draft basic assessment reportnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts...

59
DRAFT BASIC ASSESSMENT REPORT UPGRADE OF CULVERTS ON ALLANDALE ROAD City of Johannesburg Metropolitan Municipality Gaut: 002/16-17/E0278 For: FEBRUARY 2017

Upload: others

Post on 28-Apr-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

DRAFT BASIC ASSESSMENT REPORT

UPGRADE OF CULVERTS ON ALLANDALE ROAD

City of Johannesburg Metropolitan Municipality

Gaut: 002/16-17/E0278

For:

FEBRUARY 2017

Page 2: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

1

TABLE OF CONTENTS

SECTION A: ACTIVITY INFORMATION 5

1. ACTIVITY DESCRIPTION 5

2. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES 5

3. ALTERNATIVES 8

4. PHYSICAL SIZE OF THE ACTIVITY 9

5. SITE ACCESS 9

6. SITE OR ROUTE PLAN 10

7. SITE PHOTOGRAPHS 11

8. FACILITY ILLUSTRATION 11

SECTION B: DESCRIPTION OF RECEIVING ENVIRONMENT 12

1. PROPERTY DESCRIPTION 12

2. ACTIVITY POSITION 12

3. GRADIENT OF THE SITE 13

4. LOCATION IN LANDSCAPE 13

5. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE 13

6. AGRICULTURE 14

7. GROUNDCOVER 15

8. LAND USE CHARACTER OF SURROUNDING AREA 16

9. SOCIO-ECONOMIC CONTEXT 18

10. CULTURAL/HISTORICAL FEATURES 19

SECTION C: PUBLIC PARTICIPATION 20

1. ADVERTISEMENT 20

2. LOCAL AUTHORITY PARTICIPATION 20

3. CONSULTATION WITH OTHER STAKEHOLDERS 20

4. GENERAL PUBLIC PARTICIPATION REQUIREMENTS 20

5. APPENDICES FOR PUBLIC PARTICIPATION 20

SECTION D: RESOURCE USE AND PROCESS DETAILS 21

1. WASTE, EFFLUENT, AND EMISSION MANAGEMENT 21

2. WATER USE 23

3. POWER SUPPLY 23

4. ENERGY EFFICIENCY 23

SECTION E: IMPACT ASSESSMENT 24

1. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES 24

2. IMPACTS RESULTING FROM THE CONSTRUCTION AND OPERATIONAL PHASE 24

3. IMPACTS RESULTING FROM THE DECOMISSIONING AND CLOSURE PHASE 32

4. CUMULATIVE IMPACTS 32

5. ENVIRONMENTAL IMPACT STATEMENT 33

6. IMPACT SUMMARY OF PREFERRED PROPOSAL 33

7. SPATIAL DEVELOPMENT TOOLS 35

8. RECOMMENDATION OF THE PRACTITIONER 35

9. THE NEEDS AND DESIRABILITY OF THE PROPOSED DEVELOPMENT 35

10. THE PERIOD FOR WHICH THE ENVIRONMENTAL AUTHORISATION IS REQUIRED 36

11. ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) 36

Page 3: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

2

SECTION F: APPENDICES 37

Appendix A: Locality Maps

Appendix A¹: Locality Plan

Appendix A²: Layout Plan

Appendix B: Site Photographs

Appendix C: Facility illustration(s)

Appendix D: Route position information

Appendix E: Public Participation information

Appendix E¹: Proof of Notices

Appendix E²: Written Notices Issued

Appe di Eᵌ: Ne spape Ad e t

Appe di E : Minutes of Meetings

Appe di E : Co e ts of Issues ‘epo t

Appe di E : Co e ts a d I&Aps o BA‘

Appe di E : Cop of ‘egiste of I&Aps

Appendix F: Water use license(s) authorization, SAHRA information, service letters from municipalities, water supply

information

Appendix G: Specialist reports

Appendix G¹: Wetland Assessment Report

Appendix G²: Surface Water Rehabilitation and Management Plan

Appe di Gᵌ: Construction Method Statement

Appendix H: Draft EMPr

Appendix I: Other information

Page 4: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

3

Basic Assessment Report in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended, and the Environmental Impact Assessment Regulations, 2014 (Version 1)

Kindly note that: 1. This Basic Assessment Report is the standard report required by GDARD in terms of the EIA Regulations, 2014.

2. This application form is current as of 8 December 2014. It is the responsibility of the EAP to ascertain whether subsequent versions

of the form have been published or produced by the competent authority.

3. A draft Basic Assessment Report must be submitted, for purposes of comments within a period of thirty (30) days, to all State Departments administering a law relating to a matter likely to be affected by the activity to be undertaken.

4. A draft Basic Assessment Report (1 hard copy and two CD’s) must be submitted, for purposes of comments within a period of thirty (30) days, to a Competent Authority empowered in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended to consider and decide on the application.

5. Five (5) copies (3 hard copies and 2 CDs-PDF) of the final report and attachments must be handed in at offices of the relevant competent authority, as detailed below.

6. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.

7. Selected boxes must be indicated by a cross and, when the form is completed electronically, must also be highlighted.

8. An incomplete report may lead to an application for environmental authorisation being refused.

9. Any report that does not contain a titled and dated full colour large scale layout plan of the proposed activities including a coherent legend, overlain with the sensitivities found on site may lead to an application for environmental authorisation being refused.

10. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the application for environmental authorisation being refused.

11. No faxed or e-mailed reports will be accepted. Only hand delivered or posted applications will be accepted.

12. Unless protected by law, and clearly indicated as such, all information filled in on this application will become public information on receipt by the competent authority. The applicant/EAP must provide any interested and affected party with the information contained in this application on request, during any stage of the application process.

13. Although pre-application meeting with the Competent Authority is optional, applicants are advised to have these meetings prior to

submission of application to seek guidance from the Competent Authority. DEPARTMENTAL DETAILS Gauteng Department of Agriculture and Rural Development Attention: Administrative Unit of the of the Environmental Affairs Branch P.O. Box 8769 Johannesburg 2000 Administrative Unit of the of the Environmental Affairs Branch Ground floor Diamond Building 11 Diagonal Street, Johannesburg Administrative Unit telephone number: (011) 240 3377 Department central telephone number: (011) 240 2500

(For official use only)

Page 5: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

4

If this BAR has not been submitted within 90 days of receipt of the application by the competent authority

and permission was not requested to submit within 140 days, please indicate the reasons for not submitting

within time frame.

N/A

Is a closure plan applicable for this application and has it been included in this report? if not, state

reasons for not including the closure plan.

No closure of the road/culverts is anticipated

Has a draft report for this application been submitted to a competent authority and all State

Departments administering a law relating to a matter likely to be affected as a result of this

activity?

Is a list of the State Departments referred to above attached to this report including their full contact

details and contact person?

If no, state reasons for not attaching the list.

N/A

Have State Departments including the competent authority commented?

If no, why?

Report has been submitted to state departments. Comments will be included in the Final Report

NEAS Reference Number:

File Reference Number:

Application Number:

Date Received:

No

Yes

Yes

No

Page 6: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

5

SECTION A: ACTIVITY INFORMATION

1. PROPOSAL OR DEVELOPMENT DESCRIPTION

Project title (must be the same name as per application form):

The upgrading and extension of the existing 3 culvert bridges on Allandale Road as part of the associated

infrastructure upgrade for the Kyalami Gardens Ext 27 development on the Remainder of Portion 2 and

the Remaining Extent of Portion 88 of the Farm Bothasfontein 408 JR, City of Johannesburg Metropolitan

Municipality.

Select the appropriate box The application is for an upgrade

of an existing development

X The application is for a new

development

Other, specify

Does the activity also require any authorisation other than NEMA EIA authorisation?

YES NO

If yes, describe the legislation and the Competent Authority administering such legislation

A Water Use License is required in terms of the National Water Act and the competent authority is

Department of Water and Sanitation. A Water Use License application has already been submitted.

If yes, have you applied for the authorisation(s)? YES NO

If yes, have you received approval(s)? (attach in appropriate appendix) YES NO

2. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES

List of legislation, policies and/or guidelines that are applicable to the application

Title of legislation, policy or guideline: Administering authority: Promulgation Date:

National Environmental Management Act, 1998 (Act

No. 107 of 1998 as amended).

National & Provincial 27 November 1998

EIA Regulations GN 983 & GN 985 (Listing Notice 1&3) National and Provincial 8 December 2014

The National Water Act, 1998 (Act No. 36 of 1998) National Department of

Water and Sanitation

26 August 1998

The National Environmental Management: Waste Act,

2008 (Act No. 59 of 2008

National & Provincial 2008

National Environmental Management: Air Quality Act,

2004 (Act 39 of 2004) (NEM: AQA)

National & Local 24 February 2005

Occupational Health and Safety Act (No 85 of 1993) National Department of

Labour

23 June 1993

Gauteng Provincial Environmental Management

Framework

Provincial May 2015

Red List Plant Species Guidelines Provincial 26 June 2006

Gauteng Noise Control Regulations, 1999 Provincial 1999

Gauteng Urban Edge Provincial 2009

Regional Spatial Development Framework 2010/2011- Administrative Region A

City of Johannesburg 2011

Johannesburg Open Space Management Framework City of Johannesburg 2002

Page 7: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

6

Description of compliance with the relevant legislation, policy or guideline:

Legislation, policy of guideline Description of compliance

National Environmental

Management Act No. 107 of

1998 (NEMA)

The National Environmental Management Act (Act No. 107 of 1998)

(NEMA) is the overarching framework for environmental legislation as

well as the Regulations for Environmental Impact Assessment. It sets out

the principles that serve as a general framework for environmental

planning, as guidelines by reference to which organs of state must

exercise their functions and guide other laws concerned with the

protection or management of the environment. The application takes

into account the environmental and socio-economic conditions in

compliance with the NEMA principles.

The National Environmental

Management: Biodiversity Act

(Act 10 of 2004)

The Act provides for the management and conservation of South

Af i a s iodi e sit ithi the f a e o k of the NEMA. A eas of high biodiversity need to be protected. Should any protected plants be found

on site, these will be managed in consultation with GDARD

The National Environmental

Management: Waste Act, 2008

(Act No. 59 of 2008

No waste management license would be required for the construction

of the proposed activity. Only a limited amount of solid construction

waste will be stored and handled on the site, before being hauled away

and dumped at the nearest registered landfill site.

