demystifying earned value analysis

38
Presented by Tim Pyron Presented by Tim Pyron Author: Que’s Author: Que’s Special Edition Using Microsoft Project 2002 Special Edition Using Microsoft Project 2002 Que’s Que’s Special Edition Using Microsoft Project 2000 Special Edition Using Microsoft Project 2000 SAMS Teach Yourself Microsoft Project 2000 in 24 Hours SAMS Teach Yourself Microsoft Project 2000 in 24 Hours Editor: Editor: Woody's Project Watch Woody's Project Watch (www.woodyswatch.com) Phone: (210)822-0839 Email: Phone: (210)822-0839 Email: [email protected] Demystifying Demystifying Earned Value Analysis Earned Value Analysis Kansas City MPUG Chapter Kansas City MPUG Chapter June 18, 2002 June 18, 2002

Upload: chas

Post on 04-Jan-2016

109 views

Category:

Documents


5 download

DESCRIPTION

Demystifying Earned Value Analysis. Kansas City MPUG Chapter June 18, 2002. Overview. Understanding Earned Value Analysis Understanding the EV metrics Project’s Earned Value calculations Graphing Earned Value metrics in Excel Conclusion. What is Earned Value Analysis. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Demystifying  Earned Value Analysis

Presented by Tim PyronPresented by Tim PyronAuthor:  Que’s Author:  Que’s Special Edition Using Microsoft Project 2002Special Edition Using Microsoft Project 2002 Que’s Que’s Special Edition Using Microsoft Project 2000Special Edition Using Microsoft Project 2000             SAMS Teach Yourself Microsoft Project 2000 in 24 Hours           SAMS Teach Yourself Microsoft Project 2000 in 24 Hours

Editor:    Editor:    Woody's Project WatchWoody's Project Watch (www.woodyswatch.com) Phone: (210)822-0839 Email: Phone: (210)822-0839 Email: [email protected]

Demystifying Demystifying Earned Value AnalysisEarned Value Analysis

Kansas City MPUG Chapter Kansas City MPUG Chapter

June 18, 2002June 18, 2002

Page 2: Demystifying  Earned Value Analysis

2

OverviewOverview

• Understanding Earned Value AnalysisUnderstanding Earned Value Analysis

• Understanding the EV metricsUnderstanding the EV metrics

• Project’s Earned Value calculationsProject’s Earned Value calculations

• Graphing Earned Value metrics in ExcelGraphing Earned Value metrics in Excel

• ConclusionConclusion

Page 3: Demystifying  Earned Value Analysis

3

What is Earned Value AnalysisWhat is Earned Value Analysis

• EVA is the tool used by those who EVA is the tool used by those who practice Earned Value Managementpractice Earned Value Management

• EVA provides early warning signals of EVA provides early warning signals of troubletrouble

• EVA provides a basis for revising the EVA provides a basis for revising the plan (and maybe the goals) in order to plan (and maybe the goals) in order to get back on trackget back on track

• EVA provides a basis for estimating EVA provides a basis for estimating final costs and the project finish date.final costs and the project finish date.

Page 4: Demystifying  Earned Value Analysis

4

What’s wrong with using Variances?What’s wrong with using Variances?

• Each variance shows a different aspect of Each variance shows a different aspect of progress in its own units; and comparing progress in its own units; and comparing dollars and time makes it difficult to assess dollars and time makes it difficult to assess your net positionyour net position

• EVA measures everything in dollarsEVA measures everything in dollars

• Variances don’t show if productivity is at the Variances don’t show if productivity is at the levels you plannedlevels you planned

• EVA measures productivity up through the EVA measures productivity up through the status datestatus date

Page 5: Demystifying  Earned Value Analysis

5

Figure 1 (Simple Cost Variance)Figure 1 (Simple Cost Variance)

