emerging grid issues briefing...2019/01/02 · emerging grid issues briefing november 8, 2018...
TRANSCRIPT
Emerging Grid Issues Briefing
November 8, 2018
PUBLIC
Agenda
• ERCOT Forward Outlook• Bill Magness, President and Chief Executive Officer
• Future Resource Mix Changes– Solar Resources
• Dan Woodfin, Senior Director, System Operations
• Kenan Ögelman, Vice President, Commercial Operations
– Distributed Energy Resources• Bill Blevins, Director, Grid Coordination
• Kenan Ögelman, Vice President, Commercial Operations
– Energy Storage• Warren Lasher, Senior Director, System Planning
• Transmission Supporting Load Growth• Warren Lasher, Senior Director, System Planning
• Cyber Security • Cheryl Mele, Senior Vice President and Chief Operating Officer
2
Solar Resources
PUBLIC
1,487
1,487
1,487
269
1,370
1,795
1,324
2,111
15
42
82
121
193
288
556
1,000
1,756
4,181
5,394
0 MW 1,000 MW 2,000 MW 3,000 MW 4,000 MW 5,000 MW 6,000 MW
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Cumulative MW Installed
IA Signed-Financial Security Posted
IA Signed-No Financial Security
Utility-Scale Solar Generation Capacity – October 2018
4
Future outcomes uncertain
PUBLIC
Geographic Distribution of Solar Interconnection Requests
5
• Total Interconnection Requests at
any stage of interconnection process
as of October 2018
• Future outcome of these requests is
uncertain
NREL Solar Irradiance Map
PUBLIC
Solar Forecast Accuracy and Output Variability
6
• ERCOT has
already
implemented
solar forecasting.
• Increasing
geographic
diversity will
improve forecast
and intra-hour
variability.
PUBLIC
Pattern of Load, Wind and Solar on Peak Days
7
0
5,000
10,000
15,000
20,000
25,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
1 2 3 4 5 6 7 8 9 101112131415161718192021222324
Win
d a
nd
So
lar (M
W)
Lo
ad
(M
W)
Hour Ending
Summer Peak Day (7/19/2018)
H: Wind I: Solar F: Load
0
5,000
10,000
15,000
20,000
25,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
1 2 3 4 5 6 7 8 9 101112131415161718192021222324
Win
d a
nd
So
lar (M
W)
Lo
ad
(M
W)
Hour Ending
Winter Peak Day (1/17/2018)
Wind Solar Load
• Daily pattern of wind and solar generation is generally complementary
• Solar is more coincident with demand in summer
PUBLIC
Congestion in the West: July 11, 2018
8
07/11/2018 13:15
Transmission congestion drives large Locational Marginal Price (LMP)
differences in the region
07/11/2018 21:30
West Zone West Zone
Distributed Energy Resources (DERs)
PUBLIC
Distributed Energy Resources (DERs)
• DERs may include various technologies:
– Gas/diesel
– Wind/solar
– Storage
• Historically, generation resources were only connected to the
transmission system
• DERs are connected to the distribution system; ERCOT has limited
visibility and interaction with distribution systems
10
PUBLIC
Distributed Energy Resources in ERCOT
11
DER growth rate for 2015-2017 is 62%
Current 2018 DER total is ~1,300 MWs and is expected to continue to grow
PUBLIC
Integrating Registered Distributed Energy Resources
• To reliably operate and plan the ERCOT system, ERCOT is
working on DER-related improvements:
– Visibility: Worked with regulated Transmission/Distribution
Service Providers to map some (93) of the existing registered
DERs; working to map all registered DERs to transmission
system load
– Reliability: Working to provide locational price signals to
registered DERs to support reliability and efficiency
– Planning: Need reporting to properly capture capabilities and
capacity from continued growth of DERs in planning processes
12
PUBLIC
Prices Received by Distributed Energy Resources
13
• DERs currently receive the zonal price.
• The Load Zone price is a weighted average of
Locational Marginal Prices (LMPs) in the zone
and does not fully reflect the local reliability
need.
• Grid-scale resources that receive the
locational price may have to
overcompensate if nearby generation does
not respond to local price signals.
• A LMP represents the value of energy at a
specific location.
• Nodal prices better reflect the local reliability
need.
• Registered DERs should receive a LMP in
the future.
