1 OF 10 Laying of MDPE Pipeline in MBT Area DAILY PROGRESS REPORT CLIENT : M/S MAHANAGAR GAS LIMITED Report No. CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15 Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15 ACTIVITY Unit Scope Progress % COMP. Remarks Previous Today Cumm. [A] Low Pressure (L.P) 1 Jay Poonam Nagar (L.P) Mtr. 142.30 142.30 0 142.30 100.00% Billing Done RA-13 2 Gaurav Residency (A,B,C,D,E,F WING) (L.P) Mtr. 305.00 305.00 0 305.00 100.00% Billing Done 3 Geeta Ratna (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done 4 Shetal Building at Bhayander (L.P) Mtr. 9 9 0 9.00 100.00% 5 SadGuru Complex 1 to 4 (L.P) Mtr. 215.7 215.7 0 215.7 100.00% Billing Done 6 Gaurav Residency(K-Wing) (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done 7 Shree Ganesh (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done 8 Evershine Woods 5 To 7 (L.P) Mtr. 184.00 184.00 0 184.00 100.00% Billing Done 9 N.G Vedanta (L.P) Mtr. 64.8 64.8 0 64.8 100.00% Billing Done RA-13 10 Ostwal Orbit (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done 11 Rashmi Pride (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done 12 Jag Shanti (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done 13 Gopal Darshan (L.P) Mtr. 56 56.00 0 56.00 100.00% Billing Done 14 Stanley Residency (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done 15 Dev Shanti (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done 16 Meghdoot Residency (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done 17 Chandresh Aangan (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done 18 OM SHREE SHANTI NIKETAN(L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done 19 VENUS COMPLEX(L.P) Mtr. 154.40 154.40 0 154.40 100.00% Billing Done 20 Asmita Amrit(L.P) Mtr. 71.10 71.10 0 71.10 100.00% Billing Done 21 Chandresh Ashish(L.P) Mtr. 59.00 59.00 0 59.00 100.00% Billing Done 22 Mtr. 194.40 194.40 0 194.40 100.00% Billing Done 23 Solitare Complex(L.P) Mtr. 112.20 112.20 0 112.20 100.00% Billing Done 24 Shri Raj Laxmi(L.P) Mtr. 150 150.00 0 150.00 100.00% Billing Done 25 Ostwal Akshdip(L.P) Mtr. 118.70 118.70 0 118.70 100.00% Billing Done 26 Arihant Complex(L.P) Mtr. 75.20 75.20 0 75.20 100.00% Billing Done 27 Renuka D 84,85 (L.P) Mtr. 98.9 98.9 0 98.9 100.00% Billing Done RA-13 28 Sai Samarth