environmental assessment: sea gate community bulkhead ...environmental assessment sea gate community...
TRANSCRIPT
Environmental Assessment
Sea Gate Community Bulkhead Construction
Sea Gate, Kings County, New York
4085-DR-NY
May 2019
U.S. Department of Homeland Security
Federal Emergency Management Agency Region II
26 Federal Plaza, NY, NY 10278
Environmental Assessment
Sea Gate Community Bulkhead Construction
i
TABLE OF CONTENTS
LIST OF TABLES ........................................................................................................................ III
APPENDICES .............................................................................................................................. III
LIST OF ACRONYMS ................................................................................................................ IV
1.0 INTRODUCTION .................................................................................................................. 1
2.0 PURPOSE AND NEED .......................................................................................................... 1
3.0 BACKGROUND .................................................................................................................... 2
4.0 ALTERNATIVES................................................................................................................... 3
4.1 Alternative 1: No Action Alternative ................................................................................................................... 3
4.2 Alternative 2 (Proposed Action): Bulkhead Construction ................................................................................... 3
4.3 Alternatives Considered and Dismissed .............................................................................................................. 6
4.3.1 Alternative 3: USACE Installed Rip-Rap .................................................................................................. 6
4.3.2 Alternative 4: Elevation of All Existing Roadways and Structures.......................................................... 6
4.4 Summary of Alternatives .................................................................................................................................... 6
5.0 AFFECTED ENVIRONMENT AND POTENTIAL IMPACTS ........................................... 6
5.1 Resource Topics Dismissed from Detailed Analysis ............................................................................................ 7
5.2 Topography and Soils .......................................................................................................................................... 8
5.2.1 Existing Conditions ................................................................................................................................. 8
5.2.2 Potential Impacts on Topography and Soils ........................................................................................... 8
5.3 Air Quality ........................................................................................................................................................... 8
5.3.1 Existing Conditions ................................................................................................................................. 9
5.3.2 Potential Impacts on Air Quality .......................................................................................................... 10
5.4 Water Quality .................................................................................................................................................... 10
5.4.1 Existing Conditions ............................................................................................................................... 11
5.4.2 Potential Impacts on Water Quality .................................................................................................... 11
5.5 Wetlands ........................................................................................................................................................... 12
5.5.1 Existing Conditions ............................................................................................................................... 13
5.5.2 Potential Impacts on Wetlands ............................................................................................................ 13
5.6 Floodplains ........................................................................................................................................................ 13
5.6.1 Existing Conditions ............................................................................................................................... 14
5.6.2 Potential Impacts on Floodplains ......................................................................................................... 14
5.7 Coastal Resources ............................................................................................................................................. 14
5.7.1 Existing Conditions ............................................................................................................................... 15
5.7.2 Potential Impacts on Coastal Resources .............................................................................................. 15
5.8 Threatened and Endangered Species ............................................................................................................... 16
5.8.1 Existing Conditions ............................................................................................................................... 16
5.8.2 Potential Impacts on Threatened and Endangered Species ................................................................. 17
5.9 Cultural Resources ............................................................................................................................................ 17
5.9.1 Existing Conditions ............................................................................................................................... 18
Environmental Assessment
Sea Gate Community Bulkhead Construction
ii
5.9.2 Potential Impacts on Cultural Resources ............................................................................................. 19
5.10 Environmental Justice .............................................................................................................................. 20
5.10.1 Existing Conditions .......................................................................................................................... 20
5.10.2 Potential Impacts on Environmental Justice ................................................................................... 20
5.11 Land Use and Planning ............................................................................................................................. 21
5.11.1 Existing Conditions .......................................................................................................................... 21
5.11.2 Potential Impacts on Land Use and Planning .......................................................................................... 21
5.12 Noise ........................................................................................................................................................ 21
5.12.1 Existing Conditions .......................................................................................................................... 22
5.12.2 Potential Impacts of Noise .............................................................................................................. 23
5.13 Transportation ......................................................................................................................................... 23
5.13.1 Existing Conditions .......................................................................................................................... 23
5.13.2 Potential Impacts on Transportation .............................................................................................. 23
5.14 Public Health and Safety .......................................................................................................................... 24
5.14.1 Existing Conditions .......................................................................................................................... 24
5.14.2 Potential Impacts on Public Health and Safety ............................................................................... 24
5.15 Hazardous Materials ................................................................................................................................ 25
5.15.1 Existing Conditions .......................................................................................................................... 25
5.15.2 Potential Impacts on Hazardous Materials ..................................................................................... 25
5.16 Cumulative Impacts ................................................................................................................................. 25
6.0 PERMITS AND PROJECT CONDITIONS ......................................................................... 26
7.0 AGENCY COORDINATION AND PUBLIC INVOLVEMENT ....................................... 27
8.0 LIST OF PREPARERS......................................................................................................... 28
9.0 SUMMARY OF IMPACTS ................................................................................................. 28
10.0 REFERENCES ..................................................................................................................... 31
Environmental Assessment
Sea Gate Community Bulkhead Construction
iii
LIST OF TABLES
Table 5-1. Evaluation Criteria for Potential Impacts ...................................................................... 7
Table 9-1. Summary of Impacts Table ......................................................................................... 28
APPENDICES
APPENDIX A: Figures
Figure 1-1 Regional Project Map
Figure 1-2 Project Limits
Figure 5-1 Soil Data
Figure 5-2 Digital Elevation Model
Figure 5-3 Depth to Water Table Surface
Figure 5-4 National Wetlands Inventory
Figure 5-5 NYSDEC Fresh and Tidal Wetlands
Figure 5-6 Flood Zones Map
Figure 5-7 Hurricane Sandy Surge Boundary Map
Figure 5-8 Zoning
Figure 5-9 Land Use
APPENDIX B: Project Plans
APPENDIX C: Floodplains and Wetlands 8-Step Decision-Making Process Summary
APPENDIX D: NYSDEC Consultations and Permitting
APPENDIX E: LWRP Consistency Letter, NYC Department of City Planning
APPENDIX F: US Fish and Wildlife Service Coordination
APPENDIX G: New York State Historic Preservation Office Review
Environmental Assessment
Sea Gate Community Bulkhead Construction
iv
LIST OF ACRONYMS
ACHP Advisory Council of Historical Preservation
ACS American Community Survey
AFS Air Facility Systems
APE Area of Potential Effects
BMPs Best Management Practices
CBRA Coastal Barrier Resources Act
CBRS Coastal Barrier Resource System
CEHA Coastal Erosion Hazard Area
CEQ Council of Environmental Quality
CERCLIS Comprehensive Environmental Response, Compensation, and Liability
Information System
CFR Code of Federal Regulations
CRIS Cultural Resources Information System
CWA Clean Water Act
CZMA Coastal Zone Management Act
CZMP Coastal Zone Management Plan
dBA A-weighted decibels
EA Environmental Assessment
EFH Essential Fish Habitat
EJ Environmental Justice
EO Executive Order
ESA Endangered Species Act
FEMA Federal Emergency Management Agency
FONSI Finding of No Significant Impact
IPaC Information for Planning and Consultation
Ldn Day night noise level
Leq Equivalent noise level
LPC Landmarks Preservation Commission
LWRP Local Waterfront Revitalization Program
MBTA Migratory Bird Treaty Act
NAAQS National Ambient Air Quality Standards
NAVD88 North American Vertical Datum of 1988
NEPA National Environmental Policy Act
NHPA National Historic Preservation Act
NMFS National Marine Fisheries Service
NOAA National Oceanic and Atmospheric Administration
NOX Nitrogen Oxides
NPDES National Pollution Discharge Elimination System
Environmental Assessment
Sea Gate Community Bulkhead Construction
v
NRCS Natural Resources Conservation Science
NRHP National Register of Historic Places
NWI National Wetland Inventory
NYC New York City
NYCEDC New York City Economic Development Corporation
NYNHP New York National Heritage Program
NYS New York State
NYSDEC New York State Department of Environmental Conservation
NYSDHSES New York State Division of Homeland Security and Emergency Services
NYSDOS New York State Department of State
NYSHPO New York State Historic Preservation Office
OPD Office of Planning and Development
OSHA Occupational Safety & Health Administration
PAH Polycyclic Aromatic Hydrocarbons
PM Particulate Matter
RCRA Resource Conservation and Recovery Act
SCFWH Significant Coastal Fish and Wildlife Habitats
SPDES State Pollutant Discharge Elimination System
SPL Sound pressure level
SOX Sulphur Oxides
SWPPP Stormwater Pollution Prevention Plan
TMDL Total Maximum Daily Load
TRI Toxics Release Inventory
ULSD Ultra-low-sulfur diesel
ULURP Uniform Land Use Review Procedure
USACE U.S. Army Corps of Engineers
USDA U.S. Department of Agriculture
USEPA U.S. Environmental Protection Agency
USFWS U.S. Fish and Wildlife Service
Environmental Assessment
Sea Gate Community Bulkhead Construction
vi
Environmental Assessment
Sea Gate Community Bulkhead Construction
1
1.0 INTRODUCTION
On October 29, 2012, Hurricane Sandy caused storm damage to several areas of New York State,
including the Sea Gate community in Kings County, New York. President Barack Obama declared
Hurricane Sandy a major disaster on October 30, 2012. The declaration authorized the Federal
Emergency Management Agency (FEMA) to provide assistance to the state per federal disaster
declaration DR-4085-NY and in accordance with the Robert T. Stafford Disaster Relief and
Emergency Assistance Act of 1974 (42 United States Code [USC] 5170c), as amended, the Sandy
Recovery Improvement Act of 2013, and the accompanying Disaster Relief Appropriations Act of
2013.
The Sea Gate Community Relief Fund (Subrecipient) has applied to FEMA for financial assistance
to build a new “Navy Sea Wall System” at the location of the damaged former seawall in Sea Gate,
New York. Sea Gate is a private gated community located on at the far western end of Coney
Island at the southwestern tip of the New York City borough of Brooklyn (Appendix A, Figure 1-
1, Figure 1-2). The New York State Division of Homeland Security and Emergency Services
(NYSDHSES) is the Recipient partner for the Proposed Action.