Page 6: Demystifying  Earned Value Analysis

6

History of Earned Value AnalysisHistory of Earned Value Analysis

• Started with defense contractsStarted with defense contracts

• Originally used to justify staged Originally used to justify staged payments for projects in progresspayments for projects in progress

• Now widespread in private sector alsoNow widespread in private sector also

• Is becoming a world-wide standardIs becoming a world-wide standard

Page 7: Demystifying  Earned Value Analysis

7

Example: Using variancesExample: Using variances

Baseline duration is 1 Year (Jan – Dec)Baseline duration is 1 Year (Jan – Dec)

Baseline cost is $1,000,000Baseline cost is $1,000,000

Baseline work is scheduled to be 50% complete as of June 30Baseline work is scheduled to be 50% complete as of June 30

Baseline cost through June 30 is $500,000Baseline cost through June 30 is $500,000

Actuals on June 30: 60% of work is completedActuals on June 30: 60% of work is completed Actual Cost is $550,000 Actual Cost is $550,000 Cost is $1,050,000 Cost is $1,050,000 *Cost = Remaining Cost + Actual Cost*Cost = Remaining Cost + Actual Cost

$ 50,000$ 50,000

????

What is the Cost Variance?What is the Cost Variance?

Does that mean the project will go over budget?Does that mean the project will go over budget?That there’s not enough in the budget to finish the project?That there’s not enough in the budget to finish the project?

Page 8: Demystifying  Earned Value Analysis

8

Example: Using EVAExample: Using EVA

Baseline duration is 1 Year (Jan – Dec)Baseline duration is 1 Year (Jan – Dec)

Baseline cost is $1,000,000Baseline cost is $1,000,000

Baseline work is scheduled to be 50% complete as of June 30Baseline work is scheduled to be 50% complete as of June 30

Baseline cost through June 30 is $500,000Baseline cost through June 30 is $500,000

Actuals on June 30: 60% of work is completedActuals on June 30: 60% of work is completed Actual Cost is $550,000 Actual Cost is $550,000 Cost is $1,050,000 Cost is $1,050,000 *Cost = Remaining Cost + Actual Cost*Cost = Remaining Cost + Actual Cost

$500,000$500,000

$600,000$600,000

How much was How much was plannedplanned to be earned? to be earned?

How much of that value has been How much of that value has been earnedearned by June 30 by June 30??

$550,000$550,000What did it What did it actually costactually cost ? ?

$1,000,000$1,000,000What is the planned value of this project?What is the planned value of this project?

Page 9: Demystifying  Earned Value Analysis

9

Planned Value (PV)Planned Value (PV)

• PV is that part of the project/task’s PV is that part of the project/task’s value we plan to be completed up value we plan to be completed up through the through the status datestatus date..

• PMBOK formerly called PV thePMBOK formerly called PV theBBudgeted udgeted CCost of ost of WWork ork SScheduled orcheduled orBCWSBCWS..

• Total Baseline Cost called BACTotal Baseline Cost called BAC(Budgeted at Completion)(Budgeted at Completion)

Page 10: Demystifying  Earned Value Analysis

10

Earned Value (EV)Earned Value (EV)

• EV is the planned value of the EV is the planned value of the completed portion of the project/taskcompleted portion of the project/task

• EV = % Work Complete * Baseline CostEV = % Work Complete * Baseline Cost Note that % Work Complete uses Note that % Work Complete uses currently currently scheduledscheduled work – not baseline work. Example: work – not baseline work. Example: Baseline Work = 10h Actual Work = 5 h Baseline Work = 10h Actual Work = 5 h Scheduled Work = 15h % Work Complete = 33% Scheduled Work = 15h % Work Complete = 33%

BAC = $1,000 Earned Value = $333BAC = $1,000 Earned Value = $333

• PMBOK formerly called EV thePMBOK formerly called EV theBBudgeted udgeted CCost of ost of WWork ork PPerformed or erformed or BCWPBCWP

Page 11: Demystifying  Earned Value Analysis

11

Actual Costs (AC)Actual Costs (AC)

• AC is the actual cost of work that was AC is the actual cost of work that was completed as of the status datecompleted as of the status date

• PMBOK formerly called this thePMBOK formerly called this theAActual ctual CCost of ost of WWork ork PPerformed orerformed orACWP.ACWP.