C 64(L.P) Mtr. 53.40 53.40 0 53.40 100.00% Billing Done 29 Vridawan 64(L.P) Mtr. 88.30 88.30 0 88.30 100.00% Billing Done 30 Aditya Building 64(L.P) Mtr. 221.00 221.00 0 221.00 100.00% Billing Done 31 New Rahul Tower (L.P) Mtr. 125 125 0 125 100.00% Billing Done RA-13 32 Queens Classic (L.P) Mtr. 16.40 16.40 0 16.40 100.00% Billing Done 33 Soonam Heights Mtr. 71.8 71.8 0 71.8 100.00% Billing Done RA-13 34 Pragati Sadhna Road (L.P) Mtr. 66.50 66.50 0 66.50 100.00% Billing Done 35 Ritu Paradise (L.P) Mtr. 243 243 0 243 100.00% Order no not given by mgl 36 Mira Complex Mtr. 12 12 0 12 100.00% Billing Done RA-13 37 Mani Palace (L.P) Mtr. 28 28 0 28 100.00% Billing Done RA-13 38 Sarvoday residency Mtr. 41.8 41.8 0 41.8 100.00% Billing Done RA-13 39 KOMAL PALACE Mtr. 59 59 0 59 100.00% Billing Done RA-13 40 MIRA ABID CHS LTD Mtr. 102 102 0 102 100.00% Billing Done RA-20 41 NAVLAXMI krupa Mtr. 103 103 0 103 100.00% Billing Done RA-13 42 Shree park Mtr. 59.3 59.3 0 59.3 100.00% Billing Done 43 Shree Gurudev palace Mtr. 50 50 0 50 100.00% Report Submitted in MGL 44 STAR NARENDRA PARK Mtr. 20.5 20.5 o 20.5 100.00% Billing Done RA-13 45 NIRAV PARK Mtr. 24.00 24.00 o 24.00 100.00% Billing Done RA-13 46 NEW PARIJAT Mtr. 33.4 33.4 o 33.4 100.00% Billing Done RA-13 47 Navsaran Mtr. 25 25 0 25 Commissioning Balance 48 Gazala Glory CHSL Mtr. 35 30 0 30 RI & Commissioning Balance 49 Ashmita club Mtr. 25 25 0 25 100.00% Billing Done RA-20 50 Shrishty Complex A Mtr. 283 283 0 283 100.00% Billing Done RA-20 51 Shrishty Complex B Mtr. 206 206 0 206 100.00% Billing Done RA-20 52 Gaurav Green Mtr. 150 150 0 150 100.00% Report in progress 53 MIG 2 NUTAN Mtr. 60 60 0 60 RI & Commissioning Balance 54 GOLD COINE RESTAURENT & BAR Mtr. 35 35 0 35 Testing balance 56 Alokanand & Amrapali Mtr. 124 124 0 124 100.00% Report Submitted in MGL 57 Akshar sagar & Ellora shantinagar chs.ltd. Mtr. 129.8 129.8 0 129.8 100.00% Report Submitted in MGL 58 Dreamland chs.ltd. Mtr. 41.4 41.4 0 41.4 100.00% Billing Done RA-20 59 Ritu fame Mtr. 50 50 0 50 Commissioning Balance 61 Bharti Park L M Mtr. 30 30 0 30 RI & Commissioning Balance 62 Embassy County Mtr. 60 60 0 60 Commissioning Balance 63 Sagar Drasti Soc. Mtr. 70 15 0 15 Trenching in progress SL NO Work is Stop due to Labour Issue ACCORD/ARINA COMPLEX/HOODA/POONMA CLASSIC(L.P)

