DAILY REPORTFROM SITE
DAILYREPORTFROM SITE
S.No:31 Date 31.01.2013Site: M/s Baldev alloys pvt. LTD.Vwta020,VWHA052,053,054
1.Details of communications received on (E-mail, Fax, Courier, Post, by hand etc.,):Nil.
2.Details of communications sent to HO on:Nil.
3.Details of consignments / materials received from HO / others:Nil.
4.Details of payments received from HO / others:Nil.
5.Attendance with details
5.1Staff (VEESONS):MR.M.E.MANIKANDAN(2141)Mr. DINESH KUMAR.S (1832)
5.2Contract Workers (Contractor wise):Utkal Engineers: Boiler: Supervisor:00 IBR Welder -00;Fitter-03;Welder-01; Riger-02;grinder-0 Helper-06(Total=12)
6.Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,):1.contractor man power shortage2. Radiography film required from contractor.3.customer side insert plates
7.Materials, documents, payments urgently required from HO with details:1. Utkal engg Contractor payment.
8.Any urgent / important site complaints: UTKAL Engineering Should be increasing his manpower.Refractory contractor required for 3XWHRB boiler ABC Ducts.
Site status:VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM1) Dividing chute Support erection work U/P.2) Air heater to esp ducting Support ground fit up Work U/P.3) Furnace seal plate welding work U/P.
ESP; 1) Sealing roof plates erection arrangement work U/P.
Prepared by (Name): M.E.MANIKANDANSignature:Staff No : 2141
Checked & Approved by (Name) :M.E.MANIKANDANSignature:Staff No. :2141