dpr of hulasganj cluster_5dec2012
TRANSCRIPT
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 1/81
Detailed Project Report
on
‘Rural Electrification through Renewable based
Decentralized Distributed Generation System
In Hulasganj Block of Jehanabad District in Bihar
using Locally Available Renewable Energy Resource’
Submitted to
MINISTRY OF POWER&
UNDP
Prepared by :
ABPS INFRASTRUCTURE ADVISORY PVTLTDDecember 2012
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 2/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 2
Disclaimer: ABPS Infra has taken due care and caution in compilation of data as has been obtained fromvarious sources including which it considers reliable and first hand. However, ABPS Infra doesnot guarantee the accuracy, adequacy or completeness of any information and it not responsible forerrors or omissions or for the results obtained from the use of such information and especiallystates that it has no financial liability whatsoever to the subscribers / users of this Report.
No part of this report can be reproduced, stored in a retrieval system, used in a spreadsheet ortransmitted in any form or by any means without permission of ABPS Infrastructure AdvisoryPrivate Limited.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 3/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 4/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 4
9 PROJECT IMPLEMENTATION PLAN........................................................................... 589.1 Project Site and Grid Connectivity..................................................................................58
9.2 PDN and Asset Management ......................................................................................... 58
9.3 Protocol for Power Generation and Grid Management .................................................599.4 Arrangement for Insulation of Agricultural Load............................................................60
9.4.1 Feeder Separation...........................................................................................................60
9.4.2 Franchisee Arrangement................................................................................................. 60
9.4.3 Demand Response...........................................................................................................60
9.5 Franchisee Arrangement for MBC..................................................................................61
9.6 Criteria for PD selection ................................................................................................. 61
9.7 Contractual Arrangements............................................................................................. 61
9.7.1 Franchisee Agreement ....................................................................................................62
9.7.2 Power Purchase Agreement............................................................................................64
9.8 Financial assistance needed to ensure financial viability ............................................... 65
9.9 Bid Process Management............................................................................................... 66
10 Roll out plan for proposed RE based DDG project .................................................... 67
Annexure A information data base of Villages-Hamlets in selected cluster ..................... 68
Annexure B: Economic assessment of agro-residue as energy resource ........................... 78
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 5/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 5
List of Tables
Table 2.1Comparative Analysis of Potential Short-Listed Clusters ...................................... 10Table 3.1 Village & Hamlets in the Identified Cluster ......................................................... 15
Table 3.2 Demographic Details of Selected Cluster .............................................................. 16
Table 4.1 Electrification Status and Present Energy Usage in Selected Cluster ................... 18
Table 4.2 Estimation of Residential Load............................................................................. 19
Table 4.3 Estimation of Streetlight Load.............................................................................. 20
Table 4.4 Estimation of Community Building Load............................................................. 20
Table 4.5 Estimation of Non-Residential Productive Load................................................... 20
Table 4.7 Hourly scheduled load curve for sizing of RE based DDG power plant ................ 23
Table 4.8 Assessment of RE resource (Biomass) Availability within Selected Cluster .......... 26
Table 4.9 Potential Capacity for Power Generation ............................................................. 27
Table 4.10 Resource (Biomass) Feasibility Check................................................................. 27
Table 5.1 Space requirement for Biomass Storage ................................................................ 32
Table 5.2 Details of the Land Available for the DDG Plant in the Cluster ........................... 32
Table 5.3 Specifications and performance parameter of gasifier based power plant............... 32
Table 5.4 Project cost of typical 1MW gasifier based power plant ........................................ 34
Table 6.1 Panchayat wise estimated DT capacity requirement (kVA) .................................. 39
Table 6.2 Capacity wise Requirement of DTs ..................................................................... 40
able 6.3 Requirement of Distribution Transformer Capacity .............................................. 41
Table 6.4 Cost estimation of capacity addition of DTs required in the cluster ...................... 44
Table 6.5 Cost Estimation of 400V PDN Line in Cluster .................................................... 46
Table 6.6 Cost Estimate of Total PDN Infrastructure of Cluster (in Lacs) ........................... 46
Table 7.1 Various parameters and assumptions for financial analysis ................................. 48
Table 7.2 Cost of generation (COG) of electricity from biomass gasifier power plant ........... 49
Table 7.3 Cost of generation (COG) and Viability Gap under different scenarios ................ 50
Table 8.1 SWOT analysis of IPP model............................................................................... 56
Table 8.2 SWOT analysis of DGBDF Model....................................................................... 56
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 6/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 6
List of Figures
Figure 3.1Map of Jehanbad district and Hulasganj block..................................................... 12Figure 3.2 Map of Hulasganj Block, and short-listed cluster in the Block ............................ 13
Figure 3.3 Schematic of selected cluster showing villages-hamlets & existing PDN details . 14
Figure 4.1 Hourly load scheduling pattern in the cluster .................................................... 24
Figure 5.1 Schematic Diagram for Biogasifier ..................................................................... 30
Figure 5.2 Schematic Diagram proposed biomass Gasifier Power Plant............................... 35
Figure 5.3 Schematic Diagram proposed biomass Gasifier Power Plant............................... 36
Figure 8.1 Operational Structure of IPP Model .................................................................. 53
Figure 8.2 Operational Structure of DGBDF Model ........................................................... 55
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 7/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 7
1 INTRODUCTIONIndia being agriculture oriented country; the Government of India (GoI) views Rural
Electrification as a major prime mover for rural development for the improvement of
Human Development Index. Electricity is also considered as the basic pre-requisite for all
industrial activity and also contributes significantly to increasing agricultural productivity,
jobs and income generation activities. Government has given the priority for the rural
electrification in several policies and acts, also initiated several programs at the national
level to promote electrification of remote villages.
Renewable energy technologies have substantial potential to provide a reliable and secure
energy supply as an alternative to grid extension or as a supplement to grid-provided power
and therefore ideally suited to electrification of rural and especially remote areas which are
still lacking to access to modern energy source like electricity; major barrier perceived for
rural development. In India, locally available, renewable energy sources such as solar
energy, biomass, wind, or hydro energy can go a long way in alleviating the problem of lack
of electricity and can play a prominent role in extending access to energy. Government
promoted the deployment of various renewable energy technologies, which include family
biogas plants, solar street lights, solar lanterns, solar PV systems, biomass gasifiers and
micro-hydro plants. Despite all such policy interventions across the years, actual
performance on rural electricity services continues to be dismal.
In 2005, the Ministry of Power launched Rajiv Gandhi Grameen Vidyutikaran Yojana
(RGGVY) merging all ongoing rural electrification schemes, under the initiative “Power for
all by 2012”. The RGGVY scheme aims to provide electricity to rural areas through extension
of existing grid and by augmenting the infrastructure. Under RGGVY government has set
aside Rs 540 crores subsidy for electrification of hamlets and habitations which are not being
covered under the scheme on account of their remote locations through Decentralized
Distributed Generation (DDG) scheme as sub component of RGGVY. The development of
DDG based plant shall be focused on the harnessing the suitable renewable technologies
which is based on the locally available resource for generation of electricity in economical
way and distributing it in the identified cluster.
In the recent year the implementation of DDG has shown that remote village/hamlets are
spread very thinly and not offer the economy of scale to the project developers. On the other
hand there are many villages which are electrified and grid connected, but do not receive
adequate supply of electricity. Such villages are presently not covered under DDG.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 8/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 8
With continued increasing energy shortages it is difficult to expect significant improvement
in energy access situation in near future. Though India has embarked upon an ambitious
programme of rural electrification viz. RGGVY, which may be expanding the grid
connectivity rapidly to several uncovered areas, the actual supply of electricity through the
established grid would still remain unpredictable and limited. Therefore providing
accessible, affordable and acceptable electricity to villages for ensuring energy security for
the poor would continue to be a major concern in electrification.
Recently MoP has also relaxed the guidelines of DDG for Left Wing Extremism (LWE)
affected districts for decentralized generation and distribution and has allowed coverage of
grid connected villages where supply of electricity is less than 6 hours or under-electrified.
In order to achieve the target of complete electrification the un-electrified villages, Ministry
of Power (MoP) has been implementing a project “Access to Energy – enhancing
effectiveness in electricity distribution and end-uses” with core funding from UNDP with
focus on up-scaling of DDG (Decentralized Distributed Generation) for achieving goal of
overall sustainable development in remote rural India. Under this initiative, UNDP is
supporting the up-scaling of DDG system as one of the core components of the project. As
part of the initiative, Access to Energy wanted to develop a Detailed Project Report (DPR)
and a Feasibility study of rural electrification through renewable based decentralized
distributed generation in Bihar.
This report is Detail Project Report (DPR) on Rural Electrification through Renewable based
Decentralized Distributed Generation System in a selected cluster of 42 contiguous villages
(a mix of un-electrified and under-electrified) in Hulasganj Block of LWE District of
Jehanabad in Bihar, using locally available biomass resource and solar energy. This DPR
gives the requisite details on the cluster identification, socio–demographic analysis of the
selected cluster, estimation of different types of load and associated energy demand for
different power consumer categories as well as estimation of biomass resource availability
within the selected cluster for the deciding the capacity of the proposed biomass gasifier
power plant.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 9/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 9
2 CLUSTER FINALIZATION FOR DPR PREPARATIONThis section gives details of step by step approach adopted for selecting and finalizing the
selected cluster of contiguous habitations comprising of un - & under-electrified
villages/hamlets for DPR preparation.
In consultation with key stakeholders of the Project Steering Committee, a cluster of
villages/hamlets was identified in Hulasganj block of Jehanabad district of Bihar. Various
steps involved in finalizing the cluster are summarized below:
• Based on the secondary information for the targeted LWE districts, 3 potential blocks
viz Kaler (Arwal district), Haspura (Aurangabad district) and Manpur (in Gaya
district) were identified in October 2011
• In November 2011, 12 potential clusters in these blocks not covered under RGGVY
with good mix of under-electrified & un-electrified villages/hamlets were identified.
Field visits for assessment of ground realities in short-listed 4 clusters viz Nabinagar
(Aurangabad), Jhajha (Jamui), Arawal (Arwal) and Hulasganj (Jehanabad) were
carried out in December 2011. During the field visit and analysis of the electrification
status of the villages following observations made (See Table 2.1),
Nabingar – Aurangabad, almost all villages & even large tolas electrified
under RGGVY & some small tolas (10-30HHs) left out.
Hulasganj-Jehanabad: only census villages got electrified and large tolas yet
un-electrified (in many cases tolas larger than main village).
Jhajha-Jamui: Mixed situation. Some RGGVY villages are electrified & many
un-electrified and some smaller tolas un-electrified
Arwal-Arawal: All villages covered under RGGVY but yet to get electricity
and some tolas are un-electrified
Finally in December 2011, based on recommendations of Project Coordination Committee,
cluster consisting of 42 habitations (villages/hamlets both un-electrified and under-
electrified) in Hulasganj block of Jehanabad district was selected for this DPR preparation
for development of planned cluster based rural electrification project in LWE district of
Bihar under Access to Energy Programme of UNDP-MoP.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 10/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 10
Table 2.1Comparati ve Anal ysis of Pot enti al Short -Li st ed Cl ust ers
Parameters Hulasganj(Jehanabad)
Nabinagar(Aurangabad)
Arwal (Arwal) Jhajha (Jamui)
No of villages 48 300 67 172
No of villages notcovered under RGGVY
8 81 14 39
No of hamlets notcovered RGGVY
NA 88 NA 70
Possible cluster ofvillages/hamletsUnder-electrified (<6hrs)Un-electrified
~39~14~25
~39~36~3
~40~20+~20
~43~13~30
Terrain Quite plain withgood agriculturedue to adjoining
canal & river
Quite plain. Goodagriculture due tolow water table
Quite plain, Goodagriculture due toadjoining canal-
river
Hilly toughterrain. Forestarea with low
agricultureExisting electrificationstatus
RGGVYinfrastructureactive thoughunder-supply for3-6hrs. Thoughmany censusvillages gotelectricity underRGGVY manylarge tolas still leftout and even inunder-electrified
villages mostlyminimal BPLconnections andrest don’t haveelectricity supply
RGGVYinfrastructureactive thoughunder-supply for2-4hrs. Most ofvillages as well asbig tolaselectricity underRGGVY and onlysmall (5-30HHs)are left out. Somepeople have taken
connections inaddition to BPLconnections.
RGGVYinfrastructure isin-active due totheft etc andtherefore manyvillages coveredunder RGGVY arestill un-electrified.Few tolas left outand are un-electrified.
RGGVYinfrastructure isin-active in manyvillages coveredunder RGGVYthough very fewget electricity forfew hours.
Observations on clusterformation
Goodcombination(60:40) of un-electrified andunder-electrified(<6hrs supply)villages underRGGVY
Less than 10% un-electrified villageswith rest under-electrified (2-4hrssupply) villagesunder RGGVY
Though all un-electrified with~20 un-electrified-non-RGGVYhamlets but othervillages arecovered underRGGVY though
are still withoutelectricity sogetting financialclearance for sameset of villages inDPR could bemain issue
Though looksreasonablecombination(30:70) of under-electrified and un-electrified morethan 2/3rd of un-electrified villages
are still withoutelectricity thoughcovered underRGGVY so gettingfinancial clearancefor same set ofvillages in DPRcould be mainissue.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 11/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 11
Parameters Hulasganj(Jehanabad)
Nabinagar(Aurangabad)
Arwal (Arwal) Jhajha (Jamui)
Renewable energy
options
Biomass-agro
residue, solar
Biomass-agro
residue, solar
Biomass-agro
residue, micro-hydro, solar
Biomass-forest
residue, solar
Biomass availability Mainly agro-residue like ricehusk inabundance
Mainly agro-residue like ricehusk inabundance
Mainly agro-residue like ricehusk inabundance
Mainly forest-residue so mightnot be sustainable
Demonstration effect Very High Very High High Low
Private SectorParticipation
Likely Likely Unlikely Unlikely
Over ranking withremarks
1Good mix of diff
category ofvillages. Good
biomassavailability
2Large no of underelectrified but few
un-electrified
villages. Goodbiomass
availability.
3All villages
without electricityand many
covered byRGGVY. Good
biomass & hydro
4Hilly terrain, low
agro residueavailability.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 12/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 12
3 SELECTED CLUSTER PROFILEThis section provides the brief description of the selected cluster of contiguous
villages/hamlets summarizing the demographic details of the cluster consisting of various
un-electrified and under-electrified villages/hamlets covered within it.
3.1 Hulasganj blockHulasganj is one of the seven blocks in the Jehanabad district located at south eastern corner
of district sharing border with adjoining districts of Gaya and Nalanda. It consists of nine
panchayats and 48 census villages with block headquarter located at Hulasganj. This region
was earlier part of Ghoshi block before division of Jehanabad district to form new district of
Arwal. As per 2001 census, there were in all 11,239 households with total population of
77,248.
