October Storm UpdateOctober 29, 2019
SEQUENCE OF EVENTS
10/20/19, 8:58pm: EF-3 Tornado strikes NWquadrant of Dallas ISD
10/20/19, 10:00pm: Maintenance and Facilitiespersonnel begin to survey impactedschools. Gas, electricity, water shut off. 21 campuses and 1support facility impacted.
10/21/19, 8:37am: 21 campuses closed due to damage and/or no power. Supt.convenes critical staff. Contingencyplan developed within the next 5hours.
10/21/19, 1:07pm: Critical staff reconvened topresent relocation plan for mostschools unable to utilize existingfacilities.
Relocations: Stephanie ElizaldeBuilding Recovery: Scott Layne
DISD Affected Campuses
21 campuses located across DISD were affected by Sunday’s storm.
Several schools sustained significant structural damage.
Instructional resources were completely lost on several campuses.
3
School Closings
Caillet ESDealey MontessoriFoster ESFranklin MSHexter ESHillcrest HSIreland ESKramer ESMay ESMedrano MSPershing ESRichardson ESRoosevelt HSSaldivar ESSouth Oak Cliff HSMark Twain TAGBurnet ESCigarroa ESCary MSJefferson HSWalnut Hill ES
Monday
Dealey MontessoriFranklin MSHillcrest HSKramer ESMay ESMedrano MSPershing ES
Tuesday
Dealey MontessoriFranklin MSHillcrest HSKramer ESMay ESMedrano MS
Wednesday
Burnet ESCigarroa ESCary MSJefferson HSWalnut Hill ES
Cary MS
Power Outage
Power Outage/ Minor Damage
ExtensiveDamage
4
School RelocationSEMI-PERMANENT
Walnut Hill ES Tom Field ESJefferson HS Edison Learning Center
6
Students will attend alternative campuses for the remainder of the 2019-2020 school year.
School RelocationWALNUT HILL ELEMENTARY SCHOOL
Walnut Hill ES
Tom Field ES
Walnut Hill students moved to the vacant Tom Field ES campus (4.8 miles).
Existing elementary campus
Additional considerations:• Student Desks• Instructional Materials• Classroom Supplies• Transportation• IT Services• Technology
7
School RelocationTHOMAS JEFFERSON HIGH SCHOOL
Jefferson HS
Edison Learning Center
Jefferson students moved to the Edison Learning Center (9.2 miles).
Existing secondary campus
Additional considerations:• Instructional Materials• Classroom Supplies• Transportation• Technology• IT Services
Existing services moved to Nolan Estes
8
Student ReassignmentEDWARD H. CARY MIDDLE SCHOOL
Franklin MSCary MS
Cary students moved to Franklin (4.8 miles) and Medrano Middle Schools (2.6 miles).
Students split by address
Additional considerations:• Student Desks• Instructional Materials• Classroom Supplies• Transportation
Medrano MS
9
October 21, 2019October 2019 Storm Update
● Summary of Impact:○ 21 Campuses and 1 District Facility
■ Minor: 16 Campuses■ Moderate: 2 Campuses/1 District Facility
● Cigarroa; Burnet; North Dallas Bus Barn
■ Major: 1 Campus● Thomas Jefferson
■ Severe: 2 Campuses● Cary; Walnut Hill
11
Progress Update (Minor)October 2019 Storm Update
12
CAMPUS Oct. 21 Oct. 22 Oct. 23 Oct. 24 CAMPUS Oct. 21 Oct. 22 Oct. 23 Oct. 24
Calliet No Power Power Restored Saldivar No Power Power
Restored
Dealey No Power No Power No Power Power Restored Pershing No Power No Power No Power Power Restored
(Friday)
Foster No Power Power Restored Roosevelt No Power Power
Restored
Franklin No Power No Power No Power Power Restored Ireland No Power Power
Restored
Hillcrest No Power No Power No Power Power Restored Hexter No Power Power
Restored
Kramer No Power No Power No Power Power Restored SOC at
Village FairNo Power Power
Restored
Medrano No Power No Power No Power Power Restored May No Power No Power No Power Power
Restored
Richardson No Power Power Restored Mark Twain No Power Power
Restored
All debris cleared by October 21, 2019 at Minor Impact Campuses
Progress Update (Moderate)October 2019 Storm Update
13
Burnet ES Cigarroa ES North Dallas Bus Barn
Secured Campus Secured Campus Secured Campus
Built wall separating campus and gym
Need to replace Rooftop Units Restore Power to Fuel Pumps (Temp & Long-Term)
Roof/Floor Replacement Delivery of Spot Coolers Cleared Debris
Power Restoration Repaired Roof Power Restoration
Cleared Debris Cleared Debris
EHS completed evaluation of campus and cleared building
EHS completed evaluation of campus and cleared building
Custodians deep cleaning of campus
Custodians deep cleaning of campus
Plumbing cleared gutters through jetting process
Plumbing cleared gutters through jetting process
Returned to campus Thursday Returned to campus Thursday
Progress Update (Major/Severe)October 2019 Storm Update
14
Process/Next Steps
Power/Gas/Water shut offPolice WatchAdjuster/Insurance assessment ongoingAsbestos inspection complete/acceptableCampus fencedRoof tarpedStructural assessment to gain entry ongoingSite cleanedBroken windows will be boarded upBuilding component recovery this weekUtilizing existing Architect and Contractor
to assess damagesDecision to suspend ongoing construction
until assessment completeInsurance carrier to determine next steps
Jefferson High SchoolDamages (Visible)
- BB fields, dugouts, fencing demolished- Tennis court post and fencing demolished- Portables (17) are unusable and damaged- 30% of windows are shattered or gone. - Buildings missing about 10% of roof- All flashing is peeled back- Gutters and downspouts are ripped off- Gym missing about 1000 SF of roof- Standing water in both gyms/cafeteria- Academy wing has minor water intrusion- Chiller damaged- Several RTUs are tipped over.- Cooling tower leaking- Boiler room has standing water- Water in electrical rooms/damaged circuits.- Switch gear is submerged in water
Items complete
Progress Update (Major/Severe)October 2019 Storm Update
15
Cary Middle SchoolDamages (Visible)
- All portables are gone- Tree damage in front of school- SRO car moved onto fence- Windows on the east and south sides
are 90% gone. - Large portions of roof missing- Flashing has been removed from
perimeter- All RTUs are removed
Process/Next Steps
Power/Gas/Water shut offPolice WatchAdjuster/Insurance assessment ongoingAsbestos inspection complete/acceptableCampus fencedStructural assessment to gain entry ongoingSite cleanedBroken windows be boarded upBuilding component recovery this weekUtilizing an Architect to assess damagesInsurance carrier to determine next steps
Items complete
Progress Update (Major/Severe)October 2019 Storm Update
16
Walnut Hill Elementary SchoolDamages (Visible)
- All portables are gone- Tree damage in front and south side of school- Windows on east, west, south sides 80% gone - Large portions of roof missing- Flashing has been removed from perimeter- Auditorium/office area major water intrusion- Boiler room flooded- All RTUs are removed- Chiller damaged- Cooling tower gone
Process/Next Steps
Power/Gas/Water shut offPolice WatchAdjuster/Insurance assessment ongoingAsbestos inspection complete/acceptableCampus fencedStructural assessment to gain entry ongoingSite cleanedBroken windows be boarded upBuilding component recovery this weekUtilizing an Architect to assess damagesInsurance carrier to determine next steps
Items complete