dpr -23-01-15sd
DESCRIPTION
sdsdTRANSCRIPT
![Page 1: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/1.jpg)
1 OF 10
Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT
CLIENT : M/S MAHANAGAR GAS LIMITED Report No.
CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15
Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15
ACTIVITY Unit ScopeProgress
% COMP. RemarksPrevious Today Cumm.
[A] Low Pressure (L.P)
1 Jay Poonam Nagar (L.P) Mtr. 142.30 142.30 0 142.30 100.00% Billing Done RA-13
2 Gaurav Residency (A,B,C,D,E,F WING) (L.P) Mtr. 305.00 305.00 0 305.00 100.00% Billing Done
3 Geeta Ratna (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done
4 Shetal Building at Bhayander (L.P) Mtr. 9 9 0 9.00 100.00% Work is Stop due to Labour Issue
5 SadGuru Complex 1 to 4 (L.P) Mtr. 215.7 215.7 0 215.7 100.00% Billing Done
6 Gaurav Residency(K-Wing) (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done
7 Shree Ganesh (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done
8 Evershine Woods 5 To 7 (L.P) Mtr. 184.00 184.00 0 184.00 100.00% Billing Done
9 N.G Vedanta (L.P) Mtr. 64.8 64.8 0 64.8 100.00% Billing Done RA-13
10 Ostwal Orbit (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done
11 Rashmi Pride (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done
12 Jag Shanti (L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done
13 Gopal Darshan (L.P) Mtr. 56 56.00 0 56.00 100.00% Billing Done
14 Stanley Residency (L.P) Mtr. 84 84.00 0 84.00 100.00% Billing Done
15 Dev Shanti (L.P) Mtr. 100 100.00 0 100.00 100.00% Billing Done
16 Meghdoot Residency (L.P) Mtr. 60 60.00 0 60.00 100.00% Billing Done
17 Chandresh Aangan (L.P) Mtr. 50 50.00 0 50.00 100.00% Billing Done
18 OM SHREE SHANTI NIKETAN(L.P) Mtr. 80 80.00 0 80.00 100.00% Billing Done
19 VENUS COMPLEX(L.P) Mtr. 154.40 154.40 0 154.40 100.00% Billing Done
20 Asmita Amrit(L.P) Mtr. 71.10 71.10 0 71.10 100.00% Billing Done
21 Chandresh Ashish(L.P) Mtr. 59.00 59.00 0 59.00 100.00% Billing Done
22 Mtr. 194.40 194.40 0 194.40 100.00% Billing Done
23 Solitare Complex(L.P) Mtr. 112.20 112.20 0 112.20 100.00% Billing Done
24 Shri Raj Laxmi(L.P) Mtr. 150 150.00 0 150.00 100.00% Billing Done
25 Ostwal Akshdip(L.P) Mtr. 118.70 118.70 0 118.70 100.00% Billing Done
26 Arihant Complex(L.P) Mtr. 75.20 75.20 0 75.20 100.00% Billing Done
27 Renuka D 84,85 (L.P) Mtr. 98.9 98.9 0 98.9 100.00% Billing Done RA-13
28 Sai Samarth C 64(L.P) Mtr. 53.40 53.40 0 53.40 100.00% Billing Done
29 Vridawan 64(L.P) Mtr. 88.30 88.30 0 88.30 100.00% Billing Done
30 Aditya Building 64(L.P) Mtr. 221.00 221.00 0 221.00 100.00% Billing Done
31 New Rahul Tower (L.P) Mtr. 125 125 0 125 100.00% Billing Done RA-13
32 Queens Classic (L.P) Mtr. 16.40 16.40 0 16.40 100.00% Billing Done
33 Soonam Heights Mtr. 71.8 71.8 0 71.8 100.00% Billing Done RA-13
34 Pragati Sadhna Road (L.P) Mtr. 66.50 66.50 0 66.50 100.00% Billing Done
35 Ritu Paradise (L.P) Mtr. 243 243 0 243 100.00% Order no not given by mgl
36 Mira Complex Mtr. 12 12 0 12 100.00% Billing Done RA-13
37 Mani Palace (L.P) Mtr. 28 28 0 28 100.00% Billing Done RA-13
38 Sarvoday residency Mtr. 41.8 41.8 0 41.8 100.00% Billing Done RA-13
39 KOMAL PALACE Mtr. 59 59 0 59 100.00% Billing Done RA-13
40 MIRA ABID CHS LTD Mtr. 102 102 0 102 100.00% Billing Done RA-20
41 NAVLAXMI krupa Mtr. 103 103 0 103 100.00% Billing Done RA-13
42 Shree park Mtr. 59.3 59.3 0 59.3 100.00% Billing Done
43 Shree Gurudev palace Mtr. 50 50 0 50 100.00% Report Submitted in MGL
44 STAR NARENDRA PARK Mtr. 20.5 20.5 o 20.5 100.00% Billing Done RA-13
45 NIRAV PARK Mtr. 24.00 24.00 o 24.00 100.00% Billing Done RA-13