This Environmental Assessment (EA) is prepared in accordance with Section 102 of the National
Environmental Policy Act (NEPA) of 1969, as amended, and the Regulations for Implementation
of NEPA (40 Code of Federal Regulations [CFR] Parts 1500 to 1508). FEMA is serving as the
lead agency. The purpose of the EA is to analyze the potential environmental impacts of the
proposed action and a no action alternative and to determine whether to prepare an Environmental
Impact Statement (EIS) or a Finding of No Significant Impact (FONSI). In accordance with above
referenced regulations and FEMA’s guidance for NEPA compliance, FEMA Directive 108-1 and
FEMA Instruction 108-1-1, FEMA is required, during decision making, to fully evaluate and
consider the environmental consequences of major federal actions it funds or undertakes.
2.0 PURPOSE AND NEED
Section 404 of the Robert T. Stafford Relief and Emergency Assistance Act of 1974 (42 USC
5170c), as amended, authorizes FEMA to provide funding to eligible grant applicants for activities
with the purpose of reducing or eliminating risks to life and property from hazards and their effects.
The purpose of the project is to reduce damages from storm surge flooding caused by coastal
storms like nor’easters, tropical storms, and hurricanes. The project is needed because the Sea Gate
community experienced damage to structures and sections of seawall bulkheads that resulted from
storm surge flooding during Hurricane Sandy. Because of the loss of protection from the
bulkheads, the community remains vulnerable to future storm surge flooding.
Environmental Assessment
Sea Gate Community Bulkhead Construction
2
3.0 BACKGROUND
Sea Gate is a private gated community located on at the far western end of Coney Island at the
southwestern tip of the New York City borough of Brooklyn (Appendix A, Figure 1-1, Figure 1-
2). The community of Sea Gate covers all land west of West 37th Street and is bordered by water,
with Gravesend Bay to the north; Lower New York Bay to the west, the Atlantic Ocean to the
south, and mostly single-family residential neighborhoods to the east.
The project limits extend from just west of the Sea Gate Beach Club, roughly 200 feet east of
Beach 38th Street, to about 100 feet beyond Lindy Park, east of Beach 50th Street. Development
along the beachfront within the project limits is a combination of single family and multi-family
residential except for the following: Lindy Park, a community park under the jurisdiction of the
Sea Gate Association; the United States Coast Guard Station and Light House located to the south
of Beach 47th Street; and a few scattered vacant properties where buildings were destroyed by
Hurricane Sandy.
Hurricane Sandy is the most recent of coastal storms to damage the Sea Gate community. The Sea
Gate community experienced water levels at a height of 13.3 feet (North American Vertical Datum
of 1988 - NAVD88) during the peak storm surge with the entire area inundated to depths up to
approximately six feet. Hurricane Sandy brought direct wave impacts along ocean-facing areas
such as Sea Gate where coastal protections were lacking or inadequate. The severe wave impacts
caused the bulkhead at Lindy Park to collapse and destroyed other sections of existing bulkhead
scattered along the project length.
During Hurricane Sandy, brackish floodwater damaged over 750 homes behind the seawall. The
hurricane damaged roads and other infrastructure such as the electric and sewer systems. In
addition to the damage to Lindy Park, other critical community services were severely impacted,
including the Sea Gate Police Department and the Sea Gate Association Administration buildings,
which were completely flooded and beyond salvage. The community of Sea Gate also suffered
damages from flooding and storm winds during Tropical Storm Irene, Tropical Storm Lee, and
several smaller storm events. As cited in the Preliminary Flood Insurance Study (FEMA 2013),
previous storms that caused damage in Sea Gate included storms of December 12, 1992, March
1962, and November 1950.
The Sea Gate Community lies within the U.S. Army Corps of Engineers’ (USACE) “Project for
Shoreline Protection, Atlantic Coast of New York City from Rockaway Inlet to Norton Point
(Coney Island, NY).” The initial phase of the USACE project was constructed in 1994 and 1995
and included the construction of the West 37th Street terminal groin and placement of fill on the
beachfront from West 37th Street easterly. The placement of the terminal groin caused scouring of
Environmental Assessment
Sea Gate Community Bulkhead Construction
3
beach areas on the south shore of Sea Gate. To combat the issue, USACE installed T-groins to the
west of the terminal groin (USACE 2014). USACE has completed subsequent phases of work,
with the most recent phase completed in the Sea Gate Reach in 2016. Work in the Sea Gate Reach
included beach fill placement, construction of T-groins, and placement of stone reinforcement on
Norton Point Dike. The objective of the USACE Sea Gate Reach project is to improve sand
retention downdrift of the West 37th Street terminal groin.
Along the beachfront within the project limits, existing bulkheads and seawalls of different
construction types provide varied levels of protection from wave action and coastal flooding. There
are areas that are unprotected, as previous bulkheads have been completely or partially destroyed
by storms over time. The top of wall elevation of existing bulkheads ranges from a low of 11.0
feet to a high of 16.7 feet. The predominant bulkhead type is anchored steel sheet piling. Other
types of bulkheads include concrete walls and navy type walls of timber construction, which
include woodpiles, walers, and vertical sheeting.
4.0 ALTERNATIVES
FEMA and the Subrecipient evaluated alternatives based on engineering constraints,
environmental impacts, and the purpose and need of this project. The Subrecipient also considered
expected costs in evaluating the feasibility of alternatives, but costs were not the controlling factor.
Additionally, a No Action Alternative, also known as the “Future without Federal Project
Condition,” is included in the analysis. This section discusses the no action alternative, feasible
alternatives that would satisfy the purpose and need, and alternatives eliminated from further
analysis.
4.1 Alternative 1: No Action Alternative
Under this alternative, no federal action would occur to reconstruct the seawall leaving the Sea
Gate community susceptible to flooding and storm damage. The Sea Gate community would
continue to be vulnerable to damages caused by storm surge and inundation by floodwaters on
three sides of the peninsular community. In addition to flooding, the community of Sea Gate would
be susceptible to wave damage and damaged infrastructure due to storm events, including the
potential for damage by fire from wind and wave damaged utilities. The residents of Sea Gate
would face potential loss of life and would encounter significant delays in emergency service
response time due to flooding within Sea Gate.
4.2 Alternative 2 (Proposed Action): Bulkhead Construction
Alternative 2, the Proposed Action, is the reconstruction of a seawall bulkhead surrounding the
ocean side of the Sea Gate community to a height of 11 feet. The Subrecipient would construct
Environmental Assessment
Sea Gate Community Bulkhead Construction
4
approximately 1,850 linear feet of bulkhead, beginning from approximately Beach 38th Street to
Beach 50th Street, and continuing through Lindy Park in Sea Gate, Brooklyn. The bulkhead
construction would consist of two types of installation; a navy-type bulkhead wall and cantilevered
steel sheet piling wall, both of which act to retain and protect property and streets within the
community of Sea Gate. As shown on the plans in Appendix B, the navy-type bulkhead would be
installed at Lindy Park and would be approximately 950 linear feet long. Cantilevered steel sheet
piling would be installed at various locations to total approximately 900 feet and would include
segments at the following locations:
At 4602 Beach 46th Street in front of, or in line with, a concrete wall that has failed and a
return section into the embankment at the side of the U.S. Coast Guard property
A continuous line of bulkhead in front of 4504 Beach 45th Street, at the end of Beach 45th
Street and 4505 Beach 45th Street
A line of bulkhead in front of 4200 Atlantic Avenue and the end of Beach 42nd Street
At Block 7042, Lot 1 a presently undeveloped tract
At 3826 Atlantic Avenue
A continuous line of bulkhead in front of 3820 Atlantic Avenue and Block 7043, Lot 6
where a new home was recently constructed as a replacement for the structure destroyed
by Hurricane Sandy
At Block 7044, Lot 39, a presently undeveloped tract.
A navy-type bulkhead, consisting of round wood piles, timber walers, and vinyl vertical sheeting
anchored to a pile by a steel tie rod or drilled helical anchors at the front of the bulkhead, is
proposed along Lindy Park. The ground surface landward of the bulkhead would be several feet
higher than the ground surface seaward of the wall. The bulkhead would be designed to function
both to retain the soil on the landward side and to resist hydrostatic and hydrodynamic pressures
on the seaward side.
Bulkhead installations constructed of cantilevered steel sheet piling would function as essentially
a solid fence with the ground surface on both sides of the bulkhead at the same elevation. These
wall sections would be designed to have sufficient capacity to resist hydrostatic and hydrodynamic
pressures on the seaward side of the wall.
The installation of the proposed bulkheads would result in a continuous line of protection along
the project limits that would provide protection to a minimum of height of 11 feet. The top
elevation of the proposed bulkhead installations would be at a height of 11 feet. The Subrecipient
Environmental Assessment
Sea Gate Community Bulkhead Construction
5
selected a height of 11 feet for analysis because it is the lowest elevation of the existing bulkheads
that remain and continue to function.
The ends of all streets that lead to the beach, except for Beach 45th Street and Beach 47th Street,
already have anchored steel sheet piling bulkhead that provides protection from erosion, which
could undermine the roadway pavement. New bulkhead would be installed at Beach 45th Street.
At Beach 47th Street the roadway grade is higher than 11 feet. The steel sheeting at the street end
locations either have metal caps or the top section is encased with concrete and the top elevation
is higher than 11 feet except at two streets, Beach 38th Street and Beach 46th Street. At these two
locations, the middle section of the steel sheet piling/concrete cap is stepped down to roughly the
level of the roadway pavement. To allow for these locations to be used for beach access in the
future and still maintain them as part of the Proposed Action, these openings would be retrofitted
so that deployable flood control equipment can be installed, which would provide protection up to
the design elevation. In conjunction with the installation of new bulkhead across the end of Beach
45th Street, a new wood access ramp would be constructed over the top of the bulkhead to allow
for foot traffic between the beach and the street end, similar to the ramp at Beach 42nd Street.