Upload: shubham1404

Post on 07-Feb-2016

16 views

Category:

Documents


0 download

DESCRIPTION

sdsd

TRANSCRIPT

Page 1: DPR -23-01-15sd

1 OF 10

Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT

CLIENT : M/S MAHANAGAR GAS LIMITED Report No.

CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15

Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15

ACTIVITY Unit ScopeProgress

% COMP. RemarksPrevious Today Cumm.

[A] Low Pressure (L.P)

1 Jay Poonam Nagar (L.P) Mtr. 142.30 142.30 0 142.30 100.00% Billing Done RA-13

2 Gaurav Residency (A,B,C,D,E,F WING) (L.P) Mtr. 305.00 305.00 0 305.00 100.00% Billing Done

3 Geeta Ratna (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done

4 Shetal Building at Bhayander (L.P) Mtr. 9 9 0 9.00 100.00% Work is Stop due to Labour Issue

5 SadGuru Complex 1 to 4 (L.P) Mtr. 215.7 215.7 0 215.7 100.00% Billing Done

6 Gaurav Residency(K-Wing) (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done

7 Shree Ganesh (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done

8 Evershine Woods 5 To 7 (L.P) Mtr. 184.00 184.00 0 184.00 100.00% Billing Done

9 N.G Vedanta (L.P) Mtr. 64.8 64.8 0 64.8 100.00% Billing Done RA-13

10 Ostwal Orbit (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done

11 Rashmi Pride (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done

12 Jag Shanti (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done

13 Gopal Darshan (L.P) Mtr. 56 56.00 0 56.00 100.00% Billing Done

14 Stanley Residency (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done

15 Dev Shanti (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done

16 Meghdoot Residency (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done

17 Chandresh Aangan (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done

18 OM SHREE SHANTI NIKETAN(L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done

19 VENUS COMPLEX(L.P) Mtr. 154.40 154.40 0 154.40 100.00% Billing Done

20 Asmita Amrit(L.P) Mtr. 71.10 71.10 0 71.10 100.00% Billing Done

21 Chandresh Ashish(L.P) Mtr. 59.00 59.00 0 59.00 100.00% Billing Done

22 Mtr. 194.40 194.40 0 194.40 100.00% Billing Done

23 Solitare Complex(L.P) Mtr. 112.20 112.20 0 112.20 100.00% Billing Done

24 Shri Raj Laxmi(L.P) Mtr. 150 150.00 0 150.00 100.00% Billing Done

25 Ostwal Akshdip(L.P) Mtr. 118.70 118.70 0 118.70 100.00% Billing Done

26 Arihant Complex(L.P) Mtr. 75.20 75.20 0 75.20 100.00% Billing Done

27 Renuka D 84,85 (L.P) Mtr. 98.9 98.9 0 98.9 100.00% Billing Done RA-13

28 Sai Samarth C 64(L.P) Mtr. 53.40 53.40 0 53.40 100.00% Billing Done

29 Vridawan 64(L.P) Mtr. 88.30 88.30 0 88.30 100.00% Billing Done

30 Aditya Building 64(L.P) Mtr. 221.00 221.00 0 221.00 100.00% Billing Done

31 New Rahul Tower (L.P) Mtr. 125 125 0 125 100.00% Billing Done RA-13

32 Queens Classic (L.P) Mtr. 16.40 16.40 0 16.40 100.00% Billing Done

33 Soonam Heights Mtr. 71.8 71.8 0 71.8 100.00% Billing Done RA-13

34 Pragati Sadhna Road (L.P) Mtr. 66.50 66.50 0 66.50 100.00% Billing Done

35 Ritu Paradise (L.P) Mtr. 243 243 0 243 100.00% Order no not given by mgl

36 Mira Complex Mtr. 12 12 0 12 100.00% Billing Done RA-13

37 Mani Palace (L.P) Mtr. 28 28 0 28 100.00% Billing Done RA-13

38 Sarvoday residency Mtr. 41.8 41.8 0 41.8 100.00% Billing Done RA-13

39 KOMAL PALACE Mtr. 59 59 0 59 100.00% Billing Done RA-13

40 MIRA ABID CHS LTD Mtr. 102 102 0 102 100.00% Billing Done RA-20

41 NAVLAXMI krupa Mtr. 103 103 0 103 100.00% Billing Done RA-13

42 Shree park Mtr. 59.3 59.3 0 59.3 100.00% Billing Done

43 Shree Gurudev palace Mtr. 50 50 0 50 100.00% Report Submitted in MGL

44 STAR NARENDRA PARK Mtr. 20.5 20.5 o 20.5 100.00% Billing Done RA-13

