TABLE 3.10: SURFACE WATER QUALITY
Sl. No. Tests Unit Results Maximum
Acceptable
Limits As per
IS:10500-1991
Maximum Permissible
Limits in the Absence of
Alternate Source As Per
IS:10500-1991
W 3
(October)
W4
(November)
1 Odor - Agreeable Agreeable Un-objectionable Un-objectionable
2 Taste - Not
Agreeable
Not Agreeable Agreeable Agreeable
3 Turbidity NTU 7.5 2.2 5 10
4 pH - 6.96 7.72 6.50-8.50 No relaxation
5 Chlorides as Cl mg/L 70.4 85.5 250 1000
6 Total hardness as
CaCO3
mg/L 199.9 289.7 300 600
7 Calcium as Ca mg/L 34.6 50.7 75 200
8 Magnesium as Mg mg/L 27.6 39.7 30 100
9 Total dissolved solids mg/L 378.0 536.0 500 2000
10 Sulfates as SO4 mg/L 12.6 15.0 200 400
11 Copper as Cu mg/L 0.09 <0.05 0.05 1.5
12 Iron as Fe mg/L 0.29 0.06 0.30 1.0
13 Manganese as Mn mg/L <0.1 <0.1 0.1 0.3
14 Nitrate as NO3 mg/L <0.1 <0.1 45 No relaxation
15 Fluoride as F mg/L 0.2 0.3 1.0 1.5
16 Phenolic compounds as
C6H5OH
mg/L Absent Absent 0.001 No relaxation
17 Mercury as Hg mg/L <0.001 <0.001 0.001 No relaxation
18 Cadmium as Cd mg/L <0.001 <0.001 0.01 No relaxation
19 Selenium as Se mg/L <0.01 <0.01 0.01 No relaxation
20 Arsenic as As mg/L <0.001 <0.01 0.01 No relaxation
21 Cyanide as CN mg/L Absent Absent 0.05 No relaxation
22 Lead as Pb mg/L <0.001 < 0.01 0.05 No relaxation
23 Zinc as Zn mg/L 0.07 0.01 5 15
24 Anionic detergents as
MBAS
mg/L <0.2 < 0.2 0.2 1.0
25 Chromium as Cr+6 mg/L <0.01 <0.01 0.05 No relaxation
26 Residual free chlorine mg/L <0.05 <0.05 0.2 min -
27 Alkalinity as CaCO3 mg/L 211.1 281.4 200 600
28 Aluminum as Al mg/L 0.03 0.04 0.03 0.2
29 Boron as B mg/L <0.1 <0.1 1.00 5.0
30 Coliform organisms
/100 ml
- 5400 Lessthan 1 - -
31 E-coli Bacteria/100 ml - Present Absent - -
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 134-
FIG 3.4 KANNAHALLI LAKE WATER SAMPLING PHOTOGRAPHS DURING
BASELINE DATA COLLECTION
3.2.2.3.2.1 OBSERVATIONS The analysis of samples collected from the Kannahalli Lake for various parameters reveals that the quality of water is within the maximum acceptable limits as per IS:10500-1991.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 135-
3.2.2.3.3 GROUND WATER Ground water is the major source of water in the area occurring under water table conditions in the weathered mantle of granite gneisses and in the joints, cracks and crevices of the basement rock. The depth of water is also dependent on topography and varies depending on the depth of weathering. The results of the analysis of Ground water samples collected from the project site and others locations is appended in
the following table and Water Sampling Photographs During Baseline Data Collection is shown in fig 3.5.
TABLE 3.11: GROUND WATER QUALITY
Sl.
No.
Tests Unit Results Maximum
Acceptable
Limits As per
IS:10500-1991
Maximum
Permissible
Limits in the
Absence of
Alternate
Source As Per
IS:10500-1991
W 1
(During
October
month )
W 1
(During
November
month )
W 2
W 3
W 4
W 5
W 6
1 Color True
color
units
<2 <2.0 1 <2 <2 <2 <2 5 25
2 Odor - A A A A A A A Un-objectionable Un-
objectionable
3 Taste - A A A A A A A Agreeable Agreeable
4 Turbidity NTU <0.01 0.3 0.1 0.2 0.4 0.2 0.5 5 10
5 pH - 6.86 7.06 7.00 7.33 6.97 7.04 6.86 6.50-8.50 No relaxation
6 Chlorides as Cl mg/L 57.4 45.6 97.3 127.7 83.8 114.5 249.1 250 1000
7 Total hardness as
CaCO3
mg/L 392.0 248.9 450.8 402.0 500.0 529.2 784.0 300 600
8 Calcium as Ca mg/L 58.9 49.1 70.7 114.0 114.0 126.0 125.1 75 200
9 Magnesium as Mg mg/L 59.6 30.8 66.7 28.6 52.4 52.4 114.4 30 100
10 Total dissolved
solids
mg/L 602.0 478.0 764.0 720.0 736.0 796.0 1246.0 500 2000
11 Sulfates as SO4 mg/L 25.2 17.8 38.2 28.0 26.8 22.9 95.9
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 136-
12 Copper as Cu mg/L <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05 1.5
13 Iron as Fe mg/L 0.12 0.03 0.09 0.09 0.06 0.08 0.13
14 Manganese as Mn mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.1 0.3
15 Nitrate as NO3 mg/L 2.3 7.7 42.8 28.2 18.2 24.7 55.1
16 Fluoride as F mg/L <0.02 0.4 0.32 0.35 0.5 <0.02 0.2
17 Phenolic
compounds as
C6H5OH
mg/L Absent Absent Absent Absen
t
Absent Absent Absent 0.001 No relaxation
18 Mercury as Hg mg/L <0.001 <0.001 <0.001 <0.00
1
<0.001 <0.001 <0.001 0.001 No relaxation
19 Cadmium as Cd mg/L <0.001 <0.001 <0.001 <0.00
1
<0.001 <0.001 <0.001 0.01 No relaxation
20 Selenium as Se mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 No relaxation
21 Arsenic as As mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 No relaxation
22 Cyanide as CN mg/L Absent Absent Absent Absen
t
Absent Absent Absent 0.05 No relaxation
23 Lead as Pb mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.05 No relaxation
24 Zinc as Zn mg/L 0.03 0.01 0.2 0.06 0.06 0.13 0.03 5 15
25 Anionic
detergents as
MBAS
mg/L <0.2 <0.2 <0.2 <0.2 <0.2 <0.2 <0.2 0.2 1.0
26 Chromium as
Cr+6
mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.05 No relaxation
27 Residual free
chlorine
mg/L <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.2 min -
28 Alkalinity as
CaCO3
mg/L 538.0 336.0 497.4 407.0 578.0 514.0 598.9 200 600
29 Aluminum as Al mg/L 0.035 0.02 0.02 0.02 0.01 0.01 0.023 0.03 0.2
30 Boron as B mg/L <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 1.00 5.0
UO - Un-objectionable; A - Agreeable
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 137-
FIG:- 3.5 WATER SAMPLING PHOTOGRAPHS DURING BASELINE DATA COLLECTION
PROJECT SITE ANIKETHANANAGAR
CHANNENAHALLI SEEGEHALLI BUS DEPOT
SEEGEHALLI KANNAHALLI
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 138-
3.2.2.3.4 OBSERVATIONS The physicochemical quality of the ground water sources at and around the plant site has been analyzed, which indicates that almost all the parameters analyzed are within the maximum acceptable limits as per IS:10500-1991 standards.
3.2.2.4 SOIL AND GEOLOGY
Soil characteristics, erosion aspects, soil fertility etc., have direct bearing on the
environment. Knowledge of soil parameters is essential for the planning and
implementation of green belt. Hence it becomes important to study the soil
characteristics. Baseline data for land environment was collected at five locations
in order to assess the soil quality of the study area. Soil samples at a depth of one
and half feet were collected using sampling augers, spades and field capacity
apparatus. The list of locations and the orientation with reference to the project
site are listed in table 3.12. Soil sampling locations are shown in the map
appended as fig 3.4. Soil samples were analyzed for physical and chemical
parameters the results of which are given in table 3.13 and Soil Sampling
Photographs during Baseline Data Collection is shown in fig 3.6 and sampling
locations marked in the Google map is shown in fig 3.7.
TABLE 3.12: SOIL SAMPLING STATIONS
Sl. No. Code No. Name of the Station Direction from site Distance from
site (km)
1 S 1 Project site - -
2 S 2 Anikehantana Nagar South 0.35
3 S 3 Channenahalli South West 0.50
4 S 4 Seegahalli Bus Depot North- West 0.65
5 S 5 Seegehalli
(Downwind
direction)
North 0.30
6 S 6 Kannahalli South – East 1.21
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 139-
TABLE 3.13: PHYSICO-CHEMICAL CHARACTERISTICS OF SOIL
Parameter Results (on dry basis)
S1 (during
October)
S1 (during
November)
S 2 S 3 S 4 S 5 S 6
Description Pale yellow
coloured moist soil
Brown coloured moist soil
Reddish brown
coloured moist soil
Brown colored Moist soil
Dark Brown colored moist Soil
Brown colored Moist soil
Brown colored Moist soil
pH 20% suspension 7.16 7.23 6.50 8.0 8.10 7.62 6.90
Organic solids, % 3.5 3.1 3.6 5.8 7.60 6.70 3.60
Inorganic solids, % 96.5 96.9 96.4 94.2 92.4 93.3
Chlorides as Cl, % 0.023 0.008 0.008 0.007 0.009 0.009 0.009
Phosphorous as P, % 0.023 0.004 0.004 0.044 0.03 0.74 0.024
Nitrogen as N, % <0.01 0.01 0.04 0.08 0.17 0.09 0.09
Potassium as K, % 0.54 1.25 0.14 0.21 0.35 0.15 0.10
Iron as Fe, % 2.7 4.3 1.9 1.7 3.4 5.1 1.70
Sulfates as SO4, % 0.01 0.005 0.001 0.08 0.11 0.065 0.05
Calcium as Ca, % 0.80 0.20 0.03 0.25 0.73 0.13 0.05
Magnesium as Mg, % 0.40 0.99 0.07 0.12 0.34 0.04 0.11
Conductivity, microomhos/cm (20% suspension)
121.0 106.0 21.0 114.0 186.0 123.0 47.0
Moisture, % 5.06 4.3 5.6 8.2 13.7 12.3 10.9
The results of the analysis show that the nature of the soil is neutral.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 140-
FIG: - 3.6 SOIL SAMPLING PHOTOGRAPHS DURING BASELINE DATA
COLLECTION
PROJECT SITE ANIKETHANANAGAR
CHANNENAHALLI SEEGEHALLI BUS DEPOT
SEEGEHALLI KANNAHALLI
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 141-
FIG 3.7: GOOGLE MAP SHOWING SAMPLING LOCATIONS
Table 3.14: LOCATION OF SAMPLING STATIONS Code no. on
Google map
Name of the Station Direction from
site
Distance from site
(km)
Sampling location
code
A1 Project site - - A1, N1, W1, S1
A2 Anikehantana Nagar South 0.35 A2, N2, W2, S2
A3 Channenahalli South West 0.50 A3, N3, W3, S3
A4 Seegahalli Bus Depot North- West 0.65 A4, N4, W4, S4
A5 Seegehalli
(Downwind direction)
North 0.30 A5, N5, W5, S5
A6 Kannahalli South – East 1.21 A6, N6, W6, S6
SW1 Kannahalli Lake South – East 1.66 SW1
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 142-
3.2.2.5 ECOLOGY
Natural flora and fauna are important features of the environment. They are organized into natural communities with mutual dependencies among their members and show various responses and sensitivities to physical innocence. The integrated ecological thinking and planning process is an urgent need in the context of natural environment's deterioration which has a direct bearing on socio-economic development. Ecology of the study area includes the flora and fauna studies within the study zone. The investigation included field observations, discussions with local people, forest officials etc.
3.2.2.5.1 FLORA
Land within the study zone is moderately dry, barren with patches of green fields surrounding the rural village settings. Tree species attaining moderate to considerable height are found to be present in sparsely distributed area. Eucalyptus plantations raised under various social forestry or afforestation schemes are also found in the area. The biodiversity of vegetation in the area is not very high due to intense agro ecosystem. The soil in this area is low to medium fertile with reference to its agricultural potential. The soils are shallow in depth and the alluvial soils are rarely found and also they are low in organic content. The flora found in the area includes commercial plantations like Beetle, Casurine, Areca, Coconut, Mulberry, Neelgiri etc. apart from other botanical species found in the study area. The naturally growing plants, vegetation & grasses found in the study area are as
appended below table 3.15.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 143-
TABLE: - 3.15 PLANTS, VEGETATION & GRASSES Sl.
No.
