TW@ESI5TH MARCH 2017
Hello to all , hope you all had a good weekend.
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
Miltiadis Charalampidis (AKA Miltos) joined us this week as
an assistant Projects co ordinator at MDH – John please ask him to make a
Linkedin profile and join the team ESI group
Some Points Before Starting
Shridar will be on long leave from 17 Feb 2017 to 20th March
Dennis Smith has resigned from his post as Projects Co Ordinator will
work till 17th March 2017 - We will struggle to fill in Dennis’ shoes and I will need everyone’s help until we
find his replacement- I would like to thank Dennis for the service he gave ESI and wish him luck on his
future
Projects and Deadlines
16_025_DeLaRue_OFX
50% of the machines should ready for commissioning by CFH
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017
Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here
16_066_Sterling_DCS_Line2
We have started some preliminary engineering here.... Kick off is scheduled for 7th March
16_040_Playmobil_Factory
We have started design and engineering here on MCC1 and 2 and I have started placing major orders .... Kick off is scheduled for 7th March
Projects and Deadlines
16_023_GGY
We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017
15_023_FM panels
D20 ASRD being built by sub contractor and scheduled for 9th March 2017
15_023 Q012 [D10 Endicare 230V] - Beginning april 2017
D05 M 110 – scheduled for 1st May 2017
D20 ASRD 690 is presently in quotation stage
16_041_RSM_Security
We need to close off here – the sooner the better
SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)
16_058_Methode
Another fast tack project Jace Based AHU control system here
I know that CCI , DSH and installation team have done some real efforts here... Panel and most equipment has been energised- well done –
Next is testing and commissioning
Projects and Deadlines
12_043_LSP
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
We also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
13_070- SCM Lagoona Plant room
We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
01 02 03 04
DesignFor the Past week we have been working on the following
OTM – Started SSA’s Q021 docs revision request
Playmobil HF80 – Status review with SAA- Started & Finished Panel Design sketching for MCC1, Compiled and released Material quote request
Design
01 02 03 04
DesignAnd next week… we will work on
Start & complete new FM Env. Panel then send to CFH to submit
Playmobil HF80 – review Material quote, and release to Manuel to orderPlaymobil HF80 – release MCC1 to NFH for draughtingPlaymobil HF80 – Start Panel design of MCC2 and releas Material quote request
Design
OTM – Continue Q020 Netherlocks remaining DesignOTM – Start SSA’s Q021 docs revision request
This is what the Installation team have been working on last week
Mounting of panel on site at Methode
Completed indoor PIR’s and started fixing power supplies at Graham
Installation
Energized panel and equipment at MethodeCompleted control cables pulling at Methode
Continued with commissioning at RSM
….. And this is what is planned for next week
Complete snags on Methode panel
Start with panel terminations at Graham
Start commissioning at Methode
Installation
Continue with terminations at OVT
Complete commissioning at RSM
Next week we will • FM Env D20-ASRD – This will be built by a sub contractor
Panel Build
Panel Build
Week 09PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5
Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1
Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team member
Mater Dei Maintenance
Crane Currency BMS and ELV Proposals
lighting control systems in Qatar
Offer for Neatherlocks at OTM
De La Rue BMS
Actavis Solvent area Process quoteThese are the quotes the business development
team have been working on
Business Development
\
HAPPY BIRTHDAYGLENN GHIRXI MARCH 6TH
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week