Under the Proposed Action, the bulkhead installation would provide protection from a coastal
flooding event with a two-percent (50-year) annual chance. With scheduled maintenance, the
bulkhead installations would have a useful life of 50 years. The bulkhead installations would fill
in gaps in the existing bulkhead around the Sea Gate community and reduce inundation hazards to
Sea Gate properties, roads, and other infrastructure.
The Subrecipient anticipates total construction to take approximately 48 weeks, with the navy-type
bulkhead, using vertical vinyl sheeting, taking approximately 18 weeks and the installation of steel
sheet piling sections taking approximately 12 weeks. The total construction time estimate allows
for unforeseen delays and winter shutdowns that may slow the installation.
The installation of the navy-type bulkhead along Lindy Park would require pre-excavation of
concrete rubble and armor stone over a portion of its length. This pre-excavation would allow the
timber pile and vinyl vertical sheeting to be driven or vibrated in at these locations. These
materials, if not removed, would damage the vinyl sheeting and the timber piles. The timber piles
and the vinyl sheeting would penetrate approximately 15 feet into the ground and project
approximately 10 feet above the ground.
Construction staging would occur at Lindy Park, at the end of Beach 42nd Street, and at the end of
Beach 45th Street. The Lindy Park work area would be accessed via Beach 50th Street and the
various other work locations would be accessed from Beach 42nd Street or Beach 45th Street.
Environmental Assessment
Sea Gate Community Bulkhead Construction
6
4.3 Alternatives Considered and Dismissed
4.3.1 Alternative 3: USACE Installed Rip-Rap
This alternative consists of engaging USACE to install large rocks or rip-rap along the shoreline
to provide erosion resistance during normal storm surges. The Subrecipient dismissed this
alternative as insufficient because it would provide no protection against a 50- or 100-year storm
event.
4.3.2 Alternative 4: Elevation of All Existing Roadways and Structures
This alternative consists of raising the elevation of all existing homes, roads and buildings within
the Sea Gate Community. This is not a cost-efficient alternative.
4.4 Summary of Alternatives
Four alternatives were considered by the Subgrantee for implementation at Sea Gate, Two
alternatives were considered and dismissed. These are the USACE Installed Rip-Rap alternative
and the Elevation of All Existing Roadways and Structures alternative. Two alternatives were
developed and reviewed against the purpose and need for the project, and evaluated in this EA.
The remaining alternatives are:
1) Alternative 1: No Action Alternative
2) Alternative 2: Proposed Action: Bulkhead Construction
Section 5 evaluates the potential environmental impacts of the No Action Alternative and the
Proposed Action. A table summarizing the potential impacts of the alternatives is in Section 9.0,
Summary of Impacts.
5.0 AFFECTED ENVIRONMENT AND POTENTIAL IMPACTS
This section discusses the potential impacts of the No Action Alternative and the Proposed Action
on environmental resources. Potential cumulative impacts are also discussed (see Section 5.16).
When possible, quantitative information is provided to establish potential impacts, and the
potential impacts are evaluated qualitatively based on the criteria listed in Table 5-1.
Environmental Assessment
Sea Gate Community Bulkhead Construction
7
Table 5-1. Evaluation Criteria for Potential Impacts
Impact Scale Criteria
No Impact The resource area would not be affected, and there would be no impacts.
Negligible Changes would either be non-detectable or, if detected, the effects would be
slight and local. Impacts would be well below regulatory standards, as
applicable.
Minor
Adverse
Changes to the resource would be measurable, but the changes would be small
and localized. Impacts would be within or below regulatory standards, as
applicable. Mitigation measures would reduce any potential adverse effects.
Moderate
Adverse
Changes to the resource would be measurable and have both localized and
regional impacts. Impacts would be within or below regulatory standards, but
historical conditions would be altered temporarily. Mitigation measures
would be necessary, and the measures would reduce any potential adverse
effects.
Major Adverse Changes to the resource would be readily measurable and would have
substantial consequences at local and regional levels. Impacts would exceed
regulatory standards. Mitigation measures to offset the adverse effects would
be required to reduce impacts, but long-term changes to the resource would
be expected.
5.1 Resource Topics Dismissed from Detailed Analysis
In accordance with Council of Environmental Quality (CEQ) regulations, an environmental
analysis should focus on significant environmental issues (40 CFR 1502.01). FEMA considered
resource topics in the preparation of this EA but eliminated six from further consideration:
Geology; Vegetation; Wildlife and Fish; Wild, Scenic or Recreational Rivers; Farmland
Protection; and Essential Fish Habitat. FEMA expects no impacts related to geology because
bedrock in the project area is more than 2,000 feet from the surface and would not be affected by
excavation activities. FEMA anticipates no impacts to vegetation as the landward side of the
bulkhead is developed urban land and the seaward side does not support vegetation. FEMA expects
no impacts related to wildlife or fish. There are no designated Significant Coastal Fish and Wildlife
Habitats (SCFWHs), Significant Natural Communities, or Rare Plants and Animals within the
project area. There are no rivers classified as wild, scenic, or recreational under the Wild & Scenic
Rivers Act (Public Law 90-542; 16 USC 1271 et seq.) within or in the vicinity of the project area.
The land within the project area is committed to urban development and is thereby not subject to
the Farmland Protection Policy Act. FEMA anticipates no impacts to Essential Fish Habitat (EFH)
Environmental Assessment
Sea Gate Community Bulkhead Construction
8
under the Magnuson-Stevens Act, as work will not be in water and best management practices
(BMPs) and a Stormwater Pollution Prevention Plan (SWPPP) will be in place.
5.2 Topography and Soils
5.2.1 Existing Conditions
Sea Gate covers all land west of W. 37th Street and is bordered by water, with Gravesend Bay to
the north; Lower New York Bay to the west, the Atlantic Ocean to the south. The topography of
the project area is generally flat with elevations ranging between 4 and 9 feet (Appendix A, Figure
5-2). The beach areas are flooded with the daily tides and are nearly level to gently sloping areas
of sand or sand and gravel adjacent to the Atlantic Ocean. These sands and gravels are frequently
reworked by wave and wind action and not supportive of vegetation. The inland areas are nearly
level to gently sloping, with up to 80 percent buildings and impervious pavement covering the
surface.
According to the Web Soil Survey from the U.S. Department of Agriculture’s (USDA) Natural
Resources Conservation Service (NRCS), soil classifications within the project area include
Beaches (Be); Urban land-Hooksan-Verrazano complex 0 to 3 percent slopes (UHVA); and Urban
land-Verrazano complex, 0 to 8 percent slopes (UVA) (Appendix A, Figure 5-1).
5.2.2 Potential Impacts on Topography and Soils
Alternative 1: No Action Alternative
The No Action Alternative would have no impacts on topography or soils from construction. The
damaged seawall would allow erosion to occur landward of the project area potentially eroding
soils and exposing fill materials.
Alternative 2: Proposed Alternative
The Proposed Action would alter the existing topography within the project area. Under the
Proposed Action, the project would slightly reshape the topography by backfilling areas landside
of the proposed seawall to provide stabilization. Any new backfill brought to the project site will
be suitable material from a commercial source and placed according to approved plans and
specifications. There would be no change to soils. The Proposed Action would result in negligible
effects on topography (Appendix A, Figure 5-2).
5.3 Air Quality
National Ambient Air Quality Standards (NAAQS) are standards established under authority of
the Clean Air Act (42 U.S.C. 7401 et seq.) for six criteria pollutants, to protect public health with
Environmental Assessment
Sea Gate Community Bulkhead Construction
9
an adequate margin of safety, and to protect public welfare from the adverse effects associated
with pollutants in the ambient air. These pollutants are sulfur dioxide (SO2), nitrogen dioxide
(NO2), ozone, lead, carbon monoxide (CO), and particulate matter (PM) (both particles with an
aerodynamic diameter of less than or equal to 2.5 micrometers [PM2.5], and those less than or equal
to 10 micrometers [PM10]). New York State monitors and regulates emissions for these pollutants
so as to meet NAAQS requirements.
Federally funded actions in nonattainment and maintenance areas are subject to United States
Environmental Protection Agency (USEPA) conformity regulations, 40 CFR Part 51 and 93. The
air conformity analysis process ensures that emissions of air pollutants from planned federally
funded activities would not affect the state’s ability to achieve the Clean Air Act goal of meeting
the NAAQS. Section 176(c) of the Clean Air Act requires that federally funded projects must not
cause any violations of the NAAQS, increase the frequency or severity of NAAQS violations, or
delay timely attainment of the NAAQS or any interim milestone. The emissions from construction
activities are subject to air conformity review.
Under the general conformity regulations, a determination for federal actions is required for each
criteria pollutant or precursor in non-attainment or maintenance areas where the action’s direct and
indirect emissions have the potential to emit one or more of the six criteria pollutants at rates equal
to or exceeding the prescribed de minimis rates for that pollutant. In the case of this project, the
prescribed annual rates are 50 tons of volatile organic compounds and 100 tons of nitrogen oxides
(NOX) (ozone precursors), 100 tons of CO (in a CO maintenance area), and 100 tons of PM2.5,
SO2, or NOX (PM2.5 and precursors in PM2.5 attainment area).
Areas where a criteria pollutant level exceeds the applicable NAAQS are designated as being in
non-attainment of the standards. A non-attainment area may be re-designated to attainment, based
on monitoring data demonstrating attainment of the applicable standard and implementation of a
maintenance plan to assure continued attainment.
5.3.1 Existing Conditions
As of September 2018, USEPA designated the project area in Kings County as in-attainment for
lead, PM2.5 annual, and sulfur dioxide. A small portion of the site is currently in maintenance for
PM2.5 24-hour and the County is currently designated as non-attainment for the 8-hour ozone
(USEPA's Environmental Justice Screening and Mapping Tool Version 2018).