Botanical name Local name Distribution
1 Bambusa bamboo Big-Bamboo Occasional
2 Azadirachta indicia Bevu Common
3 Acacia suma Bilijali Rare
4 Casuarinas equsetifolia Galimara Occasional
5 Alangum lamrkil Ankola Rare
6 Parthenium hystresporus Congress grass Common
7 Ficus religiosa Arali Predominant
8 Mangifera indica Mavu Predominant
9 Vitex negundo Lakki-gida Rare
10 Bauhinia variegate -- Common
11 Ficus mysotrensis Gonimara Common
12 Pongamia pinnata Honge Common
13 Cleredendron inerne -- Occasional
14 Artocarpus integrifolia Halasu Rare
15 Acacua Arabica Gobli Rare
16 Asparagus recemosa -- Rare
17 Terminalia catapa -- Common
18 Michaelia chamara Sampige Occasional
19 Barleria buxifloria -- Rare
20 Eucalyptus teretilmonis Neelagiri Common
21 Govofiar ottleformis Buthale Rare
22 Acacia ferruginea Kaggali Common
23 Bombax ceiba (Bombax
malabaricum)
Burga Common
24 Tinospora cordifolia -- Occasional
25 Cymbopogon felxuosos Ginger grass Occasional
26 Dendrocalamus strictus Small bamboo Occasional
27 Crotalaria verrucosa -- Occasional
28 Emblica officinalis
(Phylanthusembilaca)
Amla, Nalli Occasional
29 Teprosia purpuria -- Common
30 Albizzia amara Chukkiau Common
31 Cymbopo nardus Citronella grass Common
32 Erythrine variegate (Erythrina
indica)
Hongarike Common
33 Delbergia latifolia Beete Occasional
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 144-
3.2.2.5.2 FAUNA
The fauna found in the region does not show much diversity, as there is no suitable
habitat for the occurrence of ecologically important fauna. Fauna observed in the
region include domestic animals, reptiles and birds. The composition of fauna in
the study area is presented in the table 3.16 below.
TABLE 3.16:- FAUNA IN THE STUDY AREA
Sl.
No.
Zoological Name Common Name
Mammals
1 Bos indicus Cow
2 Babulus indicus Buffalo
3 Lepus nigrocollis Indian hare
4 Pteropus gigantus Bats
5 Equus cabulus Donkey
6 Funambulus ponnanti Squirrel
Avian
7 Pavo cristatus Pea fouls
8 Corvus splendens Common crow
9 Psittacula cupatria Indian parakeet
10 Acrodopthesus tristis Indian myna
11 Conturnix coturnix Common quails
Reptiles & Amphibians
12 Rana tigrina Frog
13 Bufo melanosticus Toad
14 Hemidoctylus brookie Common lizard
15 Ptyas mucosus Rat snake
16 Calotes versicolor Garden lizard
3.2.2.6 SOCIO-ECONOMIC ENVIRONMENT
The baseline data referring to the socio-economic environment is collected by way
of secondary sources such as census records, statistical hand book and relevant
official records with the government agencies and primary sources such as the
socio-economic surveys conducted by different Govt. & Non Govt. Agencies.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 145-
The growth of industrial sectors and infrastructure development in and around the
agricultural area i.e. villages and semi-urban settings and towns is bound to create
certain socio-economic impacts on the local populace. The impacts may be either
positive or negative depending on the nature of development. To assess such
impact it is necessary to know the existing socio-economic order of the study area,
which will be helpful in improving the overall quality of life.
3.2.2.6.1 DEMOGRAPHIC STRUCTURE
The information collected from the secondary sources are from the district census
statistical hand books and the records of the National Informatics Center, New
Delhi in respect of the population, infrastructure facilities available and the
occupational structures of the study area.
The study has been conducted for Seegehalli village which is presented
subsequently.
The distribution of population in the study area as per the census record of the
2001 and population forecasted for 2011 are presented subsequently in the below
table 3.17.
TABLE 3.17: DISTRIBUTION OF POPULATION
Particulars Seegehalli
2001 2011
Total residential houses 61 90
Total population 305 447
Population male 157 230
Population female 148 217
Schedule caste male 78 114
Schedule caste female 82 120
Schedule tribe male 0 0
Schedule tribe female 0 0
Literates male 111 163
Literates female 74 109
Main workers male 92 135
Main workers female 37 54
Marginal workers male 6 9
Marginal workers female 11 16
Non workers male 59 87
Non workers female 100 147
Source: District census handbook
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 146-
Note: The percentage decadal growth rate for Bangalore during 2001 – 2011 is 46.68% (from http://censuskarnataka.gov.in/) Male population – 51.45 % Female population – 48.54 %
LITERACY LEVELS
The literacy level in the study area is as appended in table 3.18 below
TABLE 3.18: DISTRIBUTION OF LITERATES AND LITERACY LEVELS IN THE
STUDY AREA Particulars Seegehalli
2001
Total population 305
Total literate 185
Literate male 111
% of Male literate 60
Literate female 74
% of Female literate 40
Source: District census hand book
SOCIAL INFRASTRUCTURE AVAILABLE
The infrastructure and amenities available in the area reflects the economic well-
being of the region.
EDUCATIONAL FACILITIES: The educational facilities available in and
around the study area include primary, middle, high schools and colleges
with good facilities apart from Anganwadies in rural sectors, the details of
which are depicted in the Google map appended as fig 3.9.
COMMUNICATION FACILITIES: The study area and its surroundings have
sufficient post and telegraphs offices.
In addition to the above the study area and the villages surrounding it have
been provided with good electrical power supply for domestic, industrial
and agricultural purposes.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 147-
HOSPITALS: Hospitals & other health-care facilities are found in the
surroundings of the project site, the details of which are depicted in the
Google map appended as fig 3.8.List of infrastructural facilities in the
surroundings are presented in the below table 3.19.
TABLE 3.19: LIST OF INFRASTRUCTURAL FACILITIES IN THE
SURROUNDINGS Sl.
No.
Hospital Distance from the
Plant
Direction
w.r.t. the
Plant
1 Pooja Hospital 2.71 North
2 Tejas Hospital 3.95 South East
3 East West College of
management
4.08 North East
4 Nirman International public
school
4.49 East
5 Bangalore city railway station 17 East
6 Bengaluru International
Airport
39 North – East
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 148-
FIG 3.8: GOOGLE MAP SHOWING SURROUNDING HOSPITALS
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 149-
FIG 3.9: GOOGLE MAP SHOWING SURROUNDING SCHOOLS & COLLEGES
3.2.2.6.2 CONNECTIVITY
The Site is located to the West of Bangalore city. It is next to Sheegehalli bus depot
and has very good connectivity by public transport to city. The site is connected by
Magadi Road which is a State Highway and an internal concrete road from the Main
road which is of 2 Km in length approximately. The site location is around 17 Km
from city center bus stop called the Majestic Bus stop and the Google map showing
connectivity shown in fig 3.10.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 150-
TABLE 3.20: CONNECTIVITY FROM THE PROJECT SITE
Sl.
No.
Road Distance from the
project site (km)
Direction
w.r.t. project
site
1 Sheegehalli Main road 0.1 North
2 Magadi Main road 1.69 North
3 Nice Ring road (Toll Road) 3.31 North East
7 Bangalore city railway station 17 East
8 Bengaluru International Airport 39 North – East
Note: All distances mentioned are aerial.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 151-
FIG 3.10: GOOGLE MAP SHOWING CONNECTIVITY
3.3 ENVIRONMENTAL FEATURES
The proposed project site is in the eastern part of Bangalore at Latitude - 12o 58`
14.88‖ N Longitude - 77o 26` 48.48‖ E 962 m above MSL. The total plot area is 8
Acres. The general topographical features of the area reveal that the proposed
project site and its surroundings is generally a plain land. The Topo map covering a
radial distance of 15 km around the project site showing contours and general
features of the land is appended as fig 3.11. The Google map covering an aerial
distance of 1 km, 5 km & 10 km radials from the project site and delineating the
environmental sensitive areas is appended as fig 3.12, 3.13 & 3.14. Land use map
of the project site is shown in fig 3.15.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 152-
FIG 3.11: TOPO MAP COVERING 5 KM DISTANCE FROM THE PROJECT
SITE
Source: Survey of India; Scale: 1:50000
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 153-
3.4 BASE MAPS OF ALL ENVIRONMENTAL COMPONENTS
TABLE 3.21: EXISTING LAND-USE PATTERN
Sl.
No.
Particulars Details Distance
from the
project
site (km)
Direction
w.r.t.
project
site
1 Agriculture Minor activities - scattered - -
2 National park,
forest
Bannerghatta National Park 25.60 South West
3 Water bodies Kannahalli lake 1.54 West
Note:
a) All distances mentioned are aerial.
b) Land documents are appended as Annexure - B.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 154-
FIG 3.12: GOOGLE MAP COVERING 1 KM AERIAL DISTANCE FROM THE
PROJECT SITE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 155-
FIG 3.13: GOOGLE MAP COVERING 5 KM AERIAL DISTANCE FROM THE
PROJECT SITE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 156-
FIG 3.14: GOOGLE MAP COVERING 10 KM AERIAL DISTANCE FROM
THE PROJECT SITE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 157-
FIG 3.15: LAND USE MAP OF THE PROJECT SITE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 158-
3.5 SIGNIFICANT ENVIRONMENTAL ATTRIBUTES
Baseline environmental survey forms the basis for evaluation of the feasibility of the
proposed development in the existing conditions. This survey can be broadly grouped
into physical, social, aesthetic & economic environment. Physical environment
includes air, water, land, aquatic & terrestrial flora & fauna, civic infrastructure,
public services, etc; social environment includes demography, community facilities &
services, community characteristics, employment, commercial facilities; aesthetic
environment includes historical monuments, archaeological or architectural sites at &
in the vicinity of the proposed project activity and economic environment covers
employment levels, sources & levels of income, economic base of the area, land
values, land ownership etc. Table 3.22 gives various environmental attributes
considered for formulating environmental baseline.
TABLE 3.22: SIGNIFICANT ENVIRONMENTAL ATTRIBUTES
Sl.
No.
Environmental
attribute
Parameter Source of data
1 Ambient air quality PM10, PM2.5, SO2, NOX, CO Ambient air quality
monitoring at 6 locations.
2 Noise levels Noise levels in db(A) Noise level monitoring at 6
locations
3 Geology Geological history Secondary sources.
4 Water quality Physical, chemical and
biological parameters
Grab samples are collected at
6locations.
5 Soil Soil types and samples
analyzed for physical and
chemical parameters.
Data collected from
secondary sources and soil
sample analysis at 6 locations.
6 Ecology Existing terrestrial flora and
fauna within 5 km radius of
project influence area.
Secondary sources.
7 Socio –
economic aspects
Socio-economic characteristics
of the affected area.
Based on field survey and
data collected from
secondary sources.
8 Land-use Trend of land use change for
different categories
Master Plan 2015.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 159-
CHAPTER 4
ANTICIPATED ENVIRONMENTAL IMPACTS &
MITIGATION MEASURES
4.1 DETAILS OF INVESTIGATED ENVIRONMENTAL IMPACTS DUE TO
PROJECT LOCATION, POSSIBLE ACCIDENTS, PROJECT DESIGN, PROJECT
CONSTRUCTION, REGULAR OPERATIONS, FINAL DECOMMISSIONING OR
REHABILITATION OF COMPLETED PROJECT
Environmental components due to the construction and operation of the proposed
project. It details all the potential impacts on biophysical and socio-economic
components of the local environment due to the proposed activities and sub-
activities.
Prediction of impacts is the most important component in the Environmental Impact
Assessment studies. Several qualitative and quantitative techniques and
methodologies are used to conduct analysis of the potential impacts likely to accrue
as a result of the proposed development activities on physical, ecological and socio-
economic environments. Such predictions are superimposed over the baseline (pre-
project) status of the environmental quality to derive at the ultimate (post-project)
scenario of environmental conditions. The prediction of impacts helps to minimize the
adverse impacts and maximize the beneficial impacts on environmental quality during
pre and post project execution.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 160-
The proposed project will create impacts on the environment in two distinct phases:
During the construction phase which may be regarded as temporary or
short – term.
The other during the operation stage which would have long – term
effects.
The environmental impacts in this section have, as such, been discussed separately
for the construction phase and the operation stages of the proposed project. The
environmental impact assessment approach used to evaluate the proposed project
comprises of three sequential elements. These are impacts identification, prediction
and evaluation.
The first step of the impact assessment process involves identifying the key issues
associated with the construction and operation phases of the project. Issues and
concerns of the proposed project are scoped based on the knowledge and experience
with respect to environmental setting and project elements. Accordingly, the existing
environmental system is described and the components of the project are
determined.
This step involves identification of the environmental modification that may be
significant, forecasting of the quality and spatial dimension of change in the
environment identified and estimation of the probability that the impact will occur.
This step involve determination of the incidence of benefit to user groups and
population affected by the project, specification and comparison of effects between
various alternatives, and assessment of the likely effect of the project on the
environmental, economic and social components indicating the nature of effects.
4.1.1 PROJECT LOCATION
Major environmental impacts due to project location is not anticipated because
The Proposed ―Sustainable Waste Management and Renewable Energy‖ project
involving solid waste processing (food wet waste generated from bulk
generators) is located at Survey No. 85, Kannahalli Village, Yeshwanthpura
Hobli, Seegehalli Cross, Magadi Road, Bangalore – 560 091.
The site is located towards West of Bangalore city, next to the Seegehalli bus
depot and has very good connectivity by public transport to city.
No national park is located in the vicinity (10 km radius - aerial).
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 161-
The project emphasizes on the ―resource Recovery‖ concept of waste
management; involving the food waste processing and in turn extraction of
biogas.
Environmental impacts due to the construction and operation stages of the
project were predicted. The impacts during the construction phase will be
temporary in nature for a short construction period.