The National Water Act, 1998

(Act No. 36 of 1998)

The A t p o ides fo the a age e t of “outh Af i a s ate esou es. It ai s to e su e that the ‘epu li s ate esou es a e p ote ted, used, developed, conserved and controlled. According to the Act, any

proposed water uses must be specified and registered and/or licensed.

Similarly, any modifications to drainage lines on site must be

investigated in terms of water use requirements.

The proposed development will require a water use licences, of which

an application thereof has been sent to the relevant authority.

National Environmental

Management: Air Quality Act,

2004 (Act 39 of 2004) (NEM:

AQA)

During the construction phase, dust and the generation of noise can

become a significant factor, especially to the surrounding landowners.

However, if the development is well planned and the mitigating

measures proposed in the EMPr are successfully implemented the

p oposed de elop e t s o t i utio to ai pollutio a d the generation of air pollution can become less significant

Occupational Health and Safety

Act (No 85 of 1993)

The Act provides for the health and safety of persons at work and for

the health and safety of persons in connection with the use of

machinery; the protection of persons other than persons at work,

against hazards to health and safety arising out of or in connection with

the activities of persons at work. The EMPr provides for measures to

ensure that objectives of the Act are met on this site

EIA Regulations GN 983 & 985

(Listing Notice 1 & 3)

The proposed development constitutes an activity listed under GN R.

983 and GN R. 985, therefore a Basic Assessment Report process is

being followed to obtain authorization from the GDARD.

Gauteng Provincial

Environmental Management

Framework

The aim of the EMF is to guide the protection and enhancement of

environmental assets and natural resources along with development

patterns to ensure sustainable environmental management and

development patterns within and around the Gauteng Province. The

Page 8: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

7

Legislation, policy of guideline Description of compliance

development site is located in Zone 1 of the EMF which aims to promote

development infill, densification and concentration of urban

development within the urban development zones as defined in the

Gauteng Spatial Development Framework (GSDF). In order to establish a

more effective and efficient city region that will minimise urban sprawl

into rural areas; the proposed road expansion along with the upgrade of

the culverts is necessary. Therefore, the proposed activity will support

urban development which is fully supportive of the objectives of the

EMF.

Red List Plant Species

Guidelines

The purpose of the guidelines is to promote the conservation of Red List

Plant Species in Gauteng, which are species that face risk of extinction in

the wild. By protecting Red List Plant Species, conservation of diverse

landscapes is promoted which forms part of the overall environmental

preservation of diverse ecosystems, habitats, communities, populations,

species and genes in Gauteng.

The development will not impact on any Red listed plant species.

Gauteng Noise Control

Regulations, 1999

During the construction phase the impact of noise could be problematic,

but such impacts are generally short term. One should note that

practical mitigation measures for noise pollution are low, but certain

measures can be implemented to mitigate the severity. These measures

have been provided for in the EMPr

Regional Spatial Development

Framework (RSDF) 2010/2011-

Administrative Region A

The site falls within Sub Area 6 of Region A which consists of the Kyalami

Specialty Node, several neighbourhood nodes, high density residential

developments, agricultural holdings and farm portions. Despite some

parts of the sub area comprising low residential densities, the majority

of the sub area is developed at medium to high densities. The sub area

is connected to the rest of the region via several mobility roads and

spines, which experience severe traffic congestion. The vast majority of

the sub area falls within the Urban Development Boundary. The sub

area also has an environmentally sensitive area. The sub area further

experiences some infrastructure difficulties, especially in the

Crowthorne AH area.

The upgrade of the Allandale Road will support existing and planned

development as it will provide for the alleviation of traffic congestion in

the area.

Johannesburg Open Space

Management Framework

The JMOSS seeks to ensure inter-connected and managed network of

open spaces supporting interactions between social, economic and

ecological activities, sustaining and enhancing both ecological processes

and human settlements within the city. The open space linked to the

watercourse traversing the site will be maintained.

3. ALTERNATIVES Describe the proposal and alternatives that are considered in this application. Alternatives should include a consideration of all possible means by

which the purpose and need of the proposed activity could be accomplished. The determination of whether the site or activity (including different

processes etc.) or both is appropriate needs to be informed by the specific circumstances of the activity and its environment.

The no-go option must in all cases be included in the assessment phase as the baseline against which the impacts of the other alternatives are

assessed. Do not include the no go option into the alternative table below.

Page 9: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

8

Note: After receipt of this report the competent authority may also request the applicant to assess additional alternatives that could possibly

accomplish the purpose and need of the proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent.

Please describe the process followed to reach (decide on) the list of alternatives below

The proposal is for the extension of existing culverts which from part of the already existing Allandale

Road, leaving no room for a locational alternatives. The design alternatives are also restricted by the fact

that the existing culverts will be lengthened to accommodate additional lanes for existing road.

Provide a description of the alternatives considered

No. Alternative type, Description

1 Proposal The proposal entails the upgrading and extension of the existing 3 culvert

bridges on Allandale Road as part of the associated infrastructure upgrade

for the Kyalami Gardens Ext 27 development on the Remainder of Portion

2 and the Remaining Extent of Portion 88 of the Farm Bothasfontein 408

JR, City of Johannesburg Metropolitan Municipality. The upgrades include

road widening of sections of the road which will necessitate the extension

of existing culverts to accommodate the expanded road.

The portion of Allandale Road (M39) to be upgraded stretches from the

intersection of Allandale Road and Pitts Avenue (north western end) to

approximately 28m before the interchange of Allendale Road and Harry

Galaun Drive (eastern end). The extension of the culverts will take place

across the freshwater resources being crossed.

In the event that no alternative(s) has/have been provided, a motivation must be included in the table

below.

This application pertains to the upgrading of the Allandale road especially where it crosses the streams.

Given that the proposal is for the extension of existing three culverts which from part of the already

existing Allandale Road, there are no locational alternatives considered.

The upgrades include road widening in sections of the road including where it crosses the existing culverts.

The culverts will be upgraded through laying of pipe and box culverts to extend them. The designs for the

culverts have been influenced by the existing infrastructure, configuration of the crossings and the extent

of road upgrade required. However, the culverts designs will:

- Limit the excavations within the stream;

- Limit obstruction of water flow within the stream;

- Accommodate the required width of the road for the envisaged traffic.

4. PHYSICAL SIZE OF THE ACTIVITY

Indicate the total physical size (footprint) of the proposal as well as alternatives. Footprints are to include all

new infrastructure (roads, services etc), impermeable surfaces and landscaped areas:

Size of the activity:

Proposed activity (Total environmental (landscaping,

parking, etc.) and the building footprint)

0.25 ha

Indicate the size of the site(s) or servitudes (within which the above footprints will occur):

Size of the site/servitude:

Proposed activity 0.25 ha

Page 10: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

9

5. SITE ACCESS

Proposal

Does ready access to the site exist, or is access directly from an existing road? YES NO

If NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

Access to the route area to be from the Allandale Road.

Include the position of the access road on the site plan (if the access road is to traverse a sensitive feature

the impact thereof must be included in the assessment).

Alternative 1

Does ready access to the site exist, or is access directly from an existing road? YES NO

If NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

Include the position of the access road on the site plan. (if the access road is to traverse a sensitive feature

the impact thereof must be included in the assessment).

6. LAYOUT OR ROUTE PLAN A detailed site or route (for linear activities) plan(s) must be prepared for each alternative site or alternative activity. It must be attached to this document. The site or route plans must indicate the following: the layout plan is printed in colour and is overlaid with a sensitivity map (if applicable); layout plan is of acceptable paper size and scale, e.g.

o A4 size for activities with development footprint of 10sqm to 5 hectares; o A3 size for activities with development footprint of ˃ 5 hectares to 20 hectares; o A2 size for activities with development footprint of ˃20 hectares to 50 hectares); o A1 size for activities with development footprint of ˃50 hectares);

The following should serve as a guide for scale issues on the layout plan:

o A0 = 1: 500 o A1 = 1: 1000 o A2 = 1: 2000 o A3 = 1: 4000 o A4 = 1: 8000 (±10 000)

shapefiles of the activity must be included in the electronic submission on the CD’s; the property boundaries and Surveyor General numbers of all the properties within 50m of the site; the exact position of each element of the activity as well as any other structures on the site; the position of services, including electricity supply cables (indicate above or underground), water supply pipelines, boreholes,

sewage pipelines, septic tanks, storm water infrastructure; servitudes indicating the purpose of the servitude; sensitive environmental elements on and within 100m of the site or sites (including the relevant buffers as prescribed by the

competent authority) including (but not limited thereto): o Rivers and wetlands; o the 1:100 and 1:50 year flood line; o ridges; o cultural and historical features; o areas with indigenous vegetation (even if it is degraded or infested with alien species);

Where a watercourse is located on the site at least one cross section of the water course must be included (to allow the position of the relevant buffer from the bank to be clearly indicated)

FOR LOCALITY MAP (NOTE THIS IS ALSO INCLUDED IN THE APPLICATION FORM REQUIREMENTS)

the scale of locality map must be at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000

can be used. The scale must be indicated on the map; the locality map and all other maps must be in colour; locality map must show property boundaries and numbers within 100m of the site, and for poultry and/or piggery, locality map must

show properties within 500m and prevailing or predominant wind direction; for gentle slopes the 1m contour intervals must be indicated on the map and whenever the slope of the site exceeds 1:10, the 500mm

contours must be indicated on the map; areas with indigenous vegetation (even if it is degraded or infested with alien species); locality map must show exact position of development site or sites; locality map showing and identifying (if possible) public and access roads; and

Section A 6-8 has been duplicated 0 Number of times

Page 11: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

10

the current land use as well as the land use zoning of each of the properties adjoining the site or sites.

Figure 1: Locality

7. SITE PHOTOGRAPHS

Site photographs are included as Appendix B

8. FACILITY ILLUSTRATION

Appendix C

Page 12: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

11

SECTION B: DESCRIPTION OF RECEIVING ENVIRONMENT

Note: Complete Section B for the proposal and alternative(s) (if necessary)

Instructions for completion of Section B for linear activities 1) For linear activities (pipelines etc) it may be necessary to complete Section B for each section of the site that has a significantly different

environment.

2) Indicate on a plan(s) the different environments identified

3) Complete Section B for each of the above areas identified

4) Attach to this form in a chronological order

5) Each copy of Section B must clearly indicate the corresponding sections of the route at the top of the next page.