The demographic details of Hulasganj block can be summarized as follows:
Total population of block is 77,248
There are 48 villages in 9 panchayats and has no town
Literacy rate is 55.53%. (Female - 39.97%. & Male 70.15%)
No of households in Hulasganj is 11,239. All households are rural.
Female to male ratio of Hulasganj 93.06% (compared to 91.93% of Bihar)
Total working population is 53.65% (63.0% men & 43.71% women)
Figure 3.1Map of Jehanbad di stri ct and Hu lasganj bl ock
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 13/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 13
Main working population is 36.58% (51.94% men & 20.24% women)
Marginal working population is 17.07% (11.06% men & 23.47% women)
Total non-working population 46.35% (37.0% men & 56.29% women)
3.2 Selected cluster for rural electrification through RE based DDG plantInitially five panchayats (out of total nine panchayats in the block) spanning from entrance
of the block after crossing Phalgu river from north-west corner till the block head quarter at
Hulasganj (upper north-west portion of block), had been short-listed for the formation of the
cluster of contiguous villages/hamlets (mix of un-electrified and under-electrified) for
preparation of DPR of proposed DDG plant (see Figure 3.2).
Figure3.2 M ap of Hul asganj Block, and short -l isted cl ust er i n t he Bl ock
However, during the field survey, while gathering the information about existing electricity
distribution system, it was observed that the villages in Murgaon Panchayat have been
connected through a different grid distribution line having generally good electricity supply,
whereas rest of the villages in the remaining four panchayats of the selected cluster of
Hulasganj block are connected to the common grid distribution line coming from Hulasganj
substation. Therefore, in the final configuration of selected cluster, villages under Murgaon
Panchayat were excluded from initially short-listed cluster consisting of five panchayats, so
as to have a homogenous cluster that can be coupled to a single substation grid distribution
network later.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 14/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 14
It was also noticed that, a new substation is being constructed at Dhongra Mushari hamlet of
Tesaur village in Chiri Panchayat under RGGVY programme, which is likely to get ready in
near future. This substation is located almost at the middle of the selected cluster and
therefore can later very well be used to connect distribution network of proposed renewable
energy based grid interactive DDG Plant with the local distribution grid.
Thus, the finalized selected cluster now has 42 contiguous habitations (24 villages and 18
hamlets) comprising of both 25 under electrified (where BSEB and/or RGGVY grid line has
reached but annual average daily power supply is below 6hrs) and 17 un-electrified
habitations from four panchayats namely Bauri, Chiri, Khudaur, Kokarsa, and Murgaon,
have been considered to form the cluster for this DPR for proposed grid interactive
renewable energy based DDG plant. Figure 3.3 below, shows the map of the selected cluster
in the Hulasganj block and also gives details of existing power distribution network within
the selected cluster.
Figure 3.3 Schematic of selected cluster showing villages-hamlets & existing PDN details
The Table 3.1 below gives panchayat-wise list of census villages and respective associated
hamlets included in the selected cluster for this DPR reparation.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 15/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 15
Table 3.1 Vi ll age & Haml et s in t he I denti fi ed Cluster
Chiri Panchayat Kokarsa Panchayat
Census Village Associated Hamlets Census Village Associated HamletsChiri Kokarsa
Dumri Mirjapur
SarmaManjhi Tola Sukiyawa
Ratan Bigha Lodipur
Sisara Rustampur Beldaripur
GinjiChaiti Pipar
Dhongra
Tesaur Dhongra Mushari Bauri Panchayat
Sarthua
Bulaki Bigha Census Village Associated Hamlets
Kolbhapur Bauri Kisunpur
Sevapuri Gidarpur
Bhattu Bigha Bihta
Dersai Bigha Rupa Bigha
Khudauri Panchayat Dihuri
Census Village Associated Hamlets Adrakhi Bigha
Khudauri Rampur Dadpur
Raghunathpur Harpur
NarmaEmitdpur Kewla
Beripur
Walipur
MoqueempurGolakpur
The selected cluster falls between longitude 85.1124036E to 85.1702535E and latitude
25.06028N to 25.1688536N spanning over four panchayats (Bauri, Chiri, Khudaur, and
Kokarsa). The total geographical area of villages included in the cluster is about
4,669 hectares and the total cluster population is 43,369 (as per census -2011) residing in
6,402 households. The average household income is of about Rs 3417/- per annum within
the selected cluster habitations.
3.3 Demographic details of selected clusterThrough extensive literature survey as well as through questionnaire based village/hamlet
level focus group discussions (FGDs) and sample household surveys, large amount of data-
information such as demographic data, census data, and village profile and biomass
availability has been gathered for villages/hamlets included in the selected cluster.
Following Table 3.2 summarizes the panchayat-wise information-data giving profile of
selected cluster of villages/hamlets in Hulasganj block of Jehanabad district. Panchayat-
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 16/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 16
village/hamlet wise profile information is summarized in the tabulated form in
Annexure A.
Tabl e 3.2 Demographi c Det ai l s of Sel ected Cl ust er
Parameters\Panchayat Bauri Chiri Khudauri Kokarsa ClusterTotal
Census Code 3773600 3771900 3773700 3775100
GPS Coordinates 25°3'56"N85°7'8"E
25°11'15"N85°8'5"E
25°7'6"N85°8'36"E
25°4'48"N85°7'42"E
No VillagesNo of HamletsTotal No of
villages/hamlets
64
10
710
17
63
9
51
6
2418
42
No of electrified (under-electrified) habitations***
6 9 5 5 25
No of un-electrifiedhabitations###
4 8 4 1 17
Village Area (ha) 881 1,532 1,099 1,157 4,669
Population-2001 census 7,497 9,744 8,585 10,391 36,217
Poulation-2011 census 9,881 11,551 9,876 12,061 43,369
No of HHs – as per survey 1,680 1,697 1,160 1,865 6,402
No of BPL HHs 887 879 610 660 3036
No of Non-BPL HHs 793 818 550 1205 3366
*** villages/hamlets where BSEB and/or RGGVY grid has reached but annual average daily power supplyis below 6hrs
### hamlets/ villages where grid has not reached so far
Main lively hood activities in the cluster are agriculture, service and labour work. The
distance of various villages/hamlets to the block head quarter Hulasganj ranges from 1-
6km, whereas that to district headquarter Jehanabad ranges from 8-11km. Almost all the
villages have approachable pakka tar road from district head quarter and block head quarter
leading to census villages and good approach roads to its associated hamlets.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 17/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 17
4 CLUSTER ENERGY PLANThis session summarizes the details of energy plan of selected cluster of village. For evolving
successful energy plan for selected cluster it necessary to first gather information about
present electrification status (access and availability of electricity) and present energy
use/consumption pattern and prevailing expenditure on meeting electricity/lighting
requirement. For this purpose extensive field survey of villages/hamlets as well as selected
sample of its households was undertaken by team of trained experienced field surveyors.
Field survey team was given detailed orientation program and pilot field survey training as
a QAQC (quality assurance and quality control) measure prior to execution of survey.
Through extensive field survey viz focus group discussions at village/hamlet level as well
as household survey for confirming information gathered through focus group discussions
requisite information-data was collected in order to identify various types of loads and
estimation of energy demand for different categories of load (viz. Residential lighting,
community lighting, various commercial/productive loads, etc.). Information-data was also
gathered for assessing the potential renewable energy source available locally within the
selected cluster and assessing its availability in order to decide on viable capacity of RE
based DDG plant and sufficiency to meet the local energy demand.
This chapter gives brief summarized details of analysis of gathered information and data
about present energy use pattern, energy demand of the cluster as well as determination of
the required capacity of the proposed grid interactive RE based DDG plant for rural
electrification.
4.1 Present energy use patternThe selected cluster consists of 42 contiguous villages/hamlets in four panchayats namely
Bauri, Chiri, Khudaur, and Kokarsa in Hulasganj block of LWE district of Jehanabad in
Bihar. Out of these habitations electricity access is available in 25 habitations (mainly all
census villages except one) but are under electrified (with annual average daily power
supply of less than 6hrs), whereas the remaining 17 habitations (mainly hamlets except two
hamlets, which have not been covered under RGGVY so far) are still un-electrified. Grid
presence is there in these under-electrified habitations (villages/hamlets) with connectionsmainly to BPL families. The electricity has been supplied by the 11kV line from the
substation and then step down by the distribution transformers of suitable capacity of rating
of either 16kVA (under RGGVY scheme), 63kVA and 100 kVA. Presently the electricity
supply to the under-electrified census villages in the selected cluster is from Hulasganj
(which is also block head quarter) substation.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 18/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 18
However, the supply of electricity is quite erratic and insufficient. Some villages get
electricity sometimes even for 10-15hrs, but only for few days in a month and that too
generally single phase so that they cannot operate any electrical appliance for productive
purpose or income generation activity. Overall availability of electricity on annualized basis
is in the range of 3-6 hrs per day. As a result villagers have to depend on kerosene for
lighting (as the power is generally unavailable during evening hours when required) and
sometimes have to buy it from open market in addition to monthly 2.5liter supply through
PDS at subsidized price. However unlike other parts of Bihar use of DG set by private
operator for evening lighting is not prevalent in this cluster. However, few households
(approx 15-20) have installed solar panels with battery charging facility.
Almost every 1 in 3 households have small diesel engine of 5-8HP which is used for
irrigation pumping and also for other motive power agriculture applications such as
thrashing, milling etc. All productive application in villages such as atta chakki, cane
thrasher, fabrication shops, oil expellers of the cluster operate on diesel.
Table 4.1 summarizes the information related to present electricity availability and energy
consumption pattern of the cluster.
Table 4.1 Electr i fi cati on Stat us and Pr esent Energy U sage in Sel ected Cl uster
Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster Total
No of un-electrified habitations 4 8 4 1 17
No of electrified habitations 6 9 5 5 25
Avg supply - Hr/day (annualized) 5.42 5.00 5.50 5.10 5.23
Avg supply – day/month (annualized) 17.50 15.38 19.60 18.80 17.50
Avg monthly elect charges in electrifiedhabitants (Rs/month)
93 106 95 95 97
Avg kerosene consumption (lit/month)(2.5 lit is subsidized through PDS)
4.55 4.76 4.78 5.25 4.79
Avg monthly expenses to supplementelectricity (Rs)
114 120 129 131 122
No of Atta Chakki 13 29 17 23 82
No Irrigation Pump Sets 349 507 417 820 2093
No of Rice Hullers/mills 5 43 20 0 68
No of Sugarcane thrashers/oil mills 2 2 2 9 15
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 19/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 19
Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster Total
Avg expenses on diesel usage(Rs/HH/month)
127 117 121 113 120
Avg monthly Income (Rs) 3206 3182 3828 3820 3417
Avg willingness to pay (Rs) 79 88 88 83 85
4.2 Estimation of load and demandIn this section effort has been made to identify various load requirements in the selected
cluster and energy demand against each identified load.
4.2.1 Residential load
Residential load consists mainly of lighting and other appliances like fan/radio/TV etc used
using point. It is assumed that, minimal of 2 CFLs (11W/18W) and one socket of 70W is
provided for all BPL families (and additional socket point of 50W is provided for APL
families) for using TV/fan/etc. From the survey data and information gathered about
households of the villages/hamlets within selected clusters, and with connected load of
100W and 150W per household for BPL and APL families respectively, the total residential
load works out to be 646.80 kW with assumption of reasonable load factor of 80%
(Table 4.2).
Table 4.2 Esti mati on of Residenti al Load Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster Total
No of House Holds 1680 1697 1160 1865 6402
No of BPL Households 887 879 610 660 3036
No of Non-BPL Households 793 818 550 1205 3366
Residential Load (kW)(with 80% load factor)
166.12 168.48 114.80 197.40 646.80
Note : Average BPL HH Load = 100W (2CFL:11W&18W + 1 socket of 70W) Average APL HH Load = 150W (2CFL:11W&18W + 2 sockets of 50W&70W)
4.2.2 Street light load
Here the number of streetlights required is estimated to be around 7% of the number of
households in the village/hamlet. Thus, the number of street lights required works out to
463, for the selected cluster having 6402 number of households residing in 42 habitations.
Therefore, with 11W CFL streetlight and 100% load factor the street light connected load
works out to 5.1kW (See Table 4.3).
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 20/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 20
Table 4.3 Esti mati on of Str eetl ight L oad
Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster Total
No of Households 1680 1697 1160 1865 6402
No of street lights(@7% of No of households)
121 125 84 133 463
Streetlight Load (kW)(11W CFL) 1.331 1.375 0.924 1.463 5.093
4.2.3 Community building load
For calculating the load of community building such as school, public health centre,
cooperative banks, panchayats bhawan/community centers etc. The details of community
buildings under different panchayats and estimation of community building load along
with assumptions is summarized below in Table 4.4.
Table 4.4 Esti mati on of Communit y Buildi ng Load
Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster Total
No of Schools 7 8 6 5 26
No of Health Centers 1 5 6 3 15
No of Panchayat Bhawan/
community centers
1 3 2 2 8
No of banks 0 0 1 1 2
Total No of community building 9 16 15 11 51
Community building load (kW) 9.45 16.8 15.75 11.55 53.55Note : Connected Load in community building like Health Centre /school/ Bank
No of fans: 7 (70W each), No of Tube Lights: 14 (40W each)Power consumption per community building: 1.05kW
4.2.4 Non-residential commercial load
Apart from residential lighting load and community building as well as street lights, the
major load demand observed during the survey is due to large number of diesel engines
presently being used for running numerous productive appliances like atta chakki, huller,
thrasher, oil expeller, cane thrasher, irrigation pumpset etc. Following Table summarizes
number of such potential electrical appliances under different panchayats. Details of
estimating non-residential productive loads are summarized below in the Table 4.5.
Table 4.5 Esti mati on of Non-Residenti al Producti ve Load
Parameter\Panchayat Bauri Chiri Khudauri Kokarsa Cluster TotalNo of Atta Chakki (8HP) 13 29 17 23 82
No of cane crusher/oil mills (10HP) 2 2 2 9 15
No of small rice hullers/mills (10HP) 5 43 20 0 68
Total load demand (kW)(with 50% load factor)
64.90 254.39 132.79 102.20 554.28
No Irrigation Pump Sets (5HP) 349 507 417 820 2093Connected load of irrigation pumpset (kW) 1301.77 1891.11 1555.41 3058.6 7806.89
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 21/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 21
Thus total non-residential load due to various productive applications, which are presently
being met by diesel engines, works out to 554.28kW with reasonable load factor of 50%.
It can be seen that the irrigation pumpset load, which is quite seasonal for very few number
of days, itself accounts for whooping 7807kW connected load. Therefore irrigation pumpset
load is neglected here and not envisaged to be served by planned RE based grid interactive
DDG plant, since such a large capacity power plant might not be feasible with available
biomass resource within the cluster and might not be attractive for private developers who
might be installing and operating it.
