Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 1 of 13
1 | P a g e
HBL Power Systems Limited
Hyderabad – TS, India
Electronics Group
Procedure for Purchase
Procedure No.: EG-PU-PR-01, Rev.No.: 02
Details Name Signature Date
Prepared By P Manjula
Approved By Varaprasad SSM
CONTROL OF CONFIDENTIALITY
The information contained in this document is the property of HBL, which reserves the
right for distribution, application or reproduction for any usage.
manjula P (Aug 20, 2021 16:28 GMT+5.5)manjula P Aug 20, 2021
Aug 20, 2021
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 2 of 13
2 | P a g e
Revision History
Distribution List
This Documented Information will be uploaded in QMS application for reference.
List of Abbreviations
# Abbreviation Meaning
1 AON Acceptance of necessary
2 AVL Approved Supplier Master List
3 BOM Bill of Materials
4 BTP Build to print
5 BTS Build to Specifications
6 COC Certificate of Conformity
7 CSO Central Standards Office
8 DCH Digital Control Harness Project
Date of
Revision
Details of
Changes Reason for Change
Rev.No
From To
00 01.12.2016 All Pages Initial Version - 00
01 31.07.2019 All pages Implementation of Procedure 00 01
02 31.07.2021 Page No.
7,11,12, and 13
Organization Chart Modified
along doc no added in the
given pages
01 02
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 3 of 13
3 | P a g e
9 DOA Delegation of Authority
10 EG Electronics Group
11 ERP Enterprise Resource Planning
12 GRN Goods Receipt Note
13 HOD Head of the Department
14 IQC Incoming Quality Control
15 LC Letter of Credit
16 LOI Letter of Indent
17 MIS Monthly Information System
18 NC Non Conformance
19 PE Power Electronics
20 PO Purchase Order
21 PR Purchase requisition
22 PU Purchase
23 QA Quality Assurance
24 QCS Quotation Comparison sheet
25 QM Quality Manual
26 RE Rail Electronics
27 RDSO Research Designs and Standards Organization of railway
28 RFQ Request for Quotation
29 SCAR Supplier Corrective Action Report
30 SO Service order
31 STO Stock Transfer Order
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 4 of 13
4 | P a g e
Contents
1.0 PURPOSE ................................................................................................................................. 5
2.0 SCOPE OF PURCHASE DEPARTMENT ............................................................................. 5
3.0 RELATED DOCUMENTS ........................................................................................................ 5
4.0 OBJECTIVES ........................................................................................................................... 5
5.0 CORE FUNCTIONS ................................................................................................................. 5
6.0 ORGANIZATION CHART ....................................................................................................... 7
7.0 ROLES & RESPONSIBILITIES .............................................................................................. 8
8.0 PROCESS FLOW CHART ...................................................................................................... 9
9.0 PROCUREMENT PROCESS ................................................................................................ 10
9.1 Purchase Requisition .................................................................................................... 10
9.2 Request for Quote (RFQ) .............................................................................................. 10
9.3 Processing of quotes .................................................................................................... 10
9.4 Letter of Intent (LOI) ...................................................................................................... 11
9.5 Purchase Order (PO) ..................................................................................................... 11
9.6 R & D, Job works ............................................................................................................ 12
9.7 Quality of purchased material ..................................................................................... 12
9.8 Supplier Quality .............................................................................................................. 12
9.8.1 Supplier Selection and Assessment…………………………………………………..……12
9.8.2 Supplier Corrective Action Request (SCAR)……………………………………………..13
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 5 of 13
5 | P a g e
1.0 PURPOSE
1.1 This procedure describes the purchasing process which ensures that the
purchased product conforms to requirements.
2.0 SCOPE OF PURCHASE DEPARTMENT
2.1 The Purchase department for Electronics Group is responsible for procurement
of materials needed for various business units like PE, RE, DCH and Electric
Drive Trains.