Instructions for completion of Section B for location/route alternatives 1) For each location/route alternative identified the entire Section B needs to be completed

2) Each alterative location/route needs to be clearly indicated at the top of the next page

3) Attach the above documents in a chronological order

(complete only when appropriate)

Instructions for completion of Section B when both location/route alternatives and linear activities are applicable for

the application

Section B is to be completed and attachments order in the following way

All significantly different environments identified for Alternative 1 is to be completed and attached in a chronological order; then

All significantly different environments identified for Alternative 2 is to be completed and attached chronological order, etc.

Section B - Section of Route N/A (complete only when appropriate for above)

Section B – Location/route Alternative No. 0 (complete only when appropriate for above)

1. PROPERTY DESCRIPTION

Property description:

(Including Physical Address and

Farm name, portion etc.)

The portion of Allandale Road (M39) proposed to be upgraded stretches from the

intersection of Allandale Road and Pitts Avenue (north western end) to

approximately 28m before the interchange of Allendale Road and Harry Galaun

Drive (eastern end).

2. ACTIVITY POSITION Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should

be in decimal degrees. The degrees should have at least six decimals to ensure adequate accuracy. The projection that must be used in all cases is the

WGS84 spheroid in a national or local projection.

Alternative: Latitude (S): Longitude (E):

Culvert 1 -26.000732° 28.083168°

Culvert 2 -26.007106° 28.097302°

Culvert 3 -26.007369° 28.097806°

In the case of linear activities:

Alternative: Latitude (S): Longitude (E):

Starting point of the activity o

o

Middle point of the activity o

o

End point of the activity o o

For route alternatives that are longer than 500m, please provide co-ordinates taken every 250 meters along the route and attached in the

appropriate Appendix

Addendum of route alternatives attached 0

The 21 digit Surveyor General code of each cadastral land parcel

Section B has been duplicated for sections of the route 0 times

Section B has been duplicated for location/route alternatives 0 times

Page 13: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

12

PROPOSAL T 0 I R 0 9 5 8 0 0 0 0 2 8 5 0 0 0 0 0 0

T 0 J R 0 0 0 0 0 0 0 0 0 4 0 8 0 0 0 1 1

T O I R 0 0 0 0 0 0 0 0 0 0 0 5 0 0 0 0 1

Figure 2: Site Coordinates

3. GRADIENT OF THE SITE

General gradient of the site.

Flat 1:50 – 1:20 1:20 – 1:15 1:15 – 1:10 1:10 – 1:7,5 1:7,5 – 1:5 Steeper than 1:5

4. LOCATION IN LANDSCAPE

Indicate the landform(s) that best describes the site.

Ridgeline Plateau Side slope of

hill/ridge Valley Plain Undulating plain/low hills River front

5. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE

a) Is the site located on any of the following?

Shallow water table (less than 1.5m deep) YES NO

Dolomite, sinkhole or doline areas YES NO

Seasonally wet soils (often close to water bodies) YES NO Unstable rocky slopes or steep slopes with loose soil YES NO Dispersive soils (soils that dissolve in water) YES NO Soils with high clay content (clay fraction more than 40%) YES NO Any other unstable soil or geological feature YES NO An area sensitive to erosion YES NO

(Information in respect of the above will often be available at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional

Geotechnical Maps prepared by Geological Survey may also be used).

b) are any caves located on the site(s) YES NO

Page 14: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

13

If yes to above provide location details in terms of latitude and longitude and indicate location on site or route map(s)

Latitude (S): Longitude (E): o o

c) are any caves located within a 300m radius of the site(s) YES NO

If yes to above provide location details in terms of latitude and longitude and indicate location on site or route map(s)

Latitude (S): Longitude (E): o o

d) are any sinkholes located within a 300m radius of the site(s) YES NO

If yes to above provide location details in terms of latitude and longitude and indicate location on site or route map(s)

Latitude (S): Longitude (E): o o

If a of the a s e s to the a o e a e YE“ o u su e , spe ialist i put a e e uested the Department

6. AGRICULTURE

Does the site have high potential agriculture as contemplated in the Gauteng Agricultural Potential Atlas (GAPA 4)? YES NO

Please note: The Department may request specialist input/studies in respect of the above.

7. GROUNDCOVER All identified rare or endangered species or other elements have been indicated on the sensitivity map.

Indicate the types of groundcover present on the site and include the estimated percentage found on site

Natural veld - good

condition

% =

Natural veld with

scattered aliens

% =

Natural veld with heavy

alien infestation

% =

Veld dominated by

alien species

% =80

Landscaped

(vegetation)

% =

Sport field

% =

Cultivated land

% = 98

Paved surface

(hard landscaping)

% =12

Building or other

structure

% = 20

Bare soil

% = 8

Are there any rare or endangered flora or fauna species (including red list species) present on the site YES NO

If YES, specify and explain:

Are there any rare or endangered flora or fauna species (including red list species) present within a 200m (if within urban area

as defined in the Regulations) or within 600m (if outside the urban area as defined in the Regulations) radius of the site.

YES NO

If YES, specify and explain:

Are there any special or sensitive habitats or other natural features present on the site? YES NO

If YES, specify and explain:

The proposed activity is to occur within the riparian zone of the channelled valley bottom wetland.

Was a specialist consulted to assist with completing this section YES NO

If yes complete specialist details

Name of the specialist: Stephen van Staden of Scientific Aquatic Services Qualification(s) of the specialist: MSc (Environmental Management) BSc (Hons) Zoology (Aquatic Ecology);

BSc (Zoology, Geography and Environmental Management) Postal address: 91 Geldenhuis Rd, Malvern East, Ext 1 Postal code: 1401 Telephone: 011 616 7893 Cell: 083 415 2356

E-mail: [email protected] Fax: 086 724 3132 Are any further specialist studies recommended by the specialist? YES NO

If YES, specify:

If YES, is such a report(s) attached? YES NO

If YES list the specialist reports attached below

Signature of specialist: See attached report Date:

Please note; If more than one specialist was consulted to assist with the filling in of this section then this table must be appropriately duplicated

Page 15: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

14

8. LAND USE CHARACTER OF SURROUNDING AREA Using the associated number of the relevant current land use or prominent feature from the table below, fill in the position of these land-uses in the

vacant blocks below which represent a 500m radius around the site

1. Vacant land 2. River, stream,

wetland 3. Nature conservation area 4. Public open space 5. Koppie or ridge

6. Dam or reservoir 7. Agriculture 8. Low density residential 9. Medium to high density

residential 10. Informal residential

11. Old age home 12. Retail 13. Offices 14. Commercial &

warehousing 15. Light industrial

16. Heavy industrialAN

17. Hospitality facility 18. Church 19. Education facilities 20. Sport facilities

21. Golf course/polo

fields 22. Airport

N

23. Train station or shunting

yardN

24. Railway lineN

25. Major road (4 lanes or

more)N

26. Sewage treatment

plantA

27. Landfill or waste

treatment siteA

28. Historical building 29. Graveyard 30. Archeological site

31. Open cast mine 32. Underground

mine

33.Spoil heap or slimes

damA

34. Small Holdings

Other land uses

(describe):

NORTH

WEST

8,9 8,9 8,9 2,9 2

EAST

1,9 9,19 8 2,9 8

8 881 SITE 8 1,13

6, 8 2,8 8 1, 8 13

2 8 8 9 13 SOUTH

Note: More than one (1) Land-use may be indicated in a block

Please note: The Department may request specialist input/studies depending on the nature of the land use character of the area and potential

impact(s) of the proposed activity/ies. Specialist reports that look at health & air quality and noise impacts may be required for any feature above and

in particular those featu es a ked ith a A a d ith a N respectively.

Have specialist reports been attached YES NO

If yes indicate the type of reports below

Fauna and Flora Habitat Assessment and Ridge Study (Appendix G1) YES NO

Wetland Delineation Report YES NO

Geotechnical Investigation Report (Appendix G2) YES NO

Outline Scheme Report (Appendix G3) YES NO

Town Planning Memorandum (Appendix G4) YES NO

Traffic Impact Study YES NO

Heritage Impact Assessment Report YES NO

9. SOCIO-ECONOMIC CONTEXT Describe the existing social and economic characteristics of the area and the community condition as baseline information to assess the potential

social, economic and community impacts.

The proposal entails the upgrading of the existing 3 culverts on Allandale Road as part of the associated

infrastructure upgrade for the Kyalami Gardens Ext 27. The upgrades include widening of sections of

Allandale Road and associated culverts.

The study area falls within Sub Area 6 of Region A which consists of the Kyalami Speciality Node, several

neighbourhood nodes, high-density residential developments, agricultural holdings and farm portions.

Despite some parts of the sub area comprising low residential densities, the majority of the sub area is

developed at medium to high densities. The sub area is connected to the rest of the region via several

mobility roads and spines, which experience severe traffic congestion. The vast majority of the area falls

within the Urban Development Boundary.

The Allandale Road is historically known for traffic congestion as it links the N1 to the developed areas to

the west and east of the N1. With the recent development of the Mall Africa, office space in the vicinity and

residential area together with the Kyalami Node, investments in infrastructure include the road itself are

essential for efficient functioning of the urban space.

Page 16: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

15

10. CULTURAL/HISTORICAL FEATURES

Please be advised that if section 38 of the National Heritage Resources Act 25 of 1999 is applicable to your proposal or alternatives, then you are

requested to furnish this Department with written comment from the South African Heritage Resource Agency (SAHRA) – Attach comment in

appropriate annexure

38. (1) Subject to the provisions of subsections (7), (8) and (9), any person who intends to undertake a development categorised as-

(a) the construction of a road, wall, powerline, pipeline, canal or other similar form of linear development or barrier exceeding 300m in length;

(b) the construction of a bridge or similar structure exceeding 50m in length;

(c) any development or other activity which will change the character of a site-

(i) exceeding 5 000 m2 in extent; or

(ii) involving three or more existing erven or subdivisions thereof; or

(iii) involving three or more erven or divisions thereof which have been consolidated within the past five years; or

(iv) the costs of which will exceed a sum set in terms of regulations by SAHRA or a provincial heritage resources

authority;

(d) the re-zoning of a site exceeding 10 000 m2 in extent; or

(e) any other category of development provided for in regulations by SAHRA or a provincial heritage resources authority, must at the very earliest

stages of initiating such a development, notify the responsible heritage resources authority and furnish it with details regarding the location,

nature and extent of the proposed development.

Are there any signs of culturally (aesthetic, social, spiritual, environmental) or historically significant elements,

as defined in section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including

archaeological or palaeontological sites, on or close (within 20m) to the site?