4.2.5 Sizing of RE based grid interactive DDG plant
The total connected load of the selected cluster, excluding seasonal irrigation pumpset load,
works out to be 1260kW (See Table 4.6). With different loads occurring at different time of
the day the anticipated peak demand would be occurring when major residential load
would be occurring during the evening peak hours along with street-lighting and some
other non-residential load. In the night time the small 5.1 kW street-lighting load would be
there throughout the night till morning hours. Since street-lighting load is much smaller
compared to other major loads it is envisaged that same can be met through battery storage
system coupled with 11W CFL (as used in standalone SPV streetlight systems), with battery
charging option with battery getting charged during the normal operating hours of the DDG
plant. Also in order to optimize on sizing of RE based DDG plant it is planned to cater
different category load during scheduled time zones. Thus, the residential load has been
considered for 6hrs duration i.e. from 05:00 hours to 07:00 hours in the morning and from
19:00 hours to 23:00 hours in the evening. In winter months both morning and evening
timing can be advanced by 1hr, if required. Remaining commercial and other loads
(panchayats bhawan, hospital, school etc), which can be catered during day time operation
of the plant for 6 hours viz 10:00 hours to 16:00 hours. This would give opportunity to
operate proposed RE based DDG power plant in three time slots or shifts i.e. 2 hrs in the
morning, 6 hrs in the afternoon and 4 hours in the evening giving short time gaps available
for daily routine maintenance.
Thus anticipated peak demand is of the order of 646.8kW during evening time when
residential lighting load would be served. With annual load growth of 5% for next five years
the peak demand would go up to 786.2kW. Thus required RE based DDG plant capacity
would be would be 1MW (1.25 times anticipated peak demand after 5yrs). Table 4.6 gives
the details of sizing of proposed RE based DDG power plant.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 22/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 22
Table 4.6 Esti mati on of Total Cluster L oad and DDG Plant Size
Load Category Load (kW)
Residential Load 646.8
Street Lighting Load 5.1Community Building Load 53.6
Non-Residential Productive Appliances Load 554.3
Anticipated Peak Demand after Load Scheduling 646.8
Considering 5% annual growth rate, expected load 5yrs 786.2
Required DDG Plant Capacity (1.25 x peak load) 982.71000
Details of scheduling of different categories of load for optimization of plant size as well as
corresponding load curve are given in Table 4.7 and Figure 4.1 respectively.
4.3 Potential renewable energy resourcePotential renewable energy resources considered include
Hydro and wind resources are not considered due to non-availability within cluster
Solar energy (considered here only to meet low streetlight demand throughout the
night and not for meeting rest of the cluster load due to high and huge demand
including productive appliances)
Biomass resource (lot of agro-residue available within the cluster due main
agriculture activity in cluster, which is main livelihood source
Accordingly, biomass (agro-residue) gasifier technology seems to be most appropriateoption for DDG power plant considering locally available renewable resource in the and
possibility of installing modular nature of producer gas gensets to cater different load
demands as per load schedule during different time duration of the day.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 23/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 23
Table 4.7 Hour ly scheduled load curve for sizi ng of RE based DDG pow er pl ant
Total Hourly Load Curve without Irrigation Load
kWhHourlyLoad Curve 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
3880.8ResidentialLoad
646.8 646.8 646.8 646.8 646.8 646.8
61.08StreetLight**
5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09 5.09
163.8 School 27.3 27.3 27.3 27.3 27.3 27.3
94.5 Hospital 15.75 15.75 15.75 15.75 15.75 15.75
50.4PanchayatBhawan
8.4 8.4 8.4 8.4 8.4 8.4
12.6CooperativeBank
2.100 2.100 2.100 2.100 2.100 2.100
3325.7
NonResidentialLoad(CommercialLoad)
554.278 554.278 554.278 554.278 554.278 554.278
7588.88 Total Load 0.0 0.0 0.0 0.0 0.0 646.8 646.8 0.0 0.0 0.0 607.8 607.8 607.8 607.8 607.8 607.8 0.0 0.0 646.8 646.8 646.8 646.8 0.0
** Streetlights load would be served by battery charging option with battery getting charged during the normal operating hours of the DDG plant. Alternatively, street
lighting can be provided with standalone SPV streetlight systems..
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 24/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 24
Figure 4.1 Hourl y l oad scheduli ng pattern in t he cluster
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 25/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 25
4.4 Assessment of Biomass AvailabilityAs mentioned earlier, biomass gasifier technology was deemed as a best possible
alternative for this cluster having a forest cover of around 221 ha (as per Census 2001).
A part of this land may have been encroached upon by the villagers for agricultural
purposes. For assessment of biomass availability for planned RE based DDG power
plant wood biomass from forest and waste land is not considered in order to avoid
possible further deforestation in future. Therefore assessment of biomass availability
for estimating potential power generation from this renewable energy resource has
been done based on agro-residue alone, which has been noticed to be available in
abundance during field survey.
The quantity estimation of the biomass (agro-residue) in the cluster has been done on
the basis of the cultivated land in the cluster used for the seasonal crop production.
Once the size of cultivated land is known in the cluster, the total crop production can
be calculated by the multiplying the average productivity of the land of the cluster.
This exercise gives the total quantity of crop produced in the cluster, the total biomass
which will be produced by the crop, can be estimated by the multiplying the quantity
of crop produce to the residue production ratio for the crop. The quantity estimated by
this calculation gives the total quantity of residue produced, in the cluster. If, quantity
of biomass produced in the selected cluster is more than the quantity required to fuel
the biomass gasifier plant then the cluster is suitable to set up the plant, from fuel
security point of view.
The analysis of the availability of biomass has been done on the basis of the data
collected by the village/hamlet survey for cultivated area under different crops as well
as secondary data for agriculture yield, crop-residue ration etc. Since as per the survey,
the total land available in the cluster is around 5031 ha, and for the production of
seasonal crop the total cultivated land is around 7500 ha (considering the yearly two
seasonal crop, so, the total irrigated land in the cluster works out to around 3500 ha).
While, as per the Census 2001, the area of village 4670 ha, and total irrigated land isaround 3330 Ha. The difference between the areas of cultivated land (as per survey
3750 Ha and as per census around 3500) provided by the survey and census is only,
250 Ha, which nearly 7%, the difference is not much. This difference can be attributed
to partly encroachment on government/wasteland. Since census 2001 data, which is
around 10 year old, therefore the primary survey data collected has been considered
for the estimation of the availability of agro-residue. The estimation of biomass
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 26/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 26
availability by the cultivation of different crops in the cluster has been summarized
below in Table 4.8, whereas Table 4.9 estimates the power generation potential.
The total power generation potential by the locally available biomass works out to
around 4MW. Taking conservative practical approach, considering the agro-residue
only from the rice crop (within cluster alone) in the form of rice husk, which relatively
has less demand in the region in absence of thermal process heat needing small scale
industry, the power generation potential has been estimated here. In case of any
shortage of biomass within the cluster, additional biomass required can be procured
easily from other residues and from adjoining areas within 10km radius where rice
cultivation and husk availability is quite sufficient.
It can be observed from the Table 4.9 that for 12hr planned operation of the power
plant, the rice husk available within the cluster itself can support 2.5MW, 2MW,
1.5MW and 1MW power plant with 100%, 80%, 60% and 40% agro residue (rice husk
alone) availability as renewable energy resource. Thus planned 1MW power plant can
be easily supported by rice husk produced alone even if 40% of husk produced within
the cluster becomes available for the plant operation.
Tabl e 4.8 Assessment o f RE resource (Biomass) Ava i l abi l i t y w i t hi n Sel ected Clust er
Biomass Available for Electricity Production (in Tonne)
Crop\Panchayat Chiri Bauri Khudauri Kokarsa Total
Rice 7901 3600 6656 3906 22062
Wheat 2850 1408 2902 1804 8964
Oil Seed 143 116 83 2 343
Sugarcane 1000 500 800 208 2507
Total Biomass (agro-residue) Production (in Tonne) 33,877
Cultivated Land in Cluster for Different Crop (in Bigha )Crop\Panchayat Chiri Bauri Khudauri Kokarsa Total
Rice 5300 2415 4465 2620 14800
Wheat 4140 2045 4215 2620 13020
Oil Seed 326 265 190 5 786
Sugarcane 240 120 192 50 602
Other Crop (Arhar) 15 60 300 5 380
Total Land (in Bigha) 29,588
Total Land (in Hectares) 7657
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 27/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 27
Table 4.9 Potent ial Capacit y for Pow er Generat i on
Agro-residueAgro-Residue
(TPA)Calorific Value
(kcal/kg)SFC
(kg/kWh)
Electricity Generation Potential (MW)(for 12 hr daily operation)
(for percent availability for power)100% 80% 60% 40%
Rice 22062 3000 2 2.52 2.01 1.51 1.01
Wheat 8964 3800 1.8 1.14 0.91 0.68 0.45
Oilseed 343 3800 1.8 0.04 0.03 0.03 0.02
Sugarcane 2507 3800 1.8 0.32 0.25 0.19 0.13
Total 33,877 4.02 3.21 2.41 1.61
Table 4.10 shows that the available biomass in the form of agro residue (mainly rice
husk) is quite sufficient to meet the electricity energy demand (in MWh) of the cluster.
Tabl e 4.10 Resource (Biomass) Feasi bil i t y Check
Parameter Data
Daily Electricity Demand in kWh(From Load Curve Table)
7,588.88
Requirement of Annual Electricity Generation- toSupply Cluster Load (in kWh/yr)
2,7699,941
Biomass requirement (@2kg/kWh) (in TPA)5,540
Rice husk production within cluster (TPA) 22,062
Since, Available Agro-Residue in Cluster is Far More Than
the Requirement so, Operation of Biomass Plant of Proposed Capacity Feasible
Even under the case of potential extended operation of pr proposed power for 16
hours per day to have benefit due to economies of scale of power generation, the
annual electricity generation would work out to to 52,56,000 units on full load i.e. with
the consideration of 100% PLF. Thi will require the biomass of the order of 10,512 TPA
(@2kg/kWh) availability of which would be still sufficient, as the estimated rice husk
production within the cluster is 22,062 TPA, as can be seen from Table 4.10.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 28/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 28
5 RE BASED GRID INTERACTIVE DDG PLANTThis section gives details of proposed RE based grid interactive DDG plant for
electrification of selected cluster of 42 habitations in Hulasganj block of Jehanabad
district. As mentioned earlier the biomass gasification based grid interactive power
plant of 1MW size is proposed here for catering various categories of loads within the
cluster both residential and non-residential (community buildings/establishments,
productive appliances/commercial enterprises etc). However, in order to optimize on
sizing and thereby on capital investment and operation of huge capacity power plant
for small streetlight load throughout the night, it is decided to cater this load by stand
alone SPV based streetlight systems. Alternatively street lighting load also can be met
through battery storage system for night operation when power plant would not be
working and battery can be kept charged during day time operation of the powerplant; as streetlight load is very small.
5.1 Biomass Gasification TechnologyBiomass gasification is a process of converting solid biomass fuel into gaseous
combustible gas (called producer gas) through a sequence of complex thermo-
chemical reactions. In the first stage partial combustion of biomass to produce gas and
char occurs along with generation of heat. This heat is utilized in drying of biomass to
evaporate its moisture as well as for pyrolysis reactions to bring out volatile matter
and provide heat energy necessary for further endothermic reduction reactions toproduce producer gas which mainly consists of mixture of combustible gases such as
CO (carbon monoxide), hydrogen (H2) and traces of methane (CH4) and other
hydrocarbon.
Normally air is used as gasifying agent; however use of oxygen can produce rich
higher calorific value gas but due to cost implications is not usually preferred. Typical
volumetric composition of producer gas is as follows.
Carbon monoxide : 18%–20%Hydrogen : 15%–20%
Methane : 1%–5%
Carbon dioxide : 9%–12%
Nitrogen : 45%–55%
Calorific value : 1000–1200 kcal/Nm3
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 29/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 29
The clean producer gas obtained through gasification of biomass in gasifier can be
used for electrical power generation, either through dual-fuel IC engines (where diesel
oil is replaced to an extent of 60%–80%), or through 100% gas-fired spark ignition
engines. Typically 1kg of air dried biomass produces about 2-2.5 Nm3 of combustible
producer gas. Approximately 1.5 to 1.8 kg biomass is required to produce 1kWh of
electricity.
What can be gasi fi ed:
Most commonly available gasifiers use wood/woody biomass; some can use rice husk
as well. Many other non-woody biomass materials can also be gasified. These include
mustard stalks, and residual stalks of various agricultural crops like corn, flower
stems, cashew nut shells, lantana, coconut shells, and briquettes of residues like
sawdust, coir pith, groundnut shells, rice husk, etc. Although gasifiers have to be
specially designed to suit these materials and the biomass may have to be compacted
in many cases. Therefore briquetted biomass (with bulk density more than 400-600
kg/m3) can be used to enhance multi-fuel capability of gasifier.
A biomass gasifier based 100% producer gas (modified diesel) engine power
generation system normally consists of:
A biomass gasifier that converts biomass into combustible producer gas
A gas cooling-cleaning train that cleans and cools the gas so that it can be safely
used in engine, and
A gas (modified diesel) engine generator system capable of operating on 100%
producer gas mode.
Gasifi er ty pes:
Gasifiers can be of ‘updraft’ or ‘downdraft’ types, the latter is preferred for power
generation as it gives relatively clean gas (low tar). In a typical downdraft gasifier, fuel
and air move in a co-current manner. In updraft gasifiers, on the other hand, fuel and
air move in counter-current manner. However, the basic reaction zones remain the
same. Fuel is loaded into the reactor from the top. As the fuel moves down, it issubjected to drying and pyrolysis. Air is injected into the reactor in the oxidation zone,
and through the partial combustion of pyrolysis products and solid biomass, the
temperature rises to 1100°C. This helps in breaking down heavier hydrocarbons and
tars. As these products move downwards, they enter the reduction zone where
producer gas is formed by the action of carbon dioxide and water vapour on red-hot
charcoal. The hot and dirty gas is passed through a system of coolers, cleaners, and
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 30/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 30
filters before it is sent to engines. A schematic diagram for the operation of biomass
gasifier is shown below:
Figure 5.1 Schemat i c D iagram for Bi ogasi fi er
Majority of commonly available gasifiers use wood/woody biomass as fuel, while
some can use rice husk also. Many other non-woody biomass materials can also be
gasified, although gasifiers have to be specially designed to suit these materials
and/or available biomass can be pre-processed through chopping, pulverising andcompaction (briquetting) to convert them into more uniform size and shape.
Producer gas engi nes
For power generation, producer gas can be used in IC (internal combustion) engine.