3.0 RELATED DOCUMENTS
4.0 OBJECTIVES
4.1 The primary objectives are procurement of required materials and services
from approved Sources at targeted price at the required time with an optimum procurement process cost and continually develop suppliers’ capability and quality to meet HBL needs
Sl.NO Document No Revision Description
1 EG-PU- FT-01 Rev1 Supplier Registration
2 EG-PU- FT-02 Rev0 Supplier Assessment
3 EG-PU- FT-03 Rev0 List of Approved
Suppliers
4 EG-PU -FT-04 Rev1 Supplier Evaluation
5 EG-PU -FT-05 Rev0 Supplier Audit Report
6 EG-PU- FT-06 Rev0
List of Out sourced
Processes & Control
Methods
7 EG-PU- FT-07 Rev0 SCAR
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 6 of 13
6 | P a g e
5.0 CORE FUNCTIONS
Procurement
Sourcing
(Identifying suppliers, approval process, continual rating )
Negotiation & OrderingFollow-up, payment
processing, Data Management & MIS
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 7 of 13
7 | P a g e
6.0 ORGANIZATION CHART
Head - Purchase & Projects
(GM Purchase)
RE - IPS, EI, PMM (EDT) and R&D
(Sr.Manager)
Rack-level, Systems soft & hardware, IPS services
& TMKT Plant Capex and Civil
(Engineer)
PCB components
(Engineer)
R& D, EDT PCB components, Hundi and
GST complainace
(Executive)
RE - TCAS , TMS DCH , EIS, RAIL R&D (LTE)
(Manager)
TCAS Electrical and Mechanical
(Engineer)
TCAS/TMS/DCH Electronic components
(TBD)
Industrial Electronics and R & D
(Sr.Manager)
Switchgear, Power & Mechanical + PE Capex
(Engineer)
PCB Components
(Engineer)
All Mechanical/Electrical/ANR / R& D devep, ISO Doc and
DCH Sevrices
(Engineer)
DRE
CHA, FF , Logistics, LCs & Admin purchases
(Sr.Executive)
EDT Mech Development, Sourcing and
Kaizen Projects
(Engineer)
EDT CAPEX/Old Trucks sourcing
(Engineer)
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 8 of 13
8 | P a g e
7.0 ROLES & RESPONSIBILITIES
HOD
The Head of Procurement is responsible to achieve the Electronic
Group’s procurement Objectives. Responsibilities include:
Organizing the Purchase department and assign roles and
responsibilities to managers
Defining appropriate procurement procedures for various contexts
Ensuring compliance to the defined procedures
Developing a framework for monitoring and measuring the
performance of Purchase department and communicating with
other stakeholders in the company
Mentoring the employees for their career growth
Manager
Each manager is responsible for procurement activities of an assigned
business unit.
Responsibilities include:
Supplier identification and development
Competitive bidding and price negotiation
Issue resolution
Performance measurement and reporting
Development of team
Executive/
Engineer
Each executive is responsible for procurement activities of an assigned
business unit.
Responsibilities include:
Obtaining quotations, preparing comparison statement and
purchase proposal
Creating PO as per approval
Initiating supplier payments as per PO terms
Tracking material receipt as per PO schedule
Issue resolution at inward QC and stores
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 9 of 13
9 | P a g e
8.0 PROCESS FLOW CHART
Receive PRs, consolidate items
and float RFQ
Prepare comparative statement of offers
received
Negotiate prices and payment terms with shortlisted suppliers
Create & Release Purchase Order as
per DOA
Follow up with suppliers and
organise clearances for shipment
Organize logistics
Coordinate with QC for Inward inspection and acceptance of
materials
Resolve issues with supplier non-conformities
Organize supplier payments
Periodic supplier performance
assessment & feedback
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 10 of 13
10 | P a g e
9.0 PROCUREMENT PROCESS
9.1 Purchase Requisition
Purchase process starts with the receipt of a PR, generated through SAP, by
the indenting department. PR shall have the following minimum details.
Material Number / Description and specifications
Quantity
Delivery date
Job number/Tracking/Valuation/Costing/Budget if any
9.2 Request for Quote (RFQ)
RFQ shall be sent to selected suppliers through e-mail enclosing drawings,
specifications, etc. RFQ shall also indicate the quantities and lead times
required for the components.
Suppliers shall be selected on the basis of recommendation by the indenting
department, or from the approved supplier list.
9.3 Processing of quotes
After the quotes are received, a comparative statement of received quotes shall
be prepared. The comparative statement shall include comparison of prices,
lead times and payment terms, along with any other relevant details.
The most suitable supplier shall be determined based on the
Comparative statement of prices, prices and lead times,
Tax payment history of the suppliers,
Past record of quality and delivery times etc.
Further negotiation shall be done with the selected supplier for price, payment
terms, delivery period etc. Wherever needed, the indenting department shall be
involved in the supplier selection decision.
The following delegation of authority (DOA) shall apply to all first-time purchase
orders.
Delegation
Level
Job title of
the employee
First-time Purchase
Order approval, Rs
A1 Executive Up to 75,000
A2 Manager 75,000 to 10,00,000
A3 HOD More than 10,00,000
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 11 of 13
11 | P a g e
When procurement is repeated, the new price of components shall be
compared with the last procurement price. The following DOA shall apply,
based on price variation.
