ENHANCED STATION INITIATIVE PACKAGE 3 William Montanile, P.E. Program Manager February 13, 2018 Community Board 7

Upload: others

Post on 06-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

ENHANCED STATION INITIATIVEPACKAGE 3

William Montanile, P.E.Program Manager

February 13, 2018Community Board 7

Page 2: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Contract Information1. Award date

2. Duration

Contractor

Designer

cost

2

General Information

Contractor ECCO III with Hardesty & Hanover/Lee Harris Pomeroy

Award October 25, 2017

Substantial Completion December 2018

Construction Cost $111,190,000

Stations 163 Street - Amsterdam Avenue CCathedral Parkway (110 Street) BC86 Street BC72 Street BC

Page 3: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

3

Package 3 Summary 163 Street

Underground, two side platformsCentral large mezzanine, building entrance

Cathedral Parkway (110 Street)Underground, two side platformsSmall mezzanine, exposed express lanes

86 StreetUnderground, two level stacked platformsNo mezzanine, no connections

72 StreetUnderground, two level stacked platformsNo mezzanine, no connections

Page 4: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Scope & Key Elements1. Station Repairs

1. Waterproofing

2. Repair/replace floor topping

3. Concrete spall repair

2. Rehabilitated Station Entrances

1. Guardrail integrated or freestanding totem

2. Countdown clocks

3. Illuminated handrails

3. Improved Mezzanines

4. Improved Platforms

4

Page 5: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Scope & Key Elements5. Other Improved Customer Amenities

1. Countdown clocks

2. Wi-Fi

3. Help Points

4. LED lighting

5. Consolidated wireway

6. Design-build Contracting

5

Page 6: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Station Closures1. Award date

2. Duration

Contractor

Designer

cost

6

Scheduled datesStation Close Re-open Allowable Duration

Cathedral Parkway (110 Street) BC

April 9, 2018 September 2018 Less than 6 months

86 Street BC June 4, 2018 October 2018 Less than 6 months

72 Street BC May 7, 2018 October 2018 Less than 6 months

Page 7: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Diversions1. Award date

2. Duration

Contractor

Designer

cost

7

Weeknight Weekend

Station Northbound Southbound Northbound Southbound

CathedralParkway (110 Street) BC

86 Street BC

72 Street BC

20 20 9 9

110 St/86 St/72 St – 40 weeknight and 18 weekend diversions

Page 8: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Cathedral Parkway (110 Street)

Page 9: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Existing Entry

9

Page 10: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Proposed Canopy Entry

10

Page 11: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Existing Entry

11

Page 12: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Proposed Central Park Entry

12

Page 13: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Existing Entrance Adjacent to Building

13

Page 14: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Proposed Entry Adjacent to Building

14

Page 15: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Existing Mezzanine

15

Page 16: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Proposed Mezzanine

16

Page 17: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Existing Platform

17

Page 18: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

110 Street Proposed Platform

18

Page 19: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street

Page 20: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Existing Entrance Adjacent to Building

20

Page 21: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Proposed Entry Adjacent to Building

21

Page 22: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Existing Control Area

22

Page 23: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Proposed Control Area

23

Page 24: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Existing Platform

24

Page 25: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

86 Street Proposed Platform

25

Page 26: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

72 Street

Page 27: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Existing Station Entrance

27

Page 28: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

72 Street Proposed Entry at Adjacent Building

28

Page 29: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

72 Street Existing Control Area

29

Page 30: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

72 Street Proposed Control Area

30

Page 31: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

31

BRO

ADW

AY

72 Street Existing Platform

Page 32: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

72 Street Proposed Platform

32

Page 33: ENHANCED STATION INITIATIVE PACKAGE 3...Feb 13, 2018  · 3. Concrete spall repair 2. Rehabilitated Station Entrances 1. Guardrail integrated or freestanding totem 2. Countdown clocks

Thank You