Existing petrol (Otto Cycle) or spark ignition (CI) engines can be used but normally
they operate on lower compression ratio (and hence with lower efficiencies) and also
results in large derating when operated on low heating value producer gas. Therefore,
normally diesel engines are preferred for the use of gas in engine operation as they
normally operate with a higher compression ratio and excess air levels resulting inreduced derating. Existing diesel engines can easily be operated on dual fuel (diesel +
gas) mode (70-80% gas and 20-30% diesel). The development of a modified diesel
engine capable of operating on 100% producer gas has been initiated at several
research institutes. The engine modification basically involves:
• Modifying piston and/or cylinder head to reduce the compression ratio
• Replacing diesel injectors with spark plugs
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 31/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 31
• Using a diesel pump governing mechanism for spark distribution
• Adjusting the spark ignition timing
Several engine manufacturers are now supplying engines for 100% producer gas
operation by either modifying diesel engine or using natural gas engines.
5.2 Site RequirementWhile the power plant site area will be decided after getting clearance, about 1-
2 acres of land could be allocated to the Biomass Power Plant so as to house the
Power Plant in less than 2000 square meters and the balance area could be used
for the storage (keeping stock for few days) and handling of biomass. Some
areas within the power plant could also be left open for development of greenbelt as that may be desired. The site could ideally be selected as close to the
households for electrification.
5.3 Requirement of BiomassThe primary fuels/biomass intended to be used is Fine Biomass like Rice Husk. Thus
availability of Rice Husk on a sustainable basis does not seem to be a problem. Rice
Husk planned to be used as biomass on as is basis without the need of briquetting but
with moisture content less than 10% before feeding and devoid of any foreign
contamination like dust, dirt, stone, chips or any other. The indicative consumption of
Rice Husk would be about 1.8 ± 0.2 kgs /kWhr.
Sufficient storage facility needs to be created at the power plant location or any other
place nearby for smooth operations. This is specially required in the view of seasonal
availability of the agro-residue (biomass resource) during harvesting season. Storage
area in the project site would have to be decided depending on the agreements with
the potential biomass (rice husk) suppliers such as hullers, rice mills, etc and
accordingly sufficient area would need to be allocated for storage of the sufficient
stock of rice husk to take benefit of their low prices during harvesting season.
Approximate indicative area required for storage of rice husk considering its low bulk
density of the order of 100-150 kg/m3 is given below in Table 5.1.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 32/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 32
Tabl e 5.1 Space requi rement for Bi omass St orage
No of days for RiceHusk Storage
Approx. Tons ofRice Husk
Indicative area required for storage
Length Width Height
10 500 35 35 3
15 735 50 35 3
30 1470 70 50 3
45 2200 75 70 3
60 3000 90 80 3
5.4 Proposed DDG plant siteIt has been noticed that at Dhongra Mushari Hamlet of Teasur village in Chiri
Panchayat, one new substation is being constructed. This is incidentally located almost
in the middle of the selected cluster. During the focus group discussions with the
villagers a plot (suitable for proposed RE based DDG power plant) was identified. The
said plot is a government wasteland and can be easily made available by the
Government for any useful purpose for the development of the region. The details of
the identified plot are as follows:
Table 5.2 Detai ls of the Land Av ail able for t he DDG Plant i n the Cluster
Name of Village Hamlet Dhongra Mushari
Name of Census Village Tesaur (Census Code 3774400)
Name of Panchyat Chiri (Census Code 3771900)
Plot No 2640/2650
Khata No 335
Plot Area 24.87 acres
Type of Land Government Wasteland
It was informed locally that, the identified proposed DDG plant site land is
owned by the government and it is having enough area for setting up the
renewable energy based DDG plant.
5.5 Specifications for biomass gasifier based DDG plantThe following are suggestive specifications of proposed 1 MW capacity biomass
gasifier based power plant.
Tabl e 5.3 Speci fi cati ons and perfo rmance parameter of gasifi er based pow er pl ant
Biomass Gasifier
Gas gasifier type Downdraft
Rated gas flow (Nm3/hr) 1912.5
Rated thermal output (Kcal/hr) 2,008,125
Fuel consumption (kg/hr) 765-1020
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 33/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 34/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 34
Table 5.4 Proj ect cost of t ypi cal 1MW gasi fi er based power pl ant
Item Description Basic Price in (Rs)
Biomass pre-processing and conveying system 1,570,000
Gasifier & Related Accessories (set of 2 Nos)Gasifier, Gas cleaning-cooling systems, Cooling towers, chillers,etc with PLC based control pannels
22,835,000
Producer gas (100%) engine (set of 4 Nos) 23,000,000
Cooling towers for gas engines 1,025,000
Building cost for housing power plant 6,000,000
Sub-total capital cost 54,430,000
Capital Cost (including 2% CST against Form C) 55,518,600
Installation-commissioning of engines 800,000
Gasifier-engines integration 1,150,000
Freight and insurance cost (approx) 2,000,000
Sub-total installation-commissioning cost 39,50,000
Sub-total installation-commissioning including 12.36% service tax 4,438,220
Total Power plant cost 59,956,82060,000,000
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 35/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 36/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 36
Indicative Layout of proposed Biomass Gasifier based DDG Power Plant is as follows:
Figure 5.3 Schemat ic D iagram proposed biomass Gasifi er Pow er Pl ant
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 37/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 37
5.8 Streetlight SystemSince the street light load is relatively very small and need to be served throughout the
night time, it is planned to be provided by using battery storage system coupled to11W CFL lamp (as used in SPV streetlight module) for streetlight. These batteries can
be kept charged during the day time using power plant operation. This would avoid
RE based large MW level power plant operation at very low PLF and help scheduling
its operation for three short duration batches of 2hr in morning for residential lighting,
6 hrs in day time for commercial and other loads and 4hrs in evening for residential
load respectively; giving opportunity to operate proposed RE based DDG power plant
in three time slots or shifts giving short time gaps available for daily routine
maintenance.
Details of number of street lights required for the selected cluster works out to 463
(@7% number of households in each habitation viz village/hamlet) as shown in
Table 4.3.
Alternatively if possible and feasible in prevailing scheme, a standalone SPV
streetlight system of following specifications can also be used.
SPV module – 75Wp capacity
Battery: 12V, 75Ah rating
Streetlight: 11W CFL or later LED lamp if becomes cheap in near future.
With prevailing price of 12-14 thousand rupees, for standalone SPV streetlight of 11W
capacity, the total cost for standalone SPV Street-lighting System works out to the tune
of Rs 60 Lacs towards SPV panel, battery and CFL bulb.
Though nowadays LED based lighting systems are becoming popular even at slightly
(about 1-3 thousand rupees) cheaper than CFL bulb (due to lower panel size
requirement), presently 11W CFL based streetlights are proposed here considering
cheaper replacement of bulbs in rural areas. However, in future if LED bulb becomes
more cost effective same can be used as they can result in longer back up duration.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 38/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 38
6 POWER DISTRIBUTION NETWORK (PDN)
As mentioned earlier the cluster consists of 24 villages (42 contiguous habitation) inHulasganj block, comprising both un-electrified (where grid has not reached yet) as
well as under-electrified (where though the grid has reached but the daily power
supply is less than 6hrs on annualized basis) villages/hamlets. This section gives
detailed account of assessment carried out for the requirement of planned PDN for
rural electrification of selected cluster using proposed RE (biomass gasifier) based grid
interactive power plant.
As a first step based on the load demand estimation carried out in earlier section,
village/hamlet wise assessment of transformer capacity and the PDN length is worked
out. Efforts are made to gather as much details of existing PDN (no of DT of different
capacity and length of LT line existing) within the cluster as possible through
consultation with concerned officials in the block and lineman as well from RGGVY
database. Based on the analysis of gathered information an assessment is made with
regard to augmentation need of existing grid in under-electrified villages/hamlets as
well as extension of the grid in un-electrified villages/hamlets of the cluster.
The 42 habitations (villages/hamlets) included in the selected cluster consists of 24
census and 18 associated hamlets falling under four Panchayats (namely Bauri, Chiri,
Khudaur and Kokarsa) of Hulasganj block of LWE district of Jehanabad in Bihar. The
power supply is mainly from 33kV/11kV substation located at block head quarter of
Hulasganj. The substation has two transformers each of 3.15 MVA capacity and the
outgoing 11kV feeders from the substation supply the power to the (under)electrified
villages/hamlets of the cluster. Though main categories of the loads in the cluster
include agriculture, residential and commercial, the existing PDN is able to cater only
residential load for very few hours that too generally when not needed. As a result
villagers are required to use alternate options to meet their electricity needs viz
kerosene for lighting, diesel to energize agriculture pumpsets and other productive
appliances like aatta chakki, mill, huller, thrasher etc. As mentioned earlier, the power
requirements for the seasonal agriculture pumpset would result in huge connected
load to RE based power plant it has not been envisaged to be covered under the
proposed biomass gasifier based power plant in the cluster.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 39/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 40/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 40
be installed works out to around 0.8 MVA. Since, DTs are manufactured with standard
sizes/ratings, so the DT of rating next to the estimated size is considered. The total
capacity of DTs needs to be installed works out to around 1.0MVA. It is estimated that25 DTs of different capacities need to be installed in the different villages/hamlets in
order to meet the power requirement of the cluster as summarized in Table 6.2.
Tabl e 6.2 Capaci t y w i se Requi rement of DTs
Size of DistributionTransformer
No of DTs Required in theCluster
10 kVA 6
16 kVA 4
25 kVA 5
63 kVA 6
100 kVA 4
Total No of DTs Required 25
6.2 Distribution Line RequirementAs per the data collected under the RGGVY for the 22 villages by the field survey and
website, the total length of completed three phase 11kV line is around 16.82 km and
the length of 400V single phase LT line is around 8.04 km. In addition to this, 8.58 km
Arial Bunched Cable (ABC) of 400V for the single and 0.32 km three phase line has
also been installed under RGGVY in the villages. Under the RGGVY it has been
proposed to erect total of 42 km of 11kV line and 21 km of 400V LT line for the 22
villages covered in the cluster.
Table 6.3 represents the installed and required capacity of DTs in the habitations of the
cluster. 17 habitations are having suitable capacity of DTs and 17 habitations are un-
electrified, while the DT capacity of the remaining 8 habitations needs to be
augmented to meet the future power demand.
The existing network of the 11kV line in the cluster, is supplying the power from the
33kV/11kV Hulasganj substation to the village/hamlet Distribution Transformer. The
existing Power Distribution Network (based on the data available) of the four
panchayats covered in the cluster is schematically presented below in Figure 6.1,
which shows the village/habitation wise required and installed capacity of
Distribution Transformers, on the basis of the estimated load demand based on field
survey data.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 41/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 41
able 6.3 Requirement of Di stri buti on Transformer Capacit y
Sr
No
Panchayat Village Habitation
Capacity ofRequired DTafter 5 Years
(Taking PowerFactor 0.8)
Total InstalledCapacity
(IncludingRGGVY)
Capacity ofDT need to
be Added
Rating of ProposedTransformer
(The Next Standard
Rating of theTransformer)
1
Chiri
Chiri Chiri 97 116 -19 0
2 Dumri Dumri 108 48 60 63
3
Sarma
Sarma 63 48 15 16
4 Manjhi Tola 5 0 5 10
5 Ratan Bigha 1 0 1 10
6 Sisara Sisara 132 32 100 100
7
Ginnji
Chaiti Pipar 20 0 20 25
8 Ginnji 33 48 -15 0
9 Dhongra 36 63 -27 0
10Teasaur
Teasaur 33 64 -31 0
11
DhongraMushari 20
164
10
12
Sarthua
Sarthua 15 48 -33 0
13 Sevapuri 17 0 17 25
14 Bhatu Bigha 23 0 23 2515 Bulaki Bigha 22 0 22 25
16 Desai Bigha 15 0 15 16
17 Kolbhapur 27 0 27 63
18
Bauri
Bauri
Bauri 126 48 78 100
19 Gidarpur 35 0 35 63
20 Kisunpur 12 0 12 16
21 Rupa Bigha 44 0 44 63
22Dadpur
Dadpur 47 116 -69 0
23 Adhikari Bigha 9 0 9 10
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 42/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 42
SrNo
Panchayat Village Habitation
Capacity ofRequired DTafter 5 Years
(Taking PowerFactor 0.8)
Total InstalledCapacity
(IncludingRGGVY)
Capacity ofDT need tobe Added
Rating of ProposedTransformer
(The Next StandardRating of theTransformer)
24 Harpur Harpur 6 16 -10 025 Bihta Bihta 24 32 -8 0
26 Dihuri Dihuri 42 32 10 10
27 Kewla Kewla 19 16 3 10
28
Khudauri
KhudauriKhudauri 51 132 -81 0
29 Rampur 65 0 65 100
30 Raghunathpur Raghunathpur 34 100 -66 0
31
Narma
Narma 77 132 -55 0
32 Emitpur 35 95 -60 0
33 Benipur 16 0 16 16
34 Mokimpur Mokimpur 58 79 -21 0
35 Walipur alipur 34 0 34 63
36 Golakpur Golakpur 29 0 29 63
37
Kokarsa
Kokarsa 244 148 96 100
38 Mirzapur 63 116 -53 0
39 Sukiyawan 36 116 -80 040 Lodipur 22 32 -10 0
41 Rustampur 86 95 -9 0
42 Beldaripur 21 0 21 25
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 43/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 43
Figure 6.1 : Confi gurati on of Di stri buti on Transformers
33 / 11 kV Hulasganj Substation 33 kV Incoming from Hulasganj Substation
2 X 3.15 MVA ( 33 kV / 11 kV)
11 kV Outgoing to Panchayats / Villages / Hamlets
Chiri0 kVA
Ginji0 kVA
Manjhi Tola1 0 kVA
Ratan Bigha10kVA
Tesaur0 kVA
Sarthua0 kVA
Sevapuri25 kVA
DhongraMushri 10 kVA
BhatuBigha25 kVA
Kolabhpur63 kVA
Bauri100 kVA
Gidarpur63 kVA
Kishanpur16 kVA
AdhikariBigha16 kVA
Mokimpur25 kVA
Mirzapur0 kVA
Emitpu0 kVA
Benipu16 kVA
Beldaripu25 kVA
Harpur0 kVA
Raghunathpur0 kVA
Bihta10 kVA
Sarma16kVA
Sisara100 kVA
Dihuri10 kVA
Kokarsa100 kVA
BulakiBigha25 kVA
DesaraiBigha16 kVA
Rampu100 kVA
Walipur63 kVA
Golakpur63 kVA
Rustampur25 kVA
Lodipur0 kVA
Chaiti Pipar25 kVA
Narma0 kVA
Dhongra0 kVA
No Change is Required
Required New DT Installation
Required Capacity
Au mentation
Required Capacity Augmentation
Dumri63 kVA
Dadpur0 kVA
Sukiyawan0 kVA
Khudauri0 kVA
RupaBigha63 kVA
Kewla10 kVA
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 44/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 44
6.3 PDN Cost EstimationThis section gives detail cost estimation of Power Distribution Network (PDN) for the
installation of new network for the un electrified 17 habitations and strengthening of
the existing PDN of under electrified 8 habitations. The major cost components of PDN
include the cost of Distribution Transformers (DTs), cost of 11kV and 400V LT line.