Environmental Assessment
Sea Gate Community Bulkhead Construction
10
5.3.2 Potential Impacts on Air Quality
Alternative 1: No Action Alternative
The No Action Alternative would not involve any construction-related emissions; therefore, there
would be no impact on air quality.
Alternative 2: Proposed Alternative
Construction activities as a result of the Proposed Action may result in temporary increases in
emissions from on-site equipment, construction-related vehicles and non-road engines, and
fugitive dust. Fugitive dust or airborne dust is generated during ground breaking and excavation
activities.
Temporary impacts associated with construction emissions would be mitigated through the
implementation of air quality BMPs. Ultra-low sulfur diesel fuel would be used for all
construction-related vehicles and non-road construction equipment, limiting Sulphur Oxides
(SOX) emissions. Fugitive dust control measures such as speed limit reductions, water or other
dust suppressant application, and regular vehicle rinsing would be managed according to proper
standards and procedures. Additionally, all activities under the Proposed Action would comply
with applicable federal, state, and local laws and regulations regarding construction emissions. All
equipment and machinery would comply with applicable USEPA standards. All units would be
powered with Ultra-low-sulfur diesel (ULSD) per USEPA regulations. Emissions for construction
would be below de minimis threshold levels.
The Proposed Action would result in a temporary negligible impact on air quality due to
construction activities; FEMA anticipates no long-term impacts.
5.4 Water Quality
The Clean Water Act (CWA), enacted in 1977, regulates discharge of pollutants into waters under
the jurisdiction of the USACE and USEPA. Section 404 of the CWA establishes the USACE
permit requirements for discharging dredged or fill materials into waters of the United States and
navigable waterways. USACE regulation of activities within navigable waters is also authorized
under the 1899 Rivers and Harbors Act. Under the National Pollutant Discharge Elimination
System (NPDES), USEPA regulates both point and non-point pollutant sources, including
stormwater and stormwater runoff. Activities that disturb one acre of ground or more are required
to apply for an NPDES permit, or a State Pollutant Discharge Elimination System (SPDES) permit
at the state level. New York State Department of Environmental Conservation (NYSDEC) SPDES
permits in New York.
Environmental Assessment
Sea Gate Community Bulkhead Construction
11
Section 1424(e) of the Safe Drinking Water Act of 1974 [Public Law 93–523] authorizes USEPA
to designate an aquifer for special protection under the sole-source aquifer program if the aquifer
is the sole or principal drinking water resource for an area and if its contamination would create a
significant hazard to public health. The aquifer is the sole or principal drinking water resource for
an area if it supplies 50 percent or more of the drinking water in a particular area. No commitment
for federal financial assistance may be provided for any project that USEPA determines may
contaminate a sole source aquifer such that a significant hazard to public health is created.
5.4.1 Existing Conditions
The project area is located in the Gravesend Bay Watershed in the Raritan Bay–Lower Bay
Watershed (HUC0203020201). The project is located on the western tip of Coney Island and is
surrounded by Gravesend Bay to the north and the Atlantic Ocean to the west and south.
The current New York State (NYS) 303(d) List of Impaired/Total Maximum Daily Load (TMDL)
waters indicates that the Lower New York Bay/Gravesend Bay is an impaired water body
(NYSDEC 2016). The 303(d) list identifies the suspected source of impairment as contaminated
sediment and urban/stormwater runoff, including pesticides and heavy metals.
USEPA has designated the entirety of Kings County as a sole-source aquifer under the Safe
Drinking Water Act, which includes the project area. In Kings and southern Queens Counties, the
upper glacial aquifer is underlain by the Pleistocene Gardiners Clay which serves as the confining
layer and the Jameco Gravel Aquifer (NYSDEC 2018).
5.4.2 Potential Impacts on Water Quality
Alternative 1: No Action Alternative
The No Action Alternative would not directly impact water quality. However, future flood events
could potentially overload or damage sewage systems in Sea Gate, causing contaminated runoff
to the adjacent water bodies. The No Action Alternative could have long-term, minor adverse
impacts on water quality during and after flood events associated with storm surge.
Alternative 2: Proposed Alternative
Construction activities as a result of the Proposed Action may result in temporary, minor impacts
on water quality related to soil disturbance and to potential spills, lubricants, and machinery
leakage.
The Subrecipient will obtain a SPDES General Permit and implement a Stormwater Pollution
Prevention Plan (SWPPP) to manage discharges from the site. The SPDES permit would ensure
that stormwater runoff from construction sites related to the Proposed Action is controlled through
Environmental Assessment
Sea Gate Community Bulkhead Construction
12
BMPs and would prevent stormwater runoff from polluting Gravesend Bay, Lower New York
Bay, and the Atlantic Ocean. The following BMPs are part of the Proposed Action to protect water
quality:
Vehicle and heavy equipment refueling and maintenance would be permitted only in
designated disturbed/developed upland areas greater than 100 feet landward of the tidal
wetland boundary where accidental spills can be contained immediately.
All project-related heavy equipment would be maintained regularly to avoid fluid leaks of
gasoline, diesel fuel, hydraulic fluid, and other fluids. All leaking fluid would be stopped
or captured in a container until such time the equipment can be immediately moved off site
and repaired.
Storage of hazardous materials would not occur within 300 feet of any surface waters. A
plan would be prepared for immediate containment and cleanup of hazardous material
spills within or adjacent to the site.
The contractors would use an upland area for all storage and staging of equipment, which
would be protected by silt fencing.
Within 150 feet of any waterbody:
o All petroleum-based hydraulic fluids would be replaced with biodegradable
products.
o All equipment, vehicles, and power tools would be cleaned to keep them free of
external fluids and grease and to prevent leaks and spills from entering the water.
o Generators, cranes, or other stationary heavy equipment operated would be
maintained and protected as necessary to prevent leaks and spills from entering
the water.
5.5 Wetlands
Actions that could impact wetlands require review under several regulatory programs, including
Section 404 of the CWA (33 USC 1344), the New York State Freshwater Wetlands Act (Article
24 of Environmental Conservation Law), and the Tidal Wetlands Act (Article 25 of Environmental
Conservation Law). Executive Order (EO) 11990 Wetlands Management requires Federal
agencies to avoid funding activities that directly or indirectly support occupancy, modification, or
development of wetlands, whenever there are practicable alternatives, and that the proposed action
includes all practicable measures to minimize harm to wetlands that may result from such use.
FEMA uses the eight-step decision-making process to evaluate potential effects on wetlands and
to identify mitigation measures (Appendix C).
Environmental Assessment
Sea Gate Community Bulkhead Construction
13
5.5.1 Existing Conditions
The potential presence of wetlands was evaluated based on a review of the project area on the
NYSDEC “Environmental Resource Mapper” and the U.S. Fish and Wildlife Services (USFWS)
National Wetland Inventory (NWI) “Wetlands Mapper” websites. USFWS classifies aquatic
habitats into five distinct categories: marine, estuarine, riverine, lacustrine, and palustrine wetlands
(Cowardin et al. 1979). Based on a review of the USFWS Wetlands Mapper and NYSDEC
Environmental Resource Mapper, there are no state designated wetlands in the area, but there are
aquatic habitats with “Estuarine and Marine Wetlands” and “Estuarine and Marine Deepwater”
classifications (Appendix A, Figure 5-4). NYSDEC categorizes tidal areas to identify wetlands and
aid in administering programs for tidal wetland protection. The NYSDEC Tidal Wetlands Map is
provided in Appendix A, Figure 5-5. NYSDEC categorizes the tidal areas within the project area
as littoral zone. No wetlands meeting the definition of wetlands under Section 404 of the Clean
Water Act are within the project area.
5.5.2 Potential Impacts on Wetlands
Alternative 1: No Action Alternative
The No Action Alternative would have no impact on state or federal wetlands.
Alternative 2: Proposed Alternative
Because there are no wetlands within the project area, the Proposed Action would have no impact
on wetlands during construction. The NYSDEC map indicates the presence of a special aquatic
site (coastal shoal, bar, or mudflat) to the north of the project area. This area would not be affected
by the Proposed Action.
5.6 Floodplains
Executive Order 11988, Floodplain Management, requires federal agencies to avoid potential
adverse impacts associated with the occupancy and modification of floodplains, and to avoid
floodplain development whenever there are practicable alternatives. Any potential adverse impacts
must be mitigated when there are no practicable alternatives. FEMA regulations for complying
with EO 11988 are contained in 44 CFR Part 9. Federal actions within the 100-year floodplain
require the federal agency to conduct an eight-step review process to evaluate alternatives within
floodplains (Appendix C).
Environmental Assessment
Sea Gate Community Bulkhead Construction
14
5.6.1 Existing Conditions
The site is located within the 100-year floodplain (Zone VE EL 17, Zone AE EL 11, and Zone AO
Depth 2-3) as shown on Preliminary Flood Insurance Rate Map panel #3604970334G (Appendix
A, Figures 5-6 and 5-7) dated December 5, 2013 (FEMA 2013).
5.6.2 Potential Impacts on Floodplains
Alternative 1: No Action Alternative
The No Action Alternative would not reduce the risk of flood damage and Sea Gate would continue
to be at risk of loss of life and property damage during future storm events. The No Action
Alternative would have long-term, minor, adverse impact on floodplain functions.
Alternative 2: Proposed Alternative
The Proposed Action would reduce risk of future flood damage to the residential properties and
reduce the chance of property damage and physical danger resulting from floodwaters. FEMA
anticipates negligible short-term adverse impacts to the floodplain compared to existing
conditions. Overall, the Proposed Action would have a long-term minor beneficial impact on flood
protection.