Adequate environmental management measures were incorporated during the
entire planning of construction and operation stages of the project to minimize
the adverse environmental impacts and assure sustainable development of the
area.
4.1.2 POSSIBLE ACCIDENTS
The proposed project is ―Sustainable Waste Management and Renewable Energy‖
project. Utmost care & precaution will be taken both during construction & operation
phases to prevent any possible accidents that might impact the environment.
4.1.2.2 OPERATION PHASE
Personal Safety (PPE)
The following Personal Protection Equipments (PPE) are proposed to be provided
1. Helmet
2. Goggles
3. Nose masks
4. Uniform
5. Aprons
6. Hand gloves
7. Safety shoes
Plant safety
The following measures and initiatives are proposed to ensure plant safety
1) Safety manual
2) MSDS
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 162-
3) Onsite emergency plan
Fire extinguishers
Flame-proof fittings
Emergency no.s
4) Insurance coverage in case of fire (PLI)
5) Electric safety, audit
Environment safety
The following measures are taken for environmental safety in case of accidents
1) Important telephone no.s
2) MSDS
3) Environment policy
4) Evacuation procedure
Safety audit
1) Internal audit
2) Safety training
3) First-aid training
4) Mock drill in case of emergency with respect to fire accident and handling of
extinguishers.
Health safety
1) Annual medical check –up
2) Medi-claim scheme for all employees.
4.1.3 PROJECT DESIGN
The biogas plant is designed with utmost consideration to the environment. The
trucks are designed as drip free and odor free.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 163-
4.2 ENVIRONMENTAL IMPACTS DUE TO THE PROJECT CONSTRUCTION,
REGULAR OPEARTIONS AND MEASURES FOR MINIMIZING &/OR OFFSETTING
ADVERSE IMPACTS IDENTIFIED & MITIGATION MEASURES
The Environmental Impact Statement enumerates the likely impacts due to the
implementation of the project on the six basic environmental parameters, which
are listed below.
1. Air environment
2. Noise environment
3. Water environment
4. Land environment
5. Biological environment
6. Socio-economic environment
The impacts on the above parameters have been identified, analyzed and
classified as adverse, beneficial impacts and the impact matrix is presented later
in the report.
4.2.1 ACTIONS LIKELY TO AFFECT THE ENVIRONMENT
Table 4.1 enumerates the activities of biogas plant which are likely to have
impact on the various environmental parameters. The impact matrix appended as
table 4.2, identifies all such impacts.
4.2.1.1 AIR ENVIRONMENT
4.2.1.1.1 CONSTRUCTION PHASE
Impacts
Following impacts are anticipated during construction phase.
Increase in gaseous emissions by heavy construction equipments and vehicles.
Increase in dust by construction activities. Earth excavation work, material
storage, transportation and handling of construction materials, and wind erosion
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 164-
are the major factors that would produce a temporary, localized increase in SPM
levels.
The increased movement of heavy vehicles carrying construction Material.
Operation of DG sets as standby power back up system would generate gaseous
emissions. The degree of dust generated will be depending on the soil compaction
and moisture content of the ground surface during construction.
Dust and exhaust particulate emissions from heavy equipment operations will
be temporarily degrade air quality in the immediate construction zone.
Mitigation Measures
A dust control plan is implemented viz. regular daily spraying of water on the
roads and dust emission area in the project site.
Regular maintenance of vehicles and equipment is carried out. The vehicles
having PUC is used during the construction period and an agreement with the
contractor for water spraying and use of vehicles with PUC as well as use of
environmental friendly methods during construction phase is made.
GI sheets are provided to a height of 5 m all around the project site to control
dust;
Water is sprinkled at regular intervals;
SO2 emissions from diesel generators are expected to be low because of usage
of low sulfur content diesel;
Use of efficient machinery and schedule maintenance of the Construction
vehicles and equipments.
4.2.1.1.2 OPERATION PHASE
Impacts
Project being biogas plant, there will not be any need of combustion
process except occasional operation of DG set in case of failure of power.
Hence there will be not any regular and continuous point source of flue gas
emission.
Mitigation measures
The DGs will be operated only during emergencies when there is failure of
power supply from BESCOM.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 165-
The generators would be provided with a stack of proper height (as per E (P)
Rules, 1986, item 96) for the proper dispersal of pollutants emitted from the
stack.
As the food waste, proposed to be processed is brought from hotels on day
to day basis the fresh waste will only be collected from the generation and
fed to the plants. The waste can odors only and therefore nuisance of
odour is not expected while transport of waste.
The anaerobic digestion and continuously stirred reactor technology for
processing of waste will not generate odor. The project emphasizes on resource
recovery i.e. the biogas extracted from the waste is sent for the fuel usage as a
substitute to LPG. The slurry will be sent to polyhouse to extract out moisture
and use it as manure. Thus the major cause of foul smell has been eliminated.
4.2.1.2 NOISE ENVIRONMENT
4.2.1.2.1 CONSTRUCTION PHASE
Impacts
The noise will be produced by transporting trucks, concrete mixer etc.
Mitigation measures
Construction work is carried out during day time only.
The workers near noise producing machine and noisy area is provided with
ear plugs.
Construction equipment and vehicles is maintained in good running
condition.
Providing noise reduction gadgets, providing PPE to construction workers to
prevent its effect on them.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 166-
4.2.1.2.2 OPERATION PHASE
Impacts
During the operation phase, the source of noise shall be equipments under
working such as pumps, blowers, DG sets and treatment machinery.
Noise generated from the loading and unloading activities.
Noise generated from transportation.
Mitigation measures
The diesel generator sets should be provided with integral acoustic enclosure
at the manufacturing stage itself. Accordingly, DG sets with integral acoustic
enclosure are be purchased and installed.
The noise producing machinery placed in acoustic enclosures/acoustic rooms to
reduce the noise levels.
Workers working near noisy area will be provided with ear plugs.
4.2.1.3 WATER ENVIRONMENT
4.2.1.3.1 CONSTRUCTION PHASE
Impacts
The wastewater produced from laborers may be a concern for the public
health.
Storm water with sediments from excavated material
Mitigation measures
Care is taken to securely store the excavated material and to reuse it as early
as possible in landscaping.
Drinking Water requirement of laborers is met by Bore well Sources.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 167-
4.2.1.3.2 OPERATION PHASE
During the operation phase, wastewater will be generated from the Septic tank and
Leachate will be generated from the process.
The plant has proper system for the collection of waste water generated from
all sources. Approximately 269 KLD of waste water will be generated and
further it will be treated in 300 KLD ETP. The 148 KLD nutrient rich water will
be used in plantation.
Wastewater generated due to operation & maintenance staff will be treated
in ETP.
Rain water harvesting will be practiced at the plant site.
Hence, no negative impact on surface and ground water environment quality is
Expected due to the proposed project activities.
4.2.1.4 LAND ENVIRONMENT
4.2.1.4.1 CONSTRUCTION PHASE
Impacts
There may be change in land use pattern
Mitigation measures
The project site is a land already earmarked for treatment of waste and is an
area without vegetation or human activity; therefore major/significant changes
in land use pattern is not anticipated.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 168-
4.2.1.4.2 OPERATION PHASE
Impacts
Slurry produced during the waste processing in the digester will be handled in
polyhouse.
Mitigation measures
Processed slurry will be used as manure only after physic-chemical testing and
complying with the norms of manure for crops or green belt.
4.2.1.5 ECOLOGICAL ENVIRONMENT
There is no wildlife sanctuary located within 10km radius of the project site. There
are no known rare, endangered or ecologically significant animal and plant species.
The development of green belt at the project vicinity minimizes the impact on the
ecology.
4.2.1.5.1 OPERATION PHASE
Impacts
No impact is envisaged on the flora and fauna of the area due to the operation
of proposed biogas plant.
Mitigation measures
Biogas plant will have beneficial effect on the environment due to reduced
pollution load
The immediate effect of biogas plant would be reduced dumping of
biodegradable organic food waste on the landfill and reducing the emission of
GHGs.
The excess wastewater discharged would comply with the norms aimed; with
the stipulated norms of MoEF and will not be harmful to the receiving body.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 169-
No biological sensitive area is present within 10 km radial area.
All the activities related to construction work shall be confined to the project
site only; hence no adverse social impacts are envisaged in the surrounding
area due to the project.
4.2.1.5.2 ODOUR MANAGEMENT
Mitigation measures for Odour Management in the Biogas Plant to be built at
Kannahalli, Magadi Road.
1. Waste disposal – The waste generated by hotels and restaurants is packed and
disposed in Garbage bags. These bags are tied and they do not allow the odour
to spread. These garbage bags will be placed in waste container at every waste
generator‘s end to ensure hygiene and easy handling of waste. These
containers will be weighed before pick up in the special trucks and unloaded
into the completely enclosed trucks. This avoids any spillage, leachate leaks
and odour during transportation of the waste to the site for processing.
2. Waste pick up process - The odour in food waste is generated not because of
the waste but because of the acids that form in the food waste. Technically
acid formation will begin at 30○ C temperatures after 14 hours of storage of
food and exposure to air. Generally the waste bins at home kitchens also do
not smell before 12 hours of storage. Beyond this, the formation of acids reach
a level where the smell and odour start getting generated. The waste
generated from the hotels/restaurants/bulk generators will be picked up by
Noble Exchange twice in a day. This disallows the waste to stay in a bin or a
bag beyond 12 hours every single day. The bags are picked up and brought to
the site without compacting them. This disallows any leachate floe from the
bags and neither are the bags torn and opened.
3. Site handling process – The waste picked up and brought to the site through
the bags is directly unloaded into waste collection hoppers. Each hopper is of
40 CBM capacity and can hold waste up to 32 tons. The waste is collected in
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 170-
two shifts every day. Morning shift starts at 6 a.m. and ends at 9 a.m. The
waste is transported to the site between 7.00 a.m. and 11.00 a.m. 70% waste is
collected during morning shift and 30% during afternoon shift as per the waste
generation data collected by Noble Exchange so far. The working shift begins
every day at 9.00 a.m. to 6.00 p.m. The afternoon collection happens between
2.00 p.m. and 4.00 p.m. The afternoon waste is processed up to 6.00 pm. The
unloaded waste is started to be processed at the rate of 15 tons/hour and
continues for 8 hours/day. This enables the waste being collected fresh and
processed fresh at the site. The problem of odor at site does not occur as the
hoppers are covered with PVC sheet. After waste being unloaded, the sheets
covers are pulled up to cover the hopper as per figure below. This avoids birds
and dogs to try and pick up the waste and spillage henceforth. No allowance
for unloading waste anywhere except the hoppers is allowed. This avoids the
employees any scope to unload the waste at site. Unlike any other waste
handling site, Noble Exchange is considering the complete in vessel unloading
of waste at site.
Fig 4.1 VESSEL UNLOADING OF WASTE AT SITE.
4. Other utilities for odour control – The project also includes a air ionization
system which is incorporated inside the segregation shed which will help keep
air odour under control. Also auto sprays with de-odorants are installed.
Outside the shed near the hopper the odour absorbing cakes will be installed
and replaced at periodical intervals. The plant varieties such as citronella
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 171-
grass, jasmine plants, lemon grass, vetiver will be planted as these plants are
known for odour absorption. Plants act as filters because they absorb the toxins
through their leaves, especially those with the largest leaves. Sight barrier
trees and tall grass such as Bamboo and Ashoka (also works as a lightning
arrester) will be planted at the compound wall. Other species of odour
absorbent plants can also be selected as below.
a. Areca palm
b. Citronella
c. Indian cock tree
d. Reed palm
e. Rubber plant - good for filtering a range of nasties, such as
formaldehyde, benzene and ammonia.
4.2.1.6 SOCIO-ECONOMIC ENVIRONMENT: ASSESSMENT OF POTENTIAL
IMPACTS
4.2.1.6.1 IMPACT ON POPULATION COMPOSITION
The impact of proposed biogas plant on population composition will be either nil or
negligible as only a few skilled and managerial staff will be recruited from outside
and the rest unskilled labors would be hired from local community.
4.2.1.6.2 IMPACT ON EMPLOYMENT GENERATION
The plant is expected to provide employment opportunities to about 75 people;
including skilled and unskilled workers. It is understood that all the persons to be
deployed for various activities will be recruited locally and there is very little scope
for migration of people from outside the study area.
The employment potentiality of the project is expected to ameliorate economic
condition of the families of those persons who will get employed in the plant. This is a
positive impact associated with the proposed project.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 172-
4.2.1.6.3 IMPACT ON INCOME
The family income of those who will be employed in the proposed ―Sustainable Waste
Management and Renewable Energy‖ project will get substantial boost. Similar, is the
case with others who will get benefited by indirect employment. This is a positive
impact of the proposed project.
4.2.1.6.4 IMPACT ON HISTORICAL, ARCHEOLOGICAL AND ARCHITECTURAL
SITES
There are no historical or archeological monuments of significance within the study
area. Hence, no negative impact is anticipated in this regard.
4.2.1.6.5 IMPACT ON LAW & ORDER
As local people will be employed to run the biogas plant, no law & order problem is
envisaged. It is expected that the workers will attend to their duties from their
residence and return to their homes after the day‘s work is over. There would have
been law & order problem if the workers were migrants and lived in shanties close to
the area.