6.3.1 Cost Estimate of Distribution Transformers
Distribution Transformer is a vital link in supplying the power at 400V, in power
distribution network. Depending upon the power requirement of the area, size of
Distribution Transformer is decided. It is very much necessary to decide the capacity
of Distribution Transformer of sufficient capacity, to cater the increasing load. Based
on assessment of load demand based on field survey the necessary size of the DTs has
been calculated for all the 42 habitations. During the field visit, information gatheredabout existing PDN. In DT sizing calculation, it is found that 17 habitations are having
sufficient installed capacity of DTs, while DTs of 8 habitations required capacity
augmentation to cater the village/hamlet’s growing load and for remaining 17 un-
electrified villages/hamlets installation of new DTs is required. The total capacity
requirement of DTs in the cluster works out to around 1.0 MVA, which will cost
around Rs 58.24 Lacs. Table 6.4 provides the details of the required DTs,
Table 6.4 Cost esti mat i on of capaci ty addit i on of DTs required in t he cluster
Size of DistributionTransformer
Total Requirementin Cluster
Capacityof DTs
Unit Cost of DT(with Installation Cost)
Total Costof DT (Rs)
10 kVA(Cu Winding)
6 60 1,80,000 10,80,000
16 kVA(Cu Winding)
4 64 2,00,000 8,00,000
25 kVA(Cu Winding)
5 125 2,25,000 11,25,000
63 kVA(Al Winding)
6 378 2,75,000 16,50,000
100 kVA(Al Winding)
4 400 3,20,000 12,80,000
Total No ofDTs required 25 1027 Total Costof required DTs 59,35,000
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 45/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 45
6.3.2 Cost of Distribution Lines
11 kV LineThe power shall be distributed from the substation to the villages/hamlets by 11kV
line in the indentified cluster. At present, the power supply in the villages/hamlets in
the cluster is from the 33kV/11kV Hulasganj substation. In order to meet the growing
power demand of the cluster an additional 33kV/11kV substation is proposed for
construction at Dhongra village. This new upcoming substation will feed the cluster’s
power demand by two power transformer of capacity 5 MVA. It is assumed that, to
cater the growing power demand of the cluster, approximately 30 km long new
network of 11kV line will be sufficient. With per km cost of 11 kV line network in the
cluster is estimated at Rs 7,35,000 per km, with Raccoon Conductor with all theaccessories (e. g. pole, insulators, foundation etc), the approximate cost for the 11kV
network in the cluster works to around Rs 220.50 Lacs.
Table 6.4 Cost Estimat ion of 11 kV Li ne in Cluster
ParticularsTotal Line
Requirement(in km)
UnitCost
Cost(in Lacs)
11 kV Line(11 kV line on 152 X 152 mm, 37.1 kg/Mtr. 11 MtrLong H-Beam with Raccoon conductor averagespan of 70 mtr)
30 7,35,000 220.50
Cost of 400 V Line
In order to supply the power in the un-electrified and under-electrified
village/hamlets of the cluster, it will be required to installed new network or upgrade
the existing distribution network of 400V to feed the growing power requirement. 400
V Arial Bunched Cable or Line can be considered for Power Distribution.
400 V Overhead Arial Bunched Cable (ABC Cable)
400 V Overhead Rabbit and Weasel Conductor Line
ABC Line is being preferred more nowadays, as it minimises the possibility of the
electricity theft, but it costs significantly high as compared to the Line. It is envisaged
that, 400 V distribution network of around 3 km, shall be sufficient for power
distribution in the Village/Hamlet. As mentioned earlier 17 villages/hamlets are
having sufficient DT capacity, so it is assumed that, these villages shall have sufficient
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 46/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 46
capacity of power distribution network in the village and additional 400 V distribution
network shall not be required. Out of remaining 25 villages/hamlets, 17 need to be
electrified afresh and 8 need to be upgraded. Following Table 6.5 gives the indicative
cost estimation of 400V Distribution Network using both Cable and Line options.
Table 6.5 Cost Esti mat ion of 400V PDN Li ne in Cl ust er
Particulars
Assumed Length ofLine & Cable for One
Village/Hamlet(in km)
UnitRequirement
in Cluster
OverallCapacityRequired
Perkm
Cost
TotalCost(in
Lacs)
Cost of PDN with 400 V Cable
Cost of 400 V Cable to beerected in un-electrifiedvillages
3 17 51 650000 331.5
Cost of up gradation of
400 V line to cable (inunder-electrified villages)
3 8 24 340000 81.6
Total Cost of PDN with 400 V Cable 413.1Cost of PDN with 400 V Line
Cost of 400 V line to beerected in un-electrifiedvillages
3 17 51 185000 94.4
Cost of up-gradation of400 V line network (inunder-electrified villages)
3 8 24 120000 28.8
Total Cost of PDN with 400 V Line 123.2
Total Cost of Distribution Network
The total cost of the PDN infrastructure consists the following costs1. Cost of Distribution Transformers2. Cost of 11 kV Network3. Cost of 400 V Network4. Cost of Grid Connectivity of DDG Plant
The cost of grid connectivity has been considered, the cost of Generator Transformer,Construction of Substation at power plant, Cost of Transmission Line, Metering andprotection equipment etc. The total PDN cost estimate has be summarized below inTable 6.6.
Table 6.6 Cost Esti mat e of Tot al PDN I nfrastructure of Cl uster (in L acs)
ParticularsAmount (Rs Lacs)
400V Line 400V Line
Cost of Distribution Transformer 59.35 59.35
Cost of 11 kV Network 220.5 220.5
Cost of 400V Network 413.1 123.2
Cost of Grid Connectivity of DDG Plant 80 80.0
Total Cost 773.0 483.0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 47/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 47
7 FINANCIAL ANALYSIS OF PROPOSED RE BASED DDGPOWER PLANT
This chapter presents the detailed financial analysis of the proposed RE based DDG
Plant to arrive at cost of electricity generation. This would help in assessing the
financial feasibility of the project and if not feasible, would help in estimating the
viability gap under different project scenarios. The sensitivity analysis has also been
carried out to assess the impact of selected critical parameters like biomass fuel price,
consumer category mix, etc. under different capital subsidy options.
7.1 Cost of Electricity GenerationThis section presents the details of financial analysis carried out for proposed 1MW
biomass gasifier based grid interactive power plant for electrification of the selected
cluster. In order to determine the cost of electricity generation, the capital cost of
proposed gasifier based power plant alone has been considered. The cost of Power
Distribution Network (PDN) or augmentation of existing PDN within the cluster has
not be taken into account as the proposed project would be essentially operating as
power augmentation at the tail end of PDN for rural electrification. PDN would be
DISCOM’s asset and its cost would be either born by the DISCOM or would be
financed under separate scheme/programme. Similarly the cost of standalone street
lighting through SPV has not been considered here as it would be for community
purposes requiring one time capital expenditure and power would neither be
distributed nor billed by the project developer.
The typical investment for biomass gasifier based power plant with specifications
mentioned earlier works out to about Rs 60,000/- per kW (See Table 5.4). Thus, the
cost of the proposed 1MW gasifier based power plant is considered as Rs 600 Lacs.
This excludes PDN to be developed by the DISCOM. It is presumed that the project
developer would design, build, and operate the renewable energy based grid
interactive power plant while DISCOM shall build and operate the network for
distribution of electricity to rural consumers and would own PDN asset. All the
financial and fuel related assumptions, operation and maintenance, working capital,etc. have been adopted from the Central Electricity Regulatory Commission (Terms
and Conditions for Tariff determination from Renewable Energy Sources) Regulations
2012. The various parameters and assumptions considered while carrying out the
financial analysis of biomass gasifier based power plant for rural electrification project
are summarized below in Table 7.1.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 48/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 49/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 49
Similarly the biomass (rice husk) price has been assumed at around Rs 1000 per ton
which is quite likely within cluster, considering the absence of competing usage
(general cause for price rise due to high opportunity cost) by industries requiring it for
meeting process heat requirement. (Refer Annexure B).
Keeping into consideration the aforesaid facts and parameters, the plant shall generate
annually about 2,747,635kWh, as the net energy for distribution in the identified
cluster and the total cost of generation of electricity from proposed biomass gasifier
based power plant works out to Rs 9.21 per unit and Rs 5.94 per unit without and with
90% capital subsidy respectively. The Table 7.2 below gives detailed bifurcation of cost
of generation of electricity for levelized cost over plant life time of 20 years as well as
that for the first and twentieth year.
Table 7.2 Cost of generat i on (COG) of el ect ri ci ty from biomass gasi fi er pow er pl ant
Particulars
COG (Rs/kWh): Without Subsidy COG (Rs/kWh): With 90% Subsidy
LevellizedTariff
Year 1 Year 20Levellized
TariffYear 1 Year 20
Fuel (Biomass) cost (A) 3.03 2.22 5.62 3.03 2.22 5.62
O&M Expenses (B) 2.31 1.62 4.65 2.31 1.62 4.65
Interest on working capital (C) 0.30 0.24 0.49 0.24 0.18 0.46
Depreciation charges (D) 1.18 1.30 0.56 0.12 0.13 0.06
Interest on term loan (E) 1.00 1.83 0.00 0.10 0.18 0.00
Return on Equity (F) 1.39 1.33 1.60 0.14 0.13 0.16
Fuel cost alone (A) 3.03 2.22 5.62 3.03 2.22 5.62
Operating Cost (A+B+C) 5.64 4.08 10.75 5.58 4.02 10.72
Total COG (A+B+C+D+E+F) 9.21 8.54 12.91 5.94 4.46 10.94
Under the case of potential extended operation of the proposed power plant for 16
hours per day with the time slots of 4 hours each, and with the full load i.e. PLF of
100%, the cost of generation of the plant comes out to Rs 5.19 per unit at the fuel price
of Rs 1000 per tonne, and the units generated by the power plant comes out to
53,56,000 kWh per year.
7.2 Sensitivity AnalysisIn this section, sensitivity analysis carried out for the identified parameters related to
the operations of biomass gasifier based power plant for electrification of selectedcluster is presented. Following operational parameters have been considered for this
purpose,
Input Cost – Price of biomass (e.g. rice husk) 1000 to 2476 Rs/ton
Different consumer mix (domestic and commercial) (40:60 to 90:10)
Variations in Capital Subsidy (0 and 90% subsidy)
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 50/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 50
In order to assess the viability gap under various scenarios, the prevailing domestic
and commercial rural area tariff has been taken as Rs 1.80 and Rs 2.10 per unit as
specified by the Bihar Electricity Regulatory Commission in its order on Aggregate
Revenue Requirement (ARR) and Tariff for FY 2012-13. Annual average escalation of
5% in tariff is assumed over the plant life time of 20 years. The levelized tariff over the
lifetime of the project was calculated for pre-defined mix of consumption by domestic
and commercial categories of consumers.
The findings of the sensitivity analysis and the estimated viability gap (the gap
between the levelized cost of generation and the retail tariff of the distribution
licensee) under different scenarios are summarized below in Table 7.3.
Table 7.3 Cost of generat ion (COG) and Vi abil it y Gap under di fferent scenari os
Consumer
Mix
Levelized
Tariff
Fuel
Price
0% Capital Subsidy 90% Capital Subsidy
Cost of
Generation
Viability
gap
Cost of
Generation
Viability
gap
Dom:Comm Rs/kWh Rs/MT Rs/kWh Rs/kWh Rs/kWh Rs/kWh
40:60 3.27 2476 13.9 10.63 10.63 7.36
40:60 3.27 2000 12.39 9.12 9.12 5.85
40:60 3.27 1500 10.8 7.53 7.53 4.26
40:60 3.27 1000 9.21 5.94 5.94 2.67
60:40 3.17 2476 13.9 10.73 10.63 7.46
60:40 3.17 2000 12.39 9.22 9.12 5.95
60:40 3.17 1500 10.8 7.63 7.53 4.36
60:40 3.17 1000 9.21 6.04 5.94 2.77
70:30 3.12 2476 13.9 10.78 10.63 7.51
70:30 3.12 2000 12.39 9.27 9.12 6.00
70:30 3.12 1500 10.8 7.68 7.53 4.41
70:30 3.12 1000 9.21 6.09 5.94 2.82
80:20 3.07 2476 13.9 10.83 10.63 7.56
80:20 3.07 2000 12.39 9.32 9.12 6.05
80:20 3.07 1500 10.8 7.73 7.53 4.46
80:20 3.07 1000 9.21 6.14 5.94 2.87
90:10 3.02 2476 13.9 10.88 10.63 7.61
90:10 3.02 2000 12.39 9.37 9.12 6.10
90:10 3.02 1500 10.8 7.78 7.53 4.51
90:10 3.02 1000 9.21 6.19 5.94 2.92
It can be observed from Table 7.3 that even with the prevailing low biomass price of
Rs 1000 per tonne and consumer mix of 40:60 (domestic : commercial) the viability gap
is Rs 5.94 per unit which reduces to Rs 2.67 per unit even with 90% capital subsidy.
With increasing price of biomass upto Rs 2476 per tonne (as specified in CERC 2012
regulations) the viability gap increases further to Rs 10.63 and Rs 7.36 per unit,
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 51/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 51
without and with 90% capital subsidy respectively. The viability gap for the consumer
mix of 90:10 (domestic: commercial) increases to Rs 10.88 and Rs 7.61 per unit, without
and with 90% capital subsidy respectively.
Thus the financial and sensitivity analysis makes it clear that even with best available
biomass price, good consumer mix and even with 90% capital subsidy provision, huge
viability gap exists with prevailing low DISCOM tariff. Thus there is a need to adopt
innovative implementation mechanism for ensuring private sector participation for
rural electrification through grid interactive RE based DDG power plant to ensure
long term financial sustainability.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 52/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 52
8 POTENTIAL PROJECT IMPLEMENTATION MODELS
In this chapter an attempt has been made to discuss and suggest possible project
implementation options for the proposed cluster based rural electrification project
using grid interactive RE based DDG project for selected cluster of 42 contiguous
habitations in Hulasganj block of Jehanabad district in Bihar. Two project
implementation models have been suggested here. Based on the comparative analysis,
one potentially viable implementation model along with roll out plan has been
recommended for this project.
