Transcript
  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    1/9

    Welcome to DRBF ConferenceWelcome to DRBF Conference

    Eng. Dr. Kamal Adnan Malas

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    2/9

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    5-2 Priority of contract documents

    Extending the Completion date

    Handing Over Certificate

    44-1

    48-1

    Variations

    Claims

    Funny Arbitration Clause67

    51-1

    53-2

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    3/9

    The Engineer cancelled the Priority of Documents Clause.

    The Result:

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    5-2 Priority of Contract Documents

    In case of contradiction between the documents (which is

    common practice). And after that the dispute is to be

    resolved through Arbitration.

    Then the result in the Arbitration is unknown due to the factthat the Arbitrator is not bound with any condition

    regarding the priority of documents.

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    4/9

    The Engineer ignores the contractor requests, and did not

    give any decision regarding time for completion.

    The Engineer gives variations order with out considering any

    Extension Of Time (EOT)44-1

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    extension of time leaving that till the end of the project?

    The Result:

    In case of termination of contract then may be the result is

    not as per the engineer and (the employer) thoughts. theymissed the chance to agree with the contractor about Its request

    for EOT.

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    5/9

    The Engineer refuses to sign the handing over certificate, in-

    spite that he signed the Municipality completion certificate.

    After signing the Municipality certificate the Engineer giver

    new variation orders to the contractor, and refuses to sign the

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    Handing over certificate48-1

    handing over certificate before the executing of these newvariations.

    The Engineer issued the handing over certificate with out

    informing the contractor.

    The Engineer continue issuing snag lists and always mention

    that the work is not done even if he has letter from thecontractor informing the engineer tat the snag list work is done.

    The Result:

    Many disputes between the employer and the contractor which

    lead to big losses ( always the employer pay the price of the

    Engineer bad decision)

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    6/9

    The Engineer cancel the maximum variation limit ( %25 )

    and leave it o en ( He thinks that he could increase the

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    Variations51-1

    variation in this way )

    The Result:

    In civil Law countries ( The employer ) looses his right to order

    the contractor to execute variations with the same break down

    prices of the contract.

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    7/9

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    Claims52-1

    The Engineer refuse to give decision about the claims, and

    postponed them till the end of the Project. The Engineer refuse to give decision about the claims, andpostponed them till the end of the Project.

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    8/9

    Examples:

    All disputes will be resolved through Arbitration, and after

    completing the Arbitration procedures then recourse to courts.

    Funny arbitration clauses67

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    The Engineer is the sole Arbitrator and his decisions are finaland binding.

  • 7/29/2019 Misapplication of FIDIC Red Book 1987

    9/9

    Thank

    Some misapplications of FIDIC Red BookSome misapplications of FIDIC Red Book 19871987

    Eng. Dr. Kamal Adnan Malas


Top Related