5.7 Coastal Resources
The Coastal Zone Management Act (CZMA), administered by states with shorelines in coastal
areas, requires those states to have a Coastal Zone Management Plan (CZMP) to manage coastal
development. Federal agencies must evaluate actions within designated coastal zones to ensure
they are consistent with the CZMP. Projects receiving federal assistance must follow the
procedures outlined in 15 CFR 930.90 – 930.101 for federal coastal zone consistency
determinations. The New York State Department of State (NYSDOS) and NYSDEC have
identified and promulgated substantive policies for guiding development and resource
management in the state’s coastal area. New York City including Kings County has adopted a
Local Waterfront Revitalization Program (LWRP) (NYSDOS 2016). The Coastal Erosion Hazard
Law (Environmental Conservation Law 34) empowers NYSDEC to identify and map coastal
erosion hazard areas and to adopt regulations (6 NYCRR Part 505). The Coastal Erosion Hazard
Area Permit Program manages regulated activities or land disturbance on properties within the
coastal erosion hazard areas.
The Coastal Barrier Resources Act of 1982 created the Coastal Barrier Resource System (CBRS)
under the jurisdiction of the USFWS restricting both direct and indirect federal expenditures within
system units. Congress amended this act with the Coastal Barrier Improvement Act of 1990,
Environmental Assessment
Sea Gate Community Bulkhead Construction
15
creating Otherwise Protected Areas with lesser restrictions limited to prohibiting federal flood
insurance.
5.7.1 Existing Conditions
Long Island’s coastal areas are primarily composed of materials such as gravels, sands, and clays.
This contributes to these shorelines being dynamic environments, inherently unstable and
constantly changing in response to natural and human forces. Constructed walls and other hard
features can interrupt such natural processes as barrier island migration. Currently bulkheading
exists, to various heights and in various conditions, along most of the Sea Gate shoreline.
The adjacent beach was part of an unrelated project conducted by USACE to install T-head groins
and conduct beach nourishment activities. FEMA considered these conditions as part of the
existing baseline for this Sea Gate seawall project EA.
The project is located within the coastal zone of New York State; therefore, the Proposed Action
must comply with the forty-four policies established in the New York State CZMP (NYSDOS
2016). The proposed project is not located within a designated CBRS unit.
5.7.2 Potential Impacts on Coastal Resources
Alternative 1: No Action Alternative
The No Action Alternative would not have an impact on coastal resources.
Alternative 2: Proposed Alternative
The Subrecipient submitted the Proposed Action to NYSDOS on August 14, 2018 for
determination of Coastal Consistency Conformance. The NYSDOS sent a response letter on
September 21, 2018 confirming no objection to federal financial assistance for the Proposed
Action (Appendix D). The Subrecipient presented the Proposed Action to the New York City
Department of City Planning in a meeting on September 13, 2018. On September 17, 2018, the
Department of City Planning sent a response letter noting consistency with LWRP policies, with
additional comments on project specifics (Appendix E).
The Proposed Action would involve construction within a Coastal Erosion Hazard Area (CEHA)
as shown on the official Coastal Erosion Hazard Area Maps issued by NYSDEC. This Proposed
Action includes grading, excavating, and other disturbance of soil, which are regulated activities
under 6 NYCRR Part 505, and would likely require a Coastal Erosion Management Permit from
NYSDEC.
Environmental Assessment
Sea Gate Community Bulkhead Construction
16
The Proposed Action would contribute to additional hardening of the shoreline. However,
considering the baseline conditions of the past and existing bulkheading and the USACE
constructed T-groins, FEMA considers the Proposed Action’s long-term impacts on coastal
resources to be adverse but minor.
5.8 Threatened and Endangered Species
The Endangered Species Act (ESA) of 1973 provides for the conservation of threatened and
endangered plants and animals and the habitats in which they are found. The lead federal agencies
for implementing ESA are the USFWS and the U.S. National Oceanic and Atmospheric
Administration (NOAA) National Marine Fisheries Service (NMFS). The law requires federal
agencies to ensure that the actions they authorize, fund, or carry out are not likely to jeopardize
the continued existence of any listed species or result in the destruction or damaging modification
of designated critical habitat of such species. The law also prohibits any action that causes a
“taking” of any listed species of endangered fish or wildlife.
The Bald and Golden Eagle Protection Act (16 U.S.C. 668-668c), enacted in 1940, prohibits
anyone without a permit issued by the Secretary of the Interior from "taking" Bald and Golden
eagles, including their parts, nests, or eggs, or molesting or disturbing the birds. On the state level,
the NYSDEC has released a Conservation Plan for Bald Eagles in New York State, (NYSDEC
2016). The document describes the history and status of the Bald eagle in New York State and
provides guidelines for future management actions.
5.8.1 Existing Conditions
FEMA consulted the USFWS Information for Planning and Consultation (IPaC) system
(https://ecos.fws.gov/ipac/) which identifies four federally listed species that may occur within the
project area. They include Piping plover (Charadrius melodus), Red knot (Calidris canutus rufa),
Roseate tern (Sterna dougallii), and seabeach amaranth (Amaranthus pumilus).
The Piping plover can be found breeding from April through July (Levine 1998) and typically uses
open beach areas between the primary dune and high-tide line (Elliot-Smith and Haig 2004;
McIntyre et al. 2010; New York Natural Heritage Program (NYNHP) 2015). There is no suitable
habitat for Piping plover within the project area. The Red knot may be found in intertidal marine
habitats in New York during migration or wintering periods (Cornell Lab of Ornithology 2017).
Red knot would not likely occur in the project area. The Roseate tern arrives at its breeding grounds
between April and July and remains until fall migration, which typically occurs from August
through September (Gochfeld et al. 1998; Nisbet 1989; NYNHP 2015). The vast majority (greater
than 90 percent) of the breeding population of Roseate tern in New York breeds within the colony
Environmental Assessment
Sea Gate Community Bulkhead Construction
17
located on Great Gull Island (NYNHP 2015), approximately 110 miles east northeast of the project
area. The project area does not contain suitable habitat for the Roseate tern.
Seabeach amaranth is generally found along the dunes associated with ocean beaches (Buchanan
and Finnegan 2010). The decline of the species is most notably attributed to habitat destruction
and alteration, incompatible beach grooming practices, and recreational activities (New Jersey
Department of Environmental Protection, 2017). The project area does not contain suitable habitat
for seabeach amaranth.
Critical habitat, as defined in the Endangered Species Act, is a specific geographic area(s) that
contains features essential for the conservation of a threatened or endangered species and that may
require special management and protection. The project area does not contain any designated
critical habitats.
The Bald eagle, (Haliaeetus leucocephalus), is listed as endangered in New York State, but it is
not listed as threatened or endangered under federal law. There are no known Bald or Golden
eagles within the immediate vicinity of the project area, therefore no mitigation measures are
required per the Conservation Plan for Bald Eagles in New York State (NYSDEC 2016).
5.8.2 Potential Impacts on Threatened and Endangered Species
Alternative 1: No Action Alternative
The No Action Alternative would have no effect on threatened and endangered species.
Alternative 2: Proposed Alternative
The Proposed Action would have no effect on threatened and endangered species because there is
no suitable habitat for listed species present in the project area. FEMA requested USFWS
concurrence on December 18, 2018 (see Appendix F). As of the date of this EA, USFWS has not
provided any objection or comments concerning FEMA’s determination of no effect for all listed
species.
5.9 Cultural Resources
As a federal agency, FEMA must consider the potential impacts of any of its funded actions (i.e.,
undertakings) on cultural resources prior to engaging in any undertaking. This obligation is defined
by Section 106 of the National Historic Preservation Act (NHPA) of 1966, as amended and
implemented by 36 CFR Part 800. Cultural resources are defined as prehistoric or historic
archaeology sites, historic standing structures, historic districts, objects, artifacts, cultural
properties of historic or traditional significance, referred to as Traditional Cultural Properties that
may have religious or cultural significance to Federally-Recognized Indian Tribal Nations (Tribal
Environmental Assessment
Sea Gate Community Bulkhead Construction
18
Nations). Cultural resources listed, or eligible for listing, in the National Register of Historic Places
(NRHP) are subject to protection from adverse impacts resulting from an undertaking. To be
considered National Register-eligible, a cultural resource must meet one or more of the criteria
detailed in 36 CFR Part 60.
Pursuant to 36 CFR 800.4(a)(1), the Area of Potential Effects (APE) is defined as the geographic
area(s) within which an undertaking may directly or indirectly affect (impact) cultural resources.
Within the APE, impacts to above-ground (buildings, structures, objects, etc.) and below-ground
(archaeological) cultural resources are evaluated for National Register eligibility. The APE for this
undertaking includes the footprint of the proposed seawall’s construction along the shoreline
including a buffer to each side. The APE limits begins from a point between West 37th and Beach
38th Streets located directly to the east of the building at 3724 Atlantic Avenue to a point between
Beach 50th and 51st Streets located to the south of the building at 5010 Oceanview Avenue plus a
twenty-five (25) foot buffer (see Appendix G). The APE includes all above ground resources
adjacent to the proposed work as well as all vertical and horizontal ground disturbance for potential
impacts to below-ground resources.
5.9.1 Existing Conditions
New York State Historic Preservation Officer (NYSHPO’s) New York State Cultural Resources
Information System (CRIS), shows that the Sea Gate community is not listed in, or eligible for
listing in NRHP as a historic district. Additionally, according to New York City’s City-Map GIS
system, there are no New York City (NYC) Landmarks Preservation Commission (LPC)
designated landmarks within the Sea Gate Community. Two previously determined National
Register-eligible individual buildings are located within APE: 4200 Atlantic Ave and the U.S.
Coast Guard’s Coney Island Light House (see Appendix G). Existing bulkheads at both properties
will be reconstructed along the perimeter of the ocean side property lines. No proposed work will
physically impact the National Register-eligible buildings themselves.