9.4 Letter of Intent (LOI)
After a purchase decision is made, an LOI may be issued to the selected
supplier, if a delay is anticipated in releasing a formal purchase order for
administrative reasons. This is done in order to get the delivery time clock
started.
9.5 Purchase Order (PO)
Purchase Order is a legally enforceable Contract placed on a supplier with
mutually agreed price, terms and conditions on acceptance of the valid offer for
supply of the items/services stated therein.
All the purchase orders shall be issued through SAP only, and shall include
Description & Quantity of material / component / job work activities
Drawing number / specification number / standard
Requirements for inspection, CoC, test reports etc
Delivery schedule and payment terms
In case of any change in quantity, price, delivery or any other terms and
conditions mentioned in the PO, an amended purchase order shall be prepared
and issued to the suppliers.
Purchase
Order
value, Rs
Price is same
or less than
last purchase
price
Price is higher
than last
purchase price
by, up to 1%
Price is higher
than last
purchase price
by, 1 to 3%
Price is higher
than last
purchase price
by more than
3%
Up to
75,000 A1 A2
A3
A3 + Respective
Project or
Product Head +
EG Finance
Head
75,000 to
10,00,000 A2
A3 More than
10,00,000 A3
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 12 of 13
12 | P a g e
9.6 Job works
R&D or Operations team may decide to get some works sub-contracted. HBL
provides raw materials for such works, and the suppliers perform the required
operations. The periodic quality assessment is not applicable until unless
recommended for one time supply, Job work and services,.
Purchase department shall release a sub-contract order to an approved
supplier, after analyzing the work content and costing it appropriately. The
selection of the supplier is done in consultation with the indenting department.
List of out sourced processes & control methods will be updated in format table
EG-PU-FT-06 Rev0.
9.7 Quality of purchased material
Purchased materials shall be subject to quality and quantity checks, during
incoming inspection at HBL.
In some cases, the indenting department may require quality checks prior to
shipment from the supplier’s works. Purchase department shall organize such
inspections through HBL’s QC department or through a third party inspection
agency, as recommended by the indenting department.
Any non-conformances observed during the inspection shall be managed as
required by HBL’s QC procedures.
Purchase department shall indicate the inspection and documentation
requirements for all purchased materials in the PO. Documentation
requirements shall include requirement of CoC, test report, inspection data etc.
9.8 Supplier Quality
9.8.1 Supplier Selection and Assessment
Purchase department shall engage actively in carrying out supplier
capability assessment, prior to taking any new supplier on the approved
supplier list. Purchase department will do necessary Supplier
assessment report as per format EG-PU-FT-02 Rev0.
Based on the above report, Purchase will request for Vendor registration
using the Format EG-PU-FT-01 Rev 1,
Upon approval and registration of new vendor in the HBL SAP vendor
master, Supplier list will be updated in the format EG-PU-FT-03 Rev0
Suppliers shall be categorized on the basis of the criticality of their
supplies to HBL’s business. Based on this categorization, Vendor
Procedure for Purchase
Procedure No. EG-PU-PR-01
Revision No. 02
Page No: 13 of 13
13 | P a g e
evaluation shall be carried out time to time as per format EG-PU-FT-04
Rev 1.
Purchase department shall do necessary supplier evaluation through
SAP system, which was implemented.
Supplier quality assessment shall be done wherever required (ref clause
9.6) by a team consisting of Purchase, Quality and Engineering
departments. Purchase department shall coordinate such team activities.
All supplier quality assessments shall be documented, using the Suppler
Audit report EG-PU-FT-05 Rev0 as Supplier Quality Assessment.
Periodic re-assessment of the suppliers shall be done by the
assessment team. Supplier re-assessment is done on the basis of using
the same format with corrective actions.
Price competitiveness
Timely delivery
Quality of supplied materials
Responses and effectiveness of any agreed supplier corrective
actions
Purchase department shall prepare the necessary ranking for the
above points for an assessment of the suppliers. Re-assessment
reports shall be shared with the suppliers for corrective action.
Purchase department shall organize an annual supplier meeting, to
communicate HBL’s purchasing priorities, requirements and strategies
to the suppliers and also receive feedback from the suppliers on their
experiences.
9.8.2 Supplier Corrective Action Request (SCAR)
Wherever there is a trend of quality non-conformances with any
supplier, a corrective action shall be requested from such supplier. The
format for Supplier Corrective Action Request (<EG-PU-FT-07 Rev0
SCAR>) shall be used for documenting the trend of non-conformances
and the corrective actions proposed by the supplier.
Supplier corrective actions shall be reviewed and approved by the
supplier assessment team.