4.2.1.6.6 PUBLIC PERCEPTION ABOUT THE PROJECT
Visit to villages/area in the study area has revealed that no one is against the
proposed biogas plant project, as it would be a seviour of health and also a provider
of employment to local people. They hope that the project will definitely increase
their income which in turn will increase their purchasing power. They however, have
demanded that only local people should be provided with employment and no one
else.
4.2.1.6.7 PUBLIC HEALTH
Construction workers will be provided with basic amenities like low cost
sanitation facilities, first aid, safe drinking water supply and personal protective
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 173-
equipment etc. The workers will be provided the medical assistance whenever
required.
The workers will be provided regular medical check-up camps and hospital
facility.
The workers will be provided with skill development training and training in
risk
Assessment and disaster management. Adequate mitigation measures will be
ensured to reduce odor emissions from plant.
4.3 IRREVERSIBLE & IRRETRIEVABLE COMMITMENTS OF ENVIRONMENTAL
COMPONENTS
There are no irreversible or irretrievable commitments of the environmental
components as adequate care will be taken to prevent any major impact on the
environmental parameters.
4.4 ASSESSMENT OF SIGNIFICANCE OF IMPACTS (CRITERIA FOR
DETERMINING SIGNIFICANCE, ASSIGNING SIGNIFICANCE)
The significance of the impacts identified in the previous sections for various
environmental parameters is detailed in this section.
4.4.1 IMPACT MATRIX
The impact matrix for the actions identified in table 4.3 along with various
environmental parameters. A rating scale has been devised to give severity of impacts
in the following manner.
A : Strongly beneficial (positive) impact
B : Low beneficial impact
C : Low adverse impact (localized in nature)
D : Strong adverse (negative) impact
- : No conceivable impacts on environment
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 174-
TABLE 4.1: ACTIONS LIKELY TO AFFECT ENVIRONMENT
Sl. no. Actions Envisaged for the following
Construction phase
1 Civil works Construction of Plant and structures.
2 Fabrication and erection Plant, utilities
3 Commissioning Plant, utilities
Operational phase
1 Treated waste water and Slurry
from ETP
Nutrient Rich water will be used for
gardening and the produced sludge will be
used as manure that is found as suitable
for agriculture / horticulture activity
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 175-
4.4.2 ENVIRONEMNTAL IMPACT ASSESSMENT
TABLE 4.2: ENVIRONMENTAL IMPACT ASSESSMENT Table 4.2 gives the overview of the potential impacts due to project location, construction and operation of the project.
Sl. no.
Environmental components
Predicted impacts
Probable source of impact
Mitigation measures Remarks
A CONSTRUCTION PHASE:
1 Air emissions Minor negative impact.
• Land preparation and construction activity. • Vehicular traffic.
• Water spraying on roads in project site • Regular maintenance of vehicles
• No remarkable increase in dust emission and other air pollutants
2 Noise Minor negative
impact.
Heavy machineries and truck movement
• Construction work during day time only • Ear plugs to workers • Regular maintenance of machineries and trucks.
• Noise will be below stipulated standard
3 Water Quality
Minor negative
impact.
• Wastewater produced from labourers • Excavated material
• Treatment of wastewater There is no Labour colony will be provided, as the local employees will be engaged for construction period
4 Land Quality
Land preparation and construction activity
• Change in land use pattern • Overburden & construction waste may pollute soil
• Project site is open land allotted for waste management so no change in land use pattern • Reuse of construction waste in construction for backfilling
• Quantum of excavated soil. & construction waste will be small.
5 Ecology (Terrestrial and aquatic)
Minor negative
impact.
Land preparation for construction of plant
Construction work during day time only and vehicles will be maintained in good condition.
Increase in noise will be very small
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 176-
6 Socio- Economic
No adverse impact
- Direct and indirect employment opportunities Aesthetic and hygienic environment will be created.
Improvement in Socioeconomic status of local people. Solid waste problem of the city will be reduced.
B OPERATION PHASE:
1 Ambient air quality
Minor negative impact.
Particulate and gaseous emissions from DG set.
Odor from the Anaerobic digester.
The emissions from DG will be let out through stack of heights 3 m AGL.
The anaerobic digester will be air tight with sealant and other inflating bags. The methane gas after generation will be stored in secured manure.
DG sets shall be used only during power failure. Occupationally during the venting and maintenance which is temporary.
2 Noise Minor negative impact near noise generation sources inside the premises.
Operation of Equipment (Pumps / Blowers)
Operation of DG set.
Acoustics will be provided for noise generating equipments of the plant
DG set will be provided with acoustic enclosure.
-
3 Water quality Positive impact is envisaged as the effluent will be treated to the on land discharge standards.
Nil NA as the treated effluent will be treated.
NA
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 177-
TABLE 4.3: IMPACT MATRIX
Sl.
No.
Environmental parameter Positive impact Negative
impact
No
impact
Short
term
Long
term
Short
term
Long
term
A Project setting
i Displacement of people
ii Change of land use
iii Loss of trees/vegetation
iv Shifting of utilities
v Impact on archaeological property
B Construction phase
i Pressure on local infrastructure
ii Impact on air quality including dust
generation
iii Noise pollution
iv Traffic congestion and loss of access
v Impact on the land/soil environment
vi Stacking and disposal of construction
material
vii Impact on water quality
viii Public health and safety
ix Social impact
C Operational phase
i Increase in air pollution and noise levels
ii Water harvesting and recharge
iii Disposal of solid waste
iv Induced infrastructure development
v Quality of life
vi Increment in the green-cover
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 178-
CHAPTER 5
ANALYSIS OF ALTERNATIVES
(TECHNOLOGY & SITE)
5.1 ALTERNATIVES FOR TECHNOLOGY
The site in which biogas plant is established is basically owned by BBMP with the
land earmarked for treatment of waste. Amongst this, the 5 acres wherein the
proposed plant is set up, is being granted to BBHA as permissive use for 20 years.
The treatment technology and treatment scheme for the waste from 400 number
of hotels has been finalized on the basis of detail data collection on quality and
quantity of the effluent produced by the industries. The hotels contributing to
biogas plant feed material is located within city from the project site.
5.1.1 TECHNOLOGY BRIEF
Anaerobic digestion is the prominent technology used for degradation of
biodegradable organic waste; employing Continuously Stirred Reactors (CSTR).
5.1.1.1 GENERAL DESCRIPTION OF ANAEROBIC DIGESTION PROCESS
Anaerobic Digestion (AD) is a biological process that happens naturally when
bacteria breaks down organic matter in environments with little or no oxygen. It is
effectively a controlled and enclosed version of the anaerobic breakdown of
organic waste in landfill which releases methane.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 179-
Almost any organic material can be processed with AD, including food scraps, fats,
oils & grease (FOG), tissue paper, garden waste, sewage and animal waste.
The two main products of AD are biogas & a solid residual.
An anaerobic digestion system is the central processing plant that converts the
organic waste slurry into Biogas, which is further converted into Compressed Bio
gas (CBG) /Electricity. Waste water from the system is re-circulated to ensure
zero fresh water requirement or discharge. By-product generated from the process
will be nitrogen rich, organic fertilizer that replaces conventional chemical
fertilizers for farming and gardening purpose.
This eco-friendly gas can be used either for cooking purpose or producing
electricity as per the client‘s requirement. The plant also produces odorless and
nitrogen rich Organic Manure as by-product of the process on daily basis. The
organic manure is a cost effective and eco-friendly replacement to conventional
chemical fertilizers used for gardening and landscape purpose.
The digestion process begins with bacterial hydrolysis of the input materials in
order to break down insoluble organic polymers such as carbohydrates and make
them available for other bacteria. Acetogenic bacteria then convert the sugars and
amino acids into carbon dioxide, hydrogen, ammonia, and organic acids. Acetogenic
bacteria then convert these resulting organic acids into acetic acid, along with
additional ammonia, hydrogen, and carbon dioxide. Methanogens finally are able
to convert these products to methane and carbon dioxide.
There are a number of bacteria that are involved in the process of anaerobic
digestion including acetic acid-forming bacteria (acetogens) and methane-forming
archaea (methanogens). These organisms feed upon the initial feedstock, which
undergoes a number of different processes converting it to intermediate molecules
including sugars, hydrogen & acetic acid before finally being converted to biogas.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 180-
Different species of bacteria are able to survive at different temperature ranges.
Ones living optimally at temperatures between 35-40°C are called mesophiles or
mesophilic bacteria. Some of the bacteria can survive at the hotter and more
hostile conditions of 55-60°C, these are called thermophiles or thermophilic
bacteria. Methanogens come from the primitive group of archaea. This family
includes species that can grow in the hostile conditions of hydrothermal vents.
These species are more resistant to heat and can therefore operate at
thermophilic temperatures, a property that is unique to bacterial families.
As with aerobic systems, the bacteria in anaerobic system while growing and
reproducing microorganisms within them require a source of elemental oxygen to
survive.
In an anaerobic system there is an absence of gaseous oxygen. In an anaerobic
digester, gaseous oxygen is prevented from entering the system through physical
containment in sealed tanks. Anaerobes access oxygen from sources other than the
surrounding air. The oxygen source for these microorganisms can be the organic
material itself or alternatively may be supplied by inorganic oxides from within the
input material. When the oxygen source in an anaerobic system is derived from the
organic material itself, then the 'intermediate' end products are primarily alcohols,
aldehydes, and organic acids plus carbon dioxide. In the presence of specialized
methanogens, the intermediates are converted to the 'final' end products of
methane, carbon dioxide with trace levels of hydrogen sulfide. In an anaerobic
system the majority of the chemical energy contained within the starting material
is released by methanogenic bacteria as methane.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 181-
Populations of anaerobic microorganisms typically take a significant period of time
to establish themselves to be fully effective. It is therefore common practice to
introduce anaerobic microorganisms from materials with existing populations. This
process is called 'seeding' the digesters and typically takes place with the addition
of sewage sludge or cattle slurry.
The methane producing bacteria consume these to produce methane and carbon
dioxide.
FIGURE 5.1 SCHEME OF REACTIONS PRODUCED DURING ANAEROBIC
DIGESTION
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 182-
TABLE: - 5.1 ADVANTAGES AND LIMITATIONS
Advantages Limitations
Available resources: The starting material for anaerobic digestion is
normally some form of waste unless
biomass has been produced
specifically for use as a feedstock.
Environmental sensitiveness: Several parameters (pH, temperature, salts,
alkalinity) need to be tightly
controlled in order to achieve
optimum performance.
Useful products: AD is primarily of
interest to renewable energy
technologists as it produces methane
which on combustion produces heat
and power.
Fluctuating loads: Anaerobic digestion
is pH sensitivity process and affects
the activity of methanogens.
Gas production: Obvious benefit of
AD is the production of methane
rich biogas which offers a renewable
alternative to the consumption of
fossil fuels.
Capital investment: High initial costs
required for implementation.
Fertilizer production: Organic fertilizer produced by AD offer a
considerably cheaper alternative to
the chemical fertilizers and
agrochemicals used in agriculture.
Required expertise personnel to operate
Pathogen removal: Potential
advantage of AD is the removal of
bacteria, tapeworm, parasites etc.
present in the untreated waste.
-
Odour reduction: A well-known drawback of the spreading of raw
slurries on land is the unpleasant
smell. The smells from decomposing
faecal wastes are usually created by
the release of compounds such as
ammonia, volatile organic acids, and
sulphides. Anaerobic digestion can
reduce odour nuisance during land-
spreading by up to 80%.
Persistence of Heavy metals
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 183-
5.1.1.2 ADVANTAGES AND DISADVANTAGES OF OTHER METHODS OF
SOLID WASTE DISPOSAL
COMPOSTING
Advantages
Concentrates Nutrients
Easier to transport
Composting Kills Parasites
Usable in organic systems.
Usable on land where food is grown for direct human consumption
Kills weed seeds
No odor when spread
Disadvantages
Loses about half the available nitrogen
Releases greenhouse gases
Need to have a composting area
Need to control rainfall runoff from the composting area
Difficult to do with liquid manure
Some manures might need a carbon source
Lot of area required
Scares commodity in urban cultures.
Labor intensive
Slow process
OCEAN DUMPING
Advantages
Convenient
Inexpensive
Source of nutrients, shelter and breeding‘
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 184-
Disadvantages
Ocean overburdened
Destruction of food sources
Killing of plankton
Desalination
SANITARY LANDFILL
Advantages
Volume can increase with little addition of people/equipment
Filled land can be reused for other community purposes
Disadvantages
Completed landfill areas can settle and requires maintenance
Requires proper planning, design, and operation
Issue of segregation
Labor intensive If not proper management leads to public nuisance.
Land requirement leads to public issues.
INCINERATION
Advantages
Requires minimum land
Can be operated in any weather
Produces stable odor-free residue
Refuse volume is reduced by half
Disadvantages
Expensive to build and operate
High energy requirement
Requires skilled personnel and continuous maintenance
Unsightly - smell, waste, vermin
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 185-
OPEN DUMPING
Advantages
Inexpensive
Disadvantages
Health-hazard - insects, rodents etc.
Damage due to air pollution
Ground water and run-off pollution
RECYCLING
Advantages
Key to providing a livable environment for the future.