Current: Zonal Pricing
Future: Nodal Pricing
PUBLIC
07/11/2018 13:15 07/11/2018 21:30
-10
-8
-6
-4
-2
0
2
4
6
8
10
-350
-250
-150
-50
50
150
250
350
Ge
ne
ratio
n (M
W)
Price ($
/MW
h)
Prices and Output for Utility-Scale and Distributed Energy Resources
Load Zone Price Distributed Energy Resource
-10
-8
-6
-4
-2
0
2
4
6
8
10
-350
-250
-150
-50
50
150
250
350
0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10: 00 11: 00 12: 00 13: 00 14: 00 15: 00 16: 00 17: 00 18: 00 19: 00 20: 00 21: 00 22: 00 23: 00
Ge
ne
ratio
n (
MW
)
Price ($/MWh)
Pric es and Output for Grid-Scale and Distributed Energy Resources
Locational Price Utility-Scale Generation Resource
Zonal Pricing of DERs Results in Inefficient Price Signals
14
• In this instance, a DER solar facility does not receive negative locational prices;
instead, it receives the Load Zone price, which does not dip below zero.
Consequently, the DER solar facility does not lower its output.
• A grid-scale solar generation resource receives the LMP at its location, and in this
example, lowers output accordingly when LMPs go negative.
Energy Storage
PUBLIC
Why is Energy Storage of Interest?
• Energy storage (batteries) can be used for a variety of grid and customer
applications:
– Store energy at a resource
– Arbitrage energy prices
– Provide grid-level Ancillary Services
– Defer or eliminate the need for transmission/distribution upgrades
– Allow customers to reduce peak demand (to save on demand and/or transmission charges)
– Provide high reliability at customer location
– Enable micro-grid capability
– Provide fuel for electric transportation
• Energy storage is scalable
– A Tesla PowerWall has a maximum output of 5 to 7 kW
– Some battery facilities are greater than 200 MW
• Energy storage can take energy from variable generation (wind and solar) and
provide a dispatchable resource
• Costs of battery technologies are declining rapidly
16
PUBLIC
Current Storage Activity in ERCOT and Beyond
• Currently, ~89 MW of battery storage resources are registered with ERCOT
and participating in ERCOT Ancillary Services markets.
– There are smaller DER battery systems that are not registered with ERCOT.
– There also is a 4 MW battery in Presidio, TX, which was installed to improve
customer reliability at the end of a 60-mile radial transmission line.1
• Approximately 1,889 MW of battery storage capacity is being studied in the
ERCOT resource interconnection queue.
• In September 2016, American Electric Power applied to install batteries at
two distribution substations in lieu of more costly system upgrades. The
PUCT is reviewing the use of batteries as grid upgrades in Project No.
48023 (initial comments were submitted last week).
• FERC jurisdictional electric markets are subject to FERC Order No. 841,
which requires increased access to energy, Ancillary Services and capacity
markets for battery resources.
17
1(Approved by the Public Utility Commission of Texas [PUCT] in April 2009 [Docket No. 35994].)
PUBLIC
Integrating Energy Storage
Focus on increasing visibility and decreasing barriers to entry
• Develop increased system awareness of storage device
operation and limitations in the control room
• Identify and reduce barriers to energy and Ancillary Services
markets
• Adapt ERCOT system models to facilitate integration of storage
technologies
Approach needs to be adaptable – we don’t know how the
technology will develop in our market
18
Transmission Supporting Load Growth
PUBLIC
Transmission Development in West Texas
• Providing reliable electric service to meet the needs of oil and
gas development in West Texas is a challenge.
– Existing infrastructure was not designed for recent increases in
customer demand.
– Predicting the amount and location of future customer oil and gas
demand growth is difficult.
– Major transmission projects take five years to plan and build. Many
oil and gas development companies have 18-month planning
horizons.
– Transmission upgrades, line maintenance and connecting new
customers typically require line outages, which temporarily reduces
existing available transmission capacity.
20
PUBLIC
Culberson County Area Electricity Demand Growth
21
Permian Basin Rig Count
Culberson area
PUBLIC
Transmission Development
22
PUBLIC
Future Transmission Development
• The ERCOT Board of
Directors recently
endorsed a major
transmission project
in West Texas to
ensure continued grid
reliability in the
region.
• This project should
be fully constructed
by April 2021.
23
Cyber Security
PUBLIC
ERCOT Cyber & Physical Security Program
25
• ERCOT has strong executive management
support for security.
• ERCOT has a dedicated and integrated
cyber/physical security organization and
established strategy.
• ERCOT uses layered cyber and physical
security architectures known as a defense-
in-depth strategy, along with careful
monitoring.
• ERCOT is committed to external
collaboration with relevant government
agencies, law enforcement, industry and
national labs to enhance its and the
industry’s security posture.
PUBLIC
Security Protection Approach
National Institute of Standards and Technology
26
PUBLIC
Grid Security Collaboration
27
National LabsIndustry
• Critical Infrastructure Protection Working Group (CIPWG)
• Grid Resilience Working Group (GRWG)
Federal/National State