FEMA evaluated the existing seawall for National Register eligibility, which was constructed by
individual property owners over time using varying methods and materials. Many of the oldest
sections of the wall were destroyed by Hurricane Sandy. As a result, the seawall is discontinuous
and does not contain historical integrity, such as design, setting, materials, workmanship, feeling,
and association, to be considered eligible for listing in the NRHP (see Appendix G).
According to CRIS the APE is not located within a mapped area of archaeological sensitivity.
Likewise, there are no recorded archaeological sites within the APE and/or within one-mile of the
APE. Historic topographic maps illustrate the change in the shoreline beginning in 1898. The
shoreline extends gradually to its present shape throughout the 20th and into the 21st centuries. Soil
classifications within the project area also provide evidence of the shoreline change. Soil
Environmental Assessment
Sea Gate Community Bulkhead Construction
19
classifications include: Beaches (Be); Urban land-Hooksan-Verrazano complex (UHVA); and
Urban land-Verrazano complex (UVA) (see Appendix A, Figure 5-1, for soils). Urban soil types
are indicative of the urban built landscape that comprise the Sea Gate Community shoreline and
residential landscape. The soils are frequently reworked by wave and wind action (including daily
tidal flow) and not supportive of vegetation. For the potential preservation of archaeological sites,
such soils are classified as disturbed.
FEMA consulted with NYSHPO on December 17, 2018 for the proposed undertaking. FEMA
determined the undertaking would result in No Adverse Effect to Historic Properties that are either
in, or eligible for inclusion in, the State or NRHP. NYSHPO concurred with the determination on
December 26, 2018 (SHPO Reference 18PR08036, See Appendix G). On December 21, 2018
FEMA consulted with Tribal Nations including the Delaware Nation, the Delaware Tribe of
Indians, the Shinnecock Nation, and the Stockbridge-Munsee Community Band of Mohicans. To
date, FEMA has received no responses from the Tribal Nations.
5.9.2 Potential Impacts on Cultural Resources
Alternative 1: No Action Alternative
The No Action Alternative would have no direct impact on cultural resources because there would
be no soil disturbance to affect potential archaeological resources and no change to the surrounding
landscape. However, this alternative could result in future adverse effects to the two National
Register-eligible historic properties within the APE that are subject to repetitive flooding due to
seasonal severe storms, largescale natural disasters, and sea level rise. These events can be
damaging as both single events and multiple events that can cause cumulative damage. Therefore,
the No Action Alternative may result in long-term minor adverse impact.
Alternative 2: Proposed Alternative
The Proposed Action will not result in an adverse effect to historic properties as the existing Sea
Gate Seawall is not eligible for listing in the NRHP. Additionally, the proposed work will not
adversely impact the National Register-eligible buildings (4200 Atlantic Ave and the U.S. Coast
Guard’s Coney Island Light House), or their properties. Reconstruction of the bulkhead is critical
for the protection of these NRHP eligible historic properties, as well as the surrounding residential
community. Proposed seawall improvements will result in minimal change to viewsheds,
properties, and the surrounding landscape and will offer protection to potential unidentified
resources adjacent to the APE.
Ground-disturbing impacts would be limited to previously disturbed soils. The project is not
located in an area of archaeological sensitivity and no previous recorded archaeological sites are
located within, or within one-mile of, the APE. Based on these combined characteristics, potential
Environmental Assessment
Sea Gate Community Bulkhead Construction
20
to encounter intact archaeological resources is low. The proposed undertaking would have no
impact.
5.10 Environmental Justice
Executive Order 12898, Federal Actions to Address Environmental Justice in Minority
Populations and Low-Income Populations, requires federal agencies to identify and address
disproportionately high and adverse human-health or environmental effects its activities may have
on minority or low-income populations. In order to provide context for this report a demographic
analysis was undertaken. The first step was to define a relevant Community of Concern (COC).
5.10.1 Existing Conditions
USEPA Region 2’s Guidelines for Conducting Environmental Justice Analysis for New York, a
community would be considered a COC if the minority population is 51.1 percent or higher or if
23.59 percent or more of the population is below the poverty line.
According to the U.S. Census Bureau, 2012-2016 American Community Survey (ACS) 5-year
Estimates, the per capita income for the project area of Sea Gate was $32,988. Approximately 26%
of the residents of Sea Gate were low-income, defined as “individuals whose ratio of household
income to poverty level in the past 12 months was less than 2.” Minority population, defined as
other than white alone, make up approximately 25% of the Sea Gate community (U.S. Census
Bureau 2017).
5.10.2 Potential Impacts on Environmental Justice
Alternative 1: No Action Alternative
The No Action Alternative would continue to place the residents of Sea Gate in physical danger
of flooding impacts and would likely result in further property damage during future storm events.
However, these potential impacts would affect the entire community and would not result in a
disproportionate affect to the low-income population of the neighborhood during or after storm
and flood events. There would be no impact concerning environmental justice.
Alternative 2: Proposed Alternative
The Proposed Action would reduce risk of future flood damage to the residential properties and
reduce the chance of physical danger resulting from floodwaters. Construction under the Proposed
Action may result in minor, temporary impacts, such as noise as discussed in the Noise section
(Section 5.12). In addition, when the Proposed Action is completed, there would be beneficial
effects to the entire community, including the identified environmental justice community, such
Environmental Assessment
Sea Gate Community Bulkhead Construction
21
as improved protection against flooding from storm surge, storm damage, and sea-level rise. There
would be no impact concerning environmental justice.
5.11 Land Use and Planning
5.11.1 Existing Conditions
The existing land uses within the project area are vacant land (beach front), residential, and public
facilities and institutions (Coney Island Lighthouse). It is zoned as R3-1 per NYC Zoning and
Land Use and is within Brooklyn Community District 13. The existing land uses within the vicinity
of the project area are consistent with the underlying zoning districts (see Appendix A Figure 5-8
and Figure 5-9).
The New York City Charter requires public review through the Uniform Land Use Review
Procedure (ULURP) for most land use actions. This entails review at the community, borough,
and City levels, each with time limits to ensure regular processing.
5.11.2 Potential Impacts on Land Use and Planning
Alternative 1: No Action Alternative
The No Action Alternative would not change the land use or zoning. However, existing residential
uses within the project area may deteriorate over time, as the area would continue to be susceptible
to flooding. There would be no impact to current or planned land use.
Alternative 2: Proposed Alternative
The Proposed Action would not change the land use or zoning. However, it would reduce risk of
future flood damage to the residential properties and reduce the chance of physical danger resulting
from floodwaters. There would be no impact to current or planned land use.
5.12 Noise
The Noise Control Act of 1972 required USEPA to create a set of noise criteria. In response,
USEPA published Information on Levels of Environmental Noise Requisite to Protect Public
Health and Welfare with an Adequate Margin of Safety in 1974 which explains the impact of noise
on humans. The USEPA report found that keeping the maximum 24-hour day-night noise level
(Ldn) value below 70 A-weighted decibels (dBA) would protect the majority of people from
hearing loss. USEPA recommends an outdoor Ldn of 55 dBA. According to published lists of
noise sources, sound levels, and their effects, sound causes pain starting at approximately 120 to
125 dBA (depending on the individual) and can cause immediate irreparable damage at 140 dBA.
Environmental Assessment
Sea Gate Community Bulkhead Construction
22
Occupational Safety & Health Administration (OSHA) has adopted a standard of 140 dBA for
maximum impulse noise exposure.
Sound pressure level (SPL) is used to measure the magnitude of sound and is expressed in dBA,
with the threshold of human hearing defined as 0 dBA. The SPL increases logarithmically so that
when the intensity of a sound is increased by a factor of 10, its SPL rises by 10 dB; while a 100-
fold increase in the intensity of a sound increases the SPL by 20 dBA. Equivalent noise level (Leq)
is the average of sound energy over time so that one sound occurring for two minutes would have
the same Leq of a sound twice as loud occurring for one minute. The Ldn is based on the Leq and
is used to measure the average sound impacts for the purpose of guidance for compatible land use.
It weights the impact of sound as it is perceived at night against the impact of the same sound heard
during the day. This is done by adding 10 dBA to all noise levels measured between 10:00 pm and
7:00 am. For instance, the sound of a car on a rural highway may have an SPL of 50 dBA when
measured from the front porch of a house during the day. If the measurement were taken at night,
a value of 60 dBA would be recorded and incorporated into the 24-hour Ldn.
5.12.1 Existing Conditions
The ambient noise level in the vicinity of the project site is typical for a residential area. Most of
the land in the vicinity of the project area is comprised of residential development or beach. The
noise sensitive receptors identified in the area include schools, assisted living facilities, and houses
of worship. The schools include Public School 329, Surfside Elementary School, at 2929 W 30th
Street, approximately 0.37 miles from the nearest point of the project site; Public School 188,
Michael E Berdy Elementary School, at 3314 Neptune Ave., approximately 0.30 miles from the
nearest point of the project site; and Mesivta of Seagate, at 3803 Nautilus Ave., approximately
0.15 miles from the nearest point of the project site. Assisted living facilities include Abraham
Residence I at 3915 Neptune Ave., approximately 0.14 miles from the nearest point of the project
site; Abraham Residence II at 3811 Surf Ave., approximately 0.09 miles from the nearest point of
the project site; and Mermaid Manor Home for Adults at 3602 Mermaid Ave., approximately 0.12
miles from the nearest point of the project site. Houses of worship include Meisels Zalmen at 3868
Poplar Ave., approximately 0.08 miles from the nearest point of the project site; Chavas Daas at
3910 Neptune Ave., approximately 0.12 miles from the nearest point of the project site;
Congregation Kneses Israel of Sea-Gate at 3801 Nautilus Ave., approximately 0.15 miles from the
nearest point of the project site; Chabad by the Ocean at 3844 Lyme Ave., approximately 0.19
miles from the nearest point of the project site; and Masjid Bab-Us-Salam at 3604 Neptune Ave.,
approximately 0.28 miles from the nearest point of the project site.