Disadvantages
Expensive
Some wastes cannot be recycled
Technological push needed
Separation of useful material from waste difficult
BIO GAS PLANT ADVANTAGES
1) It‘s a renewable source of energy.
2) Its a comparatively lesser pollution generating energy.
3) Biomass energy helps in cleanliness in villages and cities.
4) It provides manure for the agriculture and gardens.
5) There is tremendous potential to generate biogas energy.
6) Biomass energy is relatively cheaper and reliable.
7) It can be generated from everyday human and animal wastes, vegetable and
agriculture left-over etc.
8) Recycling of waste reduces pollution and spread of diseases.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 186-
9) Heat energy that one gets from biogas is 3.5 times the heat from burning wood.
10) Pressure on the surrounding forest and scrubs can be reduced when biogas is
used as cooking fuel.
11) It is a more cost effective means of acquiring energy as compared to oil
supplies. As oil supplies are getting depleted day by day, it is becoming a costly
commodity.
12) Growing biomass crops use up carbon dioxide and produces oxygen.
13) Anaerobic digestion inactivates pathogens and parasites, and is quite effective
in reducing the incidence of water borne diseases.
14)Environmental benefits on a global scale: Biogas plants significantly lower the
greenhouse effects on the earth‘s atmosphere. The plants lower methane
emissions by entrapping the harmful gas and using it as fuel.
5.1.2 HEALTH ASPECTSA/ACCEPTANCE
AD is a centralized treatment technology that must be operated and maintained by
professionals. As with all waster processes, operators should take proper health
and safety measures while working in the plant.
5.1.3 MAINTENANCE
The sludge/slurry will be collected and disposed scientifically. The effluent stream
being organic in nature, Aerobic Digester technology is selected for treatment of
waste and also for resource recovery.
5.2 ALTERNATIVES FOR SITE
The land selected for establishment of biogas plant is very much suitable due to
the following reasons.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 187-
1. The site is located in the area earmarked for treatment of waste.
2. The area is owned by BBMP as is granted for permissive use of 20 years to
BBHA to process the generate food waste.
3. The area in which biogas plant is set-up is away from human settlements.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 188-
6.1 MEASUREMENT METHODOLOGY
Environmental Monitoring / sample analysis will be carried out
a) Ambient air monitoring: Bangalore Test House, Bangalore
b) Water quality: Bangalore Test House, Bangalore
c) Wastewater quality: Bangalore Test House, Bangalore
d) Soil quality: Bangalore Test House, Bangalore
e) Noise monitoring: Bangalore Test House, Bangalore
6.2 FREQUENCY, LOCATION, DATA ANALYSIS, REPORTING SCHEDULES,
EMERGENCY PROCEDURES
The Proposed “Sustainable Waste Management and Renewable Energy” project
involving solid waste processing (food wet waste generated from bulk
generators) is located at Survey No. 85, Kannahalli Village, Yeshwanthpura Hobli,
Seegehalli Cross, Magadi Road, Bangalore – 560 091. The site is located towards
West of Bangalore city, next to the Seegehalli bus depot and has very good
connectivity by public transport to city.
CHAPTER 6
ENVIRONMENTAL
MONITORING PROGRAMME
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 189-
In the project ―Sustainable Waste Management and Renewable Energy‖, the
influent weight of waste is monitored by placing the bins on an auto weighing
platform called the ―off-loader‖.
A comprehensive monitoring program is suggested in below table 6.1.
TABLE 6.1: MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS
(CONSTRUCTION & OCCUPANCY PHASE)
Sl.
No.
Particulars Monitoring
frequency
Duration of
monitoring
Important
parameters for
monitoring
I Air quality
Ambient air monitoring
1 Project premises Once in a
month
24 hourly
sample
RSPM, SPM, SO2,
NOx
2 Stack monitoring Once in 6
month
Grab SPM, SO2, NOx,
HC, CO
II Water and wastewater quality
1 Water quality
i Groundwater at two
locations (up-gradient
and down-gradient)
Once in a
month
Grab As per KSPCB
requirements
2 Wastewater quality
i Domestic sewage at the
outlet of the Sewage
Treatment Plant
Once in a
month
Grab As per KSPCB
requirements
III Soil quality
1 Within project premises
at 1 location
Once in six
months
Composite
sample
As per KSPCB
requirements
2 Ecological preservation
and up-gradation
Seasonal Visual
observations
Survival rate
IV Noise monitoring
1 Project premises Once in six
months
Day and night As per KSPCB
requirements
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 190-
The Structure of onsite emergency preparedness and response, Emergency
organization structure and Emergency coordinates are shown in fig 6.1, 6.2 & 6.3.
6.2.1 EMERGENCY PROCEDURES
FIG 6.1 STRUCTURE OF ONSITE EMERGENCY PREPAREDNESS AND
RESPONSE
Plant Level Worker
noticing an emergency
situation
Shift In-charge
1. If necessary, shutdown
the plant.
2. Contact the emergency
declarer
If emergency is off
site contact
concerned authority
and handover the
charge of emergency control operations.
Govt. Authorities
Police
Fire
Accounting of personnel
All clear signal (when
emergency is over)
Incident/Emergency controller
Fire/Security
Team
Rescue/First
Aid Team
Declarer of
emergency
Raise alarm
Inform over phone
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 191-
FIG 6.2 EMERGENCY ORGANIZATION STRUCTURE
SITE CONTROLLER & CHIEF EMERGENCY
DECLARER
(GENERAL MANAGER/PRODUCTION
MANAGER)
INCIDENT CONTROLLER/ALTERNATIVE
EMERGENCY DECLARER
(ADMINISTRATOR)
MAINTENANCE
SUPERVISORS / INCIDENT
EMERGENCY
DECLARER/CONTROLLER
MAINTENANCE
SUPERVISORS /
ALTERNATIVE
EMERGENCY DECLARER
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 192-
FIG 6.3 EMERGENCY COORDINATES
Detailed budgetary provisions for monitoring program is detailed in the following
table 6.2.
TABLE 6.2: FINANCIAL ALLOCATION/BUDGETARY PROVISIONS FOR
MONITORING PROGRAM
Sl.
no.
Description Number of
samples/year
Cost per
sample
Monitoring
cost
1 Air monitoring
12
12,000
1,44,000 a) Ambient air quality
monitoring
b) Stack monitoring 2 2,000 4,000
2 Water quality
2
1,500
3,000 a) Groundwater quality
3 Treated water from ETP
12
2,000
24,000 a) Treated water
4 Soil quality 2 2,500 5,000
5 Noise monitoring 2 250 500
TOTAL 1,80,500
Contingency at 10 % 18,050
TOTAL 1,98,550
6.3 DETAILED BUDGET
CONCERNED DEPARTMENTS
SECURITY
PERSONNEL
ESSENTIAL & SUPPORT
SERVICES
FIRE FIGHTING
RESCUE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 193-
Phased according to the priority, the implementation schedule is presented in the
following table 6.3.
TABLE: - 6.3 IMPLEMENTATION SCHEDULE FOR EMP
Sl. No. Recommendations Requirement
1 Air pollution control measures Before commissioning of respective Units
2 Water pollution control measures Before commissioning of the project
3 Noise control measures Along with the commissioning of the Project
4 Risk management During commissioning of the project
5 Green belt development Stage-wise implementation
The responsibility of EMP implementation lies with the project promoter for a
period of 3 years. Once the project is established, the EMP responsibility will be
properly handed over with clearly defined procedures and guidelines.
6.4 EMP IMPLEMENTATION SCHEDULE
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 194-
7.1 PUBLIC CONSULTATION
Amendment of the Environmental Impact Notification No. S.O. 60 (E) dated
27.01.1994, issued by the MoEF, Govt. of India has made mandatory under
Schedule-I of EIA notification for 30 different activities to obtain NOC (No
Objection Certificate) from the State Pollution Control Board and
Environmental Clearance from the Ministry of Environment & Forests (MoEF),
Govt. of India. This amendment to the EIA Notification is effective from
14.09.2006. It is in this context that all such activities need to prepare
Environmental Impact Assessment (EIA) report and also appear before Public
Hearing to ascertain the response of Public for the project based on the
General and Specific conditions in the said notification.
7.2 RISK ASSESSMENT
7.2.1 INTRODUCTION
Environmental risk analysis deals with the identification and quantification of risks,
the equipment and personnel are exposed to, from the hazards present in the
area.
Risk analysis follows hazard analysis (Risk = Hazard x Probability of occurrence). It
involves identification and assessment of risks to the plant personnel and
neighboring populations. This requires a thorough knowledge of failure probability,
CHAPTER 7
ADDITIONAL STUDIES
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 195-
credible accident scenario, vulnerability of population etc. Much of this
information is difficult to procure. Consequently, the risk analysis is confined to
maximum credible accident studies. The subsequent sections shall address the
identification of various hazards and risks in the operations, which will give a broad
identification of risks involved.
7.2.2 OBJECTIVE & SCOPE
The objective of the study is to carry out risk analysis and prepare disaster
management plan/emergency preparedness plans.
The risk analysis/assessment study covers the following:
(a) Identification of potential hazard due fuel storage.
(b) Assess the overall damage potential of the identified hazardous events and
impact zones from the accident scenarios.
(c) Suggestions and recommendations on the minimization of the accident
possibilities.
7.3 RISK ASSESSMENT & MANAGEMENT PLAN
A. CONSTRUCTION PHASE
Sl.
No.
Potential Mitigation
1 Accidental fire Fire safety gadgets
2 Fall of objects Use of personal protection devices-helmets
3 Working at great heights Protection to prevent fall with life safety belts and
nets.
4 Accidents from
machinery
Personal protection gadgets
5 Electrical mishap Adopting safety measures to prevent any act of
negligence and providing electrical safety measures like
fire extinguishers.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 196-
B. OCCUPANCY PHASE
Precautions for risk and disaster management plan:
Once the likelihood of the disaster is suspected, preventive actions should be
undertaken by the project in-charge.
Conditional maintenance of equipments, materials and expertise for use
during emergency.
The electrical systems should be provided with automatic circuit breakers
activated by over-current.
Fire extinguishers will be provided at pre-notified locations inside the
building.
Proper escape routes will be planned and displayed in the public domain.
Selected representatives will be given proper training to guide other
inhabitants during fire accidents.
Periodic awareness program will be conducted for the occupants on their
roles during emergency situations.
Important telephone numbers like police authorities, fire department and
hospitals etc. of use during emergency situations should be made available.
7.4 DISASTER MANAGEMENT
Disaster is an unexpected event due to sudden failure of the system, external
threats, internal disturbances, earthquakes, fire and accidents. Following
subsection describes the measures to be undertaken by the project proponent to
prevent / minimize risk of unexpected event.
Emergency prevention through good design, operation, maintenance and
inspection are essential to reduce the probability of occurrence and consequential
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 197-
effect of any eventuality. However, it is not possible to eliminate totally such
eventualities and random failures of equipment or human errors due to their
unconscious movements just cannot be ruled out. An essential part of major
hazard control is therefore, concerns with mitigating the effects of such
emergency and restoration of normalcy at the earliest. The overall objective of a
disaster management plan is to make use of the combined resources at the site
and outside services to achieve the following:
a) To localize the emergency and if possible eliminate it;
b) To minimize the effects of the accident on people and property;
c) Effect the rescue and medical treatment of casualties;
d) Safeguard other people;
e) Evacuate people to safe areas;
f) Informing and collaboration with statutory authorities.
g) Provide authoritative information to news media;
h) Initially contain and ultimately bring the incident under control;
i) Preserve relevant records and equipment for the subsequent enquiry into the
cause and circumstances of the emergency;
j) Investigating and taking steps to prevent reoccurrence
The DMP is therefore relates to the identification of sources, from which hazards
can arise and the maximum credible loss scenario that can take place in the
concerned area. The management plan takes into account the maximum credible
loss scenario – actions that can successfully mitigate the effects of losses/
emergency needs to be in a well-planned manner so that the requirement of
efforts to be put in is least.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 198-
7.4.1 ACTUATION OF THE PLAN
Any emergency starts as a small incident that may become a major accident, if not
controlled in time. At the initial stage, a fire organization chart (would be
prepared separately for each facility) needs to be put into action. If the incident
goes beyond control, the Main Incident Controller will need to actuate the on-site
plan at the appropriate stage as considered necessary. During idle shift/ holidays,
the security personnel will combat the incident as per the fire organization chart
below and at the same time inform various emergency controllers for guidance and
control the situation. An organization needs to be set up once the site is
operational by appointing key personnel and defining their specific duties that will
be handy in emergency.
7.4.2 EMERGENCY EQUIPMENT
The site controller will maintain a list of emergency handling equipment including
details of fire extinguishers, protective clothing, and personal protective
equipment for emergency handlers etc. Details of fire management services of
Bangalore city and neighboring hospitals will be available with site controller in his
operating checklist.
7.4.3 EMERGENCY RESPONSE
I. DANGEROUS SITUATIONS:
These are defined as the following:
• Any fire or explosion in the facility
• Any fire in the service buildings
• Exercise fire drill.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 199-
II. ACTIONS IN THE EVENT OF FIRE:
Basic actions are detailed above.
• Extinguishing fires: A small fire at a point of leakage should be extinguished by
enveloping with a water spray or a suitable smothering agent such as CO2.