YES NO

If YES, explain:

N/A

If uncertain, the Department may request that specialist input be provided to establish whether there is such a feature(s) present on or close to

the site.

Briefly explain the findings of the specialist if one was already appointed:

Will any building or structure older than 60 years be affected in any way? YES NO

Is it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)? YES NO

If yes, please attached the comments from SAHRA in the appropriate Appendix

Page 17: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

16

SECTION C: PUBLIC PARTICIPATION (SECTION 41) The public participation process is being conducted in accordance with the requirement of the EIA Regulations, 2014.

1. LOCAL AUTHORITY PARTICIPATION

Local authorities are key interested and affected parties in each application and no decision on any application can be made before the relevant

local authority is provided with the opportunity to give input. The planning and the environmental sections of the City of Johannesburg

Metropolitan Municipality have been informed of the application and given least thirty (30) calendar days to comment of on the Draft BAR.

Was the draft report submitted to the local authority for comment? YES NO

If yes, has any comments been received from the local authority? YES NO

If YE“ , iefl des i e the o e t elo also atta h any correspondence to and from the local authority to this application):

If NO iefl e plai h o o e ts ha e ee e ei ed or why the report was not submitted if that is the case.

The Draft Report has been submitted to the City of Joburg (COJ) for comment. Once received, any issues

and comments raised by COJ will be collated and responded to. These responses will be incorporated into

the Final BAR.

2. CONSULTATION WITH OTHER STAKEHOLDERS

Any stakeholder that has a direct interest in the activity, site or property, such as servitude holders and service providers, should be informed of the

application at least thirty (30) calendar days before the submission of the application and be provided with the opportunity to comment.

Has any comment been received from stakeholders? YES NO

If YE“ , iefl des i e the feed a k elo also atta h opies of a o espo de e to a d f o the stakeholde s to this application):

If NO iefl explain why no comments have been received

The Draft BAR has been advertised inviting stakeholders to review and provide comments.

3. GENERAL PUBLIC PARTICIPATION REQUIREMENTS

The public participation process has been undertaken in accordance with the requirements of the Regulations. The need for a public meeting or any

other additional measure will be determined by the responses received from the public.

All comments and responses to each comment of the public / interested and affected party are being recorded in the Comments and Responses

Report as prescribed in the regulations and will be attached to the Final BAR.

4. APPENDICES FOR PUBLIC PARTICIPATION

All public participation information is to be attached in the appropriate Appendix. The information in this Appendix is to be ordered as detailed below

Appendix 1 – Proof of site notice

Appendix 2 – Written notices issued as required in terms of the regulations

Appendix 3 – Proof of newspaper advertisements

Appendix 4 –Communications to and from interested and affected parties

Appendix 5 – Minutes of any public and/or stakeholder meetings

Appendix 6 - Comments and Responses Report

Appendix 7 –Comments from I&APs on Basic Assessment (BA) Report

Appendix 8 –Comments from I&APs on amendments to the BA Report

Appendix 9 – Copy of the register of I&Ap

Page 18: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

17

SECTION D: RESOURCE USE AND PROCESS DETAILS

Note: Section D is to be completed for the proposal and alternative(s) (if necessary)

Instructions for completion of Section D for alternatives 1) For each alternative under investigation, where such alternatives will have different resource and process details (e.g. technology

alternative), the entire Section D needs to be completed

4) Each alterative needs to be clearly indicated in the box below

5) Attach the above documents in a chronological order

(complete

only when

appropriate)

Section D Alternative No. Proposal (complete only when appropriate for above)

1. WASTE, EFFLUENT, AND EMISSION MANAGEMENT

Solid waste management

Will the activity produce solid construction waste during the construction/initiation phase? YES NO

If yes, what estimated quantity will be produced per month? 50 m3

How will the construction solid waste be disposed of (describe)?

Construction waste will comprise mainly of excess spoil material from ground excavation and trenching

activities, vegetation, construction material, general waste from site personnel, paints and solvents and

waste water and sewage to be disposed of at registered sites.

Spoil material will be reused where possible (as backfill or erosion mitigation works) while excess spoil will

need to be disposed of off-site. Spoil material will be hauled with tipper trucks to be a pre-determined spoil

site, the area will be covered with a layer of topsoil and re-vegetated.

General waste will be kept in bins within the construction site and will be collected and disposed of into a

skip and transported to the nearest landfill site.

Spent canisters for paints and solvents will be the responsibility of the respective contractor and shall be

disposed of at a suitably licensed landfill site or recycled as required.

Where will the construction solid waste be disposed of (describe)?

- Spoil material will be re-used as backfill material and excess will be disposed of at the nearest

registered Municipal Dumping site.

- General waste that is not recyclable will be disposed of at the nearest municipal landfill site;

- Should there be hazardous waste, it will be disposed of at hazardous waste site

Will the activity produce solid waste during its operational phase? YES NO

If yes, what estimated quantity will be produced per month? Not available

How will the solid waste be disposed of (describe)?

Solid waste will be collected and disposed of by the municipality.

Has the municipality or relevant service provider confirmed that sufficient air space exists for

treating/disposing of the solid waste to be generated by this activity?

YES NO

Where will the solid waste be disposed if it does not feed into a municipal waste stream (describe)?

To be disposed of at licensed landfill site.

Note: If the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a municipal waste

stream, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping

and EIA.

Can any part of the solid waste be classified as hazardous in terms of the relevant legislation? YES NO

Section D has been duplicated for alternatives

times

Page 19: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

18

If yes, inform the competent authority and request a change to an application for scoping and EIA.

Is the activity that is being applied for a solid waste handling or treatment facility? YES NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and

EIA.

Describe the measures, if any, that will be taken to ensure the optimal reuse or recycling of materials:

Reuse and recycling of materials where possible. Furthermore, it is proposed that all waste construction

materials be sorted into recyclable and non-recyclable materials. The recyclable materials should be re-used

where possible or disposed of by a recycling company.

Liquid effluent (other than domestic sewage)

Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal

sewage system?

YES NO

If yes, what estimated quantity will be produced per month? N/A

If yes, has the municipality confirmed that sufficient capacity exist for treating / disposing of the liquid

effluent to be generated by this activity(ies)?

YES NO

Will the activity produce any effluent that will be treated and/or disposed of on site? Yes NO

If yes, what estimated quantity will be produced per month? N/A

If yes describe the nature of the effluent and how it will be disposed.

N/A

Note that if effluent is to be treated or disposed on site the applicant should consult with the competent authority to determine whether it is

necessary to change to an application for scoping and EIA

Will the activity produce effluent that will be treated and/or disposed of at another facility? YES NO

If yes, provide the particulars of the facility:

Facility name:

Contact person:

Postal address:

Postal code:

Telephone: Cell:

E-mail: Fax:

Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:

Liquid effluent (domestic sewage)

Will the activity produce domestic effluent that will be disposed of in a municipal sewage system? YES NO

If yes, what estimated quantity will be produced per month?

If yes, has the municipality confirmed that sufficient capacity exist for treating / disposing of the domestic effluent to be

generated by this activity(ies)?

YES NO

Will the activity produce any effluent that will be treated and/or disposed of on site? YES NO

If yes describe how it will be treated and disposed off.

Emissions into the atmosphere

Will the activity release emissions into the atmosphere? YES NO

If yes, is it controlled by any legislation of any sphere of government? YES NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an

application for scoping and EIA.

If no, describe the emissions in terms of type and concentration:

The proposed development will not generate any emissions. Only the vehicle exhaust fumes may have an

influence during the construction phase, but is regarded as insignificant.

2. WATER USE

Indicate the source(s) of water that will be used for the activity

municipal Directly from

water board

groundwater river, stream, dam or lake other the activity will not use water

If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature, please indicate

the volume that will be extracted per month: N/A

Page 20: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

19

If Yes, please attach proof of assurance of water supply, e.g. yield of borehole, in the appropriate Appendix

Does the activity require a water use permit from the Department of Water Affairs? YES NO

If yes, list the permits required

If yes, have you applied for the water use permit(s)? YES NO

If yes, have you received approval(s)? (attached in appropriate appendix) YES NO

3. POWER SUPPLY

Please indicate the source of power supply eg. Municipality / Eskom / Renewable energy source

N/A

If power supply is not available, where will power be sourced from?

N/A

4. ENERGY EFFICIENCY

Describe the design measures, if any, that have been taken to ensure that the activity is energy efficient:

N/A

Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any:

N/A

Page 21: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

20

SECTION E: IMPACT ASSESSMENT

The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2014, and should take applicable official guidelines into

account. The issues raised by interested and affected parties should also be addressed in the assessment of impacts as well as the impacts of not

implementing the activity (Section 24(4)(b)(i).

1. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES

Summarise the issues raised by interested and affected parties.

The Draft Report has been made available for public comment. Once the PPP has been concluded, the

issues and comments raised by I&AP will be collated and responded to. These responses will be

incorporated into the Final BAR.

Summary of response from the practitioner to the issues raised by the interested and affected parties (including the manner in which the public

comments are incorporated or why they were not included)

(A full response must be provided in the Comments and Response Report that must be attached to this report):

The Draft Report has been made available for public comment. Once the PPP has been concluded, the

issues and comments raised by I&AP will be collated and responded to. These responses will be

incorporated into the Final BAR.

2. IMPACTS THAT MAY RESULT FROM THE CONSTRUCTION AND OPERATIONAL PHASE

Briefly describe the methodology utilised in the rating of significance of impacts

In order to establish a coherent framework within which all impacts could be objectively assessed, it was

deemed appropriate to establish a rating system, to be applied consistently to all the criteria. For such

purposes each aspect was assigned a value ranging from one (1) to four (4) depending on its definition. The

tables below provide a summary of the criteria and the rating scales used in the assessment of potential

impacts.

The beneficial and adverse impacts of the proposed development have been discussed below.

Nature: classification of whether the impact is positive or negative, direct or indirect.

Extent: spatial scale of impact and classified as:

o Site: the impacted area is the whole or significant portion of the site (1).

o Local: Within a radius of 2 km of the construction site (2).

o Regional: the impacted area extends to the immediate, surrounding and neighbouring

properties.

o National: the impact can be considered to be of national significance.

