Renewable Energy in Kuwait Between Vision & Reality
![Page 2: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/2.jpg)
By 2030 about 900,000 Barrels / day will be use to
cover the Demand for Electricity & Water
Which will be 1/3 of Kuwait
OIL Production
Kuwait Renewable Energy Vision
![Page 3: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/3.jpg)
Power Demand Forecasting 2030
Housing Projects 12,000 MW
KOC Upstream 1,100MW
NEW University 450 MW
Commercial & Industrial 600 MW
KNPC (NRP+CFP) 800 MW
Bobyan Island 900 MW
Additional Power Required for Kuwait Projects up to 2030
18,000 MW
![Page 4: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/4.jpg)
Peak Load & Available Capacity - 2030
5000
10000
15000
20000
25000
30000
35000
2010 2016 2020 2025 2030
Peak Load Including Projects (MW) Available + Expected Capacity (MW)
13390 MW
30274 MW
33710 MW
22622 MW
10890 MW
15682 MW
20700 MW
29510 MW
11650 MW
16905 MW
![Page 5: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/5.jpg)
Completed VS. Future
Since 2013
26 project have been completed
Total installed capacity 39.5 MW
By 2022
35 project are under design and/or construction
Total installed capacity 1,658 MW
Renewable contribution estimated to reach 11.42%
![Page 6: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/6.jpg)
MEW & MPW Buildings
First project with Mega capacity
Operation on April 20 2014
Installed Capacity 1 MW
![Page 7: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/7.jpg)
MEW Roof Top PV Projects
Applying PV’s on the Roofs of (6) Stores in Sabhan
Installed Capacity 3.75 MW.
Tendering Installation PV’s on the roofs of existing and new parking areas at
Phase I - Main Workshops - Installed Capacity 2.7 MW
Phase II - Power Stations - Installed Capacity 3.0 MW
Phase III - Other MEW Buildings - Installed Capacity 3.3 MW
Planned date for operation by 2019
![Page 8: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/8.jpg)
First CDM PV Project
Sidra 500
• Installed capacity 10 MW
• Operation date October 2016
![Page 9: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/9.jpg)
PV @ MEW Ground Water Reservoirs
• 25 Locations
• 300 MW Total Installed Capacity
• Phase 1- to be tendered 2nd Quarter 2017
• Location : Subiya - Capacity 30 MW
![Page 10: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/10.jpg)
Under Evaluation
Waste capacity 3,275 tons/day.
80 MW of production
25 yrs. from operate.
Total area of 500,000 m2.
Municipal Solid Waste Treatment Facility – Kabd Location
![Page 11: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/11.jpg)
Abdaleyah Integrated Solar Combined Cycle “ISCC” Project
Total 280 MW including 60 MW Solar.
PQ List includes 8 Consortiums.
![Page 12: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/12.jpg)
0,00 0,02 0,03 0,30 0,84
3,70 3,72
10,85 11,30 11,42
0,00
2,00
4,00
6,00
8,00
10,00
12,00
2013 2014 2015 2016 2017 2018 2019 2020 2012 2022
RENEWABLE VS DEMAND
![Page 13: Renewable Energy in Kuwait Between Vision & Reality...MEW Roof Top PV Projects Applying PV’s on the Roofs of (6) Stores in Sabhan Installed Capacity 3.75 MW. Tendering Installation](https://reader036.vdocuments.us/reader036/viewer/2022062416/61042e664fcc7d15180a76b5/html5/thumbnails/13.jpg)