Page 1: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Energy Planning and Approval Strategies

1

Page 2: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

outline

• Exam preparation• Strategic – BC Hydro Long Term Planning• Project level

– Environmental Assessment• Federal - Canadian

• Integration

2

Page 3: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

How to read an academic paper

• What’s the main argument (or puzzle)?• What subsidiary arguments support it?• Are there underlying or explicit value

assumptions?• What evidence is used to support the

argument?• Does the evidence support the argument?• Do other (better?) arguments support the

observed outcomes? 3

Page 4: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Sample examPart V: Short answer (guideline: 50-75 words). Answer three of the six questions that follow. 10 points each, total 30%. Write legibly. Explicitly incorporate course concepts and readings.

1. According to David Victor, why is global warming such a hard problem to solve?

2. According to Hoberg and Taylor in “Between Consent and Accommodation,” what are the rules for how governments need to consider First Nations concerns in decision-making?

3. Describe Unruh’s concept of “carbon lock-in” and explain the challenges it poses for developing sustainable energy policy.

4. Using the Norman Ruff reading “Executive Dominance” and the lectures, explain why premiers and prime ministers have so much power within the Canadian system of government.

5. Describe the stages of the policy cycle model, with examples from Northern Gateway Pipeline case or another energy policy with which you are familiar.

6. According to Burnstein, What is the impact of public opinion on public policy?

4

Page 5: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Overview

5

Page 6: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

BC Hydro – supply gap

6

Page 7: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

BC Hydro - planning

• Integrated electricity planning - the long-term planning of electricity generation, transmission, and demand-side resources to reliably meet forecast requirements.

• 2000s - long-term acquisition plan (LTAP) every 4 yrs – Needs to be reviewed and approved by BCUC

• 2010 Clean Energy Act – IRP replaces LTAP– Same problem for analysis and decision-making– but different consultation, review, and approval

7

Page 8: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Utility planning

• Planning context, objectives• Gross (pre-DSM) demand forecasts• Resources (supply and DSM) – ID and

measurement• Develop resource portfolios• Evaluate and select resource portfolios• Develop action plan• Consult• Get approval 8

Page 10: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

BC government response

• May 2010: Clean Energy Act passed.– New IRP process– Removed from BCUC scrutiny

10

Page 11: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Evaluation

• What are the consequences of removing BC Hydro planning from BCUC review?

11

Page 12: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

12

Page 13: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Policy Objectives

13

Page 14: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Conservation first

14

Page 15: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

15

Page 16: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

16

Page 17: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

17

Page 18: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

18

Page 19: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

outline

• Exam preparation• Strategic – BC Hydro Long Term Planning• Project level

– Environmental Assessment• Federal - Canadian

• Integration

19

Page 20: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Project level – Environmental Assessment

20

Page 21: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Environmental Assessment

• Environmental Assessment as a policy tool – a “procedural policy instrument”– Requires analysis and procedure but does not specify

outcome

21

Page 22: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Stages in EA

1. Proposal from proponent2. Screening – is EA required and if so what kind?3. Scoping – what issues?4. Assessment of the proposal5. Report preparation, submission, and review6. Decision: recommendation by EA body,

authoritative decision by political body7. Monitoring and compliance follow-up

22

Page 23: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Designated project list under CEAA

• http://laws-lois.justice.gc.ca/eng/regulations/SOR-2012-147/index.html

• Are new oil sands projects covered by CEAA?

23

Page 24: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Scope of issues, Kinder Morgan pipeline expansion

1. The need for the proposed project.

2. The economic feasibility of the proposed project.

3. The potential commercial impacts of the proposed project.

4. The potential environmental and socio-economic effects of the proposed project, including any cumulative environmental effects that are likely to result from the project, including those required to be considered by the NEB’s Filing Manual.

5. The potential environmental and socio-economic effects of marine shipping activities that would result from the proposed Project, including the potential effects of accidents or malfunctions that may occur.

6. The appropriateness of the general route and land requirements for the proposed project.

7. The suitability of the design of the proposed project.

8. The terms and conditions to be included in any approval the Board may issue.

9. Potential impacts of the project on Aboriginal interests.

10. Potential impacts of the project on landowners and land use.

11. Contingency planning for spills, accidents or malfunctions, during construction and operation of the project.

12. Safety and security during construction of the proposed project and operation of the project, including emergency response planning and third-party damage prevention.

The Board does not intend to consider the environmental and socio-economic effects associated with upstream activities, the development of oil sands, or the downstream use of the oil transported by the pipeline.

24

Page 25: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

• Should upstream effects of pipelines (expansion of oil sands facilities) be considered in pipeline review EAs?

• Should downstream effects of pipelines (refining, combustion in markets) be considered in pipeline review EAs

25

Page 26: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Environmental Assessment – Federal in Canada

• Canadian Environmental Assessment Act– Came into force in 1995– Since 1972, governed by cabinet guidelines– applies to anything that requires federal approval

or permit– Procedures managed by

Canadian Environmental Assessment Agency, within Environment Canada

• Usually, if federal EA no provincial EA

26

Page 27: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

CEAA approval standards

(a) where, taking into account the implementation of any mitigation measures that the responsible authority considers appropriate, (i) the project is not likely to cause significant adverse environmental

effects, or(ii) the project is likely to cause significant adverse environmental effects

that can be justified in the circumstancesthe responsible authority may exercise any power or perform

any duty or function that would permit the project to be carried out in whole or in part

27

Page 28: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

28

Page 29: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

EA process criteria

• Guided by sustainability principles• Participatory• Transparent • Well-informed• Coordinated to avoid jurisdictional conflicts and

overlaps• Timely

February 12, 2013 Sustainable Energy Policy 29

There are tradeoffs between these values. Fostering legitimacy while being timely requires adequately resourced processes

Page 30: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Harper’s “responsible resource development” – Spring 2012

• Replace CEAA– Definition of environmental effect narrowed– Participants limited to are “directly affected” or

have, in the review panel’s judgment, “relevant information and expertise”

– Time limits– Transfer authority to provinces

• NEB Act – final decision moved to cabinet• Fisheries Act – reduce habitat protection

Page 31: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Bill C-38 and EA process

Sustainable Energy Policy 31

Page 32: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

• Should EA procedures allow for the approval of projects likely to cause significant adverse environmental effects?

• Should EA’s have time limits?

Sustainable Energy Policy 32

Page 33: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Cumulative effects?

• “effects that are additive or interactive and result from the recurrence of actions over time. Cumulative impacts are incremental and result when undertakings build on or add to the impacts of previous impacts.”

• Consideration required in federal rules, permitted but not required in BC

• What is the best way to deal with cumulative effects in project level assessments?

33

Page 34: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Environmental Assessment - conclusion

• requires elaborate assessment• demonstration of awareness of concerns• consideration of environmental impacts and

mitigation measures• but project can still be approved if justified• By forcing agencies to consider environmental

consequences, environmental assessment is a critical tool, but it does not affect the balance of values decision-makers ultimately apply.

February 12, 2013 Sustainable Energy Policy 34

Page 35: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Overview

35

Page 36: Energy Planning and Approval Strategies 1. outline Exam preparation Strategic – BC Hydro Long Term Planning Project level – Environmental Assessment Federal

Group discussion of Jaccard et al

• According to Jaccard et al, what are the major challenges in scaling up renewables?

• What criteria do Jaccard et al use to evaluate planning processes for scaling up renewables?

• How have these issues been dealt with to date in British Columbia?

• What are the pros and cons of a strategic assessment?