46 NEW PARIJAT Mtr. 33.4 33.4 o 33.4 100.00% Billing Done RA-13
47 Navsaran Mtr. 25 25 0 25 Commissioning Balance
48 Gazala Glory CHSL Mtr. 35 30 0 30 RI & Commissioning Balance
49 Ashmita club Mtr. 25 25 0 25 100.00% Billing Done RA-20
50 Shrishty Complex A Mtr. 283 283 0 283 100.00% Billing Done RA-20
51 Shrishty Complex B Mtr. 206 206 0 206 100.00% Billing Done RA-20
52 Gaurav Green Mtr. 150 150 0 150 100.00% Report in progress
53 MIG 2 NUTAN Mtr. 60 60 0 60 RI & Commissioning Balance
54 GOLD COINE RESTAURENT & BAR Mtr. 35 35 0 35 Testing balance
56 Alokanand & Amrapali Mtr. 124 124 0 124 100.00% Report Submitted in MGL
57 Akshar sagar & Ellora shantinagar chs.ltd. Mtr. 129.8 129.8 0 129.8 100.00% Report Submitted in MGL
58 Dreamland chs.ltd. Mtr. 41.4 41.4 0 41.4 100.00% Billing Done RA-20
59 Ritu fame Mtr. 50 50 0 50 Commissioning Balance
61 Bharti Park L M Mtr. 30 30 0 30 RI & Commissioning Balance
62 Embassy County Mtr. 60 60 0 60 Commissioning Balance
63 Sagar Drasti Soc. Mtr. 70 15 0 15 Trenching in progress
SL NO
ACCORD/ARINA COMPLEX/HOODA/POONMA CLASSIC(L.P)
![Page 2: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/2.jpg)
2 OF 10
Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT
CLIENT : M/S MAHANAGAR GAS LIMITED Report No.
CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15
Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15
ACTIVITY Unit ScopeProgress
% COMP. RemarksPrevious Today Cumm.
SL NO
Highlights
There are Many complain in Bharti Park for Removal of debris & RI. (Work Done by bharat Const.)
REMARKS :
Today We have Clear the trench In nallah Crossing
![Page 3: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/3.jpg)
Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT
CLIENT : M/S MAHANAGAR GAS LIMITED
CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD.
Weather : Sunny / Cloudy / Rainy
ACTIVITY Unit ScopeProgress
Previous Today[2] Medium Pressure (M.P)
1 R. Mehta Cllg Road at Bhayandar (M.P) Mtr. 80 80.00 0
2 Gaurav Residency[a,b,c,d,e, & f](M.P) Mtr. 10 10.00 0
3 Sadguru Complex(M.P) Mtr. 10 10.00 04 Geeta Ratan(M.P) Mtr. 10 10.00 05 Rashmi Pride(M.P) Mtr. 10 10.00 06 Hooda Complex(M.P) Mtr. 15 15.00 07 Rock Wood(M.P) Mtr. 15 15.00 08 Solitare III Poonam Complex(M.P) Mtr. 3 3.00 09 Star Narendra Park(M.P) Mtr. 5 5.00 0
10 Mtr. 10 10.00 011 Krishna Sthal(M.P) Mtr. 10 10.00 012 Samash Masjid (M.P) Mtr. 7 7.00 013 Star Narendra Park(M.P) Mtr. 6 6.00 014 Penkar pada road Mtr. 6 6.00 015 Shree Raj Laxmi Mtr. 50 50.00 016 Rock & Wood (I & C Connection) Mtr. 2 2.00 017 Sadhna Pragti Mtr. 4 4 018 Vridawan Mtr. 23.30 23.30 019 Jai Krishna Mtr. 4.7 4.7 020 Mani Palace Mtr. 5.7 5.7 021 Bittu Da Dhaba(I & C Connection) Mtr. 2 2.00 022 Avkar Hotel (I & C Connection) Mtr. 10 10 023 Soonam Heights Mtr. 56.5 56.5 024 Shristi complex (Nallah) Mtr. 12 12 025 Bhayander Road Mtr. 0 0 026 Ritu Paradise Mtr. 18.5 18.5 027 Shristi complex Mtr. 50.6 50.6 028 N.G VEDANT Mtr. 2 2 0
29 RAJ ATLANTA (Nallah) Mtr. 2 2 0
30 MIRA ABID CHS LTD Mtr. 40 40 0
31 Sarvoday residency Mtr. 3.8 3.8 0
32 Sungrace,Ramdev park rd Mtr. 1.7 1.7 0
33 KOMAL D-66 Mtr. 4.4 4.4 0
34 Shristi complex MP EXT. Mtr. 13 13 035 Tapping for Allora & akshar sagar Mtr. 7 7 036 Tapping for Dreamland Mtr. 3 3 037 Time Less Resturent Mtr. 30 26 0
38 BMC Nallah Crossing At GCC Mtr. 12 12 0
SL NO
Poonam Sagar Complex Avkar Rest.(M.P)
![Page 4: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/4.jpg)
39 Ohm Sai Mtr. 15 0
40 Garib Nawaz Rest. Mtr. 18 20 0
41 Gold Coine Nallah Crossing Mtr. 6 6 0
![Page 5: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/5.jpg)
Laying of MDPE Pipeline in MBT AreaDAILY PROGRESS REPORT
Report No.