Duration: Indicates what the lifetime of the impact will be and is classified as:

o Short term: The impact will either disappear with mitigation or will be mitigated through

natural process in a span shorter than the construction phase.

o Medium term: The impact will last for the period of the construction phase, where after it will be

entirely negated.

o Long term: The impact will continue or last for the entire operational life of the development,

o but will be mitigated by direct human action or by natural processes thereafter. The only class of

impact which will be non-transitory.

o Permanent: Mitigation either by man or natural process will not occur in such a way or in such a

time span that the impact can be considered transient.

Intensity: Describes whether an impact is destructive or benign;

o Low: Impact affects the environment in such a way that natural, cultural and social functions

and processes are not affected.

o Moderate: Affected environment is altered, but natural, cultural and social functions and

Page 22: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

21

processes continue albeit in a modified way.

o High: Natural, cultural and social functions and processes are altered to the extent that they

temporarily cease.

o Very High: Natural, cultural and social functions and processes are altered to extent that they

permanently cease.

o Probability: Describes the likelihood of an impact actually occurring:

o Improbable: Likelihood of the impact materialising is very low

o Possible: The impact may occur

o Highly Probable: Most likely that the impact will occur

o Definite: Impact will certainly occur.

Significance: Based on the above criteria the significance of issues the total number of points scored for

each impact indicates the level of significance of the impact, and is rated as:

o Low: the impacts are less important.

o Medium: the impacts are important and require attention; mitigation is required to reduce the

negative impacts.

o High: the impacts are of great importance. Mitigation is therefore crucial.

Cumulative: In relation to an activity, means the impact of an activity that in itself may not be significant

but may become significant when added to the existing and potential impacts eventuating from similar or

diverse activities or undertakings in the area.

Mitigation: Where negative impacts are identified, mitigation measures (ways of reducing impacts) have

been identified. An indication of the degree of success of the potential mitigation measures is given per

impact.

Criteria for the rating of impacts

Criteria Description

Extent National

The whole of South

Africa

Regional

Provincial and parts of

neighbouring provinces

Local

Within a radius of

2km of the

construction site

Site

Confined to the

construction site

Duration Permanent

Mitigation either by

man or natural

process will not occur in

such a way or in such a

time span that the

impact can be

considered transient

Long-term- The impact

will continue or last for the

entire operational life of

the development, but will

be mitigated by direct

human action or by

natural processes

thereafter. The only class

of impact which will be

non-transitory

Medium-term

The impact will last

for the period of the

construction phase,

where after it will be

entirely negated

Short-term

The impact will either

disappear with

mitigation or will be

mitigated through

natural process in a

span shorter than the

construction phase

Intensity Very High

Natural, cultural and

social functions and

processes are altered

to extent that they

permanently cease

Natural, cultural and

social functions and

processes are altered to

extent that they

temporarily cease

Moderate

Affected

environment is

altered, but natural,

cultural and social

functions and

processes continue.

Impact affects the

environment in such

a way that natural,

cultural and social

functions

Probability Definite

ct will certainly occur

Highly Probable

Most likely that the

impact will occur

Possible

The impact may

occur

Improbable

Likelihood of the

impact materialising

is very low

Page 23: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

22

Rating 4 3 2 1

Significance Rating of classified impacts

Impact Points Description

Low 4-6 An acceptable impact for which mitigation is desirable but not essential. The impact by itself

is insufficient even in combination with other low impacts to prevent the development

being approved.

These impacts will result in either positive or negative medium to short term effects on the

social and/or natural environment.

Medium 7-9 An important impact which requires mitigation. The impact is insufficient by itself to

prevent the implementation of the project but which in conjunction with other impacts may

prevent its implementation.

These impacts will usually result in either a positive or negative medium to long-term effect

on the social and/or natural environment.

High

10 12 A serious impact, if not mitigated, may prevent the implementation of the project (if it is a

negative impact). These impacts would be considered by society as constituting a major and

usually a long-term change to the (natural &/or social) environment and result in severe

effects or beneficial effects.

Very high 13-16 A very serious impact which, if negative, may be sufficient by itself to prevent

implementation of the project. The impact may result in permanent change. Very often

these impacts are unmitigatable and usually result in very severe effects, or very beneficial

effects

Status Denotes the perceived effect of the impact on the affected area

Positive (+) Beneficial impact

Negative (-) Adverse impact

Negative impacts are shown with a (-) while positive ones are indicated as (+)

Briefly describe and compare the potential impacts (as appropriate), significance rating of impacts, proposed mitigation and significance rating of

impacts after mitigation that are likely to occur as a result of the construction phase for the various alternatives of the proposed development. This

must include an assessment of the significance of all impacts.

DESIGN AND PLANNING PHASE

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

Authorisations, Permits,

Licenses and

appointment of

personnel

- All necessary authorisations, permits and

licenses must be obtained prior to construction;

- It must be ensured that the Surface Water and

Rehabilitation Plan informs the EMPr for the

proposed upgrade of a portion of Allandale road

and associated culverts; and that the EMPr then

forms part of the contractual agreement with

the contractors and sub- contractors for the

duration of the proposed project;

- Before any work commences, the proponent

must appoint an independent Environmental

Control Officer (ECO) to monitor and report on

compliance to the authorisation during the

construction phase.

Low

Access Roads

Access to the

construction site could

impact on the

channeled valley bottom

wetland

Utilise the designated access road to the sites and

adhere to the construction guidelines developed

along with the mitigation measures stipulated in the

EMPr.

Low

Page 24: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

23

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

Construction camp

Placement of camp

could impact on river

system including on

fauna and flora

The construction camp must be erected on an area

which is already disturbed and outside of the

wetland buffer

Low

Culverts design

Impact on the river

system is unavoidable

and can be exacerbated

depending on the design

and material to be used.

The Design and Method Statement to be prepared

and provide for the following:

- setting out positions of the various structural

elements so as to limit impact on the

environment.

- Efficient and functional design for effective

stormwater management;

- Construction method that is least disruptive to

traffic movement, environmental resources and

limited movement into the wetland areas.

Low

CONSTRUCTION PHASE

Geology and soils –

- Destabilisation of

surface geology as

a result of

excavations

- Potential erosion,

degradation and loss

of topsoil due to

construction

activities as well as

storm water runoff.

- All site disturbances must be limited to the areas

where structures will be constructed.

- Erosion berms should be installed to prevent

gully formation and further siltation of the

freshwater resource, and all soil stockpiles

should be placed outside of the resource itself

and its associated 32m buffer zone, and

protected with a suitable geotextile.

- All excavated soil must be stripped and

stockpiled within a designated area, in the

vicinity of the construction site, outside of the

freshwater resources and a 30m buffer zone, for

subsequent use at a later stage (when removing

the coffer dam the contractor must backfill the

excavation with material which was originally

removed from the river bed. Further care must

be taken to minimise the amount of material

used for backfill which have abrasive surfaces).

- Stockpiles must be protected from the wind and

rain with the use of tarpaulins, where necessary;

- It must be ensured that weeds are eradicated

from topsoil prior to spoiling;

- Litter and general waste must be removed from

the soil prior to stockpiling;

- All/any erosion and silt control mechanisms

need to be regularly maintained for the duration

of the construction phase;

- All areas disturbed within the freshwater

resources should be monitored for erosion and

incision;

- Any areas compacted as a result of construction

activities, where applicable, shall be ripped to a

depth of approximately 150mm, using hand-held

equipment, prior to being infilled with topsoil.

- Where possible, plants should be cut down to

ground level instead of being removed

Mid-low

Page 25: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

24

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

completely to stabilise the soil during land-

clearing operations;

- When excavated areas are backfilled the surface

must be level with the surrounding land surface,

unless stated otherwise, to minimise soil erosion

from the areas when the excavation is complete.

Fauna and flora

- Habitat destruction

and alteration will

take place within the

footprint of the

construction site

- Existing fauna could

be harmed through

construction

activities. Impact on

natural movement of

species (dispersal

corridors.)

- Loss or displacement

of conservation

important species

- Construction of

barriers to animal

movement or

migration

- Vegetation clearing should be kept to what is

absolutely essential, to reduce the extent of

bare soils, thus limiting erosion potential of the

area;

- Should any faunal or floral Species of

Conservation Concern (SCC) be encountered

within the zone of influence of the proposed

linear development, effective relocation of

individuals to suitable offset areas must occur;

- Workers must be limited to areas under

construction within the site and access to the

undeveloped areas must be strictly regulated

o-go a eas du i g o st u tio as ell as operational activities).

- All temporary stockpile areas including litter and

dumped material and rubble must be removed

on completion of construction.

- The Contractor must ensure that no faunal

species are disturbed, trapped, hunted or killed

during the construction phase. Fines must be

imposed and immediate dismissal of any

employee who is found attempting to snare or

otherwise harms faunal species. All animals

captured must be released in appropriate

habitat away from the development.

- Building of temporary access roads should be

kept to a minimum to prevent unnecessary

impact on the surrounding vegetation.

Low

Topography

- Alteration of

topography due to

excavations/cutting,

scouring, stockpiling of

soil, construction

material and debris

and waste material on

site.

- Stability of slopes

- Avoid placing of stockpiles and other services on

areas likely to pose obtrusive visual impact

- Precautionary measures and design from the

engineer along with the proposed mitigation

measures from the wetland specialist must be

implemented.

- Re-vegetation of re-profiled slopes;

- Temporary stabilisation of slopes using

geotextiles; and installation of gabions and reno

mattresses to be implemented.

Low

Wetland and water

resources

- Loss of wetland

habitat and

ecological structure.

- Changes to wetland

ecological and socio-

cultural service

- Demarcate areas prior to commencement of

the construction in order to minimize

construction footprints and control the edge

effects from construction activities; and ensure

that vegetation clearing is kept at a minimum.

- The duration of impacts on the freshwater

resources should be minimised as far as possible

by ensuring that the duration of time in which

Medium-low

Page 26: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

25

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

provision

- Impacts on

wetland/riparian

hydrological function

- Site clearing and the

removal of

vegetation leading to

increased runoff and

erosion.

- Site clearing and

the disturbance of

soils leading to

altered wetland

habitat

- Earthworks in the

vicinity of the

features leading to

increased runoff and

erosion and altered

runoff patterns

- Changes to wetland

community due to

alien invasion

resulting in altered

wetland conditions

- Contamination of

surface and

groundwater due to

spillage, leakage,

incorrect storage

and handling of

chemicals, oils,

lubricants, cement,

fuels and other

hazardous materials.