Page 12: Demystifying  Earned Value Analysis

12

Prerequisites for using EVAPrerequisites for using EVA

• Work and cost must be distributed over time Work and cost must be distributed over time (Microsoft Project’s timephased data)(Microsoft Project’s timephased data)

• The must capture the baselineThe must capture the baseline

• You must define a Status Date for assessing You must define a Status Date for assessing performance (Project, Project Information)performance (Project, Project Information)

• You must track actual start and finish dates, You must track actual start and finish dates, work, and costs; and you must reschedule work, and costs; and you must reschedule work not completed on time and work that is work not completed on time and work that is completed ahead of schedule. completed ahead of schedule.

Page 13: Demystifying  Earned Value Analysis

13

The Sample TaskThe Sample Task

Task 1 Task 1

• Duration = 4 days Duration = 4 days

• Abe is assigned 100% to the taskAbe is assigned 100% to the task

• Abe's standard rate is $1/hr. Abe's standard rate is $1/hr.

• Figure 1 illustrates the task and Abe's Figure 1 illustrates the task and Abe's assignment before any actual work is assignment before any actual work is recorded. recorded.

Page 14: Demystifying  Earned Value Analysis

14

Figure 2 (Before actuals)Figure 2 (Before actuals)

Page 15: Demystifying  Earned Value Analysis

15

Figure 3 (Task is 50% Complete)Figure 3 (Task is 50% Complete)

Page 16: Demystifying  Earned Value Analysis

16

Planned Value and Earned Value Planned Value and Earned Value • Are equal if everything goes as plannedAre equal if everything goes as planned

• Both use Baseline Cost for different amounts Both use Baseline Cost for different amounts of work (planned vs actual) of work (planned vs actual)

• Any difference is due to the amount of work Any difference is due to the amount of work completed by the status datecompleted by the status date

• Differences can arise when (for example): Differences can arise when (for example): • Estimated work changes after the baseline was Estimated work changes after the baseline was

capturedcaptured• Overtime is used but not scheduled (or vice versa)Overtime is used but not scheduled (or vice versa)• Resources are diverted to higher priority tasks or Resources are diverted to higher priority tasks or

projects.projects.

Page 17: Demystifying  Earned Value Analysis

17

SV: Earned Value Schedule VarianceSV: Earned Value Schedule Variance

• Equals Earned Value minus Planned Value Equals Earned Value minus Planned Value

• SV = Earned Value – Planned ValueSV = Earned Value – Planned ValueSV = BCWP – BCWSSV = BCWP – BCWSTask1: $16 – $24 = - $8Task1: $16 – $24 = - $8

• Positive SV means more work completed than Positive SV means more work completed than planned. If continued, project may finish earlyplanned. If continued, project may finish early Might be possible to transfer some resources to Might be possible to transfer some resources to

other tasks or projectsother tasks or projects

• Negative SV means work is not being Negative SV means work is not being completed on time. Project might finish late completed on time. Project might finish late PM should determine the cause to avoid missing PM should determine the cause to avoid missing

the finish goal.the finish goal.