Firefighting personnel working in or close to un-ignited vapor clouds or close to
fire, must be protected continuously by water sprays. Fire fighters should advance
towards the fire downwind if possible - BE CAREFUL TO AVOID H2S EXPOSURE.
• In case the only valve that can be used to stop the leakage is surrounded by fire,
it may be possible to close it manually. The person attempting the closure should
be continuously protected by water sprays, fire entry suit, water jet blanket etc.
The person must be equipped with a safety belt and a manned lifeline. In case of
rapid increase in decibel level, evacuate the area, as there would have been over
pressurization.
III. RESPONSE SEQUENCE FOR DANGEROUS SITUATIONS:
Person noticing the fire should attempt to isolate and extinguish the fire with the
available equipment and inform or arrange to inform the leader/ senior
representative regarding the
• Location of the fire
• What is burning
• The extent of fire
• Callers name and number
• Do not disconnect unless the person on the other side repeats the message or
acknowledges it.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 200-
A.SECURITY ON DUTY COORDINATORS WILL:
• Respond to the scene of the incident
• Arrange to send the necessary firefighting equipment to the scene of the
incident
• Extinguish the fire with the available equipment.
B.SECURITY OFFICER WILL:
• Sound the Siren as per the Siren Code
• Inform the Site Main / Incident Controller and act as per his instructions.
• To ensure gates are open to regulate traffic in such a way that free movement of
outside assistance like fire tenders, ambulance etc., is available.
A. Security should cordon off the area and local city firefighting staff should
benotified. The facility will have the firefighting water system but may not
be equipped with staff to operate it. Local fire fighters may need to be
notified.
B. All Other Management / Asst. / Labour Staff on hearing the siren, should
STOP their operations/ work, switch off lights, fans, engines, air
conditioners etc., close pipeline valves and line up in front of their working
places and meet at a pre-arranged location. These people will assist in
evacuating the residents if necessary.
IV. POST EMERGENCY FOLLOW UP:
• All cases of fire occurrence, no matter how small, must be reported promptly to
the Coordinator for follow up.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 201-
• Under no circumstances should fire extinguishing equipment once used be
returned to its fixed location before it is recharged/ certified fit by the Fire chief/
Safety Manager.
• Used fire extinguishers must be laid horizontally to indicate that they have been
expended.
V. EARLY WARNING / ALARM SYSTEM:
An audible electric alarm (siren) should be located in the main gate. The different
sounds that should be generated by the alarm are:
SMALL FIRE : No Siren
MAJOR FIRE : A wailing Siren for two minutes.
Sirens will be sounded three times for thirty seconds with an interval of 15 seconds
in between
EMERGENCY : Same type of Siren as in case of major fire but the
same will be sounded for three times at the interval of two minutes.
ALL CLEAR (For Fi re) : Straight Run Siren for two minutes.
TEST : Straight run Siren for two minutes.
7.4.5 EMERGENCY CONTROL CENTRE (ECC)
The Control Room will be nominated as the ECC. At the time of the emergency On-
site Controller assisted by other designated coordinators shall take position to
perform their duties. The security office at the gate shall be the standby. The
Emergency Control Center will be the focal point in case of an emergency from
where the overall operations to handle the emergency are directed and
coordinated. It will be located outside the area of potential hazards and easily
approachable.
The Emergency Control Center should have the following resources available:
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 202-
• Copies of the DMP
• Layout Plan of the complex.
• Information regarding Safety Equipment, Fire Fighting material
• A list of telephones of key and essential staff of the company along with their
residential numbers.
• Copies of the local Telephone Directories.
• A list of important telephone numbers like those of neighboring industries, Fire
Brigade, Hospital s etc.
• Personal Protective Equipment.
• First – Aid Kit.
• Communication equipment – Internal and External telephones and other
communication equipment.
• Requisite stationary items.
• Personnel to act as messengers.
The communication equipment is checked periodically to ensure that they are
functional.
The ECC is capable of being activated within a few minutes upon declaration of an
emergency.
7.4.6 MEDICAL RESOURCES:
The medical management for the possible emergency situations essentially
consists of treatment for burns and maybe some asphyxiation cases. They could
cause burns injuries. Material Safety Data Sheets and other relevant information
would also be available at the facility to enable ready treatment of any casualty,
should the unfortunate need arise. It is also proposed to circulate any important
Health and Toxicology material available through the latest research to all
Doctors.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 203-
7.4.7 RESPONSE EVALUATION, TESTING AND UPDATING OF THE PLAN:
Formulation of a Disaster Management Plan cannot possibly be an end by itself. It
needs to be tested by holding of periodical mock emergency simulations and drill.
Any shortcomings revealed during such exercise should thereafter be corrected by
amending the plan. The plan should be for times to come; hence, it must be
reviewed at periodic intervals. The plan should also be reviewed and updated
when:
• Major alteration or extension of plant is carried out.
• Major change in habitation or land use of the neighborhood takes place.
• Important telephone numbers used are altered, facilities are changed.
Mock drills activating the Disaster Preparedness Plan will be conducted
periodically for ensuring its efficiency during emergency as well as for refinement
and updation. These drills based on the plan will help achieve its objectives.
7.4.8 PREVENTIVE ACTION
Once the likelihood of a disaster is suspected, action has to be initiated to prevent
a failure. Engineers responsible for preventive action should identify sources of
repair equipments, materials, labor and expertise for use during emergency.
7.4.9 REPORTING PROCEDURES
The level at which a situation will be termed a disaster shall be specified. This
shall include the stage at which the surveillance requirements should be increased
both in frequency and details. The project in-charge should notify the officer for
the following information
Exit points for the public,
Safety areas at the site,
Nearest medical facilities.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 204-
7.4.10 EMERGENCY MEASURES
The proposed project is designed as per the NBC norms and occurrence of
accidents is not envisaged. The emergency measures are adopted to avoid any
failure in the system such as lights, fire, means of escape, ventilation shafts etc.
The aim of Emergency Action Plan is to identify areas, population and structures
likely to be affected due to a catastrophic event of accident. The action plan
should also include preventive action, notification, warning procedures and co-
ordination among various relief authorities. These are discussed in following
sections.
7.4.11 EMERGENCY LIGHTING
Emergency lights operated on battery power should be provided at appropriate
locations. The system should supply power to at least 25 % of the lights at those
locations for a period of 2 hours. Minimum of 2 transformers should be kept
energized and should feed independently alternate rows of lights so that incase of
failure of one transformer, there will not be complete darkness.
7.4.12 FIRE PROTECTION
Fire protection is one of the most essential services to be provided. In design
component of the project adequate measures have to be undertaken as per the
provisions of the National Building Code (SP 7: 1983 Part IV Amendment No. 3 of
January 1997).
The building materials should be of appropriate fire resistance standard. Wood
shall not be used for any purpose, excluding artificial wood products, which are
flame resistant. The materials which have zero surface burning characteristics
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 205-
need to be used. The electrical systems shall be provided with automatic circuit
breakers activated by the rise of current and by over-current. The design will
include provision for the following:
Fire prevention measures,
Fire control measures,
Fire detection systems,
Means of escape,
Access for fireman &
Means of firefighting.
Accumulation of refuse of any inflammable material like paper, plastic cartons
constitute a major fire hazard and should not be permitted. Smoking should be
strictly prohibited at all public locations.
All aspects of fire prevention and control will be dealt in close collaboration with
the city firefighting authority. Smoke control will be achieved by the following
means
Down stand bulkheads of a minimum depth of 600 mm to provide smoke
containment. These will be provided around openings for escalators, lifts and
stairs in underground stations. Adequate firefighting measures have been taken
into account while designing the distribution system for the area.
7.4.13 SAFETY ASPECTS FOR OCCUPATIONAL HAZARD
1. Fire Hydrant system with storage of 480 m3 of water and with two electric + 1
diesel pumps. Line is distributed to all sides of the plot plant with outlets and
spay nozzles where ever necessary.
2. Firefighting equipment like fire retardant cylinders and fire extinguishing sand
buckets are kept near the CBG area, manure area and the segregation shed.
3. All safety valves, pressure release valves, over and under pressure valves.
4. Gas flare for emergency gas release with ionizer and spark ignition system
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 206-
5. PLC control for the entire process control
6. All electrical in Zone 2, are ex-proof
7. All cabling is underground
8. Safety distances as per PESO norms are followed in the CBG area.
7.5 FIRE FIGHTING FACILITY:
The site plan includes a fire hydrant tank at the south west corner of the facility.
The excess process water from the separation after manure will be directed to this
tank. The tank hosts 480 m3 water and is of dimensions 7.7 meters width x 15
meters length x 4.5 meters height with 0.3 meters head space. The tank will be
associated with a pumping room which will host 2 Nos. electric pumps and 1 No
diesel pump as a mandatory norm for fire hydrant tank. The entire site will have a
fire hydrant line with spray hoses and fire boxes at required intervals. The CBG
storage area will be covered with a shed and will have spray nozzles for fire
retardant water spraying over the top. Apart from this as per Zone classification
the entire CBG area will have flame proof equipment. Throughout the site, fire
hydrant sand buckets and fire retardant CO2 pressurized canisters will be placed as
required.
7.6 SOCIAL IMPACT ASSESSMENT R&R ACTION PLANS
The proposed project in a vacant plot which does not have any habitation and
therefore no re-settlement & re-habilitation is envisaged.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 207-
CHAPTER 8
PROJECT BENEFITS
8.0 INTRODUCTION
The benefits arising from the project is improved environmental and living
conditions and public health in the vicinity of project site. Benefits are achieved
through more effective removal of waste from in and around inhabitant areas and
prevention of waste leachate entering drains and waterways and sometimes in
broken water supply pipelines. Improved disposal of waste will also result in more
pleasant surroundings through a reduction in odour and an improvement in the
aesthetic quality of drains, waterways, low-lying areas and other areas where
waste is dumped.
8.1 HEALTH BENEFIT
However, quantifying environmental and health benefits are difficult because of
the need for data to establish the magnitude of impacts of the improvements and
to separate out the effects of improved waste collection and scientific disposal
system from other factors such as personal hygiene habits, housing standards,
water quality etc.,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 208-
Research findings indicate that sanitation improvements result in more health
benefits, mainly in terms of reducing the waterborne diseases. Sanitation
improvements in urban areas will help to reduce this high incidence of annual
household medical expenditure by reducing the impact of waterborne diseases
considerably. This will apply to the present project town also. The inadequacies
of the waste management system were considered major contributing factors to
personal hygiene and public health conditions. The risk of environmental
sanitation related diseases would be reduced with properly maintained and
functioning waste management together with increased public awareness on the
effects of indiscriminate disposal of wastes into waterways and dumping of rubbish
in open areas.
8.2 ECONOMIC BENEFIT
The economic benefits considered in the present analysis for the waste
management component in Bangalore town include:
(i) Reduction of household medical expenditure due to improved hygienic living
condition.
(ii) Time, Energy, Money savings due to organized scientific Waste Treatment
and Disposal;
(iii) Economic revenue through sales of manure and CBG ;
(iv) Reduction of cost in private and public money for mosquito control;
(v) Positive impact on tourism and tourist-related businesses.
With the coming up of the project there will be many positive impact on the area.
The project benefits are described in different sections of this chapter.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 209-
8.3 MARKET POTENTIAL
There is a lot of demand for CBG and manure. Our country having predominance of
agriculture and horticulture is now facing acute shortage of good quality of
compost. Since the required quantities of compost are not available, most of the
users are currently relying on synthetic chemical fertilizer for nourishment of
crops. There is now resistance from consumers of food items against chemically
grown products. The trend in last 7-8 years has shifted in favour of originally
produced food items.
Even horticulturists, landscapers and home garden promoters are reluctant to use
chemical sources of plant nutrients due to their soil sickening effects and possible
toxicity of water resources.
8.3.1 MAJOR MARKETS FOR CBG AND MANURE
BIOGAS, UTILIZATION AND PRICE:
An alternative and sustainable form of energy can be seen in biogas. The main
components of biogas are methane and carbon dioxide along with traces of
hydrogen sulphide, water vapor etc., Biogas occurs naturally and is formed by a
microbiological process of decomposition of organic matter. In controlled
conditions such as in biogas plants the formation process of biogas can be
efficiently established in order to recover energy from biological conversion of
organic matter.
More advanced technologies are being incorporated for using the biogas for
combined heat and electricity production or for the up-gradation of biogas to a
high quality fuel which is of more relevance for emerging economies. In general,
the up-gradation process of biogas implies the removal of carbon dioxide and other
impurities. In this way the methane content in the gas is concentrated to a level of
92% to 99%, depending on the chosen up-gradation technology. After the up-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 210-
gradation process the biogas becomes an energy rich fuel, which is generally
marketed as bio-methane or compressed biogas (CBG). Unlike the raw biogas the
up-graded biogas has the quality and the properties to be compressed into
cylinders or to be injected into the natural gas grid. Herein the up-graded biogas
can be distributed to various consumers, replacing for example furnace oil, diesel,
natural gas or liquefied petroleum gas.