- Loss of ability to

assimilate phosphate

and toxicants due to

vegetation clearing

- Inability to support

biodiversity due to

vegetation clearing

and contamination

of the soil within the

wetland areas

- Pollution and

contamination of

wetland soils as a

result of waste

dumping within

wetland areas

- Incision of wetland

flow alteration and sedimentation will take

place is minimised – therefore the construction

period should be kept as short as possible, and if

at all feasible, construction activities should be

scheduled for the drier months/low flow season

to decrease the risk of erosion during heavy

thunderstorms;

- The following mitigation measures are

applicable to the creation of any temporary

stream diversions:

o Prior to creating any required diversions,

erosion and sediment controls such as

sandbags and protection of exposed soils

with suitable geotextiles, must be

implemented around the site, in order to

minimise the risk of sedimentation of the

downstream areas;

o The inlet and outlet of temporary stream

diversions must be stabilized using

appropriate erosion control techniques,

and the outlet of the diversion must be

monitored for erosion; and

o Following completion of the extension of

the culverts, the stream diversion must be

removed and the affected area

rehabilitated.

o Ensure that the functionality of the

permanent, seasonal and temporary zones

of the freshwater resources is maintained

through provision of measures to ensure

that soil wetting conditions are maintained

and the freshwater resource functions are

reinstated;

- Erosion control measures around the culvert

construction sites are considered crucial. Such

measures may include sandbags to stabilize

banks and side slopes, and protection of

exposed soils with suitable geotextiles such as

hessian sheeting;

- Adequate stormwater management must be

incorporated into the rehabilitation plan in

order to prevent erosion and the associated

sedimentation of the freshwater resources. In

this regard special mention is made of:

- Any area where active erosion is observed must

be immediately rehabilitated in such a way as to

ensure that the hydrology of the area is re-

instated to conditions which are as natural as

possible.

- Drift fences constructed from hessian sheets

should be installed at erodible areas to minimise

erosion. Silt traps should also be provided to

Page 27: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

26

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

areas and erosion of

wetland areas due to

disturbance of

wetland soils during

construction related

activities

- Concentration of

flow due to

increased runoff

from areas cleared

for construction

- Earthworks in the

vicinity of the

wetland areas

leading to increased

runoff and erosion

and altered runoff

- Disturbance of soils

resulting in sediment

deposition into the

wetland areas during

runoff.

remove sand/silt particles from runoff;

- Any construction-related waste must not be

placed in the vicinity of any wetland/riparian

areas;

- Adequate stormwater drainage should be

constructed. Stormwater culverts and drains are

to be located and covered with metal grids to

prevent blockages;

- Monitor the wetland/riparian areas for erosion

and incision; and

- Implement an alien vegetation control program.

- Following completion of construction,

reprofiling of the banks of disturbed riparian

areas must take place, and must be revegetated

with indigenous gramminoid species such as

Arundinella nepalensis, Imperata cylindrica,

Setaria sphacelata and Eragrostis gummiflua;

Air Quality:

- Dust from access

roads and areas

cleared for

construction of the

culverts

- Dust suppression measures through regular

application of water must be implemented on

temporary dirt roads and during the

transportation of material during dry periods.

Water used for this purpose must be used in

quantities that will not result in the generation

of run-off.

Very low

Noise

There is likely to be an

increase in noise

pollution due to, among

others, the excavations

and site clearing,

construction vehicles

and construction staff

- All equipment and activities to comply with

noise regulations.

- All construction activities should be undertaken

according to daylight working hours between

the hours of 07:00 – 17:00 on weekdays and

7:30 – 13:00 on Saturdays.

- All operations should meet the noise standard

requirements of the Occupational Health and

Safety Act (Act No. 85 of 1993).

Low

Visual Intrusion & Light pollution

- Unkempt site due to littering and illegal

dumping on site and

surrounding areas. - Removal of

vegetation may cause visual

intrusion.

- Unsightly construction waste

pile may be visually intrusive

- All rubbish and excess rubble including excess

soil and bedrock to be removed to a registered

waste disposal facility. A certificate of disposal

must be obtained for any waste that is disposed

of.

- Refuse bins must be provided on site and these

must be emptied regularly.

- The location of the construction camp must be

carefully selected so that the camp is not

visually intrusive.

- Light pollutions should be minimised. Lighting is

to be sufficient for safety and security purposes,

but shall not be intrusive to neighbouring

residents, disturb wildlife.

Low

Page 28: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

27

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

- Construction activities must be limited to the

daylight hours.

Waste management

Waste generation

during the construction

phase will have a

negative impact on

the environment, if not

controlled adequately.

Waste streams likely to

include domestic

waste, spent grinding

material, mixed

concrete, paint cans

and brushes,

construction rubble

and other construction

waste

- Waste should be temporarily stored on site

before being disposed of appropriately. . General

waste should be placed in water tight containers

and disposed of on a regular basis.

- Where possible construction waste should be

recycled or reused. Building rubble must be re-

used, where possible, where this is not possible,

the rubble will be disposed of at an appropriate

site.

- Records of all waste taken off site and disposed

of must be kept as evidence.

- Burning of waste material will not be permitted.

- In case of spillages of hazardous substances;

they must be cleaned up using absorbent

material provided in spill kits on site, and must

be disposed of together with other hazardous

material at a hazardous waste landfill.

Absorbent materials used to clean up spillages

should be disposed of in a separate hazardous

waste bin.

Low

Traffic

- Construction is likely

to lead to restricted

traffic flow and

generation of

additional traffic in

terms of construction

vehicles and heavy

vehicles delivering

materials to the site.

- Restricted traffic flow

in the vicinity of

construction site

- Clear construction signs must be displayed along

Allandale Road and entrance to the site

indicating a construction site and turning of

construction vehicles

- The access road to be properly positioned and

road signage provided to limit conflict with

passing traffic.

- No construction vehicles are to be parked along

the Allandale Road or in such a way as to block

movement on the Allandale Road or any other

roads leading to the neighbouring properties

- Construction vehicles and activities must aim to

avoid peak hour traffic times (weekdays 7-8am

and 5-6pm).

Low

Safety and Security

A construction site can

be a dangerous place

and could result in harm

to people and property

and by their nature act

as a magnet to the

unemployed, resulting in

large numbers of people

gathering around the

site.

- The site camp to be fenced off to prohibit

unauthorized entry.

- Health and Safety Officer to be appointed to

continuously monitor the safety conditions during

construction.

- All construction staff must have the appropriate

PPE.

- Staff handling chemicals or hazardous materials

must be trained in the use of the substances and

the environmental, health and safety

consequences of incidents.

- Access to fuel and other equipment stores is to be

strictly controlled

- Record and report any environmental, health

and safety incidents to the responsible person.

- Signs should be erected to warn of construction

Low

Page 29: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

28

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

activities.

- The site and crew are to be managed in strict

accordance with the Occupational Health and

Safety Act (Act No. 85 of 1993) and the National

Building Regulations

- All structures that are vulnerable to high winds

must be secured.

- All manhole openings are to be covered and

clearly demarcated with danger tape.

- Potentially hazardous areas such as trenches are

to be cordoned off and clearly marked at all times.

- The basic spill control kit must be available at each

construction camp within the site.

- The Contractor is to ensure traffic safety at all

times, and shall implement road safety

precautions for this purpose.

- All vehicles and equipment used on site must be

operated by appropriately trained and / or

licensed individuals in compliance with all safety

measures as laid out in the Occupational Health

and Safety Act (Act No. 85 of 1993) (OHSA).

- An environmental awareness training programme

for all workers shall be put in place by the

Contractor. Before commencing with any work, all

workers shall be appropriately briefed about the

EMPr and relevant occupational health and safety

issues.

- Adequate emergency facilities must be provided

for the treatment of any emergency on the site.

Emergency procedures must be available on site

and communicated to all.

- The nearest emergency service provider must be

identified and Emergency contact numbers are to

be displayed conspicuously at prominent position.

- No loitering around the site for people seeking

temporary employment is to be allowed

Disruption to Road

Users & Road

Infrastructure

- Access to the construction area must be

predetermined and used during constructions.

- Excavated earth material should not be dumped/

Warning signage must be erected as appropriate

to warn road-users of the presence of construction

workers and construction vehicles.

Low

Impacts to Cultural/

Historical Resources

Any artifacts or cultural resources encountered

during construction must be preserved and

removed with the assistance of a qualified specialist

Low

Employment /job

opportunities created

+ve Construction activities will result in the creation of

some job opportunities

No mitigation required

+ve

Alignment with spatial

plans

+ve The activity supports intensive land use within an

urban area.

+ve

OPERATIONAL PHASE

Fauna and flora - If vegetation adjacent to the abutments of the Low

Page 30: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

29

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

- Fauna and flora

Reduced/limited

connectivity in the

ecological system

- Invasion of alien

species

- Lighting and its

negative impact on

fauna;

- Pollution of water

resources

culverts is to be removed it must be mowed or cut

short to between approximately 6 – 9 inches as a

maintenance procedure (at this height basal

erosion of the grasses will be minimised and the

grass must not be ploughed, as ploughing disturbs

the soils creating conditions for alien plant species

to invade the area, as well as increasing the

possibility of soil erosion by water runoff. The

grass cuttings must be carefully collected and

disposed of at a separate waste facility and not be

allowed to enter the river, as high grass loads can

impair the water quality during the low flow

season;

- All maintenance vehicles must remain on

designated roads with no indiscriminate driving

through the riparian zone;

- Appropriate lighting that does not shine into the

surrounding areas must be used;

- Monitoring and removal of alien vegetation must

be undertaken continuously for three months

after the construction of the bridge has been

completed and during the first growing season.

- Prevent contamination of natural wetland from

any source of pollution, effluent, etc.

- Ongoing monitoring of the resource and any

stormwater facilities which discharges into the

resource is required, to ensure that any litter or

solid wastes which do reach the resource are

removed in a timely manner.

Noise

Disturbing noise from

traffic using the road and

bridge structure

Noise attenuation measures to be implemented.

These to include low noise road surface, noise

retention walls and embankments as well as

retention or planting of vegetation along the road to

absorb noise from the road.

Low

Socio-economic impacts

- Ease of vehicular

movement in the area

and support to

residential and

economic activities.

- Job opportunities

created through

maintenance work

+ve No mitigation required +ve

NO-GO OPTION

Potential impacts:

Significanc

e rating of

impacts

Issues and Proposed mitigation:

Significanc

e rating

after

mitigation

Risk of

mitigation not

being

implemented

Geology and soils

+ve No disturbance of soils on the site. However,

erosion control will be required.