Page 18: Demystifying  Earned Value Analysis

18

Figure 4 (SV, SV%, SPI)Figure 4 (SV, SV%, SPI)

Page 19: Demystifying  Earned Value Analysis

19

SV%: Schedule Variance PercentSV%: Schedule Variance Percent

• Expresses SV as a % of Planned ValueExpresses SV as a % of Planned Value

• SV% = SV / PV SV% = SV / PV = (BCWP – BCWS) / BCWS = (BCWP – BCWS) / BCWS

Task1: ( $16 – $24 )/ $24 = – 33%Task1: ( $16 – $24 )/ $24 = – 33%

That means 33% of planned work was not finishedThat means 33% of planned work was not finished

• SV% is useful when comparing SV between projects SV% is useful when comparing SV between projects of vastly different sizesof vastly different sizes

Page 20: Demystifying  Earned Value Analysis

20

SPI: Schedule Performance IndexSPI: Schedule Performance Index

• Most important version of SVMost important version of SV

• Is ratio of Earned Value to Planned ValueIs ratio of Earned Value to Planned Value SPI = EV / PV = BCWP / BCWS SPI = EV / PV = BCWP / BCWS

Task1: $16 / $24 = 0.67Task1: $16 / $24 = 0.67

• SPI < 1.0 is unfavorableSPI < 1.0 is unfavorable SPI = 0.67 means we earned only $0.67 of every $1 SPI = 0.67 means we earned only $0.67 of every $1

we planned to earn this periodwe planned to earn this period

• SPI > 1.0 is favorableSPI > 1.0 is favorable SPI = 1.25 would mean we earned $1.25 for every SPI = 1.25 would mean we earned $1.25 for every

$1 we planned to earn during this period.$1 we planned to earn during this period.

Page 21: Demystifying  Earned Value Analysis

21

SPI: Revise Estimated DurationSPI: Revise Estimated Duration

• Use SPI to revise estimated total duration,Use SPI to revise estimated total duration,thus the new estimated finish datethus the new estimated finish date

• Assumes current SPI will continue to end of Assumes current SPI will continue to end of projectproject

• Revised Remaining Duration (Rem.Dur.)Revised Remaining Duration (Rem.Dur.) = Remaining Duration / SPI = Remaining Duration / SPITask 1: = 2d / 0.67 = 3dTask 1: = 2d / 0.67 = 3d

• Finish Date = Status Date + Rem. Duration Finish Date = Status Date + Rem. Duration Task 1: = Day 3 + 3d = Day 6Task 1: = Day 3 + 3d = Day 6

Page 22: Demystifying  Earned Value Analysis

22

Earned Value and Actual Costs Earned Value and Actual Costs

• Are equal if everything goes as plannedAre equal if everything goes as planned

• Both use Actual Work, but it’s valued at Both use Actual Work, but it’s valued at different costs (planned vs actual) – any different costs (planned vs actual) – any difference is due to the cost of the workdifference is due to the cost of the work

• Differences can arise when (for example):Differences can arise when (for example):• Unplanned overtime was usedUnplanned overtime was used

• Resource cost rates changedResource cost rates changed

• Higher cost resources were substitutedHigher cost resources were substituted

• Earned Value minus Actual Costs is the Earned Value minus Actual Costs is the Earned Value Cost Variance: CV = EV – ACEarned Value Cost Variance: CV = EV – AC

Page 23: Demystifying  Earned Value Analysis

23

Figure 5 (substitute more costly resource)Figure 5 (substitute more costly resource)

Page 24: Demystifying  Earned Value Analysis

24

Figure 6 (CV, CV%, CPI)Figure 6 (CV, CV%, CPI)

Page 25: Demystifying  Earned Value Analysis

25

CV: Earned Value Cost VarianceCV: Earned Value Cost Variance

• CV = Earned Value – Actual CostsCV = Earned Value – Actual Costs

• CV = BCWP – ACWPCV = BCWP – ACWPTask 1: $16 – $20 = – $4Task 1: $16 – $20 = – $4

• Positive CV is favorable: the value of the work Positive CV is favorable: the value of the work was greater than the cost of producing it.was greater than the cost of producing it.

• Negative CV is unfavorable: the value of the Negative CV is unfavorable: the value of the work is less than the cost of producing it.work is less than the cost of producing it.

