enclosure design for mass timber buildings - …€¦ · enclosure design for mass timber buildings...

76
1 of 63 Enclosure Design for Mass Timber Buildings COLIN SHANE M.ENG., P.ENG., P.E. PRINCIPAL, SENIOR PROJECT MANAGER RDH BUILDING SCIENCE INC. Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. NOVEMBER 16, 2017

Upload: donguyet

Post on 07-Sep-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

1 of 63

Enclosure Design for Mass Timber Buildings

COLIN SHANE M.ENG., P.ENG., P.E.

PRINCIPAL, SENIOR PROJECT MANAGER

RDH BUILDING SCIENCE INC.

Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board.

NOVEMBER 16, 2017

This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written

permission of the speaker is prohibited.

© RDH Building Sciences Inc. 2015

Copyright Materials

“The Wood Products Council”is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES), Provider #G516.

Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.

This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.__________________________________

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Course Description

• Larger and taller mass timber buildings are becoming common in North America. These buildings typically utilize cross-laminated timber or nail-laminated timber panels, glulam beams and columns, and new engineered timber components to meet the structural and fire requirements associated with greater heights. With these larger wood structures and heavier timber components comes the need for efficient building enclosure assemblies that can be installed quickly on tight sites and are in many cases new and unique to the industry. Prefabricated building enclosure elements are now also commonly used. This presentation shares guidance on building enclosure design and detailing best practices for mass timber buildings. It includes case studies and lessons learned from the design, construction, and monitoring of enclosures for recently completed projects.

Learning Objectives

à Review building enclosure design principles for mass timber

buildings.

à Discuss common details used for mass timber wall and roof

enclosure assemblies.

à Highlight the potential for increased construction efficiency through

the use of prefabricated enclosure assemblies.

à Referencing case studies and details from recently completed

mass timber projects, demonstrate lessons learned and best

practices associated with enclosure assemblies.

6 of 63

à Building enclosure design + mass timberà What’s the same? What’s different?

à Lessons learnedà Case Study – Wood Innovation Design Centerà Case Study – Brock Commons

7

Building Enclosure Design

8

Taller Wood Building Structures

à Fast

à Sensitive to moisture

à Greater movement (shrinkage& drift)

à Fire code challenges

à Mixed steel, concrete& wood materials

à Is not the same as light wood-frame and also different fromhigh-rise steel or concrete structures

9

Tall Wood Building Enclosures

à Need for Speed

à Erect and seal fast

à Protect wood structure

à Accommodating of inclement weather

à Ensure Durability

à Robust materials –high-rise appropriate

à Tolerant of movement

à Thermally efficient

à Non-combustible

10

The Building Enclosure

Image Credit: MGA - Wood Innovation

Design CentreStructure

11

Building Enclosure Design Fundamentals

à Primary function of the Building Enclosure/Façade: Separate the exterior & interior environments

à Protects mass timber during construction & in-service

à Both functional and aesthetic

à Controls heat, air, and moisture

à Designed to accommodate building movement, structural loads, initial & seasonal wood movement

à Key passive design element for an sustainable, energy efficient building

12

What is Unique about Mass Timber Buildings?

à Greater use of engineered heavier timber components (panels, beams, columns)

à Alternate structural systems (post/beam, engineered panels, infill components)

à Unique & new connections, interfaces & details

à Longer & heightened exposure of large wood components to rain and weathering during construction

à Is not the same as light mid-rise wood-frame, but is also different from high-rise steel or concrete structures

13

Tall Versus Shorter Mass Timber Buildings

à Tall Wood Structuresà More repetitive, more exposed, difficult

access, need for more speed – ideal for prefabricated facades

à Less focus on roof and more on walls for weather protection

à Low to Mid-rise Wood Structuresà Easier access to walls from ground à Greater focus on roof for weather

protection than wallsà Prefabrication of façade also possible

though less economies of scale

14

Rain Control – Taller Buildings

à Increased height = increased rain deposition at upper floors and cumulative run-down at lower levels

à Water shedding features become more critical – continuity, drip edges, flashings etc.