45 NIRAV PARK Mtr. 24.00 24.00 o 24.00 100.00% Billing Done RA-13

46 NEW PARIJAT Mtr. 33.4 33.4 o 33.4 100.00% Billing Done RA-13

47 Navsaran Mtr. 25 25 0 25 Commissioning Balance

48 Gazala Glory CHSL Mtr. 35 30 0 30 RI & Commissioning Balance

49 Ashmita club Mtr. 25 25 0 25 100.00% Billing Done RA-20

50 Shrishty Complex A Mtr. 283 283 0 283 100.00% Billing Done RA-20

51 Shrishty Complex B Mtr. 206 206 0 206 100.00% Billing Done RA-20

52 Gaurav Green Mtr. 150 150 0 150 100.00% Report in progress

53 MIG 2 NUTAN Mtr. 60 60 0 60 RI & Commissioning Balance

54 GOLD COINE RESTAURENT & BAR Mtr. 35 35 0 35 Testing balance

56 Alokanand & Amrapali Mtr. 124 124 0 124 100.00% Report Submitted in MGL

57 Akshar sagar & Ellora shantinagar chs.ltd. Mtr. 129.8 129.8 0 129.8 100.00% Report Submitted in MGL

58 Dreamland chs.ltd. Mtr. 41.4 41.4 0 41.4 100.00% Billing Done RA-20

59 Ritu fame Mtr. 50 50 0 50 Commissioning Balance

61 Bharti Park L M Mtr. 30 30 0 30 RI & Commissioning Balance

62 Embassy County Mtr. 60 60 0 60 Commissioning Balance

63 Sagar Drasti Soc. Mtr. 70 15 0 15 Trenching in progress

SL NO

ACCORD/ARINA COMPLEX/HOODA/POONMA CLASSIC(L.P)

Page 2: DPR -23-01-15sd

2 OF 10

Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT

CLIENT : M/S MAHANAGAR GAS LIMITED Report No.

CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15

Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15

ACTIVITY Unit ScopeProgress

% COMP. RemarksPrevious Today Cumm.

SL NO

Highlights

There are Many complain in Bharti Park for Removal of debris & RI. (Work Done by bharat Const.)

REMARKS :

Today We have Clear the trench In nallah Crossing

Page 3: DPR -23-01-15sd

Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT

CLIENT : M/S MAHANAGAR GAS LIMITED

CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD.

Weather : Sunny / Cloudy / Rainy

ACTIVITY Unit ScopeProgress

Previous Today[2] Medium Pressure (M.P)

1 R. Mehta Cllg Road at Bhayandar (M.P) Mtr. 80 80.00 0

2 Gaurav Residency[a,b,c,d,e, & f](M.P) Mtr. 10 10.00 0

3 Sadguru Complex(M.P) Mtr. 10 10.00 04 Geeta Ratan(M.P) Mtr. 10 10.00 05 Rashmi Pride(M.P) Mtr. 10 10.00 06 Hooda Complex(M.P) Mtr. 15 15.00 07 Rock Wood(M.P) Mtr. 15 15.00 08 Solitare III Poonam Complex(M.P) Mtr. 3 3.00 09 Star Narendra Park(M.P) Mtr. 5 5.00 0

10 Mtr. 10 10.00 011 Krishna Sthal(M.P) Mtr. 10 10.00 012 Samash Masjid (M.P) Mtr. 7 7.00 013 Star Narendra Park(M.P) Mtr. 6 6.00 014 Penkar pada road Mtr. 6 6.00 015 Shree Raj Laxmi Mtr. 50 50.00 016 Rock & Wood (I & C Connection) Mtr. 2 2.00 017 Sadhna Pragti Mtr. 4 4 018 Vridawan Mtr. 23.30 23.30 019 Jai Krishna Mtr. 4.7 4.7 020 Mani Palace Mtr. 5.7 5.7 021 Bittu Da Dhaba(I & C Connection) Mtr. 2 2.00 022 Avkar Hotel (I & C Connection) Mtr. 10 10 023 Soonam Heights Mtr. 56.5 56.5 024 Shristi complex (Nallah) Mtr. 12 12 025 Bhayander Road Mtr. 0 0 026 Ritu Paradise Mtr. 18.5 18.5 027 Shristi complex Mtr. 50.6 50.6 028 N.G VEDANT Mtr. 2 2 0

29 RAJ ATLANTA (Nallah) Mtr. 2 2 0

30 MIRA ABID CHS LTD Mtr. 40 40 0

31 Sarvoday residency Mtr. 3.8 3.8 0

32 Sungrace,Ramdev park rd Mtr. 1.7 1.7 0

33 KOMAL D-66 Mtr. 4.4 4.4 0

34 Shristi complex MP EXT. Mtr. 13 13 035 Tapping for Allora & akshar sagar Mtr. 7 7 036 Tapping for Dreamland Mtr. 3 3 037 Time Less Resturent Mtr. 30 26 0

38 BMC Nallah Crossing At GCC Mtr. 12 12 0

SL NO

Poonam Sagar Complex Avkar Rest.(M.P)

Page 4: DPR -23-01-15sd

39 Ohm Sai Mtr. 15 0

40 Garib Nawaz Rest. Mtr. 18 20 0

41 Gold Coine Nallah Crossing Mtr. 6 6 0

Page 5: DPR -23-01-15sd

Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT

Report No.

