earned value analysis
DESCRIPTION
Earned Value Analysis. Cost Planning Cost Control Cost Reporting. €1. €1. €1. €1. €1. progress at milestone 1:. €1.50. €2.50. Earned Value Analysis. the original plan. BAC = Budget At Completion = €5. EV = €2. Only 2 tasks; both overspent. - PowerPoint PPT PresentationTRANSCRIPT
Earned Value Analysis
Cost Planning Cost Control
Cost Reporting
Earned Value Analysis
€1 €1 €1 €1 €1
the original plan
BAC = Budget At Completion = €5
progress at milestone 1:
€1.50
€2.50
Only 2 tasks; both overspent.We had planned to do €3 of work, but only ‘earned’ €2.Unfortunately it cost us €4 to do it.We can use the power of EVA to forecast the future…
EV = €2
Earned Value Analysis
If you, in the role of project manager, convince your customer that the project will cost xxx, and you also cost each task or major milestone along the way, then in the customer’s mind each task or milestone will be worth what you said.
So if you are so poor at controlling the project that a task has cost you twice the original estimate why should the customer pay for your incompetence?
This is the essence of EVA; you will only earn what the customer sees as the value of task. Many large organisations pay their contractors in this way
Earned Value Analysis – Jargon - 1
EV is Earned Value
PV is Planned Value
AC is Actual Cost
EV = €2
PV = €3AC = €4
Earned Value means the total value of the tasks we have actually completed by this timePlanned Value means the total value of the tasks we had meant to complete by this timeActual Cost means the total cost we have incurred getting to this point in time
From the original estimates
So What? – 1
EV is less than AC
AC is less than EV
PV is less than EV
PV is less than AC
IF:… We have spent more than we have earned
We have earned more than we have spent
We have earned more than we had planned
We have spent more than we had planned
The Graphs
time
costPV
AC
EV
The Actual Cost is running ahead of the Planned Value, therefore the project is over budget
The Earned Value is running behind Planned Value, therefore the project is behind schedule
This poor performance could have been identified here…
Earned Value Analysis – Jargon - 2
CV is Cost Variance; CV = EV - AC CV = 2 - 4 = -2
SV is Schedule Variance; SV = EV - PV
SV = 2 - 3 = -1
We can look at variance:
A negative variance is BAD…
Earned Value Analysis – Jargon - 3
CPI is Cost Performance Index; CPI = EV/AC CPI = 2/4 = 0.5
EAC is Estimate At Completion; EAC = BAC/CPI
EAC = 5/0.5 = 10
We can extrapolate from the current position:….
Warning: may be a naive assumption:…
Everything we do seems to cost us twice what we had planned:…
So What? - 2
EAC is Estimate At Completion; EAC = BAC/CPI
EAC = 5/0.5 = 10
This is only true if all future tasks overrun at the same rate as now. If we think we have fixed the problems behind the current cost overrun then a better EAC formula is:…
EAC = AC + Remaining PVEAC = AC + (BAC-EV)
EAC = 4 +(5-2) = 7
This is a much smaller EAC, but remember our premise…
Earned Value Analysis – Jargon - 4
EAC is Estimate At Completion; EAC = BAC/CPI
EAC = 5/0.5 = 10
The EAC is obviously a really important figure in the overall cost control for the project, but there is another figure that many people will want to know:…
ETC is Estimate to Complete, meaning how much more money will it take to finish this project. ETC is easy to compute.
ETC = EAC - AC ETC = 10 – 4 = 6
Earned Value Analysis – Jargon - 5
EV = €2 PV = €3
AC = €4
CPI = 2/4 = 0.5
SPI is Schedule Performance Index; SPI = EV/PV
SPI = 2/3 = 0.66
More extrapolation, albeit slightly more risky. We know that every task we have finished seems to be taking longer than planned, so maybe we can infer that all future tasks will overrun their schedule by a similar amount. This means we can calculate a Schedule Performance Index, as follows:
So if the original duration was 5, the new duration could be:OD/SPI = 5/0.66 = 7.6
Earned Value Analysis
EVA can be a powerful tool for forecasting outturnit requires accurate estimating as well as controlIt assumes future cost performance will be similar to current
1.01.11.2
0.9
0.8 Lower Control Limit
Upper Control Limit
Classroom Practice - 1
All figures are cumulative
month PV AC EV
1 1000 1000 1000
2 2000 2500 2000
3 3000 4000 3000
4 7000 8000 6000
5 12000
6 14000
7 18000
8 20000
1. What is the CPI at the end of month 4
2. What is the SPI at the end of month 4
3. What is the EAC at the end of month 4
4. What is the ETC at the end of month 4
Classroom Practice - 2
All figures are cumulative
month PV AC EV
1 1000 1000 1000
2 2000 2500 2000
3 3000 4000 3000
4 7000 8000 6000
5 12000
6 14000
7 18000
8 20000
1. What is the CV at the end of month 4
2. What is the SV at the end of month 4
3. If all the work completed in Month 4 fails quality testing, and has to be reworked in Month 5, meaning that none of Month 5’s tasks can be completed:3a. What is the EV at the end of month 5
3b. What is the AC at the end of month 5
3c. What is the CPI at the end of month 5