Report Date 23/Jan/15
Weather : Sunny / Cloudy / Rainy Progress Date 23/Jan/15
Progress% COMP. Remarks
Cumm.
80.00 100.00% Commissioning & Charging balance
10.00 100.00% Billing Done
10.00 100.00% Billing Done10.00 100.00% Billing Done10.00 100.00% Billing Done15.00 100.00% Billing Done15.00 100.00% Billing Done3.00 100.00% Billing Done5.00 100.00% Billing Done
10.00 100.00% Billing Done10.00 100.00% Billing Done7.00 100.00% Billing Done6.00 100.00% Billing Done6.00 100.00% Billing Done
50.00 100.00% Billing Done2.00 100.00% Billing Done
4 100.00% Billing Done23.30 100.00% Billing Done
4.7 100.00% Billing Done5.7 100.00% Billing Done RA-132.00 100.00% Billing Done RA-1310 100.00% Billing Done
56.5 100.00% Billing Done RA-1312 100.00% Billing Done RA-130 Backfilling by BMC without completing work
18.5 100.00% Commissioning reports are under process50.6 100.00% Billing Done RA-13
2 100.00% Billing Done RA-132 100.00% Commissioning reports are under process
40 100.00% Billing Done RA-133.8 100.00% Billing Done RA-131.7 100.00% Billing Done RA-134.4 100.00% Billing Done RA-1313 100.00% Billing Done RA-207 100.00% Billing Done RA-203 100.00% Billing Done RA-20
30 Nallah Xing Comp. Commissioning Balance12 Laying completed
![Page 6: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/6.jpg)
Nallah Crossing IP20 Nallah Xing Comp. Commissioning Balance6 Nallah Xing Comp. Joints & Backfilling Balance
![Page 7: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/7.jpg)
NEXT DAY PROGRAMME
CLIENT : M/S MAHANAGAR GAS LIMITED Report No.
CONTRACTOR : M/S ADVANCE INFRASTRUCTURES PVT. LTD. Report Date 23/Jan/15
Next Date 24/Jan/15
ACTIVITY LOCATION CONTACT PERSON Mob. No. REMARKS
3 Sagar Drasti Mira Road Prabhat 9892792610
4 MP at Gold Coine Rest. Mira Road Rajib 8898654795
SL NO
![Page 8: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/8.jpg)
LAYING OF MDPE Pipeline in MBT AreaMANPOWER Date:23/01/2015
Category No.
1 Project Manager 12 Planning Engineer 13 Store In-charge/Supervisor 14 HSE - Officer5 QA/QC Engineer6 Site Engineer7 Site Supervisor / Foreman8 Skilled Manpower9 Semi Skilled Manpower
10 Un - Skilled Manpower11 Civil Labour (Murgan) 2+(2Naka Labour)
SL.NO.
![Page 9: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/9.jpg)
LAYING OF MDPE Pipeline in MBT AreaMANPOWER Date:23/01/2015
REMARKS
Naka labour For trial pit at G.C.C
![Page 10: DPR -23-01-15sd](https://reader035.vdocuments.us/reader035/viewer/2022081505/55cf91a4550346f57b8f2989/html5/thumbnails/10.jpg)
Page 10 of 10
LAYING OF MDPE Pipeline in MBT Area
Equipment
Date:23/01/2015
S. No. Description No. Remarks
1 Barricades 30 15 Issued to Bharath const.
2 Fire Extinguisher 2
3 First Aid Box 2
4 Air Compressor 1
5 Two Wheller 1
6 Tools Tackle (MDPE Pipeline) - 1 Transfer to Thane AIPL
7 Fusion Machine
8 Rotometer 1 Need to Repair
9 CPU 1 Send to Repairing(6 months ago)
10 COMPUTER & PRINTER One Set