Report Date 23/Jan/15

Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15

Progress% COMP. Remarks

Cumm.

80.00 100.00% Commissioning & Charging balance

10.00 100.00% Billing Done

10.00 100.00% Billing Done10.00 100.00% Billing Done10.00 100.00% Billing Done15.00 100.00% Billing Done15.00 100.00% Billing Done3.00 100.00% Billing Done5.00 100.00% Billing Done

10.00 100.00% Billing Done10.00 100.00% Billing Done7.00 100.00% Billing Done6.00 100.00% Billing Done6.00 100.00% Billing Done

50.00 100.00% Billing Done2.00 100.00% Billing Done

4 100.00% Billing Done23.30 100.00% Billing Done

4.7 100.00% Billing Done5.7 100.00% Billing Done RA-132.00 100.00% Billing Done RA-1310 100.00% Billing Done

56.5 100.00% Billing Done RA-1312 100.00% Billing Done RA-130 Backfilling by BMC without completing work

18.5 100.00% Commissioning reports are under process50.6 100.00% Billing Done RA-13

2 100.00% Billing Done RA-132 100.00% Commissioning reports are under process

40 100.00% Billing Done RA-133.8 100.00% Billing Done RA-131.7 100.00% Billing Done RA-134.4 100.00% Billing Done RA-1313 100.00% Billing Done RA-207 100.00% Billing Done RA-203 100.00% Billing Done RA-20

30 Nallah Xing Comp. Commissioning Balance12 Laying completed

Page 6: DPR -23-01-15sd

Nallah Crossing IP20 Nallah Xing Comp. Commissioning Balance6 Nallah Xing Comp. Joints & Backfilling Balance

Page 7: DPR -23-01-15sd

NEXT DAY PROGRAMME

CLIENT : M/S MAHANAGAR GAS LIMITED Report No.

CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15

Next Date 24/Jan/15

ACTIVITY LOCATION CONTACT PERSON Mob. No. REMARKS

3 Sagar Drasti Mira Road Prabhat 9892792610

4 MP at Gold Coine Rest. Mira Road Rajib 8898654795

SL NO

Page 8: DPR -23-01-15sd

LAYING OF MDPE Pipeline in MBT AreaMANPOWER Date:23/01/2015

Category No.

1 Project Manager 12 Planning Engineer 13 Store In-charge/Supervisor 14 HSE - Officer5 QA/QC Engineer6 Site Engineer7 Site Supervisor / Foreman8 Skilled Manpower9 Semi Skilled Manpower

10 Un - Skilled Manpower11 Civil Labour (Murgan) 2+(2Naka Labour)

SL.NO.

Page 9: DPR -23-01-15sd

LAYING OF MDPE Pipeline in MBT AreaMANPOWER Date:23/01/2015

REMARKS

Naka labour For trial pit at G.C.C

Page 10: DPR -23-01-15sd

Page 10 of 10

LAYING OF MDPE Pipeline in MBT Area

Equipment

Date:23/01/2015

S. No. Description No. Remarks

1 Barricades 30 15 Issued to Bharath const.

2 Fire Extinguisher 2

3 First Aid Box 2

4 Air Compressor 1

5 Two Wheller 1

6 Tools Tackle (MDPE Pipeline) - 1 Transfer to Thane AIPL

7 Fusion Machine

8 Rotometer 1 Need to Repair

9 CPU 1 Send to Repairing(6 months ago)

10 COMPUTER & PRINTER One Set