à Need for more robust water penetration control strategy – good practice: drained & ventilated rainscreen

à Increased exposure to moisture during construction (severity & length of time)

15

Site Protection & Sequencing

16

Wall Design for Taller Wood Buildings

à Key Considerations:

Durability, Airtightness &

Thermal Efficiency

à Strategies:

à Non-combustible rainscreen

claddings

à Exterior or split-insulated with

thermally efficient cladding

attachments through exterior

insulation

à Non-combustible & moisture

tolerant cavity insulation

Screws through insulation over split insulated wall

Clip & rail cladding attachment system through exterior insulation

17

Wall Design for Taller Wood Buildings

Curtainwall systems w/ modified anchors for wood framing

à Strategies (continued)

à Pre-fabricated components

where possible

à Robust air-tight, water resistant

& vapour permeable wall

membrane (AB/WRB)

à Membrane compatibility with

glazing, roofing, and other

assembly materials

à Simple integration with glazing

systems & other penetrations

à Details, details, details!

SIPs & other Pre-fabricated wall panels

18

Roof Design for Larger Wood Buildings

Conventional roof with tapered insulation over wood joists

Protected membrane roof over vented & tapered structure over CLT

à Key Considerations: Keep dry,

allow to dry, robustness of

assemblies, sloping strategy

à Strategies:

à Protect wood roof from getting wet

during construction

à Design assembly with redundancy

for in-service drying

à Slope structure where possible

à Insulation on top - conventional or

protected membrane assemblies

à Question the need for heavy timber

panels up here?

19

Lessons Learned

20

Potential Challenges with Mass Timber Buildings

21

Lessons Learned - Roofs

à CLT/ NLT roofs get really wet when rained on and are very hard to dry out in-service and need expansion gaps

à Careful with selection of temporary waterproofingmembranes – assume it will be exposed roofing for a while. Need for water-tight laps/details

22

Lessons Learned - Roofs

à Protect large wood roofs from rain – but not too late

à Mechanical drying of wetted roofs is slow & causes costly construction delays

23

Lessons Learned - Roofs

à Design for the inevitable to keep roofing and project on schedule

à Design roof assemblies for redundancy and in-service drying where possible

24

Industry Lessons – Protection

5 ply CLT – ½ Untreated & ½ Treated with water repellant

End grain is very absorptive

Splits, checks & joints that allow water past top layer can be problematic

Erect & roof as fast as possible to protect from rain to avoid delays

Water repellants can help reduce uptake into wood

25

Industry Lessons - Long Term Exposure

26

Case Study 1Wood Innovation and Design 6 Stories, 98’ Feet

27

Taller Wood Building Precedents

28

à 6 ‘tall’ storeys (equivalent to 8 storey, 98’ tall)

à CLT shear walls, glulam columns with glulam beams and staggered CLT floor & roof structure

à Thermal performance design targets (effective R-values)

à R-40 roof

à R-25 walls

à R-5 wood curtainwall glazing

à Pre-fabricated design for infill walls and wood curtain wall

Wood Innovation Design Center

Michael Green Architecture (MGA) –Contractor: PCL Construction

29

WIDC – Structure & Enclosure Systems

Design & Architectural Renders: Michael Green Architecture (MGA)

30

Wood Veneer Curtainwall/Windows

à Aluminum veneer curtainwall

framing over LVL mullions

à Installed as individual window

units, ground bearing

à Stick built/site glazed with triple

glazed IGUs, argon filled, dual

low-e coatings

(U-0.15)

à R-5 (U-0.20) overall thermal

performance

(vs. ~R-3.5 for aluminum system)

31

Wood Veneer Curtainwall/Windows

32

Infill Wall Assembly Design

à Designed for prefab light-frame wall assemblies between curtainwall units

à Target R-25 effective R-value

à Structurally Insulated Panels (SIPs) proved cost effective, fast & easy to install

à WRB/AB membrane on exterior surface (applied in factory) ties nicely into curtainwall assembly

à Sealed joints (interior & exterior & filled)