The economic evaluation reveals the fact that the highest value generation is in
the replacement of liquid and gaseous crude oil products. Herein biogas gains
relevance for an emerging and oil dependent economy such as India. With a daily
consumption of 3,182,000 bbl/d India is the 5th largest consumer of oil and with
approx. 80% heavily dependent on imports. As per various projections, India‘s
energy needs are expected to grow by 40% in the next five years and more than
triple by the end of 2030. Depending on the biogas plant development biogas may
play an important role in contributing an indigenous source of energy to the
overall demand and reduces the dependency on imported fossil energy.
8.3.2 MAJOR MARKETS FOR CBG AND MANURE
Following are the key areas for consumption of manure generated out of waste
from cities.
Agriculture: In the farming of cereals, vegetables and flowers.
Landscaping: Various grades of soil conditioners, moisture retainers and
nutrient provider.
Horticulture and Plantations: As growing media, soil conditioner, mulching
material, nutrient supplier, alternative to peat, moisture retainer.
Land restoration programme: For soil conditioning effect, to overcome
salinityproblems mulching material to control water evaporation losses.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 211-
Silviculture/Afforestation: For biomass/greenification promotion.
Golf course/lawns: Fine quality compost is most essential input for lawn and
golf courses, turfs.
Avenue trees in city beautification: As a nutrient supplier, moisture retainer.
Green houses: As a potting media and root condition.
8.4 RECYCLING OF MATERIALS
The materials like metals, plastic, glass etc. will be segregated first from the
waste generated. The segregated waste will then be sold to authorized vendors to
minimize the raw material consumption.
8.5 SOCIO-ECONOMIC BENEFITS
With coming up of the proposed project the employment opportunities
(direct as well as indirect) will increase and local people will be employed
on the priority basis as per their skills.
During operation phase 75 people will get direct employment opportunity.
The transportation of the material will involve a network of persons
engaged in collection and transportation of material, thus developing the
indirect employment opportunity.
The proposed project will help in creating pollution free clean environment
and will generate source of income from otherwise considered waste. This
will help in improving the living conditions of the people.
The project will involve the treatment of waste in scientific way without
causing environmental problems such as odour, health hazard etc.
Rain water will be harvested; it will improve the ground water level.
Local people will be employed in the project. Due to coming of the
proposed project the surrounding environment will not face any problem
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 212-
related to pollution because appropriate pollution control equipments will
be followed.
During operational phase more than 33% of the plant area will become
green under landscape/land cover.
Conducting Medical Camps for medical examination of the villagers and
distribution of medicines.
Funding the local educational facilities.
The company will also provide funds for the various development activities
of the neighboring villages as and when required.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 213-
CHAPTER 9
ENVIRONMENTAL COST
BENEFIT ANALYSIS
9.1 INTRODUCTION
Cost–benefit analysis (CBA), sometimes called benefit–cost analysis (BCA), is a
systematic process for calculating and comparing benefits and costs of a project
for two purposes
to determine if it is a sound investment (justification/feasibility)
to see how it compares with alternate projects (ranking/priority
assignment)
It involves comparing the total expected cost of each option against the total
expected benefits, to see whether the benefits outweigh the costs, and by how
much.
In CBA, benefits and costs are expressed in money terms, and are adjusted for
the time value of money, so that all flows of benefits and flows of project costs
over time (which tend to occur at different points in time) are expressed on a
common basis in terms of their "present value."
ENVIRONMENTAL COST-BENEFIT ANALYSIS, refers to the economic appraisal of
policies and projects that have the deliberate aim of improving the provision of
environmental services or actions that might affect (sometimes adversely) the
environment as an indirect consequence.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 214-
9.2 USES OF CBA
CBA has traditionally been applied to big public sector projects such as
new motorways, by-passes, dams, tunnels, bridges, flood relief schemes
and new power stations.
The basic principles of CBA can be applied to many other projects or
programmes. For example, -public health programmes (e.g. the mass
immunization of children using new drugs), an investment in a new rail
safety systems, or opening a new railway line, or the costs and benefits
of the new deal programme designed to reduce long-term
unemployment. Cost benefit analysis was also used during the recent
inquiry into genetically modified foods. Increasingly the principles of
cost benefit analysis are being used to evaluate the returns from
investment in environmental projects such as wind farms and the
development of other sources of renewable energy.
Because financial resources are scarce, CBA allows different projects to
be ranked according to those that provide the highest expected net
gains in socialwelfare - this is particularly important given the
limitations of government spending.
9.3 MAIN STAGES
The main stages in the CBA approach are detailed below
Stage 1(a)
Calculation of social costs & social benefits. This would include calculation of
Tangible benefits and costs (i.e. direct costs and benefits)
Intangible benefits and costs (i.e. indirect costs and benefits – externalities)
This process is very important – it involves trying to identify all of the significant
costs & benefits.
Stage 1(b)
Sensitivity analysis of events occurring i.e. determination of how likely is it that a
predicted outcome will occur? If we are reasonably sure that a benefit or cost will
‗occur‘ – what is the scale of uncertainty about the actual values of the costs and
benefits?
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 215-
Stage 2
Discounting the future value of benefits - costs and benefits accrue over time.
Individuals normally prefer to enjoy the benefits now rather than later – so the
value of future benefits has to be discounted.
Stage 3
Comparing the costs and benefits to determine the net social rate of return.
Stage 4
Comparing net rate of return from different projects – the government may have
limited funds at its disposal and therefore faces a choice about which projects
should be given the go-ahead.
9.4 DISADVANTAGES
There are several objections to the use of CBA for environmental impact
assessment:
1) Problems in attaching valuations to costs and benefits: Some costs are easy
to value such as the running costs (e.g. staff costs) + capital costs (new
equipment). Other costs are more difficult – not least when a project has a
significant impact on the environment. The value attached to the
destruction of a habitat is to some ―priceless‖ and to others ―worthless‖.
Costs are also subject to change over time – i.e. the construction costs of a
new bridge over a river or the introduction of electronic road pricing.
2) The CBA may not cover everyone affected (i.e. all third parties): Inevitably
with major construction projects such as a new airport or a new road, there
are a huge number of potential ―stakeholders‖ who stand to be affected
(positively or negatively) by the decision. CBA cannot hope to include all
stakeholders – there is a risk that some groups might be left out of the
decision process, for example future generations & ―non-human‖
stakeholders
3) Distributional consequences: Costs and benefits mean different things to
different income groups - benefits to the poor are usually worth more (or
are they?). Those receiving benefits and those burdened with the costs of a
project may not be the same.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 216-
4) Social welfare is not the same as individual welfare: What we want
individually may not be what we want collectively. A different value is not
attached to those who feel ―passionately‖ about something (for example
the building of new housing on greenfield sites) contrasted with those who
are more ambivalent?
5) Valuing the environment: Valuation of the public goods such as the
environment where there is no market established for the valuation of
―property rights‖ over environmental resources is very difficult. Similarly
things such as ―nuisance‖ and ―aesthetic values‖ are very ambiguous &
difficult to value.
6) Valuing human life: Some measurements of benefits require the valuation of
human life – many people are intrinsically opposed to any attempt to do
this. This objection can be partly overcome if we focus instead on the
probability of a project ―reducing the risk of death‖ – and there are
insurance markets in existence which tell something about how much
people value their health and life when they take out insurance policies.
7) Attitudes to risk – e.g. a cost benefit analysis of the effects of genetically
modified foods
Precautionary principle: Assume toxicity until proven safe; if in doubt,
then regulate
Free market principle: Assume it is safe until a hazard is identified; if in
doubt, do not regulate.
Despite these problems, most economists argue that CBA is better than other ways
of including the environment in project appraisal.
Cost benefit analysis is basically an appraisal technique that tries to place
monetary values on all benefits arising from a project and then compares the total
value with the project's total cost. It has numerous potential applications although
there are inherent difficulties with the issue of valuation. Essentially the process
of CBA is a comparative one, so that we can perhaps make judgments about which
projects from a limited choice should be given the go ahead.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 217-
9.5 DISCOUNTING THE FUTURE
Discounting is a widely used technique as part of cost benefit analysis. The
technique of discounting reflects the following:
the value of a cost or benefit now
the value of a cost or benefit in future years
Discounting reflects this by reducing all future costs and benefits to express them
as today‘s values. The key question being - how to choose an ‗interest rate‘ for
reducing future costs to give them a present value today?
Setting a general discount rate for new projects has important implications for the
environment:
A low discount rate is often favored by economists since they argue that
investing a high proportion of current income is a good way of providing for
the future.
A high discount rate may also be favored since it discourages investment
(and by implication environmental damage) in the present.
Most projects have lifetimes of 20-30 years – with many of the big costs arising
early in a project e.g. from construction whereas the stream of benefits from a
project occur over a much longer period of time. But for many huge construction
projects, some of the costs only become apparent in the long run. Consider the
building of a new nuclear power station. Environmentalists would argue that there
is a long list of costs from waste management and decommissioning which stretch
over 100 years into the future whereas no social benefits exist to offset these costs
beyond year 30 or 40 (where the nuclear power station might reasonably be
expected to be ready for closure).
The value of decommissioning costs over 100 years away is almost negligible no
matter what discount rate we use. This makes discounting difficult to justify.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 218-
9.6 COST-BENEFIT ANALYSIS FOR M/S. NOBLEEXCHANGE ENVIRONMENT
SOLUTIONS PRIVATE LIMITED (NEX)
CBA for M/s. Noble Exchange Environment Solutions Private Limited (NEX) Is
tabulated below table9.1
Table 9.1: CBA for M/s. Noble Exchange Environment Solutions Private Limited
(NEX)
Costs Benefits
Charges paid to Pollution Control Board
for not meeting standards or threat of
closure.
Savings in costs for meeting standards.
DAMAGES CAUSED BY WATER
POLLUTION
a) Waterborne diseases
b) Losses to farmers
c) Degradation of soil fertility and
increase in toxicity
d) Degradation of water aquifer
BENEFITS INCURRED DUE TO WATER
POLLUTION PREVENTION/CONTROL
a) Savings due to water borne diseases
avoided through proper treatment of
both domestic & industrial
wastewater.
b) Degradation of soil fertility & water
aquifer reversed.
DAMAGES CAUSED BY AIR
POLLUTION
a) Airborne diseases.
b) Losses to farmers due to increase in
oxides of sulfur concentrations.
BENEFITS INCURRED DUE TO AIR
POLLUTION PREVENTION/CONTROL
a) Savings due to air borne diseases
avoided through proper maintenance
& management of air pollution
sources. b) Losses to the farmers reversed.
DAMAGES CAUSED BY NOISE
POLLUTION
Health & behavioral effects on humans
BENEFITS INCURRED DUE TO NOISE
POLLUTION PREVENTION/CONTROL
Health & behavioral effects on humans
reversed.
DAMAGES CAUSED BY
SOLD/HAZARDOUS WASTE
a) Impact on aesthetics.
b) Degradation of groundwater aquifer.
BENEFITS INCURRED DUE TO SOLID
WASTE MANAGEMENT/CONTROL
a) Impacts on aesthetics reversed by
proper management.
b) Degradation of water aquifer reversed
by proper management.
- BENEFITS TO THE SOCIAL/ECONOMIC
ENVIRONMENT
a) Employment and income generation
from industries. b) Infrastructural development benefits
due to proximity of plant.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 219-
CHAPTER 10
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
10.1 INTRODUCTION
The Environment Management Plan (EMP) is required to ensure sustainable
development in the area of the proposed project. Hence it needs to be an all
encompassive plan for which the industry, Government, Regulating agencies like
Pollution Control Board working in the region and more importantly the
population of the area need to extend their co-operation and contribution.
It has been evaluated that the project area will not be affected significantly with
proposed project. Mitigation measures at the source level and an overall
Management Plan at the site level are elicited so as to improve the surrounding
environment.
The following mitigation measures are recommended in order to synchronize the
economic development of the project area with the environmental protection of
the region. The construction phase impacts are mostly short term, restricted to
the plot area and not envisaged on the larger scale. In the operational phase the
environmental impacts are due to continuous operation of the project, hence,
the emphasis in the Environment Management Plan (EMP) is to minimize such
impacts.
The emphasis on the EMP development is on the following:
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 220-
Mitigation measures for each of the activities causing the environmental
impact;
Monitoring plans for checking activities and environmental parameters and
monitoring responsibilities;
Role responsibilities and resource allocation for monitoring.
Following sections describes in brief the environment management plan proposed
for construction and operation phases.
10.2 MITIGATION MEASURES
Each of the activities during Operation phase is critically reviewed for suggestion
of mitigation measures. Based on this, the table 10.1 gives the mitigation
measures for the activities considered to be causing significant environmental
impacts during construction phase & table 10.2 during operation phase. Table 10.3
gives the environmental management plan during waste transportation,
treatment.
In general the best housekeeping practices are incorporated in the design as well
as in operation phase to reduce the short term impacts due to the proposed
activities.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 221-
10.3 ENVIRONMENTAL MANAGEMENT PLAN (EMP)
a. ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION
PHASE
Table 10.1: Environmental management plan during construction phase
Activity Environmental
impacts
Mitigation Remarks
Construction &
erection of
plant
Air
Land
Water
Noise
Socio economy
Water spraying during earth
work, PPE’s will be used.
Well maintained vehicles will
be used.
Metalled road for vehicle
movement.
File foundation top soil will
be conserved and be utilized
for landscaping & gardening.
Site barricading will be done
during building & plant
construction.
Well maintained equipment
will be utilized to prevent
noise generation.