+ve

Fauna and flora

+ve No disturbance to fauna and flora due to

construction. However, clearance of alien

+ve

Page 31: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

30

Potential impacts:

Significance

rating of

impacts

(+ve or -ve)

Proposed mitigation:

Significance

rating after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

vegetation required

Topography No impact

Air Quality No impact

Wetland and water

Resources

+ve No pollution as a result of upgrade +ve

Noise

+ve No noise disturbance to neighboring residential

estates due to construction works on site

+ve

Visual Intrusion & Light

pollution +ve No impact +ve

Waste management No impact

Traffic -ve Although no traffic resulting from construction

activities, traffic congestion to continue to increase

in the area. Therefore alternative routes to be used

or constructed.

-ve High

Disruption to Road

Users

No impact

Impacts to Cultural/

Historical Resources

No impact

Employment /job

opportunities created

-ve No job opportunities will be created. Alternative

sources of employment to be investigated and

implemented

-ve High

Alignment with spatial

plans

-ve Plans to be amended to align with open space

provision

-ve

List any specialist reports that were used to fill in the above tables. Such reports are to be attached in the appropriate Appendix.

- Wetland and Ecological Assessment

- Surface Water Rehabilitation and Management Plan

- Geotechnical Assessment Describe any gaps in knowledge or assumptions made in the assessment of the environment and the impacts associated with the proposed

development.

It is assumed that all information provided by the Applicant and the appointed specialists is correct and

valid and all data from an unpublished research is valid and accurate. The EAP will not accept any

responsibility in the event that additional information not reasonably foreseen at the time of this report

comes to light at a later stage of the process.

3. IMPACTS THAT MAY RESULT FROM THE DECOMISSIONING AND CLOSURE PHASE Briefly describe and compare the potential impacts (as appropriate), significance rating of impacts, proposed mitigation and significance rating of

impacts after mitigation that are likely to occur as a result of the decommissioning and closure phase

Although no decommission is envisaged in the long-term, the table below presents potential impacts and

mitigation measures should this take place in future.

Page 32: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

31

Potential impacts: Significance

rating of

impacts:

Proposed mitigation: Significance

rating of

impacts after

mitigation:

Risk of the

impact and

mitigation not

being

implemented

Geology and soils - Soil erosion and loss

of soils. - Stability of slopes

and stream banks

- Protection of exposed soils.

- Soil erosion prevention measures

implemented especially during rainy

season.

- Immediate rehabilitation of exposed

areas.

- Provide effective short-term measures for

slope stabilisation, sediment control and

subsidence control

- Provide adequate drainage systems to

Medium

Hydrology and Water

pollution

Sediment mobilisation and

transport in short to medium

term

Debris in the wetland system

- Prevention of sediment transportation by

use of sediments ponds.

- Use of trappings to reduce amount of

debris in the water.

- Avoid works during high-flow periods.

Limit movement into and across the

stream to the essential.

- Diverting stream-flow to avoid mixing of

water with high solid content.

Medium

Fauna and Flora-

- Re-establishment of

natural vegetation

(long-term)

- Connectivity and

ecosystem establishment

(long- term)

Rehabilitation measures including planting of

vegetation implemented

Low

Waste

Generation and

disposal of solid waste could

have negative consequences

on the environment

- Part of demolition material to be re-used

on other construction sites;

- Limit disposal at landfills to non-

recyclable material;

- Waste must be disposed of in the

appropriate manner at a licensed disposal

site.

Low

Air quality

Dust pollution Noise pollution

- Dust control measures (water

suppression, covers etc)

- Avoid demolition during windy months

Restricted working hours

- Noise abatement measures implemented

Low

Negative Socio-economic

impacts

Loss of accessibility. Traffic

congestion on alternative

routes Scaring of the affected

land in the short-

medium term

- Alternative routes/diversions used.

- Upgrades on other adjacent roads to

accommodate traffic

- Decommissioning and rehabilitation plan

created and implemented

Medium

Employment opportunities

Temporary job opportunities

created

+ve Use of labour from surrounding communities +ve

Page 33: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

32

Where applicable indicate the detailed financial provisions for rehabilitation, closure and ongoing post decommissioning management for the

negative environmental impacts.

N/A

4. CUMULATIVE IMPACTS

Describe potential impacts that, on their own may not be significant, but is significant when added to the impact of other activities or existing impacts

in the environment. Substantiate response:

Cumulative impacts refer to the incremental impacts resulting from the implementation of an activity on a

common resource which are added to the impacts of other past, present or reasonably foreseeable future

activities. The potential cumulative impacts of the township both during construction and occupation by

considering the effects of the development have been considered relative to the;

- The biophysical environment; and

- Socio-economic conditions

Specific impacts will include:

- Increase in noise pollution during construction- construction only during daytime, to reduce noise

pollution and not upset residents of the area.

- Increase in water pollution as a result of construction of the culverts and general construction

activities in the area:- measures to be put in place to limit water pollution, siltation and soil

compression. Excavated materials to be stockpiled in designated areas to prevent interference with

the natural drainage or cause siltation or water pollution.

- Alteration of surface water flows during construction and operational phases and general

disturbances to the water resources as a result of alien vegetation and siltation. Storm water

management plan to be implemented and alien vegetation cleared.

- Dusty conditions may increase: -access roads to be checked and dust prevention measures

implemented.

- During the construction phase some safety and security problems (especially for the surrounding

residents) are likely to occur.

- Improvement in vehicular flow and traffic movement in the area due to additional high order road

being opened up.

The impacts can be mitigated if activities are correctly planned and measures implemented to manage

activities which could cause any negative cumulative impacts.

5. ENVIRONMENTAL IMPACT STATEMENT Taking the assessment of potential impacts into account, please provide an environmental impact statement that sums up the impact that the

proposal and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account with

specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts.

Proposal

The application is for the upgrading and extension of the existing 3 culverts bridge on Allandale Road as part

of the associated infrastructure upgrade for the Kyalami Gardens Ext 27 development on the Remainder of

Portion 2 and the Remaining Extent of Portion 88 of the Farm Bothasfontein 408 JR, City of Johannesburg

Metropolitan Municipality. The upgrades in Allandale Road include road widening in sections of road with

three existing culverts. These culverts will be extended to suit the wider new road. The development is

necessary to improve traffic circulation in the area and to allow for the development of the remaining

phases of the abovementioned township.

Since the proposed development will traverse a freshwater resource, the probability that some short term

egati e i pa ts ill o u is o side ed defi ite . Ho e e due to the development only spanning across

the channeled valley bottom wetland and a small tributary if the Jukskei which is not too wide, impact

significance prior to the implementation of mitigation measures during construction is deemed to be of

Page 34: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

33

medium to low levels, whilst without mitigation, impact significance during the operational phase will be of

low levels. However, efficient and effective implementation of well-designed mitigation measures can

reduce impact significance during both phases to low and very levels.

The primary modifier of the watercourse in terms of geomorphology is due to the insufficient amount of

existing culverts underneath Allandale Road, creating higher velocity and concentrated flows which has

significantly eroded the downgradient system, causing stream bank, stream bed incision and sedimentation

of the downstream system. Increased sediment loads entering the system are also due to reduced

vegetation cover, and this additional sediment contributes to scouring of the wetland channel and is

exacerbated at the culvert invert. Sediment deposits north of Allandale Road have also created additional

substrate for vegetation to establish within the wetland, increasing the surface roughness of this resource.

Due to increased velocity of stormwater inputs because of the increased impermeable surfaces and loss of

vegetation in the catchment, modifiers to the geomorphology of the tributary can mainly be attributed to

stream bank and stream bed incision and erosion. Increased sediment into the system are also anticipated

due to reduced vegetation cover and impermeable surfaces, which contributes to stream bed scouring

(especially at long drops of the culverts).

The vegetation component om this wetland is dominated by reed species (Phragmites australis and Typha

capensis). The sediment substrate allowed for the invasion of a monoculture of Phragmites australis,

dominating the entire northern section of this wetland, reducing the available substrate for other

indigenous species to establish. Due to this monoculture, floral biodiversity is low, but this wetland still has

the potential to provide habitat for other faunal species. Some proliferation of alien and invasive floral

species was also evidenced at the outer edges of the wetland, and where infrastructure (road, culverts) has

been constructed. Despite alterations to the surrounding environment, Hypoxis hemerocallidea was

observed within the wetland zone. This species is considered to be declining according to the SANBI Red List

and GDARD (orange listed species), and as such is considered as a Species of Conservation Concern (SCC).

Since the applicable section of the tributary is deemed to have been significantly modified, it is deemed

unlikely that further negative impacts would have a significant impact on the ecology of this section,

although cognisance must be taken of downstream, cumulative effects of such impacts. Therefore, it is

recommended that measures be implemented to preserve and improve the ecological functioning of this

section.

It is therefore concluded that whilst the freshwater resource is deemed to be in a heavily modified

condition, primarily as a result of various historic and recent anthropogenic activities which have caused

modifications to the geomorphology, vegetation and hydrological functioning of the system, further

degradation of the resource should not be permitted. Whilst it is not feasible to completely avoid potential

impacts as a consequence of constructing the proposed linear development, the need to prevent further

degradation should not be seen as a fatal flaw, but rather as an opportunity to improve the present state of

the river system, whilst simultaneously providing key infrastructure for development associated with this

road. Moreover, the road will help manage traffic issues related to the burgeoning development of

residential and commercial estates around the area.

Throughout the report it has been demonstrated that the proposal is sound and impacts are very minimal

and can be mitigated to acceptable le els, the e s o st o g justifia le easo to ot autho ise the development.

No-go (compulsory)

The o-go alte ati e is the optio of ot upg adu g the oad. This alte ati e ould esult potentially result in opportunities for provision of services on the site not realised. Access to good

Page 35: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

34

infrastructure services is vital in an ever expanding urban landscape in Johannesburg. The

extension of the existing culverts bridge on Allandale Road as part of the associated infrastructure

upgrade for the Kyalami Gardens Ext 27 development on the Remainder of Portion 2 and the

Remaining Extent of Portion 88 of the Farm Bothasfontein 408 JR, City of Johannesburg

Metropolitan Municipality is viable in making the development viable.