Page 26: Demystifying  Earned Value Analysis

26

CV%: Cost Variance PercentCV%: Cost Variance Percent

• Expresses CV as a % of Earned ValueExpresses CV as a % of Earned Value

• CV% = CV / EV CV% = CV / EV = (BCWP – ACWP) / BCWP = (BCWP – ACWP) / BCWPTask 1: = ( $16 – $20 ) / $16 = - 25%Task 1: = ( $16 – $20 ) / $16 = - 25%That means 25% of planned work was not That means 25% of planned work was not finishedfinished

• CV% is useful when comparing CV between CV% is useful when comparing CV between projects of vastly different sizesprojects of vastly different sizes

Page 27: Demystifying  Earned Value Analysis

27

CPI: Cost Performance IndexCPI: Cost Performance Index

• Most important version of CVMost important version of CV

• Is ratio of Earned Value to Actual CostIs ratio of Earned Value to Actual Cost CPI = EV / AC = BCWP / ACWP CPI = EV / AC = BCWP / ACWPTask1: $16 / $ 20 = 0.80Task1: $16 / $ 20 = 0.80

• CPI < 1.0 is unfavorableCPI < 1.0 is unfavorable

If CPI = 0.80 means for every dollar of actual cost If CPI = 0.80 means for every dollar of actual cost we produce work worth only $0.80 we produce work worth only $0.80

• CPI > 1.0 is favorableCPI > 1.0 is favorable

IF CPI = 1.25 it would mean that for every $1 we IF CPI = 1.25 it would mean that for every $1 we actually spent we produced work worth $1.25actually spent we produced work worth $1.25

• Use CPI to calculate if project will go over budget and Use CPI to calculate if project will go over budget and by how much by how much

Page 28: Demystifying  Earned Value Analysis

28

Estimate to Complete (ETC)Estimate to Complete (ETC)

• What will it cost to finish the remaining What will it cost to finish the remaining budgeted work (budgeted work (unearned unearned value) assuming value) assuming the current CPI will continue to the end of the the current CPI will continue to the end of the project?project?

• DivideDivide remaining budgeted work by CPIremaining budgeted work by CPI

• Remaining budgeted work = BAC - EVRemaining budgeted work = BAC - EV *BAC is Budgeted At Completion (Baseline Cost)*BAC is Budgeted At Completion (Baseline Cost)

• ETC = (BAC – EV ) / CPIETC = (BAC – EV ) / CPITask 1: ( $32 – $16 ) / 0.80 = $20Task 1: ( $32 – $16 ) / 0.80 = $20

Page 29: Demystifying  Earned Value Analysis

29

Estimate at Completion (EAC)Estimate at Completion (EAC)

• A revised total cost at completionA revised total cost at completion

• EAC = AC + ETCEAC = AC + ETCTask 1: $20 + $20 = $40Task 1: $20 + $20 = $40

• Project 2002 now calculates EAC this Project 2002 now calculates EAC this wayway

• The new Earned Value Cost Indicators The new Earned Value Cost Indicators table shows EAC, BAC, and VAC table shows EAC, BAC, and VAC (Vac = Variance at Completion)(Vac = Variance at Completion)

Page 30: Demystifying  Earned Value Analysis

30

Figure 7: (BAC, EAC, VAC, TCPI)Figure 7: (BAC, EAC, VAC, TCPI)

Page 31: Demystifying  Earned Value Analysis

31

TCPI: To Complete Performance IndexTCPI: To Complete Performance Index

Is there enough left in the budget to complete the project?Is there enough left in the budget to complete the project?