Environmental Assessment
Sea Gate Community Bulkhead Construction
23
5.12.2 Potential Impacts of Noise
Alternative 1: No Action Alternative
Under the No Action Alternative, there would be no additional noise added to current conditions.
Therefore, the No Action Alternative would have no impact on existing noise levels.
Alternative 2: Proposed Alternative
The Proposed Action would result in increases in noise levels during construction. NYC Noise
Code requires a written noise mitigation plan before starting construction work and every project
must have the plan on-site. For projects close to noise-sensitive locations like schools, hospitals
and places of worship, the noise mitigation plan must be designed to accommodate the needs of
these buildings. There are also schedule requirements for construction projects. Temporary
increases in noise levels due to construction activities would be minimized through compliance
with these local noise ordinances.
Potential construction-related noise impacts of the Proposed Action would be temporary and
minor. Implementation of the Proposed Action would not result in new permanent sources of noise
and would have no ongoing impact on noise levels.
5.13 Transportation
5.13.1 Existing Conditions
Sea Gate is served by local roadways and accessible by direct municipal express bus service to
New York City. The nearest subway station, which offers D, F, Q, and N trains, is approximately
1.5 miles from the project site and the closest public bus stop, which serves the B36 and B74 lines,
is approximately 0.5 miles away.
5.13.2 Potential Impacts on Transportation
Alternative 1: No Action Alternative
The No Action Alternative would not impact traffic or transportation, but the roadways would
remain vulnerable to future storm surge and flooding.
Alternative 2: Proposed Alternative
FEMA anticipates short-term impact on traffic during the construction period. The project would
not alter existing roads or bus routes, nor would it create housing or other traffic generators. The
presence of construction and delivery vehicles is unavoidable; however, this would be a minor
Environmental Assessment
Sea Gate Community Bulkhead Construction
24
temporary adverse impact, and all site construction activities would comply with local ordinances
that relate to operations on a construction site.
5.14 Public Health and Safety
5.14.1 Existing Conditions
During Hurricane Sandy, brackish floodwater damaged over 750 homes behind the seawall. In
addition, Hurricane Sandy caused damage to roads and other infrastructure such as the electric and
sewer systems. In addition to the damage to Lindy Park, other critical community services that
were severely impacted include the Sea Gate Police Department and the Sea Gate Association
Administration buildings, which were completely flooded and beyond salvage. The community of
Sea Gate has also suffered damages from flooding and storm winds during Tropical Storm Irene,
Tropical Storm Lee, and several smaller storm events.
5.14.2 Potential Impacts on Public Health and Safety
Alternative 1: No Action Alternative
The No Action Alternative would have a minor adverse impact on the community’s public health
and safety because residents would remain vulnerable to flooding, placing the residents of Sea
Gate in physical danger and would likely result in further property damage during future storm
events. The No Action Alternative could also have minor adverse impacts on public services and
utilities during and after flood events associated with storm surge. Future flood events could
potentially damage powerlines and wastewater systems in the Sea Gate community, causing
contaminated runoff and nutrient loading to the adjacent water bodies. Effluent from damaged
sanitary wastewater systems could also contaminate groundwater and aquifers in the area.
Flooding can also greatly increase the risk of electrical fires.
Alternative 2: Proposed Alternative
The Proposed Action would have beneficial long-term minor effects on public health and safety,
public services, and utilities. The Proposed Action would reduce the susceptibility to future flood
hazards, thereby protecting the public health and safety of the Sea Gate community. Utilities must
be located and avoided during the final design of the Proposed Action.
Environmental Assessment
Sea Gate Community Bulkhead Construction
25
5.15 Hazardous Materials
5.15.1 Existing Conditions
Sites near the proposed project location that have hazardous materials, contamination, toxic
chemicals, gases and radioactive substances were identified through the review of NEPAssist. The
NEPAssist review included an examination of the USEPA’s Superfund List (CERCLIS), National
Priorities List, Toxics Release Inventory (TRI), Brownfields, Air Facility Systems (AFS), and
hazardous waste (Resource Conservation and Recovery Act - RCRA) databases.
There are 46 RCRA sites identified within, or immediately adjacent to, the Sea Gate community
during the NEPAssist review, including two that are within/directly adjacent to the project
footprint. The first is Metron Environmental Ltd IS285 located at Beach 47th Street and the second
is Con Edison Service Box: 23513, 452 Beach 45th Street.
5.15.2 Potential Impacts on Hazardous Materials
Alternative 1: No Action Alternative
The No Action Alternative would result in no change in current conditions at the site and therefore
have no effect on hazardous materials.
Alternative 2: Proposed Alternative
FEMA anticipates negligible temporary impacts due to the presence of identified RCRA sites
during construction.
5.16 Cumulative Impacts
In accordance with NEPA, this EA considers the overall cumulative impact of the Proposed Action
and other actions that are related in terms of time or proximity. According to the CEQ regulations,
cumulative impacts represent the impact on the environment, which results from the incremental
impacts of the action when added to other past, present, and reasonably foreseeable future actions,
regardless of what government agency (federal or non-federal) or private entity undertakes such
other actions. Cumulative impacts can result from individually minor but collectively significant
actions taking place over a period of time (40 CFR 1508.7).
In addition to NEPA, other statutes require federal agencies to consider cumulative impacts. These
include the Clean Water Act Section 404 (b) (1) guidelines; the regulations implementing the
conformity provisions of the Clean Air Act; the regulations implementing Section 106 of the
NHPA; and the regulations implementing Section 7 of the ESA.
Environmental Assessment
Sea Gate Community Bulkhead Construction
26
The entire Atlantic Coast of New York is undergoing recovery efforts after the 2012 hurricane
season, which includes demolition, reconstruction, and new construction. The USACE is
undertaking multiple projects, including the Atlantic Coast of New York, Rockaway Inlet to
Norton Point Coney Island Area – Shore Protection Project, which included 2500 linear feet of
shoreline between Norton Point and the West 37th Terminal Groin. The Sea Gate Reach was first
designed in 2005 and reformulated in 2016 as a response to impacts of Hurricane Sandy. The
project included constructing four T-groins and the placement of 70,000 cubic yards of sand. This
project is not designed to meet 100-year level of risk reduction, and there is expectation of future
renourishments of 30,000 cubic yards of sand every 10 years. The New York Governor’s Office
of Storm Recovery has undertaken several NY Rising Community Reconstruction Programs in the
Sea Gate area. The New York City Economic Development Corporation (NYCEDC) undertook
the Coney Island Creek Resiliency Study in 2016, which drains into Gravesend Bay (NYCEDC
2016). The combination of all recovery development projects, including those mentioned above,
would have cumulative effects to Sea Gate area. However, FEMA anticipates that this Proposed
Action would not have cumulative impacts on resources addressed in this EA.
6.0 PERMITS AND PROJECT CONDITIONS
The Subrecipient is responsible for obtaining all applicable federal, state, and local permits and
other authorizations for project implementation prior to construction, as well as adherence to all
permit conditions. Any substantive change to the approved scope of work would require re-
evaluations by FEMA for compliance with NEPA and other laws and EOs. The Subrecipient must
also adhere to the following conditions during project implementation and consider the below
conservation recommendations. Failure to comply with grant conditions may jeopardize federal
funds.
The Proposed Action’s consistency with applicable federal, state, and local laws, regulations, and
programs is part of this EA. In addition to this EA, the following permits and/or consultations are
also required by local, state and federal agencies:
Clean Water Act, Section 401 Permits (New York State Department of Environmental
Conservation)
New York State Coastal Consistency Review (New York State Department of State Coastal
Management Program – Appendix D)
Endangered Species Act, Section 7 (87 Stat.884, as amended 16 U.S.C. 1531 et seq.)
Consultation (Appendix F)
National Historic Preservation Act Section 106 Consultation (New York State Historic
Preservation Office (NYSHPO) (Appendix G)
Environmental Assessment
Sea Gate Community Bulkhead Construction
27
USACE Authorization for Coverage under Nationwide Permit #27 under Clean Water Act
Section 404
NYSDEC Article 25 Tidal Wetland Permit
NYSDEC Coastal Erosion Management Permit
7.0 AGENCY COORDINATION AND PUBLIC INVOLVEMENT
This EA will be made available for agency and public review and comment for a period of 30 days.
The public information process will include a public notice with information about the Proposed
Action in the Brooklyn Courier / Bay News, with targeted outreach to environmental justice
populations through notices to community organizations. The EA will also be made available for
download at https://www.fema.gov/media-library/assets/documents.
A hard copy of the EA will be available for review at the following locations:
Sea Gate Office
3700 Surf Ave.
Brooklyn NY 11224
Brighton Beach Library
16 Brighton First Rd.
Brooklyn, NY 11235
718.946.2917
Ardurra Office
1305 Franklin Ave.
Suite 210
Garden City, NY 11530
Interested parties may request an electronic copy of the EA by emailing FEMA at
[email protected]. This EA reflects the evaluation and assessment of the
federal government, the decision maker for the federal action; however, FEMA will take into
consideration any substantive comments received during the public review period to inform the
final decision regarding grant approval and project implementation. The public is invited to submit
written comments by emailing [email protected] or via mail to:
FEMA Region II – DR-4085-NY
26 Federal Plaza
New York, NY 10278
Attn: Sea Gate Community Bulkhead Construction EA Comments
Environmental Assessment
Sea Gate Community Bulkhead Construction
28
If FEMA receives no substantive comments from the public and/or agency reviewers, this EA will
be adopted as final, and FEMA will issue a FONSI. If FEMA receives substantive comments, it
will evaluate and address those comments as part of the FONSI documentation and may consider
whether changes to the grant or project implementation is appropriate.