Proposed RE based biomass gasifier plant is aimed to strengthen the rural
electrification of cluster of 42 contiguous habitations, comprising both, the already
electrified but under-electrified, as well as un-electrified villages/hamlets. Thus the
biomass gasifier power plant would be connected to existing grid, after its proposed
expansion and strengthening, and thus no longer would remain DDG per se as
electricity would be generated by the power plant but will be distributed through local
DISCOM network. Thus the proposed grid interactive RE based DDG plant would
function more like tail end power supply augmentation plant, being used for
enhancing the power supply position. Therefore, as mentioned earlier, PDN would
remain in the domain of DISCOM. Following two options for implementation of the
proposed project are possible.
Project developer to act as an Independent Power Producer
Project developer as an IPP as well as Franchisee
8.1 Independent Power Producer ModelIn this, PD will generate the electricity while DISCOM would continue distributing it
through its PDN. PD and DISCOM will sign the PPA for the lifetime of the proposed
RE based power plant. Accordingly, PD will commission and operate the RE based
power plant to generate and supply the electricity into the local grid by connecting it
to 11kV substation serving the selected cluster. The DISCOM will provide the Feed intariff (FIT) as per signed PPA to the PD and consumers would continue paying tariff to
DISCOM as per the prevailing mechanism of metering and billing with consumers of
existing PDN. Figure 8.1 below presents the operating structure of proposed IPP
model.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 53/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 53
Figure 8.1 Operational Structure of IPP Model
The key steps in implementation of the IPP model are as given below:
PD to identify and develop cluster based project scheme which will include;
o Detailed prefeasibility study of the project
o RE technology selection based on resource availability
o Preparation of Detailed Project Report
DISCOM to approve DPR, which would include
o Approval of selected RE technology by DISCOM
o Approval of selected cluster by DISCOM (contiguous un-electrified and
under-electrified habitation)
PD and DISCOM to form a PPA at FIT
PD to achieve the financial closure
PD to develop and commission the project
PD to generate and supply electricity to the grid substation as per PPA and
receive FIT from DISCOM
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 54/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 54
GoI may provide, though not mandatory, central financial assistance to the
DISCOM through SNA for RE based power plant
DISCOM to continue supply of electricity to connected consumers and collect
revenue as per prevailing tariff order
8.2 Distributed Generation based Distribution Franchisee (DGBDF)In DGBDF model, PD will not only generate the electricity but would also distribute
electricity and carry out the task of metering, billing and collection (MBC) on behalf of
DISCOM, within the selected cluster. Thus, the PD will be performing dual role of the
generator as well as that of franchisee. As a result, there will be two agreements
between PD and DISCOM
(i) PPA for the lifetime of the proposed RE based power plant.
(ii) Franchisee agreement for distribution of electricity and also for
metering, billing and collection of revenue on behalf of DISCOM
According to PPA, PD will commission and operate the RE based power plant to
generate and supply the electricity into the substation and would be connected on
11kV side of the 33/11kV Power Sub-Station along with needed breaker system to
enable isolation mode operation when power is not available in the grid. The DISCOM
will provide FIT as per signed PPA to the PD. The PD will also distribute electricity to
rural consumers and the PD will carry out metering, billing and collection activities
under the Franchisee Agreement. PD shall perform MBC for its own plant as well as
for the grid supply and even in case of grid supply available to rural consumers; the
PD shall supply electricity to grid at the pre decided hours for generation of electricity
from the proposed grid interactive DDG plant. Figure 8.2 below presents the operating
structure for the proposed DGBDF model.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 55/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 55
Figure 8.2 Operational Structure of DGBDF Model
The key steps of implementing the DGBDF model are presented below:
PD to identify and develop cluster based project scheme which will include;
o Detailed prefeasibility study for the project
o RE technology selection based on resource availability
o Detailed Project Report
DISCOM to approve DPR, which would include
o Approval of selected RE technology by DISCOM
o Approval of selected cluster by DISCOM (contiguous un-electrified and
under-electrified habitation)
PD and DISCOM to sign two agreements viz. PPA and Franchisee Agreement
PD to achieve the financial closure
PD to develop and commission the project
Project Developer
DISCOM
Flow of Electricity
Tariff (Cash Flow)
FIT (Cash Flow)
Agreement
Consumer
Govt. of India
CFA (optional)
Grid
Consumer Consumer Consumer
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 56/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 56
PD to generate and supply electricity to the power substation as per PPA and
receive FIT from DISCOM
PD to act as Franchisee of DISCOM and PD distribute electricity and would
carry out functions of metering, billing and collection (MBC)
GoI may provide, though not mandatory, central financial assistance to the
DISCOM for RE based power plant.
8.3 SWOT Analysis of Implementation ModelsIn this section, an attempt has been made to undertake SWOT (Strengths, Weaknesses,
Opportunities and Threats) analysis comparing various advantages and disadvantages
associated with the proposed IPP as well as DGBDF models. Tables 8.1 and Table 8.2
below summarizes the SWOT analysis of IPP and DGBDF model respectively.
Table 8.1 SWO T analysis of IPP model
Strengths Already in operation in power sector in India May attract private sector participation
Weaknesses DISCOM to manage PDN in rural areas Low collection efficiency in rural remote areas
by DISCOM
Opportunity Helps DISCOM to meet responsibility to
provide electricity in rural areas Help DISCOM to meet RPO obligation
Threats Disinterest by DISCOM due to increased FIT
burden with low collection efficiency fromrural areas
Table 8.2 SWOT analysis of DGBDF Model
Strengths
Shall help attract private sector participation Better revenue collection efficiency as
responsibility of revenue collection is withFranchisee
Certainty of cash flow for PD Relatively low financial assistance required as
compared to IPP model
Weaknesses
Involvement of franchisee framework Complexity in revenue management
Opportunity
Helps DISCOM to meet responsibility toprovide electricity in rural areas
Helps DISCOM to improve rural outreachalong with improvement in collectionefficiency
Help DISCOM to meet RPO obligation
Threats
Long term sustainability of both agreements incase of non-improvement in revenue collection
8.4 RecommendationsOn the basis of the SWOT analysis presented above, ABPS Infra recommends DGBDF
Model to be adopted for the proposed grid connected RE based DDG pilot project in
identified Hulasganj cluster of LWE district of Jehanabad in Bihar. The rationale for
the recommendation for DGBDF model is given below:
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 57/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 57
Attractiveness to private sector participation due to certainty of revenue for
lifetime operation of the plant (DISCOM shall pay FIT, and also CFA, if any
from GoI, and tariff from consumers)
Relatively less financial assistance required
Better collection efficiency for DISCOM, as responsibility of revenue collection
is with project developer
Opportunity to DISCOM for fulfilling its responsibility of rural electrification,
meeting RPO, and promoting renewable as well as strengthening present weak
rural power supply position due to power augmentation at the tail-end.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 58/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 58
9 PROJECT IMPLEMENTATION PLAN
This chapter presents the detailed project implementation plan for the proposed 1 MW
grid interactive pilot project in Hulasganj block of Jehanabad district in Bihar using
locally available RE resource. The chapter also discusses the various linkages required
for the project implementation; such as the project site and grid interconnectivity, PDN
and asset management, protocol for power generation, contractual arrangements
between DISCOM and PD, etc.
9.1 Project Site and Grid ConnectivityThe selected cluster consists of both types of villages; electrified and un-electrified. In
case of villages that are electrified, electricity is available for less than 6 hr/day as the
grid does not have sufficient power. The proposed biomass based 1MW power plant is
expected to augment the power supply to cater energy demand of the 42 contiguous
habitations in the selected cluster in Hulasganj block. As a result it is necessary to have
not only connectivity with the grid but also ability to operate the plant in isolation
mode in the event of non-availability of the grid during scheduled power supply
durations. Therefore, it is envisaged that the proposed RE based grid interactive DDG
plant be located close to planned Dhongra substation (being constructed at the site and
likely to be available soon) and would be connected on 11kV side of the 33/11kV
Power Sub-Station along with necessary isolator-breaker system to enable isolation
mode operation when power is not available in the grid. The concerned departmentswithin State Government would be required to provide the requisite land clearance for
the proposed site and permission for grid connectivity with the proposed Power Sub
Station (PSS). Thus the planned DDG project would be connected to PSS at Dhongra
Mushari being constructed under RGGVY, instead of grid sub-station at Hulasganj,
which is providing power to the existing under-electrified villages of the selected
cluster.
9.2 PDN and Asset Management
The pilot project is proposed in a cluster of 42 contiguous habitations out which 24 arealready electrified and are having some PDN which need to be strengthened. Also
there is need to expand it to cater other un-electrified villages within the cluster.
Augmentation and expansion of PDN as per the requirement of project area along
with grid interactive system including power evacuation equipments & controls etc.
shall form part of the project and the entire project cost including such system shall
need to be considered as capital expenditure for considering financial assistance from
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 59/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 59
Central Government through Capital subsidy. Strengthening and expansion of the
PDN will be carried out by the implementing agency through PD as per the final DPR.
The PD will be allowed to use the existing as well as newly created infrastructure as a
franchisee of the DISCOM for distribution of electricity in the project area. The PD will
bear all the operation and maintenance costs during the contract period. At the end of
the project agreement period, the PD would transfer the PDN infrastructure back to
the DISCOM at prevailing valuation cost and DISCOM and State Government may
agree to this arrangement.
9.3 Protocol for Power Generation and Grid ManagementThe proposed project would be grid interactive, wherein the consumers would have
grid access. The PD would ensure minimal duration of power supply to consumers
(excluding irrigation load) during the pre-determined time slots even in the event of
non-availability of grid power. This will call for islanding operation of DDG plant in
absence of grid power. In order to ensure smooth power management within the
cluster, there would be a need to develop a pre-agreed protocol for the DDG plant
operations and the time slots to be agreed / resolved among BSEB, project developer
and the State Government. This grid management protocol would define the
methodology for operation of the plant in case non-availability of the grid.
The project developer shall operate the grid interactive power plant to generate power
from 0500 hours to 0700 hours in the morning as domestic load. The plant will be
operated from 1000 hours to 1600 hours in the evening so as to cater the commercial
load mainly for school, community centres and hospitals and later the plant shall be
operated for power generation to supply evening lighting load to rural domestic
consumers from 1900 hours to 2300 hours. This would give opportunity to operate
proposed RE based DDG power plant in three time slots of 2 hrs in morning, 6 hrs in
afternoon and 4 hours in the evening with short time gaps available for carrying out
daily routine maintenance. The project developer shall have to generate power during
the agreed hours from the 1 MW biomass gasifier power plant and shall distribute
power to the rural consumers of the Hulasganj block of Jehanabad district.
In case the grid supply is available during the agreed duration for generation of power
from the plant, the project developer shall continue to generate during the agreed time
slots and will supply power to the local grid so as to strengthen power situation.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 60/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 60
This protocol thus shall ensure the supply duration of the power plant which will
necessitate the project developer to achieve its financial viability in order to have
smooth running of the plant and even the rural consumers will also be benefited to
have regular and time based supply in which consumers can plan their day to day
routine activities as well as to utilize electricity for variety of commercial activities.
This will help in maximum utilization of the grid interactive power plant.
9.4 Arrangement for Insulation of Agricultural LoadIrrigation is one of the major loads within the cluster but can not be supplied through
the proposed grid-interactive RE based DDG power plant. Significant increase in the
capacity would be required if irrigation load is to be catered necessitating enormous
financial assistance. Also agriculture load cannot be supplied using DDG as per the
prevailing scheme and will have to be catered using the grid power whenever
available within the cluster. In this section, we have developed three different
mechanisms for insulation of agricultural load, which are briefly described below.
9.4.1 Feeder Separation
Agriculture, being one of the major loads of the cluster, there would be a need to
develop an arrangement for the proposed plant which will as work on islanding mode
for operation. In order to reduce losses, one of the simplest ways is to segregate
irrigation load is the feeder separation mechanism. In this mechanism, there would be
separate feeders for the agricultural load. DICOM would bear the cost of developing
separate feeders for the irrigation load, and would be responsible for operation and
maintenance for the concerned PDN for the agricultural area.
9.4.2 Franchisee Arrangement
In this arrangement, the franchisee means the project developer would develop the
complete PDN network for the identified Hulasganj cluster in Jehanabad district
including domestic, commercial and even agricultural. The project developer will
monitor the agricultural load of the cluster, and would be responsible for operation
and maintenance of the PDN for agricultural load which is to be based on incentive
mechanism. This means the project developer would be incentivised for monitoring
the PDN of the agricultural area.
9.4.3 Demand Response
Demand response comprises short-term actions taken by end-use customers to change
(usually reduce) their electricity use in response to high prices in the electricity market;
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 61/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 61
and/or problems on the electricity network. In network-related demand response, the
network operator notifies customers and demand response providers when short-term
load reductions are required. In this mechanism, the consumers having agricultural
load would install meters along with load control mechanisms on the pump sets. The
load control mechanism would allow franchisee to disconnect the load in case of non-
availability of grid supply there by restricting demand that can be served by the
proposed 1MW DDG.
9.5 Franchisee Arrangement for MBCIn order to help enhance the financial viability of the project due to low revenue to
meet operating expenses, PD (as distribution franchisee) would be allowed to device
appropriate mechanism (such as prepaid meters, load controllers etc.) for billing and
revenue collection as well as for preventing possible power theft within the cluster.The PD should also be allowed to develop and implement any DSM initiative within
cluster in an effort to manage the load and enhance financial viability.
Therefore, it is proposed that the PD will act both as generator as well as franchisee
and would be allowed to device appropriate mechanism (such as prepaid meters, load
controllers etc.) for billing and revenue collection as well as for preventing power theft
within the cluster.
9.6 Criteria for PD selectionPD would be one entity, both for carrying out the generation and distribution tasks.
There could be many players available for the same. But considering the fact that, for
remote operation there might be unwillingness or non-availability of one entity doing
both the tasks. Therefore, consortia can be allowed to participate with minimal lock-in
period of partnership for 5 year or more. Pre-condition would be if any one of the
agreements viz PPA and FA gets terminated, then both the agreements would get
terminated. Considering the fact that PD is investing 30% equity and it would be in
business interest of PD to continue both, there is less likelihood of PD would like to
terminate one of the two agreements.
9.7 Contractual ArrangementsThe DISCOM shall sign the PPA and Franchisee Agreement with the project
developer. The DISCOM, before signing of agreements, shall undertake necessary
verification of the project developer, the status of un-electrified as well as under-
electrified villages, etc. In case the project developer shall not be able to provide the
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 62/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 62
services as mentioned in any one of the agreements, both of the agreements shall be
cancelled. There will also be a possibility of development of one single contract in the
name of Franchisee cum Power Purchase Agreement consisting of features of the both
the Franchisee and PPA.
9.7.1 Franchisee Agreement
There shall be a franchisee agreement between the project developer and the DISCOM.