6. IMPACT SUMMARY OF THE PROPOSAL OR PREFERRED ALTERNATIVE

Impact Significance after mitigation

Proposal No-Go

DESIGN AND PLANNING PHASE

Authorisations, Permits, Licenses and appointment of personnel

Access Roads

Construction camp

Culverts design

CONSTRUCTION PHASE

Geology and soils +ve

Fauna and flora +ve

Topography

Air Quality

Wetland and surface water +ve

Noise +ve

Visual Intrusion & Light pollution +ve

Waste management

Traffic -ve

Safety and Security

Disruption to Road Users & Road Infrastructure

Impacts to Cultural/ Historical Resources

Employment /job opportunities created +ve -ve

Alignment with spatial plans +ve -ve

OPERATIONAL PHASE

Fauna and flora

Compliance with municipal spatial plans +ve -ve

For proposal:

After mitigation, the significance of all impacts in the short-term, are rated as low. Positive impacts of

medium significance would be realised in employment opportunities as well as compliance with the spatial

plans.

No-go alternative:

The no-go option will have low impacts on the environment; it will also have pronounced negative

impacts on the social and economic environment and therefore is not preferred.

Having assessed the significance of impacts of the proposal and alternative(s), please provide an overall summary and reasons for selecting the

proposal or preferred alternative.

The summary opinion of the proposed development is provided below as follows:

Bio-Physical Environment

- The portion of the channeled valley bottom wetland to be traversed by the road is not considered to

be particularly ecologically sensitive as a result of historical and ongoing impacts (associated

primarily with rapid urban development in the catchment). Although the activity will affect a water

course, adherence to cogent, well-conceived and ecologically sensitive site development plans, and

Page 36: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

35

the mitigation measures provided as well as general good practice mitigation will greatly reduce the

significance of perceived impacts.

- No red listed species or sensitive fauna and flora are present on site or adjoining areas.

- The significance of most of the negative construction related impacts can be mitigated to between

low and very low significance

The information contained in this DBAR and specialist studies, provides a detailed and comprehensive

description of the proposed project, baseline environment and potential environmental impacts associated

with the proposed activity. As no significant impacts that cannot be mitigated were identified, we are of the

opinion that the project should proceed, provided the necessary mitigation and management measures are

implemented.

Social-economic Environment

- The road infrastructure and the related bridge are necessary to allow for the development of the

approved Kyalami extension 27 developments to proceed.

- The road will improve the north-south linkages and traffic flow in the area.

- Some employment opportunities will be created during the construction phase.

Alignment with spatial plans

The development proposal is compatible with the RSDF and the Provincial EMF and will support integrated

development.

7. SPATIAL DEVELOPMENT TOOLS Indicate the application of any spatial development tool protocols on the proposed development and the outcome thereof.

The Present Ecological State (PES) of the watercourse and its associated riparian zone was determined

according to the WET-IHI method described by DWAF (2007) The function and service provision of the A

channelled valley bottom wetland was assessed utilising the WET-Ecoservices as described by Kotze et al.

(2009). Further, the activity is compatible with:

- City of Johannesburg Metropolitan Regional Spatial Development Framework;

- Gauteng Environmental Management Framework.

8. RECOMMENDATION OF THE PRACTITIONER

Is the information contained in this report and the documentation attached hereto sufficient to make a decision in respect of the

activity applied for (in the view of the Environmental Assessment Practitioner as bound by professional ethical standards and the

code of conduct of EAPASA).

YES NO

If NO , i di ate the aspe ts that e ui e fu the assess e t efo e a de isio a e ade list the aspe ts that require further assessment):

Nil

If YE“ , please list a e o e ded o ditio s, i ludi g itigatio easu es that should e o side ed fo i lusio i a y authorisation that may

be granted by the competent authority in respect of the application:

The assessment has indicated that, with mitigation measures identified, the negative impacts associated

with the activity will be mitigated to acceptable levels, while the positive impacts will be enhanced. From

the socio-economic and biophysical implication aspects the application should be approved, provided that

the esse tial itigatio , eha ilitatio a d o ito i g easu es a e i ple e ted. N““ elie es the e s reasonable motivation and enough mitigation measures to mitigate the impacts of the development on the

wetland and river system.

RECOMMENDATIONS

- The recommendations of the Surface Water Rehabilitation and Management Plan must be strictly

Page 37: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

36

implemented to manage impacts.

- Monitoring and removal of alien vegetation must be undertaken continuously for three months after the

construction of the bridge has been completed and during the first growing season.

- Effective and strict erosion control throughout the construction phase is imperative. Erosion berms

should be installed to prevent gully formation and further siltation of the channeled valley bottom

wetland. Erosion controls must be regularly maintained, at minimum on a fortnightly basis, particularly if

rain is forecast or immediately following a rainfall event. Soil stockpiles should be placed outside of the

32m buffer zone, and protected with a suitable geotextile.;

- All areas where soils are exposed or destabilised need to be stabilised taking into account the following:

o As far as possible soft engineering techniques and earthworks should be used, with special mention

of resloping of banks, revegetation of banks and stabilisation using products such as hessian sheets

and socks;

o Hard engineering techniques should only be implemented in areas where engineering and hydraulic

constraints require such interventions. In particular mention is made of gabions, reno mattresses

and reinforced walls.

o Following completion of construction, reprofiling of the banks of disturbed riparian areas must take

place, and must be revegetated with indigenous gramminoid species such as Arundinella

nepalensis, Imperata cylindrica, Setaria sphacelata and Eragrostis gummiflua;

- Adequate stormwater management must be incorporated into the design in order to prevent erosion,

bank incision and streambed scouring and the associated sedimentation of the watercourse. Use of

g ee o soft e gi ee i g te h i ues su h as “ustai a le D ai age “ ste s [“uD“] is highl recommended;

9. THE NEEDS AND DESIREBILITY OF THE PROPOSED DEVELOPMENT (as per notice 792 of 2012, or the

updated version of this guideline)

In terms of securing ecologically sustainable development and proper use of natural resources, the

proposed activity is essential for efficient traffic movement and will allow for the development of the

approved Kyalami Extension 27. Although the activity affects the channeled valley bottom wetland, the

portion of the river to be traversed by the proposed linear development is not considered to be particularly

ecologically sensitive as a result of historical and ongoing impacts (associated primarily with rapid urban

development in the catchment. However, as part of the development, mitigation measures, including

implementation of a Rehabilitation Plan will be implemented.

The demand for efficient traffic movement in and around Midrand means that the roads and associated

infrastructure need to be upgraded to support this demand, therefore the proposed upgrading of culvert on

Allandale Road is crucial to fulfilling the objectives of the Regional Spatial Development Framework.

10. THE PERIOD FOR WHICH THE ENVIRONMENTAL AUTHORISATION IS REQUIRED (CONSIDER WHEN THE

11. ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) (must include post construction monitoring requirements and when these will be concluded.)

If the EAP answers Yes to Point 7 above then an EMP is to be attached to this report as an Appendix

EMPr attached Yes

10 years

Page 38: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

37

SECTION F: APPENDICES The following appendixes must be attached as appropriate (this list is inclusive, but not exhaustive):

It is required that if more than one item is enclosed that a table of contents is included in the appendix

Appendix A: Site Plan

Appendix A¹: Locality Plan

Appendix A²: Layout Plan

Appendix B: Site Photographs

Appendix C: Facility illustration(s)

Appendix D: Route position information

Appendix E: Public Participation information

Appendix E¹: Proof of Notices

Appendix E²: Written Notices Issued

Appe di Eᵌ: Ne spape Ad e t Appe di E : Mi utes of Meeti gs

Appe di E : Co e ts of Issues ‘epo t Appe di E : Co e ts a d I&Aps o BA‘

Appe di E : Cop of ‘egiste of I&Aps

Appendix F: Water use license(s) authorization, SAHRA information, service letters from municipalities,

water supply information

Appendix G: Specialist reports

Appendix G¹: Wetland Assessment Report

Appendix G²: Surface Water Rehabilitation and Management Plan

Appe di Gᵌ: Co st u tio Method “tate e t

Appendix H: Draft EMPr

Appendix I: Other information

The public participation information will be included on the Final Basic Assessment Report

CHECKLIST

To ensure that all information that the Department needs to be able to process this application, please check

that:

Where requested, supporting documentation has been attached;

All relevant sections of the form have been completed.

Page 39: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

38

APPENDIX A: SITE PLAN

Page 40: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

39

APPENDIX A¹: LOCALITY PLAN

Page 41: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

40

APPENDIX A²: LAYOUT PLAN

Page 42: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

41

APPENDIX B: SITE PHOTOGRAPHS

Page 43: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

42

APPENDIX C: FACILITY ILLUSTRATION

Page 44: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

43

APPENDIX D: ROUTE POSITION

N/A

Page 45: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

44

APPENDIX E: PUBLIC PARTICIPATION

INFORMATION

Page 46: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

45

APPENDIX E¹: PROOF OF NOTICES

(To be included on the Final BAR)

Page 47: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

46

APPENDIX E²: WRITTEN NOTICES ISSUED

(To be included on the Final BAR)

Page 48: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

47

APPENDIX Eᵌ: PROOF OF NEWSPAPER

ADVERTISEMENTS

Page 49: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

48

APPENDIX E : COMMUNICATIONS TO AND FROM INTERESTED PARTIES

(To be included on the Final BAR)

Page 50: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

49

APPENDIX E : MINUTES OF ANY PUBLIC AND/OR STAKEHOLDER MEETINGS

(To be included on the Final BAR)

Page 51: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

50

APPENDIX E : COMMENTS AND RESPONSES REPORT

(To be included on the Final BAR)

Page 52: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

51

APPENDIX E : COMMENTS FROM I&APs ON

BASIC ASSESSMENT (BA) REPORT

(To be included in the Final BAR)

Page 53: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

52

APPENDIX E : COPY OF THE REGISTER OF I&APS

Page 54: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

53

APPENDIX F: WATER USE LICENSE(S)

AUTHORISATION, SAHRA INFORMATION

SERVICE LETTERS FROM MUNICIPALITIES,

WATER SUPPLY INFORMATION

Page 55: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

54

APPENDIX G: SPECIALIST REPORTS

Page 56: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

55

APPENDIX G¹: WETLAND ASSESSMENT

Page 57: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

56

APPENDIX G²: REHABILITATION AND

MANAGEMENT PLAN

Page 58: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

57

APPENDIX Gᵌ: CONSTRUCTION METHOD

STATEMENT

Page 59: DRAFT BASIC ASSESSMENT REPORTnalisustainabilitysolutions.co.za/wp-content/... · 2. impacts resulting from the construction and operational phase 24 3. impacts resulting from the

Upgrade of Culverts Along Allandale Road - Gaut 002/16-17/E

58

APPENDIX H: DRAFT EMPR