8.0 LIST OF PREPARERS
FEMA Region II
26 Federal Plaza
New York, NY 10278
CDM Smith
110 Fieldcrest Avenue
Edison, NJ 08837
9.0 SUMMARY OF IMPACTS
Table 9-1. Summary of Impacts Table
Resource Environmental
Consequence
Environmental Protection
Measures and Required
Permits
Topography & Soils
See Section 5.2 for details
No Action Alternative: No
Impact
Proposed Action: Negligible
Adverse
New backfill will be suitable
material from commercial
source placed according to
approved plans and
specifications
Air Quality
See Section 5.3 for details
No Action Alternative: No
Impact
Proposed Action: Temporary,
Negligible, Adverse
All equipment and machinery
would comply with
applicable USEPA standards.
All units would be powered
with ULSD per USEPA
regulations.
Water Quality
See Section 5.4 for details
No Action Alternative: Long-
term, Minor, Adverse
Proposed Action: Temporary,
Minor, Adverse
Clean Water Act, Section 404
and Section 401 Permits (See
Appendix D)
Other BMPs are listed in
Section 5.4.2.
Wetlands
See Section 5.5 for details
No Action Alternative: No
Impact
Proposed Action: No Impact
Not Applicable
Floodplains
See Section 5.6 for details
No Action Alternative: Long-
term, Minor, Adverse
Not Applicable
Environmental Assessment
Sea Gate Community Bulkhead Construction
29
Resource Environmental
Consequence
Environmental Protection
Measures and Required
Permits
Proposed Action: Short-term
Negligible Adverse; Long-
term, Minor, Beneficial
Coastal Resources
See Section 5.7 for details
No Action Alternative: No
Impact
Proposed Action: Long-term,
Minor, Adverse
Coastal Erosion Management
Permit from NYSDEC
Threatened and
Endangered Species
See Section 5.8 for details
No Action Alternative: No
Impact
Proposed Action: No Impact
Not Applicable
Cultural Resources
See Section 5.9 for details
No Action Alternative: Long-
term, Minor, Adverse
Proposed Action: No Impact
Not Applicable
Environmental Justice
See Section 5.10 for details
No Action Alternative: No
Impact
Proposed Action: No Impact
Not Applicable
Land Use and Planning
See Section 5.11 for details
No Action Alternative: No
Impact
Proposed Action: No Impact
NYC Uniform Land Use
Review Procedure (ULURP)
Noise
See Section 5.12 for details
No Action Alternative: No
Impact
Proposed Action: Temporary,
Minor, Adverse; Long-term,
No Effect
NYC Noise Code required
Noise Mitigation Plan
Transportation
See Section 5.13 for details
No Action Alternative: No
Effect
Proposed Action: Short-term,
Minor, Adverse; Long-term,
No Effect
Not Applicable
Public Health and Safety
See Section 5.14 for details
No Action Alternative: Long-
term, Minor, Adverse
Proposed Action: Long-term,
Minor, Beneficial
Not Applicable
Hazardous Materials
See Section 5.15 for details
No Action Alternative: No
Effect
Proposed Action: Negligible,
Temporary
BMPs as outlined in the
Water Quality Section 5.4.2.
Environmental Assessment
Sea Gate Community Bulkhead Construction
30
Resource Environmental
Consequence
Environmental Protection
Measures and Required
Permits
Cumulative Impacts
See section 5.16 for details
When added to past, present,
and reasonably foreseeable
actions, the Proposed Action
is not expected to have
adverse cumulative impacts
on any resource.
Not Applicable
Environmental Assessment
Sea Gate Community Bulkhead Construction
31
10.0 REFERENCES
Buchanan, M.F. and J.T. Finnegan. 2010. Natural Heritage Program List of the Rare Plant
Species of North Carolina. NC Natural Heritage Program, Raleigh, NC.
Cornell Laboratory of Ornithology. 2017. All About Birds Guide. Accessed October 15, 2018.
Available at: https://www.allaboutbirds.org/guide/search/
Cowardin, L. M., V. Carter, F.C. Golet, E.T. LaRoe. 1979. Classification of Wetlands and
Deepwater Habitats of the United States. U.S. Department of the Interior, Fish and Wildlife
Service. Accessed October 15, 2018. Available at:
https://www.fws.gov/wetlands/Documents/Classification-of-Wetlands-and-Deepwater-
Habitats-of-the-United-States.pdf
Edinger, G.J., D.J. Evans, S. Gebauer, T.G. Howard, D.M. Hunt, and A.M. Oliver (editors).
2014. Ecological Communities of New York State. Second Edition. A revised and
expanded edition of Carol Reschke's Ecological Communities of New York State. New
York Natural Heritage Program, New York State Department of Environmental
Conservation, Albany, NY.
Elliott-Smith, E., S.M. Haig, B.M. Powers. 2009. Data from the 2006 International Piping Plover
Census: U.S. Geological Survey Data Series 426, p. 332
Federal Emergency Management Agency (FEMA). 2013. Preliminary Flood Insurance Rate
Maps. Accessed January 17, 2019. Available at: https://msc.fema.gov/fmcv
Federal Emergency Management Agency (FEMA). 2013. Preliminary Flood Insurance Study.
Accessed January 17, 2019. Available at:
https://floodmaps.fema.gov/prelim/PrelimData/New%20York/Kings%20County/prelim_iss
ue_date-2013-12-05/FIRM/3604970334G.pdf
Gochfeld M., J. Burger, and I.C.T. Nisbet. 1998. Roseate Tern (Sterna dougallii). In A. Poole
and F. Gill, editors, The Birds of North America, No. 370. The Birds of North America,
Inc., Philadelphia, PA. 32 pp.
Levine, E. 1998. Bull’s Birds of New York State. Comstock Publishing Associates, Ithaca, NY.
McIntyre, A.F., J.A. Heath, and J. Jannsen. 2010. Trends in Piping Plover Reproduction at Jones
Beach State Park, NY, 1995-2007. Northeastern Naturalist 17(3): 493-504.
New Jersey Department of Environmental Protection, Division of Parks and Forestry, Office of
Natural Lands Management. Endangered Plants of New Jersey Fact Sheet: Sea-beach
Amaranth (Amaranthus pumilus). Accessed October 15, 2018. Available at:
https://www.fws.gov/northeast/njfieldoffice/pdf/sbanjfact.pdf
Environmental Assessment
Sea Gate Community Bulkhead Construction
32
New York City Economic Development Corporation (NYCEDC). 2016. Coney Island Creek
Resiliency Study. Available at:
https://www.nycedc.com/sites/default/files/filemanager/Projects/Coney_Island_Creek/CIC
BWFS_Report_-_7.8.16.pdf
New York Natural Heritage Program. 2015. New York Natural Heritage Program Conservation
Guide. Accessed October 15, 2018. Available at: http://www.acris.nynhp.org/
New York State Department of State. 2016. The New York City Waterfront Revitalization
Program. Accessed October 15, 2018. Available at: https://docs.dos.ny.gov/opd-
lwrp/LWRP/New%20York%20City/Amendment2/Final/NYC%20WRP%202015.pdf
New York State Department of State. 2016. New York State Coastal Boundary Map. Accessed
October 15, 2018. Available at: https://appext20.dos.ny.gov/coastal_map_public/map.aspx
New York State Department of Environmental Conservation (NYSDEC). March 2003. EJ
Related Policy and Regulations. Accessed January 28, 2019. Available at:
https://www.dec.ny.gov/public/36929.html
New York State Department of Environmental Conservation (NYSDEC). 2016. New York
State Section 303(d) List of Impaired/TMDL Waters . Accessed October 15, 2018.
Available at: http://www.dec.ny.gov/docs/water_pdf/303dListfinal2016.pdf
New York State Department of Environmental Conservation. March 2016. Conservation Plan for
Bald Eagles in New York State. Accessed October 15, 2018. Available at:
http://www.dec.ny.gov/docs/wildlife_pdf/nybaldeagleplan.pdf
New York State Department of Environmental Conservation. 2018. Environmental Resource
Mapper. Accessed October 15, 2018. Available at: http://www.dec.ny.gov/gis/erm/
New York State Department of Environmental Conservation. 2018. Long Island Aquifers.
Accessed October 15, 2018. Available at: https://www.dec.ny.gov/lands/36183.html
New York State Department of Environmental Conservation. 2019. Coastal Erosion
Management Permit Program. Accessed March 7, 2019. Available at:
https://www.dec.ny.gov/permits/6064.html
Nisbet I. C. T. 1989. Status and biology of the northeastern population of the Roseate Tern
(Sterna dougallii): a literature survey and update. 1981-1989. Contract Report 50181-88-
8105. U.S. Fish Wildlife Service, Newton Corner, MA.
U.S. Army Corps of Engineers (USACE). June 2014. Improvement of the Atlantic Coast of New
York City, Rockaway Inlet to Northern Point Project at Sea Gate. Accessed January 18,
Environmental Assessment
Sea Gate Community Bulkhead Construction
33
2019. Available at:
https://www.nan.usace.army.mil/portals/37/docs/civilworks/projects/ny/coast/coney/coney
_island-seagate_june_2014_info_session_posters_20140610.pdf
U.S. Environmental Protection Agency (USEPA). 2018. Environmental Justice Screening and
Mapping Tool Version 2018. Accessed October 15, 2018. Available at:
https://www.epa.gov/ejscreen
U.S. Fish and Wildlife Service (USFWS). 2017. Information for Planning and Consultation.
Accessed October 15, 2018. Available at: https://ecos.fws.gov/ipac/
U.S. Fish and Wildlife Service Chesapeake Bay Field Office. 2016. Migratory Birds. Accessed
October 15, 2018. Available at: https://www.fws.gov/chesapeakebay/migbird.html
U.S. Fish and Wildlife Service (USFWS). 2018. National Wetland Inventory Wetlands Mapper.
Accessed October 15, 2018. Available at: http://www.fws.gov/wetlands/data/mapper.html
Whole Building Design Guide (WBDG). (1990). Executive Order 12699: Seismic safety at
National Institute of Building Sciences. Available at:
www.wbdg.org/ccb/FED/FMEO/eo12699.pdf