33

Curtainwall to SIPs Interface

Aluminum CurtainwallVeneer Framing

Silicone Applied Liquid AB/WRB

Interior Air Seal at Joints

Silicone Transition Strip AB/WRB attached with silicone to curtainwall and wall membrane

LVL Framing Backup

SIPs

Charred fire-treated cedar cladding attached to plywood backup & cleat system over drained & ventilated rainscreen cavity

34

Liquid Applied AB/WRB over SIPS

35

Wood Movement & Wall Detailing

Plywood over end grain

Larger movement joint at curtainwall & SIPs panel head

Continuous Columns

Horizontal wood kept relatively dry during construction to minimize swelling

36

Curtainwall & Wall Movement Joints

Flexible joint material at head & jamb

Slip structural connection

37

SIPs & Curtainwall Movement Joints

38

Charred Fire-Treated Cedar Cladding Panels

John Boys, Nicola Log-works

39

Charred Fire-Treated Cedar Cladding Panels

40

Conventional Roof Assembly

R-40+ Conventional Roof Assembly – 2 ply SBS, 4” Stonewool, 4” Polyiso, Protection board, Tapered EPS (0-8”), Torch applied Air/Vapor Barrier(Temporary Roof), ¾” Plywood, Ventilated Space (To Indoors), CLT Roof Panel Structure (Intermittent)

Construction Photos by PCL/MGA/RDH

41

Wood Innovation Design Center

42

Wood Innovation Design Center

43

WIDC – Building Enclosure Summary

à Durable and energy efficient

à High performance materials and

systems

à Small panel pre-fabrication

à Required full exterior access

during construction

à Scaffolding, exterior sealants

à Appropriate for suburban site

and modest height

44

Case Study 2UBC Brock Commons 18 Storeys – 175 Feet

45

UBC Brock Commons– Façade Challenge

46

Initial Concerns & Questions from Project Team

à Vancouver = Temperate rainforest

à How to protect mass timber from rain during construction in any season

à Giant tarps?

à Temporary roof lifted by crane?

à Waterproof the floors?

à Enclose as fast a possible?

à Enclosure must keep up with pace of structure

à How long can mass timber floors get wet for? Best way to protect it?

à How to enclose & seal the walls quickly and not be slowed by inclement weather?

47

UBC Brock Commons - Façade Design Criteria

Fast installation – 1 floor/day & water tight to

protect structure Thermally

Efficient, >R-16

effective walls

Inexpensive, <$50/sqftinstalled & finished

Installed without access to exterior –no sealing or

finishing

Pre-installed cladding & windows

Durable & High-

performance

Resistant to water & able to install in

rain

48

Precedents for Prefabrication of Tall Wood

49

Precedents for Prefabrication of Tall Wood

50

Precedents for Prefabrication of Tall Wood

51

UBC Brock Commons- What Wasn’t Feasible

52

Unitized Curtain wall OptionProblem: Cost, Schedule, Energy

53

Window-Wall OptionProblem: Schedule, Energy

54

Small Panel Prefabrication Wall – PrecedentsProblem: Schedule

55

Tall Wood Prefabrication Option – Large Panel with Pre-installed Windows

Tall Wood Concept Panel

Tall Wood Concept Panel

58

Prefabricated Panel Competition Mock-ups

59

UBC Brock Commons - The 4 Panel Contenders!

Pre-Cast Concrete Sandwich Panels Steel Stud Framed Panels

Wood Stud framed or CLT Panels Aluminum Window-wall

Not thermally efficient enough for project nor met the design intent, but

kept as contingency and costed

60

61

62

63

64

Laboratory Mockup & Physical Testing

65

66

Centura – Factory Floor Prefabrication

67

68

Site Installation – at Pace with Structure – 1 floors/day

69

70

71

Field Testing and Commissioning

72

73

74

Future Facades?

This concludes The American Institute of Architects Continuing Education Systems Course

Colin Shane – [email protected]

76 of 63

à rdh.com

Discussion + Questions

Colin Shane – [email protected]