Local labor will be hired for
the work so that housing
arrangement for them is
avoided.
Implementation
responsibility:
M/s.
NobleExchange
Environment
Solutions Private
Limited (NEX).,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 222-
b. OPERATION OF THE FACILITIES/UTILITIES
Table 10.2: Environmental management plan during operation of the
facilities/utilities
Activity Environmental
impacts
Mitigation Remarks
“Sustainable
Waste
Management
and Renewable
Energy” Project.
Air
Land
Water
Noise
Ensure proper collection,
transportation and handling of
waste.
Ensure usage of PPE’s by
workers.
Gas detectors with alarm system
will be installed in strategic
locations to detect any fugitive
emission of methane etc.
MSDS of Methane will be
displayed at storage & handling
area.
Water usage will be strictly
regulated by installation of water
meter plant-wise.
Monitored data will be analyzed
and reviewed from time to time
so that correct action can be
taken.
Storage area will be designed in
line with the safety & factories
department requirement.
Nutrient rich water and manure
will be handled properly.
Implementation
responsibility: M/s.
NobleExchange
Environment
Solutions Bangalore
Private Limited
(NEX).,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 223-
Operation of DG
sets.
• Air
• Noise
• Water
Provision of adequate stack
heights for DG sets.
Waste water from the plant will
be treated in Effluent Treatment
Plant.
Ensure usage of Personal
Protective Equipments.
Implementation
responsibility: M/s.
NobleExchange
Environment
Solutions Bangalore
Private Limited
(NEX).,
Temporary
solid waste
storage and
Handling within
the premises.
• Water
• Land
Install proper facilities for storage
of manure and solid waste.
Implementation
responsibility: M/s.
NobleExchange
Environment
Solutions Bangalore
Private Limited
(NEX).,
c. STORAGE, HANDLING & TRANSPORTATION OF WASTE AND
BYPRODUCTS
Table 10.3: Environmental management plan during storage, handling &
transportation of waste and byproducts
Activity Environmental
impacts
Mitigation Remarks
Collection and
transportation of
waste and
Storage of
byproducts.
• Air
• Water
• Land
The generated food waste to the facility
via specially designed drip free trucks
meant for the transportation of this
feed material.
Food and kitchen waste will be
transported to the site via compacting
trucks which ensure all leachate is
collected in the tank situated
underneath the truck. The collected
leachate is pumped to the biogas
system.
Implementation
responsibility: M/s.
NobleExchange
Environment
Solutions
Bangalore Private
Limited (NEX).,
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 224-
The trucks will be regularly maintained
at a workshop for vehicle maintenance
at the site.
The biogas plant has been designed
based on anaerobic digestion (AD) and
continuously stirred reactor (CSTR)
technology for a capacity of 250 TPD.
Storage area will be designed in line
with the safety & factories department
requirement.
Transportation
of CBG
• Air
• Water
• Land
Trained/Approved Transports will be
engaged for the transportation of the
waste/products.
TREMCARD will be followed to ensure
availability of MSDS of CBG to the off-
site emergency team.
Implementation
responsibility: M/s.
NobleExchange
Environment
Solutions
Bangalore Private
Limited (NEX).,
10.4 ENVIRONMENTAL POLICY
M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX), Door
No.200, 4th Cross, 5th Main, ITI Layout, Mallathalli, Bangalore. is proposes
establishing “Sustainable Waste Management and Renewable Energy” Project
at Survey No. 85, Kannahalli Village, Seegehalli Cross, Magadi Road,
Yeshwanthpura Hobli, Bangalore – 560 091..
The Board of Directors of M/s. NobleExchange Environment Solutions Bangalore
Private Limited (NEX)., recognize the important responsibility it has towards the
environment, and is committed to:
Complying with all applicable environmental legislation.
Planned evaluation of compliance by external auditors and the
implementation of improvement programmes.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 225-
Continuous improvement by following best practice guidance produced by
appropriate regulatory and advisory organisations and aim to get certified
to ISO14001, the internationally recognised Environmental Management
System standard.
Ensuring that all employees are aware of their duty to fellow employees,
customers and those who live in the surrounding community, to act in an
environmentally responsible and safe manner.
Collecting, analysing and publishing key environmental performance metrics
to enable the Group to continually review, assess and improve its
environmental performance.
The Board delegates responsibility for oversight of environmental policy and
performance to all to the Director, Management and employees for local
implementation of this policy. This policy and its implementation will be reviewed
on a regular basis by the Board to ensure that it remains appropriate and relevant
to the organization. The Group is committed to providing the necessary support in
order to ensure that all sites can fulfill the requirements outlined in this policy.
This policy will be communicated to everyone working for or on behalf of the
Group. The noncompliance will be communicated and will be brought to the notice
of all the board of directors during the board meeting.
10.5 DESCRIPTION OF THE ADMINISTRATIVE ASPECTS OF ENSURING
THAT MITIGATIVE MEASURES ARE IMPLEMENTED & THEIR EFFECTIVENESS
MONITORED, AFTER APPROVAL, IMPLEMENTATION AND DURING
OPERATION
In order to maintain the environmental quality within the standards, regular
monitoring network to maintain environmental quality will be implemented.
10.5.1 ENVIRONMENT MANAGEMENT CELL
A separate Environment Management Cell will be established to monitor and
control the environmental quality. Members of the Environmental Cell would be
well qualified and experienced in the concerned field. Some experienced people &
few new people will be appointed to take care of the requirement.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 226-
Services of reputed laboratories as well as that of a consultant of repute would be
engaged for various monitoring & other environmental management needs of the
plant.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 227-
CHAPTER 11
SUMMARY & CONCLUSION
11.1 OVERALL JUSTIFICATION FOR IMPLEMENTATION OF THE PROJECT
The Environmental Impact Assessment studies carried out for the proposed project
of M/s. NobleExchange Environment Solutions Bangalore Private Limited (NEX),has
been completed. The study conducted has covered various facets of the proposed
project starting with the need for project, collection and transportation of waste,
water requirement, availability of land, process involved etc.,
In addition to this the metrological data and baseline environmental features have
been evaluated to understand the environmental setting of the project site. Also
the ecological features of the location including the flora & fauna, socio-economic
environment, the demographic structure have been evaluated.
Based on the above studies an Environmental Impact Statement has been prepared
to ascertain the possible impacts of the proposed project on the environmental
parameters like air, water, land, biological and socio-economic environment. An
impact matrix has also been prepared based on the observations of the impacts on
the environment.
An Environmental Management Plan has been prepared covering the environmental
aspect and the management plan required to be adopted by the management not
only during the course of setting up of the proposed project but also during its
operational phase. An environmental monitoring plan is envisaged deciding
frequency, location, data analysis, reporting schedules.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 228-
Detailed risk assessment study is carried out to evaluate the risks involved due to
storage of various solvents & precautionary measures to be taken for
prevention/management of such risks.
The conclusions drawn from the above study relates to the fact that the proposed
project of the “Sustainable Waste Management and Renewable Energy Project
―activity undertaken by the management of the plant has certain level or marginal
impacts on the local environmental setting, which will not affect the natural
environmental setting of the study zone either drastically or otherwise. However,
certain beneficial impacts are anticipated in terms of the employment
opportunities created during the operation of the plant. Also there will be
economic growth at the regional level.
The plant proposes to create Environmental Management Cell in its organization to
monitor and implement programs to improve its environmental status from time to
time and will adopt all such technological advances to reduce the impact due to
its operation on the environment.
Mitigation measures will be undertaken to prevent adverse impacts on the
surrounding environment like air, water, land and biological.
There shall be economic growth and development at the local and regional level.
To put it in a nutshell the management of M/s. NobleExchange Environment
Solutions Bangalore Private Limited (NEX), strongly believes in the concept of
sustainable development and understands the impacts of the proposed project on
the environment from the Environmental Impact Assessment studies conducted. It
is committed to construct and establish the project without giving room for any
adverse impacts on the environment and also lays emphasis on the implementation
of the recommendations of the Environmental Management Plan in true spirits.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 229-
11.2 EXPLANATION OF HOW ADVERSE EFFECTS HAVE BEEN MITIGATED
The measures adopted to mitigate the impacts due to the proposed project is
tabulated below table 11.1.
TABLE 11.1 POSSIBLE EFFECTS AND ITS MITIGATIVE MEASURES FROM THE
PROPOSED PROJECT
The measures adopted to mitigate the impacts due to the proposed expansion is tabulated
below
Sl. no. Parameter Mitigation measures
1 Water pollution sources
Domestic sewage Treated in ETP
Wastewater from
Digester
Treated in ETP
2 Air pollution sources
D.G. sets Stacks of adequate heights
3 Noise pollution
sources – DG
sets
In-built acoustic enclosures.
4 Solid/Hazardous waste
Domestic garbage Organic portion will be treated in Digesters & in-organic
portion is sent for recycling.
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 230-
CHAPTER 12
DISCLOSURE OF CONSULTANTS ENGAGED
12.1 Environmental Consultants:-
M/s. AQUA TECH ENVIRO ENGINEERS,
No. 3391, 6th Main, 3rd Cross,
RPC Layout, Vijayanagar 2nd Stage,
Bangalore – 560 040.
Phone No. 080 23142697, Fax No. 080 23148166
E – mail id – [email protected]
INTRODUCTORY PROFILE
AQUA TECH ENVIRO ENGINEERS is a South India based Environmental Engineering
Consultancy established in the year 2000 with its registered office and works
located in Bangalore. The company is certified with ISO 9001-2008 and is
specialized in Water and Wastewater Management. The Organization is a team of
specialized professionals, technically qualified and competent graduates and post
graduates in disciplines of Environmental, Chemical, Civil, Electrical and
Mechanical Engineering,capable of achieving comprehensivesolutions for pollution
control and Environmental Management.
The infrastructure of the organization includes a modern office backed with 600
Sqmts of manufacturing facility to produce treatment plant equipments
KEY PERSONNEL OF THE ORGANISATION:
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 231-
Name Qualifications Designation Experience
Mr K.R Sree Harsha B.E (Civil & Env.
Engg)
M. Tech (Env
Engg )
Chief Executive 18 Years.
Mr. C.T Puttaswamy B.E (Chem.),
M Tech (Env.)
Technical Advisor. 15 Years
Dr. Shambanna Siddappa
Hotanahalli
M Sc. Tech,
Ph D. Tech
Technical Advisor 32 Years
Mr. Channakesava B.E (Env.)
Environmental
Engineer.
13 Years
Mr.Hanumantha Raj Urs M Sc (Envi Sc) Environmental
Analyst
9 Years
Mrs. Rohini. S B.E.(Env.) Environmental
Engineer.
8 Years
Ms. Jyothi B.E (Env.)
Environmental
Engineer
Trainee
Ms. Vidhya B.E (Env.)
Environmental
Engineer
Trainee
Mr. Karthik K.M. B.E.(Env.) Environmental
Engineer
Trainee
Mr. Vinay Kumar M Com., MBA Accounts Assistant 9 Years
Mr. Jahirdhar DME Site Engineer 15 Years
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 232-
FIG: - 12.1 ORGANIZATIONAL CHART
AQUA TECH ENVIRO ENGINEERS
Mr. Hanumanth Raj Urs M. Sc., (Env Science)
Env. Analyst
Ms. Rohini BE., (Env. Engg)
Env. Engineer
Mr. J.C Channakeshav BE., (Env. Engg.)
Env. Engineer (Projects)
Mr. C.T. PUTTASWAMY B.E., (Chemical Engg) M. Tech (Env. Engg.)
Technical Advisor
DR. SHAMBANNA SIDDAPPA HOTANAHALLI M Sc. Tech, Ph D. Tech Technical Advisor
Mr. K.R. SREE HARSHA B.E. ( Civil & Env Engg),
M.Tech (Env. Engg.)
Chief Executive
Mr. Jahirdhar DME
Site Engineer
Ms. Vidhya BE., (Env. Engg)
Trainee Engineer
Ms. Jyothi BE., (Env. Engg)
Trainee Engineer
Ms. Karthik K.M BE., (Env. Engg)
Trainee Engineer
Mr. Santosh Kumar (M A) Project Assistant
Mr. G.K. Vinay M Com., MBA
Manager Accounts
Projects Team
Maintenance Team
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 233-
LABORATORY FOR ANALYSIS:
NAME OF LABORATORY SCOPE OF SERVICES ACCREDITATION
STATUS
M/s. Bangalore Test House
#65, 20th Main,, Marenahalli,
Vijaynagar, Bangalore – 560 040
Monitoring and Analysis of:
1. Ambient Air Quality Monitoring
2. Ground and Surface Water Quality
Monitoring
3. Noise Level Monitoring and
4. Soil Quality Monitoring
5. Metrological data collection
M/s. Bangalore Test House is a NABL certified laboratory
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 234-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 235-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 236-
Annexure - A
HAZOP Studies and MSDS
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 237-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 238-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 239-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 240-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 241-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 242-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 243-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 244-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 245-
ANNEXURE - B
Copy of land records
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 246-
ANNEXURE - C
Environmental Policy Letter
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 247-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 248-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 249-
Annexure1
Topo Map of 15km radius
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 250-
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 251-
Annexure 2
Drawings
―Sustainable Waste Management and Renewable Energy‖ Project
Environmental Impact Assessment Report - 252-