• (BAC – BCWP) (Budgeted cost of unfinished work) (BAC – BCWP) (Budgeted cost of unfinished work) --------------------- = --------------------------------------------------------------------- = ------------------------------------------------(BAC – ACWP) (Unspent Budget)(BAC – ACWP) (Unspent Budget)

* *where BAC = Baseline Costwhere BAC = Baseline Cost

• Task1: = ($32 - $16) / ($32 - $20) Task1: = ($32 - $16) / ($32 - $20) = 16 / 12 = 1.33 = 16 / 12 = 1.33

• If TCPI > 1: Not enough in the budget to complete the planned If TCPI > 1: Not enough in the budget to complete the planned work. Must increase productivity or reduce scope or quality.work. Must increase productivity or reduce scope or quality.

• If TCPI < 1: Running under budget. Could increase scope or If TCPI < 1: Running under budget. Could increase scope or quality, or can increase contract profitquality, or can increase contract profit

Page 32: Demystifying  Earned Value Analysis

32

Summary of EV MetricsSummary of EV MetricsThree core metricsThree core metrics

Planned Value PV (BCWS)Planned Value PV (BCWS)

Earned Value EV (BCWP)Earned Value EV (BCWP)

Actual Costs AC (ACWP)Actual Costs AC (ACWP)

VariancesVariances

Schedule Variance SV = EV-PV; SV% = SV/PVSchedule Variance SV = EV-PV; SV% = SV/PV

Cost Variance CV = EV-AC; CV% = CV/EVCost Variance CV = EV-AC; CV% = CV/EV

Indicators (performance indexes)Indicators (performance indexes)

Schedule Performance Index SPI = EV/PVSchedule Performance Index SPI = EV/PV

Cost Performance Index CPI = EV/ACCost Performance Index CPI = EV/AC

To Complete Performance Index TCPI = (BAC-EV)/(BAC-AC)To Complete Performance Index TCPI = (BAC-EV)/(BAC-AC)

Page 33: Demystifying  Earned Value Analysis

33

MS Project’s EV CalculationMS Project’s EV Calculation

For Assignments:For Assignments:EV = % Work Complete * BACEV = % Work Complete * BAC

For Tasks:For Tasks:

1.1. Calculate Actual Duration ( = % Complete * Calculate Actual Duration ( = % Complete * Duration)Duration)

2.2. Sum timephased Baseline Cost for periods Sum timephased Baseline Cost for periods spanned by Actual Durationspanned by Actual Duration

Note: Assignments are not rolled-up to the task. Note: Assignments are not rolled-up to the task. So, Sum of Assignment EV’s <> Task EV So, Sum of Assignment EV’s <> Task EV

Page 34: Demystifying  Earned Value Analysis

34

Work around: How to con Project intoWork around: How to con Project into using % Work Complete using % Work Complete

1.1. Work with a backup copy of the project fileWork with a backup copy of the project file

2.2. Choose Tools, Options, Calculation tab: Choose Tools, Options, Calculation tab: Disable Disable Updating task status updates resource statusUpdating task status updates resource status

3.3. Add Add % Complete % Complete and and % Work Complete% Work Complete columns to the Earned Value tablecolumns to the Earned Value table

4.4. Copy Copy % Work Complete% Work Complete column column into into % Complete% Complete column column

* Assignments still don’t roll up to tasks, but …* Assignments still don’t roll up to tasks, but …

Page 35: Demystifying  Earned Value Analysis

37

Generating EV GraphsGenerating EV Graphs

• Graphing EV metrics reveals trends Graphing EV metrics reveals trends

over timeover time

• Use Analysis Toolbar:Use Analysis Toolbar:

Analyze Timescaled Data in Excel Analyze Timescaled Data in Excel

• Adjust data and graph formatsAdjust data and graph formats

Page 36: Demystifying  Earned Value Analysis

38

Figure 9 Plain EV GraphFigure 9 Plain EV Graph

Page 37: Demystifying  Earned Value Analysis

39

Figure 10 BCWS extended to Finish DateFigure 10 BCWS extended to Finish Date

Page 38: Demystifying  Earned Value Analysis

40

Figure 11 PV, EV, AC, SV, and CVFigure 11 PV, EV, AC, SV, and CV