The agreement shall follow Model Draft Franchisee Agreement approved by the
Government of India as a part of Rajiv Gandhi Grameen Vidyutikaran Yojana and
would contain the following:
Date Agreement
Contracting Parties
Definitions and Interpretations
Definition of Area
Period of the Contract
Billing and Payment Cycle
Agreed Power Price
MRV Process
Force Majeure Conditions
Roles and Responsibilities of Project Developer / Franchisee
Right of Use - The franchisee shall be entitled to use the DISCOM’s existing
distribution assets to perform its obligation under this Agreement.
Load Forecast – Franchisee shall carry out demand estimation / load forecast
of the Franchise Area periodically and apprise the same to the DISCOM
Operation and Maintenance – Franchisee shall at its own cost perform
following within the cluster:
o O&M of Distribution Assets from the start of input feeders
o O&M of sub-stations and transformer stations
o Installation and replacement of metering devices and carry out meter
reading of all feeders and distribution transformers
o Repair, maintain and replace failed distribution transformers as per the
applicable Supply Code and Standards of Performance notified by
BERC
o Maintain a minimum level of rolling stock of transformers and other
necessary material
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 63/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 63
o Upgrade, renovate and maintain the existing distribution network/
systems/ IT assets and systems as per Prudent DISCOM Practices and
the standards that may be prescribed by BERC.
Compliance Standards - Franchisee shall take all reasonable steps to ensure
that all consumers within the franchise area receive a safe and reliable supply
of electricity as defined by BERC.
Consumer Complaint Handling – Franchisee shall develop complain handling
procedure to be approved by DISCOM.
Consumer Services – Franchisee, on request of the consumer, to the extent that
is reasonably available to the franchisee, shall provide, information on all
services such as meter readings, information on status of customer’s account,
etc.
Obligation to connect consumers - Franchisee shall, on the application of the
owner or occupier of any premises within the Franchise Area
Commercial and Responsibilities – Franchisee shall perform the following,
o Meter reading and billing to the consumers as per the retail tariffs
approved by BERC from time to time;
o Collection from consumers as per billing;
o Collection of arrears / adjustment of arrears on account of Consumers
who are permanently disconnected by the Franchisee;
o Make timely payments of collected revenue to DISCOM as per the
terms and conditions of this Agreement;
o Replace defective meters with new meters;
o Maintain consumer data base and billing records;
o Initiate necessary action, in accordance with the procedure of anti-theft.
Roles and Responsibilities of DISCOM
Supply of Energy – DISCOM shall supply energy at input points of the grid
sub-station. However, this supply may vary subject to SLDC Directives on load
shedding. Without prejudice to the foregoing, DISCOM shall not discriminate
in the supply of power between the Franchise Area and its other Distributionareas
DISCOM shall ensure the supply of power to Franchisee of acceptable quality
standards
DISCOM shall communicate to Franchisee any shortfall or inability to supply,
the power requirements of the Franchisee
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 64/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 64
DISCOM shall carry out meter reading jointly with Franchisee on a monthly
basis at Input Points / interconnection point of the Franchise Area
DISCOM shall support the Franchisee initiatives to adopt innovative practices
to bring about effectiveness and efficiency in electricity distribution business
DISCOM shall incur capital expenditure in case further augmentation of PDN
is required during the period of franchisee agreement.
9.7.2 Power Purchase Agreement
There shall be a PPA between the project developer and the DISCOM. The PPA shall
contain the following information:
Date of Agreement
Contracting Parties
Definitions and Interpretations
Capacity of the project in kW and also in kWh.
Complete details of the distribution network, declare the voltage levels, etc.
Measurement, Reporting and Verification (MRV) process
Grid Synchronization
Tariff
Period of Contract
Billing and Payment Cycle
Delayed Payment Charge
Force Majeure Conditions
Roles and Responsibilities of Project Developer
Project developer shall comply with the Grid Code, Load Despatch & System
Operation Code, Metering Code, Performance Standards, Protection Code and
Safety Code etc. as applicable from time to time in the State
Project developer shall also provide suitable protection and control devices /
islanding devices as a future provision for synchronization of plant with grid
The project developer shall be responsible for security & protection of metering
arrangement based on the location of metering as stipulated in the metering
code.
The project developer shall develop the meter reading, sealing and billing
procedure
Project developer shall submit the billing details to DISCOM and shall raise
invoice based on the sale of utility power as well as the sale of proposed 1 MW
biomass gasifier power to the consumers.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 65/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 65
Roles and Responsibilities of DISCOM
The DISCOM and Project Developer shall jointly read the metering system
The DISCOM shall purchase RE based power generated by DDG from PD to
for agreed operation duration as per protocol of plant operation. Even if grid
power is available DISCOM would import power from RE based DDG plant at
least for agreed generation as per protocol signed among PD-DISCOM-SERC.
The DISCOM shall purchase power from PD on the Feed-in-tariff as specified
by BERC from time.
DISCOM shall pay the FIT to project developer based on the invoice received
from project developer
9.8 Financial assistance needed to ensure financial viabilityPreliminary financial analysis presented in previous section indicates that, with the
prevailing DISCOM tariff, the proposed RE based DDG project is not financially viable
even with 90% capital subsidy. Therefore there is a need of additional financial
assistance to ensure viability of the plant operation over its lifetime. This viability gap
would further increase if the cost of PDN augmentation is included into the capital
cost of the DDG project.
Thus the financial assistance for DDG project would consist of capital subsidy (under
DDG scheme of the Central Government) as well as additional viability gap supportthrough DISCOM/State Government. This requirement of additional viability gap
funding would be required to cover the difference between cost of generation and
distribution (at given capital subsidy) and DISCOM Tariff. Since the BSEB will be
purchasing entire electricity generated by the Project, the said may be accounted to
fulfil its RPO and therefore the viability gap in the form of difference between Cost of
Generation and Consumer Tariff may be absorbed by the BSEB.
It is proposed that the financial assistance to project developer would comprise of both
capital subsidy while commissioning of the DDG power plant and additional viabilitygap on annual basis to meet difference between cost of power distribution and
prevailing Discom tariff while generating and supplying power over lifetime of the
project. The capital subsidy would be limited to 70% of the total project cost so as to
have minimal 30% as equity contribution by PD in line with prevailing practise in
power sector. Reduced subsidy level and increased equity share might increase the
additional viability gap required for providing power but would help attract private
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 66/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 66
sector participation due to enhanced business interest and ownership would help
ensure effective plant operation throughout its life time. Project cost for the proposed
pilot project would comprise of RE based DDG power plant cost (excluding land cost;
as land would be provided by the State Government) along with grid interactive
control equipments and PDN augmentation. Though in the long run PDN cost can be
treated separately (resulting in reduced viability gap requirement for providing
power) and can be covered under distribution infrastructure enhancement programme
and can be financed separately. The viability gap for providing power and prevailing
DISCOM tariff would be paid annually over the lifetime of power plant and would be
borne by the BSEB. Necessary support may be provided by the State Government.
As per the preliminary calculations with 30% equity (70% capital subsidy) and
assumptions (prevailing biomass price of Rs 1000/ton, domestic to commercial load
profile of 60:40, etc) the levelized annual viability gap for generating and supplying
power works out to approx Rs 197 Lakh annually over lifetime of 20 years. However,
at the time of project approval this viability gap would need to be calculated based on
the agreed operating parameters for given RE technology and prevailing values of
different parameters and DSCOM tariff and also quantum of capital subsidy to be
provided by Central govt.
9.9 Bid Process Management
It is proposed that the necessary financial support as well as assistance to
Implementing Agency which is DISCOM for bid process management of this first pilot
project be provided by UNDP-MoP under its ongoing `Access to Energy’ programme.
UNDP will help accelerate the project bidding process through its own channel and
can help in identification of consultant and provide needed assistance so as to keep
project on track before closure of ongoing programme by December 2012.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 67/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 67
10 ROLL OUT PLAN FOR PROPOSED RE BASED DDGPROJECT
This chapter presents the possible ‘Roll Out Plan’ for implementation of the proposed
cluster based rural electrification project in selected cluster of 42 contiguous
habitations in Hulasganj block of Jehanabad district in Bihar. The step-by-step roll out
plan for implementation of the IPP model is given below:
Approval of DPR from UNDP-MoP as well as Project Coordination Committee
of the key stakeholders
Site Clearance for the proposed DDG Plant site near upcoming substation at
Dhongra Mushari, Village Tesaur of Chiri Panchayat
Allocation of fund by MoP and/or UNDP and State Government for the
implementation of the proposed project
Concurrence of BSEB/DISCOM for participation in the project and handing
over distribution assets to PD
Filing of the petition before BERC for determination of FIT by BSEB
Approval of FIT by BERC
Preparation of bid document by BSEB (implementing agency)
Conduct tariff based reverse bidding by BSEB
Selection of the project developer and award the contract by BSEB
Signing of PPA and Franchisee Agreement between DISCOM and PD
Financial closure by PD
Construction and commissioning of RE based Power Plant by PD
Construction/ refurbishment of the PDN network by PD
Generation and distribution of electricity by PD and connecting to power sub-
station and payment of FIT as per PPA by DISCOM to PD throughout the RE
power plant life duration.
MBC to be carried out by PD.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 68/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 68
ANNEXURE A INFORMATION DATA BASE OF VILLAGES-HAMLETS IN SELECTED CLUSTER
Bauri Panchayat
Bauri PanchayatCensus Village Bauri Dadpur Harpur Bihta Dihuri Kew
Habitation (Villag/Hamlet) Total/ Average Bauri Gidarpur KisunpurRupa
BighaDadpur
Adhikari
BighaHarpur Bihta Dihuri Kew
Village Census Code (Census 2001) 3773600 NA NA NA 3773500 NA 3773200 3773300 3773400 37724
Village Area (ha) (Census 2001) 881 289 88 25 176 171 132
No of Households (Census 2001) 1104 449 90 49 184 267 65
Village Population (Census 2001) 7497 3088 636 317 1131 1849 476
Village Population (Census 2011) 9881 4182 889 260 1830 2177 543
No BPL HH (Survey) 887 375 65 20 40 100 10 15 50 152 60
No of Non-BPL HHs (Survey) 793 350 55 20 60 70 20 25 55 98 40
No of Total HHs (Survey) 1680 725 120 40 100 170 30 40 105 250 100
Average HH Annual Income (Rs) 3206 3250 3250 2850 4250 1750 3206 3750 3500 3250 300
Avg kerosene consumption (lit/month)
(2.5 lit is subsidized through PDS)4.55 5.5 5 4.5 4.5 4.5 3.5 4.5 4.5 5.0 4.0
Avg expense for s upplementing electricity
(Rs/HH/month) 114 140 125 130 115 115 80 90 125 100 120
Avg Expenses on Diesel Usage
(Rs/HH/month)127 125 125 130 125 125 125 135 125 120 130
Willingness to pay (Rs/month) 79 75 85 75 79 80 50 75 90 85 100
Community Buildings in Village/Hamlet
Panchayat Bhawan / Community Centre 1 1 0 0 0 0 0 0 0 0 0
School 7 1 1 0 1 1 0 0 2 1 0
Public Health Center 1 0 0 0 1 0 0 0 0 0 0
Cooperative-Bank 0 0 0 0 0 0 0 0 0 0 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 69/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 69
Bauri PanchayatCensus Village Bauri Dadpur Harpur Bihta Dihuri Kew
Habitation (Villag/Hamlet) Total/ Average Bauri Gidarpur KisunpurRupa
BighaDadpur
Adhikari
BighaHarpur Bihta Dihuri Kew
Commercial Activities in Village/Hamlet
Atta chakki 13 3 1 0 3 2 1 0 1 1 1Cane crusher/oil mill 2 0 2 0 0 0 0 0 0 0 0
Rice mill/huller 5 0 0 1 2 2 0 0 0 0 0
No of Irrigation Pumpsets 349 50 80 15 70 50 0 9 10 25 40
Sources of Energy
Grid availability in Villages/Hamlets 6 1 0 0 0 1 0 1 1 1 1
Daily power supply (hr) Annual Avg 5.4 5.5 NA NA NA 5.5 NA 5.5 5.0 6.0 5.0
Monthly availability (day) Avg 17.50 15 NA NA NA 25 NA 12 20 18 15
Crop Residue Production
Rice 2415 800 350 125 150 250 50 10 300 300 80
Wheat 2045 700 300 125 150 200 0 10 250 250 60
Oil Seed 265 100 0 5 10 10 0 0 50 50 40
Sugarcane 120 0 20 5 20 15 0 0 20 20 20
Other Crop (Arhar) 60 0 0 0 0 20 0 0 20 20 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 70/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 70
Khudaur Panchayat
Khudaur PanchayatVillage Total/
Average
Khudauri Raghunathpur Narma Mokimpur Walipur Golakpur
Habitation Khudauri Rampur Raghunathpur Narma Emitpur Benipur Mokimpur Walipur GolakpurVillage Census Code (Census 2001) 3773700 NA 3773800 3773900 NA NA 3774000 3775200 3775500
Village Area (ha) (Census 2001) 1099 223 85 372 54 230 135
No of Households (Census 2001) 1275 330 133 334 35 232 211
Village Population (Census 2001) 8585 2095 930 2331 222 1581 1426
Village Population (Census 2011) 9876 2375 991 2484 1169 1924 933
No BPL HH (Survey) 610 100 20 20 180 80 20 120 40 30
No of Non-BPL HHs (Survey) 550 100 35 55 155 45 10 80 60 10
No of Total HHs (Survey) 1160 200 55 75 335 125 30 200 100 40
Average HH Annual Income (Rs) 3828 2750 3500 4000 4500 4500 3000 4250 4250 3700
Avg kerosene consumption (lit/month)
(2.5 lit is subsidized through PDS)4.8 4.5 4.0 4.5 5.5 5.5 5.0 5.0 4.5 4.5
Avg expense for s upplementing electricity
(Rs/HH/month)129 135 125 125 145 135 135 100 130 130
Avg Expenses on Diesel Usage
(Rs/HH/month)121 120 150 110 145 135 135 90 100 100
Willingness to pay (Rs/month) 88 80 70 90 100 100 90 100 80 85
Community Buildings in Village/Hamlet
Panchayat Bhawan / Community Centre 2 1 1 0 0 0 0 0 0 0
School 6 1 1 1 1 1 0 1 0 0
Public Health Center 6 1 1 0 2 0 0 1 1 0
Cooperative-Bank 1 0 0 0 1 0 0 0 0 0
Commercial Activities in Village/Hamlet
Atta chakki 17 1 5 2 2 1 0 2 0 4
Cane crusher/oil mil 2 1 0 0 0 0 0 1 0 0
Rice mill/huller 20 1 5 2 2 2 2 2 3 1
No of Irrigation Pumpsets 417 100 30 10 100 40 12 100 20 5
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 71/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 71
Khudaur PanchayatVillage Total/
Average
Khudauri Raghunathpur Narma Mokimpur Walipur Golakpur
Habitation Khudauri Rampur Raghunathpur Narma Emitpur Benipur Mokimpur Walipur Golakpur
Sources of Energy
Grid availability in Villages/Hamlets 5 1 0 1 1 1 0 1 0 0
Daily power supply (hr) Annual Avg 5.50 6 NA 5 6 5 NA 5.5 NA NAMonthly availability (day) Avg 19.60 15 NA 18 15 25 NA 25 NA NA
Crop Residue Production
Rice 4465 1700 0 1000 1000 140 15 160 250 200
Wheat 4215 1500 0 1000 1000 140 15 160 250 150
Oil Seed 190 100 0 0 30 0 0 0 10 50
Sugarcane 192 50 0 0 50 10 2 10 20 50
Other Crop (Arhar) 300 0 0 300 0 0 0 0 0 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 72/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 72
Kokarsa Panchayat
Kokarsa PanchayatVillage Total/
Average
Kokarsa Mirzapur Sukiyawan Lodipur Rustampur Rustampur
Habitation Kokarsa Mirzapur Sukiyawan Lodipur Rustampur BeldaripurVillage Census Code (Census 2001) 3775100 3774100 3774200 3775700 3775000 NA
Village Area (ha) Census 2001 1157 457 66 204 58 372
No of Households (Census 2001) 1522 555 107 220 105 535
Village Population (Census 2001) 10391 4105 753 1493 719 3321
Village Population (Census 2011) 12061 5118 789 1628 911 3615
No BPL HH (Survey) 660 200 70 35 80 250 25
No of Non-BPL HHs (Survey) 1205 900 40 25 40 100 100
No of Total HHs (Survey) 1865 1100 110 60 120 350 125
Average HH Annual Income (Rs) 3820 4000 3820 4000 3700 3700 3700
Avg kerosene consumption (lit/month)
(2.5 lit is subsidized through PDS)5.25 6 5 4.5 5 6.5 4.5
Avg expense for supplementing electricity
(Rs/HH/month)130.8 140 125 120 130 135 135
Avg Expenses on Diesel Usage (Rs/HH/month) 113 100 120 130 100 115 135
Willingness to pay (Rs/month) 83.3 70 90 100 90 75 75
Community Buildings in Village/Hamlet
Panchayat Bhawan / Community Centre 2 1 0 0 1 0 0
School 5 1 1 1 1 1 0
Public Health Center 3 1 0 1 1 0 0
Cooperative-Bank 1 0 0 1 0 0 0
Commercial Activities in Village/Hamlet
Atta chakki 23 10 5 5 0 3 0
Cane crusher/oil mil 9 1 4 0 0 4 0
Rice mill/huller 0 0 0 0 0 0 0
No of Irrigation Pumpsets820 500 30 20 20 250 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 73/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 74/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 74
Chiri Panchayat
Chiri PanchayatVillage Chiri Dumri Sarma Sisara Ginnji
Habitation Chiri Dumri Sarma Manjhi Tola Ratan Bigha Sisara Ginji ChaitiPipar DhongraVillage Census Code (Census 2001) 3771900 3772000 3772100 NA NA 3772200 3772300 NA NA
Village Area (ha) Census 2001 218 132 193 133 185
No of Households (Census 2001) 371 150 162 69 170
Village Population (Census 2001) 2401 985 1141 604 1256
Village Population (Census 2011) 2982 1021 1103 798 1527
No BPL HH (Survey) 125 90 50 40 10 51 37 80 5
No of Non-BPL HHs (Survey) 225 80 100 0 0 24 98 15 100
No of Total HHs (Survey) 350 170 150 40 10 75 135 95 105
Average HH Monthly Income (Rs) 4000 1500 4000 1200 2500 3000 4500 2500 3750
Avg kerosene consumption (lit/month)
(2.5 lit is subsidized through PDS)6 6 6 2.5 4.5 5.5 5.5 4.5 4.5
Avg expense for supplementing electricity
(Rs/HH/month)150 150 150 65 125 125 135 125 115
Avg Expenses on Diesel Usage
(Rs/HH/month)120 150 150 50 130 110 120 125 100
Willingness to pay (Rs/month) 120 100 125 90 80 60 100 100 80
Community Buildings in Village/Hamlet
Panchayat Bhawan / Community Centre 1 0 0 0 0 0 0 1 0
School 1 1 1 0 0 1 0 0 1
Public Health Center 1 1 0 0 0 1 1 0 0
Cooperative-Bank 0 0 0 0 0 0 0 0 0
Commercial Activities in Village/Hamlet
Atta chakki 8 5 2 0 0 1 2 0 1
Cane crusher/oil mil 0 0 0 0 0 0 0 0 0
Rice mill/huller 0 10 5 0 0 20 0 1 2
No of Irrigation Pumpsets 100 70 5 0 0 30 20 0 90
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 75/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 75
Chiri PanchayatVillage Chiri Dumri Sarma Sisara Ginnji
Habitation Chiri Dumri Sarma Manjhi Tola Ratan Bigha Sisara Ginji ChaitiPipar Dhongra
Sources of Energy
Grid availability in Villages/Hamlets 1 1 1 0 0 1 1 0 1
Daily power supply (hr) Annual Avg 4 5 5 NA NA 5 5 NA 4.5Monthly availability (day) Avg 10 12 15 NA NA 18 10 NA 13
Crop Residue Production
Rice 1000 400 150 0 0 300 400 25 300
Wheat 800 300 100 0 0 300 320 25 300
Oil Seed 150 25 20 0 0 0 5 5 1
Sugarcane 50 40 5 0 0 15 40 3 5
Other Crop (Arhar) 0 0 0 0 0 5 0 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 76/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 76
Chiri Panchayt (Contd….)
Chiri Panchayat (contd....)Village
Total/
Average
Teasaur Sarthua
Habitation Teasaur DhongraMushari
Sarthua Sevapuri BhaguBigha
Bulaki Bigha DesaiBigha
Kolbhapur
Village Census Code (2001) 3774400 NA 3774500 NA NA NA NA NA
Village Area (ha) 1532 346 325
No of Households (2001) 1383 183 278
Village Population (2001) 9744 1421 1936
Village Population (2011) 11551 1670 2450
No BPL HH (Survey) 879 75 140 75 15 25 1 25 35
No of Non-BPL HHs (Survey) 818 15 0 25 11 45 10 35 35
No of Total HHs (Survey) 1697 90 140 100 26 70 11 60 70
Average HH Annual Income (Rs) 3182 4250 1750 3600 4250 3800 3000 2000 4500
Avg kerosene consumption (lit/month)
(2.5 lit is subsidized through PDS)4.76 5.5 4 4.5 4.5 4 4 5 4.5
Avg expense for supplementing electricity
(Rs/HH/month)120 130 90 140 100 85 100 120 130
Avg Expenses on Diesel Usage
(Rs/HH/month)117 90 120 130 85 100 165 130 110
Willingness to pay (Rs/month) 88 75 100 75 75 80 80 75 80
Community Buildings in Village/Hamlet
Panchayat Bhawan / Community Centre 3 0 0 0 0 0 0 0 1
School 8 1 1 1 0 0 0 0 0
Public Health Center 5 0 1 0 0 0 0 0 0
Cooperative-Bank 0 0 0 0 0 0 0 0 0
Commercial Activities in Village/Hamlet
Atta chakki 29 3 0 0 3 0 2 0 2
Cane crusher/oil mil 2 0 0 0 0 0 2 0 0
Rice mill/huller 43 1 0 0 0 2 0 1 1
No of Irrigation Pumpsets 507 15 0 100 20 10 4 3 40
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 77/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 77
Chiri Panchayat (contd....)Village
Total/
Average
Teasaur Sarthua
Habitation TeasaurDhongra
MushariSarthua Sevapuri
Bhagu
BighaBulaki Bigha
Desai
BighaKolbhapur
Sources of Energy
Grid availability in Villages/Hamlets 0/1 1 1 1 0 0 0 0 0
Daily power supply (hr) Annual Avg 5.0 6 5 5.5 NA NA NA NA NA
Monthly availability (day) Avg 15.4 30 16 15 NA NA NA NA NA
Crop Residue Production
Rice 5300 900 100 1200 100 0 0 25 400
Wheat 4140 800 70 650 100 0 0 25 350
Oil Seed 326 0 20 100 0 0 0 0 0
Sugarcane 240 50 10 0 10 0 0 2 10
Other Crop (Arhar) 15 0 0 0 10 0 0 0 0
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 78/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 78
ANNEXURE B: ECONOMIC ASSESSMENT OF AGRO-RESIDUE AS ENERGY RESOURCE
PreambleBiomass can be classified as woody and non-woody biomass. Non-woody biomasscomprises of agro-crop and agro-industrial processing residue such as rice husk,groundnut shells, coffee husk, straws and stalks, coconut shells, coconut husk, jutesticks etc.
Crop residues are plant materials remaining in the farm after removal of the main cropproduce. The remaining materials could be of different sizes, shapes, forms anddensities i.e. straw, stalks, sticks, leaves, haulms, fibrous materials, roots, branches,twigs etc. The agro-industrial residues, are by-products of post harvest processes ofcrops viz. cleaning, threshing, delinting, sieving, crushing, etc. and could be in theform of husk, dust, straws etc. The major crop residues produced in India are straws of
paddy, wheat, millet, sorghum, pulses, and oil-seed crops, maize stalks and maizecobs, cotton stalks, jute sticks, sugar cane trash, mustard stalks etc. The agro-industrialresidues are groundnut shells, rice husk, bagasse, cotton waste, coconut shell and coirpith.
The quantity of agricultural residues produced, differs from crop to crop and is alsoaffected by seasons, soil type, irrigation conditions etc. Production of agriculturalresidues is directly related to the corresponding crop production and ratio betweenmain crop produce and residues, which varies from crop to crop and at times with thevariety of the seeds in one crop itself. Thus for known amounts of crop production, itmay be possible to estimate the amounts of agricultural residues produced using theresidue to crop ratio.
Most of the agricultural residues are not available throughout the year and becomeavailable at the time of harvest. This makes collection easy, but creates storageproblems if residues have to be saved for use during other months of the yearespecially due to its low bulk density. The amount available depends upon harvestingtime, their storage-related characteristics, the storage facility etc.
In India normally two crops are taken, namely Kharif and Rabi, therefore, availabilityof crop residues is expected to be spread evenly over the year. As a result, cropresidues of one kind or the other are available throughout the year. Since the cropproduction depends upon the agro-climatic conditions, all agro-residues are notavailable in all parts of the country.
Analysis to estimate monetary value of biofuelsBiomass, both woody as well as agricultural residues, have acquired considerableimportance as biofuels for variety of energy enduses such as domestic cooking,industrial process heating, electrical power generation etc. In order to formulate andimplement long-term strategies for efficient and economic utilization of biomass asenergy source, it is important to estimate their monetary value for the end user.
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 79/81
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 80/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
Page 80
The supply cost of rice has been calculated using above approach and by usingprevailing price values and findings are tabulated below.
Supply cost components of rice husk (Rs/tonne)Distance Production Collection Transportation cost Total supply Cost
Animal cart Tractor trolley Animal cart Tractor trolley
0-15km
304 48
108 134 706 732
15-30km 216 268 814 866
30-45km 324 402 922 1000Note : Separate harvesting not considered for rice husk as included in production cost (no separate harvesting of residues) and storage cost is
not considered as normally rice husk is stored in open space
It can be observed that the minimum cost to ensure the supply of rice as biomass fuelas an economically viable proposition varies from Rs 706 to 922 and Rs 732 to 1000 pertonne for animal and tractor trolley respectively for a distance range from 0-15 km to0-45km.
Cost of Agro-Residues: Demand Side ApproachIn the supply side approach the contribution of the costs of production, harvesting,collection, transportation and storage is taken into account to arrive at a reasonableestimate of minimum monetary value of agro-residue. This method does not take intoaccount the quality of the agro-residue such as its energy content (calorific value) andthe effect on efficiency for its utilization, during energy conversion to meet energyrequirement. In order to overcome this drawback there is need calculate the maximumaffordable cost (monetary value of opportunity cost) of agro-residue as biomass fuelfor given energy application. This maximum affordable cost (MACar) of the agro-residue is essentially the monetary value of equivalent amount of fossil fuel that can be
replaced by use of agro-residue as bio-fuel, which can be used as A measure of equivalent monetary worth of agro-residues
A basis for comparison of the prices of two or more agricultural residue for agiven application
An upper limit to the price of agro-residue beyond which the use of fossil fuelmay be better economical/financial option.
Normally, the calorific value of agro-residues and the efficiency of their utilization forparticular energy application differ from that of alternate fossil fuel that is presentlybeing used. The maximum affordable cost of agricultural residue (MACar) can bedetermined by taking into consideration of these differences in calorific values andefficiencies of their utilization by using following equation
ff
ff ff
ar ar
ar C CV
CV MAC
Where, CVar and CVff represents the calorific value of agro-residue and fossil fuel
(being substituted by agro-residue) respectively, while ar and ff represents thethermal efficiency of utilization for the same enduse for agro-residue and fossil fuelrespectively, and Cff is the unit price of fossil fuel at the enduse location. The
8/13/2019 DPR of Hulasganj Cluster_5dec2012
http://slidepdf.com/reader/full/dpr-of-hulasganj-cluster5dec2012 81/81
DPR for ‘Rural Electrification’ through RE based DDG Systemin a cluster of Contiguous Villages in Hulasganj Block of Jehanabad
using Locally Available Renewable Energy Resource
expression in the square bracket of equation represents the equivalent specific mass offossil fuel that is being replaced by agro-residue. The characteristics of rice husk are
Characteristic of selected biomass agro-residuesCalorific value(kcal/kg)
C(%)
H(%)
N(%)
O(%)
Ash(%)
3180 37.03 5.25 0.09 40.94 16.69
The maximum affordable cost (MACar) calculated for rice husk for various competingfuel usage for thermal heat requirements can be tabulated as below.
Maximum affordable cost (MACar) of agro-residues
Fuel Rice husk Coal FO/LDO
Calorific Value (kcal/kg) 3180 3300 9600
Efficiency (%) 15 40 70
Price (Rs/tonne) 3000 37000
MAC of rice husk (Rs/tonne) 1084 2626
The estimated maximum affordable cost (MACar) for rice husk works out to Rs 1084and Rs 2626 per tonne, in competing process industries; presently using coal andFO/LDO for meeting heat energy requirement. Thus the price of rice husk within thecluster would range from minimum of Rs 700 per tonne (supply cost within 0-15km)to Rs 2626 per tonne if competing usage gets developed consuming significantquantity of available rice husk from cluster for replacing present use of FO/LDO. Incase of scarcity within cluster rice husk can be procured at around Rs 1000 per tonnefrom distance of about 45km having surplus availability.